Basement communicating port deformation joint leaking stoppage construction method

By embedding rubber water stop belts and drainage pipes, combined with the use of rubber expansion water stop strips and sealing paste, the problem of leakage in the deformation joints of the basement communication port is solved, and a fast and convenient leakage plugging effect and significant waterproof effect are achieved.

CN120211320APending Publication Date: 2025-06-27CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510290930.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-12
Publication Date
2025-06-27

AI Technical Summary

Technical Problem

Leakage of deformation joints at the basement communication opening is relatively common, which leads to high difficulty in plugging, long construction time, many personnel, and inconvenient maintenance and maintenance.

Method used

The pre-embedded rubber water stop belt and drain pipe are used to clean deformation joints, expand expansion bolts are used, rubber expansion water stop strips are embedded, seal them with sealing paste, and removable water stop belts and sealing steel plates are installed to achieve leakage plugging.

Benefits of technology

It effectively saves leak plugging operation time, reduces the number of personnel, is easy to construct, is easy to maintain and maintain, and has significant waterproofing effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120211320A_ABST
    Figure CN120211320A_ABST
Patent Text Reader

Abstract

The invention discloses a plugging construction method for a deformation joint of a basement communication port. The plugging construction method comprises the following steps: pre-burying a middle-buried rubber waterstop and a drain pipe; formwork erecting; pouring concrete; cleaning the deformation joint; an expansion bolt is screwed after drilling; embedding a rubber expansion water-stop strip into the deformation joint; sealing and embedding the deformation joint by using sealing paste; a detachable water stop belt is installed; according to the invention, the plugging operation time can be saved, the construction is easy, and the maintenance and repair are convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of basement construction, and more specifically, to a leakage plugging construction method for the deformation joint of a basement connection opening. Background Art

[0002] With the development of high-rise buildings, the scale of basements such as underground civil air defense and garages is getting larger and larger. Due to changes in engineering hydrogeology, structural stiffness, and temperature deformation, during structural design, the principle of "release" is generally adopted, and post-cast strips or deformation joints are set. There are specific practices for the waterproof structure of deformation joints in design and standard drawings. However, in actual construction, due to factors such as the buried depth of the basement, soil layer properties, hydrodynamic pressure, and construction quality, leakage of the deformation joints of the connection opening caused by structural deformation changes and uneven settlement occurs frequently, and it is very difficult to plug the leakage. Summary of the Invention

[0003] Aiming at the problems existing in the prior art, the purpose of the present invention is to provide a leakage plugging construction method for the deformation joint of a basement connection opening, which can save the leakage plugging operation time, reduce the number of leakage plugging operators, and is easy to construct and convenient for maintenance and repair.

[0004] The present invention adopts the following technical solutions:

[0005] A leakage plugging construction method for the deformation joint of a basement connection opening, comprising the following steps:

[0006] Embed a middle embedded rubber waterstop and embed a drain pipe;

[0007] Formwork;

[0008] Pour concrete;

[0009] Clean the deformation joint;

[0010] Drill holes and drive expansion bolts;

[0011] Embed a rubber expansion waterstop strip into the deformation joint;

[0012] Use sealant to seal the deformation joint;

[0013] Install a removable waterstop;

[0014] Close the steel plate.

[0015] Further, before the concrete construction of the deformation joint of the connection opening, embed a drain pipe in the deformation joint of the floor slab. Embed it before pouring the floor slab. The drain pipe leads to the nearest sump from the position of the deformation joint to introduce the water flow into the sump.

[0016] Further, the drain pipe is a PVC pipe.

[0017] Further, after pouring the concrete, after the construction of the deformation joint is completed and the concrete strength of the shear walls on both sides of the deformation joint reaches the design grade, remove the formwork and clean the deformation joint to make the two sides of the deformation joint horizontal and vertical.

[0018] Further, the spacing of the holes drilled for the expansion bolts is 15 cm.

[0019] Further, the width of the rubber expansion water stop strip is 3 cm.

[0020] Further, the steel plate is installed on the expansion bolts and the steel plate covers the rubber expansion water stop strip.

