Building hanging basket support and installation method

By designing a triangular stable structure of cross bars, support bars and tie bars, the problem of installation obstacles of traditional hanging basket brackets in special-shaped buildings is solved, and efficient hanging basket installation and construction progress is achieved.

CN120367374APending Publication Date: 2025-07-25CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510841875.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-06-23
Publication Date
2025-07-25

AI Technical Summary

Technical Problem

Traditional hanging basket brackets are unable to spread stably in special-shaped structure buildings due to fixed length and limited extension of legs, resulting in installation obstacles and full scaffolding is required to erect the mobility of the hanging baskets and slow down the construction progress.

Method used

A building hanging basket bracket is designed, including cross bars, support bars and tie bars, which are fixed to the wall through mounting seats to form a triangular stable structure, which can cross the blind spots of the convex structure columns and the ends of the shear wall, avoiding installation obstacles of traditional brackets, and no need to set up scaffolds.

Benefits of technology

The stable installation of hanging baskets in special-shaped building structures has been achieved, the construction efficiency has been improved, the use of steel pipe fasteners has been reduced, the mobility of hanging baskets has been enhanced, and the construction progress has been avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120367374A_ABST
    Figure CN120367374A_ABST
Patent Text Reader

Abstract

The invention relates to the field of buildings, and discloses a building hanging basket support and a mounting method.The building hanging basket support comprises a cross rod, a supporting rod, a pull rod and a plurality of mounting bases, the end of the supporting rod is arranged on the first side of the cross rod, the end of the pull rod is arranged on the second side of the cross rod, and the mounting bases are fixedly arranged on a wall; mounting seats are arranged at the ends, deviating from each other, of the transverse rod, the supporting rod and the pull rod, and the transverse rod is perpendicular to the wall. The transverse rod, the supporting rod and the pull rod are independently fixed to the wall body through the mounting base, the transverse rod is perpendicular to the wall body, and the supporting rod and the pull rod are arranged on the two sides of the transverse rod correspondingly to form a triangular stable structure, so that a structural mounting blind area formed by an outwards-protruding structural column and the end of the shear wall can be spanned; installation obstacles caused by fixed length and limited supporting leg unfolding of a traditional support are avoided, meanwhile, an all-round scaffold does not need to be erected, and the problems that the using amount of steel pipe fasteners is large, the maneuverability of a hanging basket is hindered, and the construction progress is slowed down are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of construction, and in particular to a construction hanging basket bracket and an installation method thereof. Background Art

[0002] In the field of high-rise building exterior wall construction, hanging baskets are widely used as aerial work platforms. Traditional hanging basket installation is highly dependent on standard building facade structures, and its bracket system needs to lay load-bearing fulcrums along a continuous and flat wall surface. However, with the diversified development of modern architectural design, a large number of special-shaped structures (such as sharp corners, protruding structural columns, and curved curtain wall substrates) have become the norm. This special structure causes the preset installation position of the bracket to be physically blocked by concrete columns, shear wall ends, or non-continuous facades, forming a structural installation blind spot.

[0003] Especially in areas with dense shear walls or building corners, traditional brackets are unable to cross column obstacles or spread stably in narrow corners due to their fixed length and limited leg expansion space. Currently, full-height scaffolding is usually used, but this method requires a large number of steel pipe fasteners and hinders the mobility of the hanging basket, significantly slowing down the construction progress. Summary of the invention

[0004] In view of this, the purpose of the present application is to overcome the deficiencies in the prior art and to provide a building hanging basket bracket and an installation method.

[0005] To achieve the above objectives, the technical solutions adopted in this application are as follows: This application provides: A building hanging basket support, comprising: Crossbar; A support rod, wherein an end of the support rod is disposed on a first side of the cross bar; A pull rod, the end of which is disposed on the second side of the cross bar; A plurality of mounting seats are provided, wherein the mounting seats are fixedly arranged on the wall, and the ends of the cross bar, the support bar and the pull rod which are away from each other are all provided with the mounting seats, and the cross bar is perpendicular to the wall.

