A construction measurement method for steel structures used in building micro-vibration control

By using a coordinate system method based on a three-level reference control network, combined with BIM and CAD software, high-precision steel structure construction surveying for a single-building circular structure on the ground was achieved. This solved the problem of insufficient positioning accuracy in traditional methods, ensuring the micro-vibration control of the building and the normal operation of scientific research equipment.

CN120445167BActive Publication Date: 2026-11-17MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510556123.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-04-29
Publication Date
2026-11-17
Estimated Expiration
2045-04-29

AI Technical Summary

Technical Problem

Traditional measurement methods are insufficient for the construction measurement of complex buildings, such as single-building circular structures on the ground, which require high-precision positioning. In particular, the positioning accuracy of steel structures is insufficient in micro-vibration environments, which affects the performance of buildings and the normal operation of scientific research equipment.

Method used

A coordinate system method based on a three-level reference control network is adopted. Multi-level coordinate systems are established through BIM model and CAD software. Combined with a total station, the steel column components are precisely positioned and adjusted, including the comprehensive positioning of the first-level network, second-level network and third-level network, to ensure the high-precision installation of the steel column components.

Benefits of technology

It improves the accuracy of steel structure construction surveying, adapts to the biaxial nonlinear grid layout of complex buildings, and provides reliable micro-vibration control, especially in scientific research buildings, ensuring the overall performance of the building and the normal operation of scientific research equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120445167B_ABST
    Figure CN120445167B_ABST
Patent Text Reader

Abstract

This invention discloses a steel structure construction surveying method for building micro-vibration control, comprising: verifying and adjusting the primary network reference points based on the primary network coordinate system; establishing a secondary network coordinate system, using the BIM model of the steel structure and CAD software to transpose the adjusted primary network reference points into reference point coordinates in the secondary network coordinate system, and adding secondary network control points within the construction site; setting up a total station and installing steel column assemblies according to the coordinates of the steel column control points in the secondary network coordinate system, and adjusting the steel column assemblies; wherein, the step of adjusting any of the steel column assemblies includes: using the station of the total station adjacent to the steel column assembly as the origin, and establishing a tertiary network coordinate system perpendicular to the steel column assembly together with the first ray; unidirectionally adjusting the installation position of the steel column assembly using the steel column control points in the tertiary network coordinate system; and re-measuring and adjusting the steel column assembly using the corresponding steel column control points in the secondary network coordinate system. This invention effectively improves the accuracy of steel structure construction surveying.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of steel structure construction technology, and in particular to a steel structure construction measurement method for micro-vibration control in buildings. Background Technology

[0002] With the rapid development of modern scientific research buildings, the requirements for structural precision are becoming increasingly stringent. This is especially true for geometrically complex buildings, such as single-building circular structures above ground. Due to their unique geometry and biaxial nonlinear grid layout, traditional measurement methods face numerous challenges. The construction of such complex structures demands extremely high precision in the positioning of the steel structure. Even the slightest deviation can affect the overall performance and safety of the building. This is particularly critical in scientific research buildings, which are subject to extremely high requirements for micro-vibration control; precise positioning can even impact the normal operation of subsequent research equipment and the conduct of scientific research.

[0003] To address this, we designed a construction measurement method for steel structures used in scientific research buildings to control micro-vibration. Summary of the Invention

[0004] To address the aforementioned problems, this invention discloses a steel structure construction measurement method for building micro-vibration control, in order to solve the problem that the measurement accuracy of building installation with a biaxial nonlinear grid layout needs to be improved.

[0005] A construction measurement method for steel structures used in building micro-vibration control includes the following steps:

[0006] Step S1: Verify the primary grid reference points provided by the surveying unit based on the primary grid coordinate system, and perform adjustment;

[0007] Step S2: Establish a secondary network coordinate system with the center point of the original design drawing as the origin. Using the BIM model of the steel structure, the adjusted primary network reference points are transformed into reference point coordinates in the secondary network coordinate system using CAD software. Secondary network control points are added in the construction site. The reference point coordinates and secondary network control points both include steel column control points.

[0008] Step S3: Set up a total station according to the coordinates of the steel column control points in the secondary network coordinate system, install the steel column assembly, and adjust the steel column assembly, wherein the steel column assembly includes a steel column and a reinforcement assembly;

[0009] In step S3, the step of adjusting any of the steel column components includes:

[0010] Step S31: Using the station of the total station adjacent to the steel column assembly as the origin, and together with the first ray, establish a third-level network coordinate system perpendicular to the steel column assembly. The first ray is a ray perpendicular to the steel column in the steel column assembly, drawn from the origin of the second-level coordinate system to the steel column assembly. At the same time, the coordinates of the steel column control points in the second-level network coordinate system are transposed to the coordinates of the steel column control points in the third-level network coordinate system, and the transposed data is remeasured through the origin of the third-level network coordinate system.

[0011] Step S32: Use the steel column control points in the three-level network coordinate system to adjust the installation position of the steel column assembly in one direction.