[0021] Beneficial effects

[0022] The present invention can save the plugging operation time and reduce the number of plugging operation personnel. Moreover, the construction is easy and the maintenance and repair are convenient. If leakage occurs during the completion stage or during long-term use, the open drainage waterproof effect is remarkable. Description of the drawings

[0023] Figure 1 It is the construction flow chart of an embodiment of the present invention;

[0024] Figure 2 It is the schematic diagram of the embedded drainage pipe of an embodiment of the present invention;

[0025] Figure 3 It is the schematic diagram after cleaning the deformation joint of an embodiment of the present invention;

[0026] Figure 4 It is the schematic diagram after the steel plate is closed of an embodiment of the present invention. Specific implementation manners

[0027] In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0028] As shown in the figure, the present invention discloses a construction method for plugging the deformation joint of the basement connecting opening, including the following steps:

[0029] Embed the center-embedded rubber water stop belt and embed the drainage pipe 1;

[0030] Formwork;

[0031] Pour the concrete;

[0032] Clean the deformation joint 2;

[0033] Drill holes and then drive expansion bolts 3;

[0034] Embed the rubber expansion water stop strip 4 into the deformation joint;

[0035] Embed the deformation joint with sealant 5;

[0036] Install the removable water stop 6;

[0037] Close the steel plate 7.

[0038] In an embodiment of the present invention, before the concrete construction of the deformation joint 2 of the communication port, a drain pipe 1 is embedded in the deformation joint of the floor slab, which is embedded before the floor slab is poured. The drain pipe 1 leads to the nearest sump from the position of the deformation joint, and the water flow is introduced into the sump. After the residence is delivered for use, the water at the communication port can flow into the sump through the embedded drain pipe, achieving the effect of water stop and waterproofing.

[0039] In an embodiment of the present invention, the drain pipe 1 is a PVC pipe.

[0040] In an embodiment of the present invention, after the concrete is poured, after the construction of the deformation joint 2 is completed and the concrete strength of the shear walls on both sides of the deformation joint 2 reaches the design grade, the formwork is removed and the deformation joint is cleaned to make the two sides of the deformation joint horizontal and vertical. Cleaning the deformation joint 2 is for facilitating the next construction step.

[0041] In an embodiment of the present invention, the spacing of the holes drilled for installing the expansion bolts 3 is 15 cm.

[0042] In an embodiment of the present invention, the width of the rubber expansion water stop strip 4 is 3 cm. For different construction positions, the width of the rubber expansion water stop strip 4 can be adjusted as needed.

[0043] In an embodiment of the present invention, the steel plate 7 is installed on the expansion bolts 3, and the steel plate 7 covers the rubber expansion water stop strip. The steel plate 7 plays a sealing role. The expansion bolts 3 are used to install the steel plate 7.

[0044] The above is only a preferred specific embodiment of the present invention; however, the protection scope of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed by the present invention, according to the technical solution of the present invention and its improved concept, makes equivalent substitutions or changes, and all should be covered within the protection scope of the present invention.

Claims

1. A method for plugging leakage in deformation joints of basement communication ports, characterized in that: The following steps are involved: Pre-buried mid-buried rubber waterstop and pre-buried drainage pipe; Formwork; pouring concrete; Clean the expansion joints; After drilling, install expansion bolts; Insert rubber expansion water stop strips into the deformation joints; Use sealing paste to seal the expansion joints; Install removable waterstop; Closed steel plate.

2. A method for plugging leakage in deformation joints of basement communication openings according to claim 1, characterized in that: Before the concrete construction of the connecting expansion joint, a drainage pipe is embedded in the expansion joint of the base plate before the base plate is poured. The drainage pipe leads to a sump closest to the expansion joint to direct the water flow into the sump.

3. A method for plugging leakage in deformation joints of basement communication openings according to claim 2, characterized in that: The drainage pipe is a PVC pipe.

4. A method for plugging leakage in deformation joints of basement communication openings according to claim 1, characterized in that: After pouring concrete, wait until the expansion joint construction is completed and the concrete strength of the shear walls on both sides of the expansion joint reaches the design level, remove the formwork, clean the expansion joint, and make both sides of the expansion joint horizontal and vertical.

5. A method for plugging leakage in deformation joints of basement communication openings according to claim 1, characterized in that: The spacing between the holes for drilling expansion bolts is 15cm.

6. A method for plugging leakage in deformation joints of basement communication openings according to claim 1, characterized in that: The width of the rubber expansion waterstop is 3cm.

7. A method for plugging leakage in deformation joints of basement communication openings according to claim 1, characterized in that: The steel plate is installed on the expansion bolts, and the steel plate covers the rubber expansion waterstop strip.