[0006] Furthermore, the support rod is welded and fixed to the first side of the pull rod, and a reinforcement component is provided at the connection between the support rod and the pull rod, the reinforcement component includes a first connecting hole passing through the cross rod and a second connecting hole passing through the support rod, a pad is provided at the support rod, one side of the pad abuts against the support rod, the pad is provided with a third connecting hole, a second connecting piece is passed through the channel formed by the third connecting hole, the first connecting hole and the second connecting hole, and a second screwing piece is provided at the end of the second connecting piece.

[0007] Furthermore, a protrusion is provided on the surface of the cushion block abutting against the support rod.

[0008] Further, a first connection component for detachably connecting the pull rod and the cross bar is provided therebetween. The first connection component includes a first through hole penetrating through the cross bar and a second through hole formed in the pull rod. The first connection component further includes a first connecting member passing through the first through hole and the second through hole, and a first screwing member is provided at an end of the first connecting member.

[0009] Further, a third connection component for detachably connecting the pull rod and the cross bar is provided therebetween. The third connection component includes a first through hole penetrating through the cross bar and a second through hole formed in the pull rod. Side plates are provided on both sides of the cross bar, and a third through hole and a fourth through hole are respectively formed in each side plate. The third connection component further includes a fourth connecting member passing through the first through hole and the third through hole, a fourth screwing member is provided at an end of the fourth connecting member, and a fifth connecting member passing through the second through hole and the fourth through hole, and a fifth screwing member is provided at an end of the fifth connecting member.

[0010] Further, a second connection component for detachably connecting the pull rod and the mounting seat at its position is provided therebetween. The second connection component includes two fixing plates fixedly provided on a side surface of the mounting seat. A receiving space is defined between the two fixing plates. A first mounting hole is formed in each of the fixing plates, and a second mounting hole is formed at an end of the pull rod facing away from the cross bar. A third connecting member passes through holes formed by the first mounting hole and the second mounting hole, and a third screwing member is provided at an end of the third connecting member.

[0011] Further, the mounting seat includes a mounting plate, and at least two first avoiding holes penetrating through the mounting plate are provided on the mounting plate. Each first avoiding hole is provided with an embedding member, a gasket is sleeved on the embedding member, and a fastening member is provided at an end of the embedding member facing away from the mounting plate.

[0012] Further, a cushion plate is provided between the mounting plate and the wall body, and a second avoiding hole adapted to the first avoiding hole is formed in the cushion plate.

[0013] Further, a mounting member is provided at an end of the cross bar facing away from the mounting seat, and a suspension rope is provided on the mounting member.

[0014] The present application further provides an installation method for installing the building hanging basket support in any one of the above. The method includes: S100: Weld and fix the cross bar and the support rod, and fixedly install the mounting seat on the cross bar, the support rod and the pull rod; S200: Open a fixing hole in the wall body; S300: The mounting seats at the positions of the cross bar, the support bar and the tie bar are fitted and installed on the wall through the fixing holes; S400: Install the end of the tie bar facing away from the wall on the cross bar; S500: Complete the installation.

[0015] In this application, the cross bar, the support bar and the tie bar are respectively and independently fixed to the wall through the mounting seats, and the cross bar is perpendicular to the wall. The support bar and the tie bar are arranged on both sides of the cross bar to form a triangular stable structure, which can cross the structural installation blind areas formed by the protruding structural columns and the ends of shear walls, avoiding the installation obstacles caused by the limited length fixation and the limited expansion of the legs of the traditional bracket. At the same time, there is no need to set up full hall scaffolding, solving the problems of large consumption of steel pipe fasteners, hindering the mobility of the hanging basket and delaying the construction progress. It is especially suitable for the installation of hanging baskets for special-shaped building structures such as acute-angle corners and discontinuous facades.