[0012] Step S33: Transpose the steel column control points in the third-level network coordinate system back to the second-level network coordinate system, and remeasure and adjust the steel column assembly through the corresponding steel column control points in the second-level network coordinate system to complete the installation of the steel column assembly.

[0013] In some embodiments, in step S1, a total station is used to adjust the primary network reference points based on the primary network coordinate system provided by the verification survey unit.

[0014] In some of these embodiments, a BIM model of the steel structure is created using TEKLA.

[0015] In some embodiments, the primary network coordinate system is a geodetic coordinate system, the secondary network coordinate system is a construction site coordinate system, and the tertiary network coordinate system is a local coordinate system.

[0016] In some of these embodiments, the building is a building with a dual-axis nonlinear grid layout.

[0017] In some of these embodiments, the building is a single, above-ground circular structure.

[0018] In some embodiments, the primary network reference points are reference points in the measurement control point results table provided by the surveying unit.

[0019] Compared with the prior art, the above invention has at least one of the following advantages or beneficial effects:

[0020] This invention discloses a steel structure construction measurement method for building micro-vibration control. By utilizing a comprehensive positioning method based on the coordinate system of a three-level reference control network, the accuracy of steel structure construction measurement is effectively improved. The method is optimized for the dual-axis nonlinear grid layout of above-ground circular buildings, exhibiting good adaptability and providing reliable technical support, especially for scientific research buildings with extremely high precision requirements. Attached Figure Description

[0021] The invention, its features, shape, and advantages will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings. Like reference numerals denote like parts throughout the drawings. The drawings are not drawn to scale; their focus is on illustrating the gist of the invention.

[0022] Figure 1 This is a flowchart of a steel structure construction measurement method for building micro-vibration control in an embodiment of the present invention;

[0023] Figure 2 This is a schematic diagram of establishing a secondary grid coordinate system with the center point of the original design drawing as the origin in an embodiment of the present invention;

[0024] Figure 3 This is a schematic diagram illustrating the addition of secondary network control points within the construction site in an embodiment of the present invention.

[0025] Figure 4 This is a schematic diagram of installing the steel column assembly in the secondary network coordinate system according to the steel column control points in an embodiment of the present invention;

[0026] Figure 5 This is a schematic diagram illustrating the adjustment of the steel column assembly and the establishment of a three-level network coordinate system in an embodiment of the present invention;

[0027] Figure 6 This is a schematic diagram illustrating the unidirectional adjustment of the installation position of the steel column assembly using the steel column control points in the three-level network coordinate system in an embodiment of the present invention.

[0028] Among them, 1. Steel column control point; 2. Steel column assembly; 3. Total station; 4. First ray. Detailed Implementation

[0029] The present invention will be further described below with reference to the accompanying drawings and specific embodiments, but these are not intended to limit the scope of the invention.

[0030] like Figure 1 As shown, this invention discloses a construction measurement method for steel structures used in building micro-vibration control. This method is applicable to buildings with a biaxial nonlinear grid layout, such as above-ground single-unit circular research buildings. Specifically, the method includes the following steps:

[0031] Step S1: Verify the primary network reference points based on the primary network coordinate system provided by the surveying unit (the primary network reference points are the reference points in the measurement control point results table provided by the surveying unit), and use a total station to re-measure and adjust the primary network reference points based on the primary network coordinate system provided by the surveying unit; wherein, the primary network coordinate system is the geodetic coordinate system.

[0032] Step S2, as follows Figure 2 and 3As shown, a secondary network coordinate system is established with the center point of the original design drawing as the origin. This secondary network coordinate system is the coordinate system of the construction site. Using the BIM model of the steel structure and CAD software, the adjusted primary network reference points are transposed into the reference point coordinates in the secondary network coordinate system (see X1 and X2 in the figure). Secondary network control points are added in the construction site (see P1, P2, P3, P4 and P5 in the figure), and the number of added points is ensured to cover the entire construction area. The reference point coordinates and secondary network control points both include steel column control point 1.

[0033] Specifically, in step S2 above, the coordinates of the secondary network control points are associated with the coordinates of the reference points to form a complete control network system, and the secondary network control points (newly added control points) are identified and recorded.

[0034] The specific steps for creating the BIM model of the steel structure include: collecting design drawings, geological survey reports, planning documents, and other materials; using BIM software (such as TEKLA) to create a BIM model of the steel structure; numbering and labeling the steel structure components in the BIM model; using the coordinate transformation method of CAD software to associate and export the coordinate system in the BIM model and the coordinate information of each component with the coordinate system (secondary network coordinate system) of the construction site, so as to unify the coordinate system and quickly locate the position of each component during construction; and transposing the steel column control point 1 with the coordinate system of the construction site.

[0035] Step S3, as follows Figure 4 As shown, in the visible area, a total station 3 is set up at the construction site according to the coordinates of the steel column control point 1 in the secondary network coordinate system, and the steel column assembly 2 is installed using the coordinates of the steel column control point 1 in the secondary network coordinate system, and the steel column assembly 2 is adjusted. The steel column assembly 2 includes a steel column and a reinforcement component.