[0016] In order to make the above-mentioned objects, features and advantages of the present application more obvious and understandable, the following specifically gives preferred embodiments and, in conjunction with the accompanying drawings, makes the following detailed description. Brief Description of the Drawings

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following will briefly introduce the drawings required to be used in the embodiments. It should be understood that the following drawings only show some embodiments of the present application, and therefore should not be regarded as limiting the scope. For those of ordinary skill in the art, without creative efforts, other related drawings can also be obtained based on these drawings.

[0018] Figure 1 Shows the three-dimensional structure schematic diagram of the hanging basket bracket of the present application; Figure 2 Shows the schematic diagram of the hanging basket bracket of the present application fixed to the wall; Figure 3 Shows the schematic diagram of the hanging basket bracket of the present application fixed to the wall in another embodiment; Figure 4 Shows the schematic diagram of the reinforcing component structure of the present application; Figure 5 Shows the schematic diagram of the third connection component of the present application in a side view state; Figure 6 Shows the schematic diagram of the third connection component of the present application in a top view state; Figure 7 Shows the schematic diagram of the second connection component structure of the present application; Figure 8 Shows the schematic diagram of the state where the cross bar of the present application is installed on the mounting plate; Figure 9 Shows the schematic diagram of the cushion plate structure of the present application; Figure 10 The structural schematic diagram of the installation method flow of the present application is shown.

[0019] Description of main component symbols: 100, cross bar; 200, support rod; 300, tie rod; 310, first connection assembly; 311, first connecting piece; 312, first screwing piece; 400, mounting seat; 410, mounting plate; 420, first avoidance hole; 430, embedding piece; 440, gasket; 450, fastener; 460, backing plate; 461, second avoidance hole; 500, strengthening assembly; 510, cushion block; 511, third connection hole; 520, second connecting piece; 530, second screwing piece; 540, protrusion; 600, second connection assembly; 610, fixing plate; 611, accommodating space; 620, third connecting piece; 630, third screwing piece; 700, third connection assembly; 710, side plate; 720, fourth connecting piece; 721, fourth screwing piece; 730, fifth connecting piece; 731, fifth screwing piece; 800, mounting piece; 810, lifting rope. Detailed implementation manners

[0020] The embodiments of the present application will be described in detail below. The examples of the embodiments are shown in the drawings, where the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions from beginning to end. The embodiments described below with reference to the drawings are exemplary and are only used to explain the present application, and should not be construed as a limitation to the present application.

[0021] In the description of the present application, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as a limitation to the present application.

[0022] In addition, the terms "first" and "second" are only used for descriptive purposes and should not be construed as indicating or implying relative importance or implicitly indicating the quantity of the indicated technical features. Thus, the features defined with "first" and "second" may explicitly or implicitly include one or more of such features. In the description of the present application, "a plurality of" means two or more unless otherwise specifically defined.

[0023] In this application, unless otherwise clearly defined or limited, terms such as "installed", "connected", "joined", "fixed", etc. shall be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or integrated; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the communication inside two components or the interaction relationship between two components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0024] In this application, unless otherwise clearly defined or limited, the first feature being "on" or "under" the second feature can be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "over" and "on top of" the second feature can be that the first feature is directly above or obliquely above the second feature, or merely indicates that the first feature has a higher horizontal height than the second feature. The first feature being "under", "beneath" and "underneath" the second feature can be that the first feature is directly below or obliquely below the second feature, or merely indicates that the first feature has a lower horizontal height than the second feature.

[0025] Please refer to Figure 2 and Figure 3 As shown, an outwardly protruding structure is provided on the exterior wall of a building, thereby forming a blind area. When the bracket is installed at the topmost part of the wall, due to the obstruction of the outwardly protruding structure, construction on the wall directly below the outwardly protruding structure cannot be carried out. Therefore, conventionally, a scaffolding is usually erected below the part directly below the outwardly protruding structure, but this method is inefficient and thus slows down the construction progress. Therefore, in this application, it is directly provided on the wall below the outwardly protruding structure, so that construction on the wall directly below the outwardly protruding structure can be carried out.

[0026] This application provides a building hanging basket bracket, which includes a cross bar 100, a support rod 200, a pull rod 300, and a plurality of mounting seats 400. The end of the support rod 200 is arranged on the first side of the cross bar 100, the end of the pull rod 300 is arranged on the second side of the cross bar 100, the mounting seats 400 are fixedly arranged on the wall, and mounting seats 400 are arranged at the mutually facing ends of the cross bar 100, the support rod 200, and the pull rod 300. The cross bar 100 is perpendicular to the wall.

[0027] Please refer to Figure 1 and Figure 2As shown, the first side of the crossbar 100 above is its lower side, and the second side of the crossbar 100 is its upper side. In this application, the crossbar 100 is connected to the support rod 200 and the pull rod 300 respectively. And the other ends of the crossbar 100, the support rod 200 and the pull rod 300 are connected to the wall through the mounting seat 400, so that the entire bracket is fixedly connected to the wall. It can be understood that the crossbar 100 is perpendicular to the wall. In order to prevent the crossbar 100 from bending, a support rod 200 is fixedly installed below the crossbar 100 to support the crossbar 100. At this time, the crossbar 100, the support rod 200 and the wall form a triangular stable shape. Further, in order to improve the stability of the crossbar 100, a pull rod 300 is arranged on the top of the crossbar 100 to apply a pulling force to the crossbar 100 to keep it stable, and the crossbar 100, the support rod 200 and the pull rod 300 also form a triangle.

[0028] Refer to Figure 2 and Figure 3 As shown, an installation part 800 is arranged at the end of the crossbar 100 away from the mounting seat 400, and a suspension rope 810 is arranged on the installation part 800; the hanging basket is lifted by the suspension rope 810.

[0029] In this embodiment, the crossbar 100 and the support rod 200 are fixedly connected to the corresponding mounting seat 400 by welding. Further, the crossbar 100 and the support rod 200 are also connected by welding. The pull rod 300 and the corresponding mounting seat 400 are detachably connected, and the pull rod 300 and the crossbar 100 are also detachably connected. The detachable connection method is described in detail below and will not be elaborated here.

[0030] In some specific embodiments, the support rod 200 is welded and fixed to the first side of the crossbar 100. A strengthening component 500 is also arranged at the connection between the support rod 200 and the crossbar 100. The strengthening component 500 includes a first connection hole penetrating the crossbar 100 and a second connection hole penetrating the support rod 200. A cushion block 510 is arranged at the support rod 200. One side of the cushion block 510 abuts against the support rod 200. The cushion block 510 is provided with a third connection hole 511. A second connecting piece 520 is penetrated in the channel formed by the third connection hole 511, the first connection hole and the second connection hole. A second screwing piece 530 is arranged at the end of the second connecting piece 520.

[0031] Refer to Figure 1 , Figure, Figure 3 and Figure 4As shown, in order to further improve the connection between the cross bar 100 and the support bar 200, at the welding position of the cross bar 100 and the support bar 200, a first connection hole is penetrated through the cross bar 100, and a second connection hole is penetrated through the end of the support bar 200 facing the cross bar 100. The first connection hole, the second connection hole and the third connection hole 511 are coaxial, and the second connecting member 520 passes through the first connection hole, the second connection hole and the third connection hole 511 from top to bottom, and then the second screw member 530 is screwed in. 0 is screwed to the end of the second connecting member 520, at which time the cushion block 510 is tightly abutted against the support rod 200. It should be noted that the bottom surface of the cushion block 510 is a horizontal plane, that is, the surface where the second screwing member 530 contacts the cushion block 510 is a horizontal plane, so that the second screwing member 530 can be installed on the second connecting member 520 without being offset. As the tightening force generated by the screwing of the second screwing member 530 increases, the abutment force between the cushion block 510 and the support rod 200 increases, preventing the cushion block 510 from slipping.