[0036] Specifically, in step S3 above, the step of adjusting any steel column assembly 2 includes:

[0037] Step S31, as follows Figure 5 As shown, the origin (i.e., the coordinate point of the total station 3 located near the steel column assembly 2 and closest to it) is used as the origin (i.e., its coordinate point is zeroed out). Together with the first ray 4 (selecting two points on the line), a third-level network coordinate system perpendicular to the steel column assembly 2 is established. The first ray 4 is a ray perpendicular to the steel column in the steel column assembly 2, drawn from the origin of the second-level coordinate system to the steel column assembly 2. At the same time, the coordinates of the steel column control point 1 in the second-level network coordinate system are transposed to the coordinates of the steel column control point 1 in the third-level network coordinate system through software. The transposed data is then remeasured through the origin (0,0) of the third-level network coordinate system. This third-level network coordinate system is a local coordinate system.

[0038] Step S32, as follows Figure 6 As shown, the installation position of the steel column assembly 2 is adjusted unidirectionally using the steel column control point 1 in the three-level network coordinate system.

[0039] Step S33: Transpose the steel column control point 1 in the third-level network coordinate system back to the second-level network coordinate system, and re-measure and adjust the steel column assembly through the corresponding steel column control point 1 in the second-level network coordinate system. After meeting the requirements, reinforce the steel column to complete the installation of the steel column assembly 2.

[0040] In the embodiments of the present invention, due to the unidirectional adjustment of the steel column assembly 2 and the angle problem of the positioning axis of the secondary grid coordinate system, the steel column is difficult to adjust, so it is necessary to introduce a tertiary grid coordinate system.

[0041] Those skilled in the art should understand that variations can be implemented by combining existing technology with the above embodiments, which will not be elaborated here. Such variations do not affect the essence of the present invention, and will not be elaborated here either.

[0042] The preferred embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the specific embodiments described above, and the devices and structures not described in detail should be understood as being implemented in a conventional manner in the art. Any person skilled in the art can make many possible variations and modifications to the technical solutions of the present invention using the methods and techniques disclosed above, or modify them into equivalent embodiments with equivalent changes, without departing from the scope of the present invention. This does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the present invention's technical solutions still fall within the protection scope of the present invention.

Claims

1. A method for measuring the construction of steel structures for micro-vibration control in buildings, characterized in that, Includes the following steps: Step S1: Verify the primary grid reference points provided by the surveying unit based on the primary grid coordinate system, and perform adjustment; Step S2: Establish a secondary network coordinate system with the center point of the original design drawing as the origin. Using the BIM model of the steel structure, the adjusted primary network reference points are transformed into reference point coordinates in the secondary network coordinate system using CAD software. Secondary network control points are added in the construction site. The reference point coordinates and secondary network control points both include steel column control points. Step S3: Set up a total station according to the coordinates of the steel column control points in the secondary network coordinate system, install the steel column assembly, and adjust the steel column assembly, wherein the steel column assembly includes a steel column and a reinforcement assembly; In step S3, the step of adjusting any of the steel column components includes: Step S31: Using the station of the total station adjacent to the steel column assembly as the origin, and together with the first ray, establish a third-level network coordinate system perpendicular to the steel column assembly. The first ray is a ray perpendicular to the steel column in the steel column assembly, drawn from the origin of the second-level coordinate system to the steel column assembly. At the same time, the coordinates of the steel column control points in the second-level network coordinate system are transposed to the coordinates of the steel column control points in the third-level network coordinate system, and the transposed data is remeasured through the origin of the third-level network coordinate system. Step S32: Use the steel column control points in the three-level network coordinate system to adjust the installation position of the steel column assembly in one direction. Step S33: Transpose the steel column control points in the third-level network coordinate system back to the second-level network coordinate system, and remeasure and adjust the steel column assembly through the corresponding steel column control points in the second-level network coordinate system to complete the installation of the steel column assembly; The building is a building with a dual-axis nonlinear grid layout. The first-level grid coordinate system is the geodetic coordinate system, the second-level grid coordinate system is the construction site coordinate system, and the third-level grid coordinate system is the local coordinate system.

2. The steel structure construction measurement method for micro-vibration control in buildings as described in claim 1, characterized in that, In step S1, a total station is used to adjust the primary network reference points based on the primary network coordinate system provided by the verification survey unit.

3. The steel structure construction measurement method for building micro-vibration control as described in claim 1, characterized in that, A BIM model of the steel structure was created using TEKLA.

4. The steel structure construction measurement method for micro-vibration control in buildings as described in claim 1, characterized in that, The building is a single, circular building above ground.

5. The steel structure construction measurement method for micro-vibration control in buildings as described in claim 1, characterized in that, The primary network benchmark points are the benchmark points in the measurement control point results table provided by the surveying unit.

Citation Information

Patent Citations

  • Method for measuring construction steel structure special-shaped component three-dimensional coordinates

    CN101324428A

  • Construction quality detection method and system based on BIM and three-dimensional laser scanning

    CN111121733A