[0032] In this embodiment, the second connecting member 520 is a bolt, and the second screwing member 530 is a nut. When the second connecting member 520 is a stud, it is necessary to screw and install nuts on both ends of the stud.

[0033] In order to further increase the abutment force between the cushion block 510 and the support rod 200, a protrusion 540 is provided on the surface where the cushion block 510 abuts against the support rod 200. By providing the protrusion 540 on the cushion block 510, the bonding force between the cushion block 510 and the support rod 200 is increased to prevent the cushion block 510 from slipping.

[0034] In some specific embodiments, a first connecting component 310 for detachably connecting the pull rod 300 and the cross bar 100 is provided between the pull rod 300 and the cross bar 100. The first connecting component 310 includes a first through hole extending through the cross bar 100 and a second through hole provided on the pull rod 300. The first connecting component 310 also includes a first connecting member 311 passing through the first through hole and the second through hole. A first screwing member 312 is provided at the end of the first connecting member 311.

[0035] See also Figure 1 and Figure 2 As shown, holes are opened on both the cross bar 100 and the pull rod 300, that is, a first through hole is opened on the cross bar 100, and a second through hole is opened on the pull rod 300, and the first through hole and the second through hole are coaxial, and then the first connecting member 311 is passed through the first through hole and the second through hole, and finally the first screwing member 312 is screwed and installed on the end of the first connecting member 311. As the first screwing member 312 is screwed, the cross bar 100 and the pull rod 300 are connected, completing the connection between the cross bar 100 and the pull rod 300.

[0036] When it is necessary to disassemble the cross bar 100 and the pull rod 300, only need to reversely screw the first screwing member 312 to disengage it from the first connecting member 311, and then make the first connecting member 311 disengage from the first through hole and the second through hole, then the disassembly of the cross bar 100 and the pull rod 300 can be realized.

[0037] Exemplarily, the first connecting member 311 is a bolt, and the first screwing member 312 is a nut.

[0038] In another embodiment, different from the above solution, a third connecting assembly 700 for detachably connecting the pull rod 300 and the cross bar 100 is provided between the pull rod 300 and the cross bar 100. The first connecting assembly 310 includes a first through hole penetrating through the cross bar 100 and a second through hole opened on the pull rod 300. Side plates 710 are provided on both sides of the cross bar 100. A third through hole and a fourth through hole are respectively opened on each side plate 710. The third connecting assembly 700 further includes a fourth connecting member 720 passing through the first through hole and the third through hole, a fourth screwing member 721 is provided at the end of the fourth connecting member 720, and a fifth connecting member 730 passing through the second through hole and the fourth through hole, a fifth screwing member 731 is provided at the end of the fifth connecting member 730.

[0039] Please refer to Figure 3 、 Figure 5 and Figure 6 As shown, the detachable connection between the cross bar 100 and the pull rod 300 can be realized by using the two side plates 710 as a connecting frame. Specifically, the first through hole and the third through hole are coaxially arranged, and the second through hole and the fourth through hole are coaxially arranged. First, the fourth connecting member 720 passes through the first through hole and the third through hole, and then the fourth screwing member 721 is screwed on the fourth connecting member 720, so as to realize the fixed connection between the two side plates 710 and the cross bar 100. Next, the fifth connecting member 730 passes through the second through hole and the fourth through hole, and then the fifth screwing member 731 is screwed and installed on the fifth connecting member 730 to realize the fixed connection between the two side plates 710 and the pull rod 300, thereby realizing the detachable connection between the cross bar 100 and the pull rod 300 through the two side plates 710.

[0040] When it is necessary to disassemble the cross bar 100 and the pull rod 300, only need to reversely screw the fourth screwing member 721 to disengage it from the fourth connecting member 720, and then make the fourth connecting member 720 disengage from the first through hole and the third through hole, then the separation of the cross bar 100 and the pull rod 300 can be realized; or, reversely screw the fifth screwing member 731 to disengage it from the fifth connecting member 730, and then make the fifth connecting member 730 disengage from the second through hole and the third through hole, then the separation of the cross bar 100 and the pull rod 300 can be realized.

[0041] Exemplarily, both the fourth connecting member 720 and the fifth connecting member 730 are bolts, and both the fourth screwing member 721 and the fifth screwing member 731 are nuts.

[0042] In some specific embodiments, a second connection assembly 600 for detachably connecting the pull rod 300 and the mounting seat 400 at its position is provided between the pull rod 300 and the mounting seat 400. The second connection assembly 600 includes two fixing plates 610 fixedly arranged on the side surface of the mounting seat 400. A receiving space 611 is defined between the two fixing plates 610. A first mounting hole is formed in each fixing plate 610. A second mounting hole is formed at the end of the pull rod 300 facing away from the cross bar 100. A third connecting member 620 is passed through the holes formed by the first mounting hole and the second mounting hole. A third screwing member 630 is arranged at the end of the third connecting member 620.

[0043] Please refer to Figure 7 As shown, in order to enable the pull rod 300 to be detachably mounted on the mounting seat 400 corresponding to its position, two spaced fixing plates 610 are fixedly welded on the mounting seat 400, and the receiving space 611 formed between the two fixing plates 610 is used to receive the end of the pull rod 300, so that the end of the pull rod 300 can be placed in the receiving space 611. And during installation, the second mounting hole formed at the end of the pull rod 300 is coaxially arranged with the first mounting hole formed in the fixing plate 610. Next, the third connecting member 620 is passed through the first mounting hole and the second mounting hole, and finally the third screwing member 630 is screwed to the end of the third connecting member 620 to prevent the third connecting member 620 from disengaging from the first mounting hole and the second mounting hole.

[0044] Exemplarily, the third connecting member 620 is a bolt and the third screwing member 630 is a nut.

[0045] As Figure 8 shown, in this embodiment, both the cross bar 100 and the support rod 200 are connected by welding. Therefore, only the figure showing the connection state of the cross bar 100 and the mounting plate 410 is presented in this application.

[0046] In some specific embodiments, the mounting seat 400 includes a mounting plate 410. The mounting plate 410 is provided with at least two first avoiding holes 420 penetrating through it. Each first avoiding hole 420 is passed through by a buried part 430. A gasket 440 is sleeved on the buried part 430. A fastening member 450 is arranged at the end of the buried part 430 facing away from the mounting plate 410.

[0047] Please refer to Figure 7 and Figure 8As shown, at least two first avoidance holes 420 are provided in the mounting plate 410 so that the embedding member 430 can be stably fixed to the wall, maintaining its stability. When the number of the first avoidance holes 420 is two, the two first avoidance holes 420 are arranged diagonally or symmetrically. In this embodiment, the number of the first avoidance holes 420 is four and they are distributed along the four corners of the mounting plate 410. Correspondingly, the number and position of the embedding members 430 correspond to those of the first avoidance holes 420.

[0048] Furthermore, in this embodiment, the first avoidance holes 420 are oblong holes, which facilitates the embedding member 430 to pass through the first avoidance holes 420. Specifically, during installation, four embedding members 430 can be first fixedly arranged on the wall in a manner of being distributed along the four corners, and then the embedding members 430 can be passed through the first avoidance holes 420, the gasket 440 is sleeved on the embedding member 430, and finally the fastening member 450 is screwed and installed on the embedding member 430. As the fastening member 450 is screwed, the mounting plate 410 is pressed against the wall to achieve position fixation.

[0049] In this embodiment, in order to apply the screwing force from the fastening member 450 to the mounting plate 410, the width of the first avoidance hole 420 is L, and the width of the gasket 440 is D, and it should satisfy D > L, so that the gasket 440 can be separated from the mounting plate 410, and the screwing force from the fastening member 450 is transmitted to the mounting plate 410 through the gasket 440, causing the mounting plate 410 to be pressed against the wall.

[0050] Exemplarily, since the embedding member 430 is installed in the wall and holes need to be drilled in the wall first, in order to ensure the connection strength between the embedding member 430 and the wall, the embedding member 430 can be a chemical bolt, and the gasket 440 can be a nut adapted to the chemical bolt. The cooperation between the nut and the chemical bolt fixes the mounting plate 410 to the wall.

[0051] In some specific embodiments, a backing plate 460 is provided between the mounting plate 410 and the wall, and a second avoidance hole 461 adapted to the first avoidance hole 420 is provided in the backing plate 460.

[0052] Please refer to Figure 2 、 Figure 3 and Figure 9 As shown, since some walls are not flat and have some small unevenness, in order to ensure the fit between the mounting plate 410 and the wall, a backing plate 460 is provided on the side of the mounting plate 410 facing the wall, and the uneven part is compensated by the deformation of the backing plate 460.

[0053] The backing plate 460 can be made of a material such as rubber that can undergo a certain amount of deformation.

[0054] Refer toFigure 10 As shown in the figure, the embodiment of the present application further provides an installation method, which is used to install the building hanging basket bracket in any one of the above, and the method includes: S100: Weld and fix the cross bar 100 and the support bar 200, and install the mounting seat 400 at the fixed settings of the cross bar 100, the support bar 200 and the tie rod 300; S200: Open fixing holes in the wall; S300: The mounting seat 400 at the positions of the cross bar 100, the support bar 200 and the tie rod 300 is fitted and installed on the wall in cooperation with the fixing holes; S400: Install the end of the tie rod 300 facing away from the wall on the cross bar 100; S500: Complete the installation.

[0055] In the above S100, the cross bar 100 and the support bar 200 can be welded and assembled on the ground, and the cross bar 100, the support bar 200 and the corresponding mounting seat 400 can be welded. At this time, the cross bar 100, the support bar 200 and the two mounting seats 400 are an integral body. After opening the fixing holes in the wall, the embedding part 430 of the mounting seat 400 is installed in the fixing holes to prepare for the connection of the mounting plate 410. Next, the mounting plate 410 needs to be installed first at the position where the tie rod 300 is to be installed. Next, the cross bar 100, the support bar 200 and the mounting plate 410 at their positions can be hoisted to the position of the embedding part 430 by means of hoisting or the like. Finally, the mounting plate 410 is installed at the position of the corresponding embedding part 430. Finally, the fastener 450 is screwed on the corresponding embedding part 430 to complete the installation of the cross bar 100 and the support bar 200. Next, one end of the tie rod 300 can be installed on the mounting plate 410 through the second connection assembly 600, and the other end is installed on the cross bar 100.

[0056] In another embodiment, the cross bar 100, the support bar 200, the tie rod 300 and each mounting plate 410 can be assembled on the ground first, and finally the mounting plates 410 are installed at the positions of the corresponding embedding parts 430 by means of hoisting. Those skilled in the art can change the installation method according to the actual working conditions, and specific limitations are not made here.

[0057] In the description of this specification, the descriptions with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples", etc., mean that the specific features, structures, materials, or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of this application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, without contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.

[0058] Although the embodiments of this application have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting this application. Those of ordinary skill in the art can make changes, modifications, substitutions, and variations to the above embodiments within the scope of this application.

Claims

1. A building hanging basket support, characterized in that, Comprising: Cross bar (100); Support rod (200), the end of the support rod (200) is arranged on the first side of the cross bar (100); Tie rod (300), the end of the tie rod (300) is arranged on the second side of the cross bar (100); A plurality of mounting seats (400), the mounting seats (400) are fixedly arranged on the wall, and the mounting seats (400) are arranged at the ends of the cross bar (100), the support rod (200) and the tie rod (300) facing away from each other, and the cross bar (100) is perpendicular to the wall.

2. The construction hanging basket support according to claim 1, wherein, The support rod (200) is fixedly welded to the first side of the tie rod (300), and a strengthening component (500) is further arranged at the connection between the support rod (200) and the tie rod (300). The strengthening component (500) includes a first connection hole penetrating through the cross bar (100) and a second connection hole penetrating through the support rod (200). A cushion block (510) is arranged at the support rod (200). One side surface of the cushion block (510) abuts against the support rod (200). The cushion block (510) is provided with a third connection hole (511). A second connecting piece (520) is inserted into the channel formed by the third connection hole (511), the first connection hole and the second connection hole. A second screwing piece (530) is arranged at the end of the second connecting piece (520).

3. The construction hanging basket support according to claim 2, characterized in that, A protrusion (540) is arranged on the surface of the cushion block (510) abutting against the support rod (200).

4. The construction hanging basket support according to claim 1, characterized in that, A first connection component (310) for detachably connecting the tie rod (300) and the cross bar (100) is arranged between the tie rod (300) and the cross bar (100). The first connection component (310) includes a first through hole penetrating through the cross bar (100) and a second through hole arranged on the tie rod (300). The first connection component (310) further includes a first connecting piece (311) inserted into the first through hole and the second through hole. A first screwing piece (312) is arranged at the end of the first connecting piece (311).

5. The construction hanging basket support according to claim 1, characterized in that, A third connection component (700) for detachably connecting the tie rod (300) and the cross bar (100) is arranged between the tie rod (300) and the cross bar (100). The third connection component (700) includes a first through hole penetrating through the cross bar (100) and a second through hole arranged on the tie rod (300). Side plates (710) are arranged on both sides of the cross bar (100). A third through hole and a fourth through hole are respectively arranged on each side plate (710). The third connection component (700) further includes a fourth connecting piece (720) inserted into the first through hole and the third through hole. A fourth screwing piece (721) is arranged at the end of the fourth connecting piece (720), and a fifth connecting piece (730) inserted into the second through hole and the fourth through hole. A fifth screwing piece (731) is arranged at the end of the fifth connecting piece (730).

6. The construction hanging basket bracket according to claim 1, characterized in that, A second connection assembly (600) for detachably connecting the pull rod (300) and the mounting base (400) at its position is provided between the pull rod (300) and the mounting base (400) at its position. The second connection assembly (600) includes two fixing plates (610) fixedly arranged on the side surface of the mounting base (400). A receiving space (611) is defined between the two fixing plates (610). A first mounting hole is formed in each of the fixing plates (610). A second mounting hole is formed at the end of the pull rod (300) facing away from the cross bar (100). A third connecting member (620) is passed through the holes formed by the first mounting hole and the second mounting hole. A third screwing member (630) is arranged at the end of the third connecting member (620).

7. The construction hanging basket support according to claim 1, characterized in that, The mounting base (400) includes a mounting plate (410). The mounting plate (410) is provided with at least two first avoiding holes (420) penetrating therethrough. Each of the first avoiding holes (420) is passed through by an embedding member (430). A gasket (440) is sleeved on the embedding member (430). A fastening member (450) is arranged at the end of the embedding member (430) facing away from the mounting plate (410).

8. The construction hanging basket support according to claim 7, characterized in that, A backing plate (460) is arranged between the mounting plate (410) and the wall body. A second avoiding hole (461) adapted to the first avoiding hole (420) is formed in the backing plate (460).

9. The building hanging basket support according to claim 1, characterized in that, An installation member (800) is arranged at the end of the cross bar (100) facing away from the mounting base (400). A suspension rope (810) is arranged on the installation member (800).

10. An installation method for installing the building hanging basket support according to any one of claims 1 to 9, characterized in that: The cross bar (100) and the support rod (200) are welded and fixed, and the mounting base (400) is fixedly arranged on the cross bar (100), the support rod (200), and the pull rod (300). Fixing holes are formed in the wall body. The mounting bases (400) at the positions of the cross bar (100), the support rod (200), and the pull rod (300) are cooperatively installed on the wall body in cooperation with the fixing holes. The end of the pull rod (300) facing away from the wall body is installed on the cross bar (100). The installation is completed.