Construction method of abutment cofferdam in cliff deepwater area

By adopting the steel concrete composite cofferdam structure and internal support frame in the deep water area of Linjia, the problems of difficulty in dismantling the steel cofferdam in high flow velocity environment and the long demolition period of the concrete cofferdam are solved, and the rapid demolition of the cofferdam is achieved, ensuring the smooth progress of the construction of the arch ring section 1#.

CN120465374APending Publication Date: 2025-08-12贵州交通建设集团有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510566476.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-30
Publication Date
2025-08-12

AI Technical Summary

Technical Problem

In the construction environment of the Linjia deep water area, the steel cofferdam is not suitable for high-flow water areas, and the concrete cofferdam has a long demolition period, which affects the construction period of the arch ring section 1#.

Method used

The steel concrete composite cofferdam structure is adopted, and the front wall adopts a concrete foundation combined with a steel cofferdam. The steel cofferdam can be quickly removed during the construction of the arch ring. The concrete cofferdam is used in other locations, combined with the inner support frame structure to enhance stability.

Benefits of technology

The cofferdam is quickly demolished in the deep water area of Linjiao where construction space is limited, avoid affecting the construction cycle of section 1 of the arch ring, reduce costs and adapt to the hydrostatic pressure in the deep water area.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120465374A_ABST
    Figure CN120465374A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge construction, and particularly discloses a cliff deep water area skewback cofferdam construction method which comprises the following steps: step 1, cofferdam foundation pit construction: setting out the position of a cofferdam by using measurement control points and densification points, determining the foundation pit boundary of the cofferdam, and excavating a foundation pit; 2, formwork installation and pre-burying are conducted, specifically, a soil cofferdam is used as an outer side formwork installation mold, and a pre-buried part of a steel cofferdam is pre-buried in the mold; 3, a concrete cofferdam is poured, specifically, the concrete cofferdam is poured in the mold installed in the step 2; and 4, the steel cofferdam is arranged, specifically, the steel cofferdam is welded to the embedded part in the step 2, a cofferdam support is arranged behind the steel cofferdam, and construction of the cofferdam is completed. The technical problems that in the prior art, when the cofferdam faces the construction environment with insufficient construction width such as cliff deep water, a steel cofferdam is not suitable for the high-flow-speed environment of the cliff deep water, the dismantling period of a concrete cofferdam is long, and the construction period of the 1 # section of the arch ring is seriously affected are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, in particular to a method for constructing an arch cofferdam in a cliff-side deep-water area. Background Art

[0002] Currently, an arch bridge is a type of bridge with an arch structure as its core load-bearing component. By converting vertical loads into axial pressure transmitted along the arch axis, it efficiently achieves force distribution and load-bearing. From ancient stone arch bridges to modern steel-concrete composite structures, arch bridges have become an important type of bridge engineering due to their beautiful shape and strong spanning capacity. The arch seat, located at the arch foot of an arch bridge, is the key connection point between the main arch ring and the piers / abutments. Because an arch bridge is a structure that pushes in both directions, the arch seat is a critical component that transmits the huge horizontal thrust and vertical load generated by the arch ring to the foundation.

[0003] Arch bridges often span mountains and rivers, so during the construction of their arch abutments, cofferdams are often required. A cofferdam is a temporary, impermeable structure built around a foundation pit or construction area. By intercepting water flow and preventing soil from entering the construction area, it creates a dry and safe working environment and facilitates drainage, foundation pit excavation, and building construction. Cofferdams are typically categorized as concrete and steel. Concrete cofferdams are water-retaining structures cast in concrete and are typically used in rock-based riverbeds. They offer high strength and scour resistance, can withstand the impact of high-velocity water flows, and are suitable for retaining high-head water. However, they are large, difficult to dismantle, and cannot be reused. Steel cofferdams are temporary water-retaining structures primarily constructed of steel sheet piles or double-walled steel structures. They are self-floating, easy to adjust their underwater posture, can be mechanically assembled, have a short construction period, and are reusable. However, they require a large amount of steel and demand high machining precision and welding technology. Underwater welding and leak plugging require specialized equipment and diving operations, which are costly.

[0004] With the development of infrastructure, the locations where arch bridges need to be built are becoming increasingly complex. For example, building an arch bridge near a cliff and deep water poses a threat to the construction of the arch abutment. Deep water means greater water depth and hydrostatic pressure, while the cliff face creates significant water impact. Even with optimized designs (such as double walls and concrete infill), steel cofferdams can only accommodate moderate flow rates (≤4 m / s) and require additional protective measures. They are not suitable for the high-flow areas of large rivers and cliffs. If a concrete cofferdam is chosen, the construction environment near the cliff will be affected by the steep slope and cliff at the front edge of the arch abutment, making it impossible to move the cofferdam forward. The distance between the cofferdam and the arch abutment is short. Later, when constructing the arch ring on the arch abutment, the first segment of the arch ring will collide with the front wall of the cofferdam. Therefore, direct construction is impossible and the front wall must be demolished before the first segment of the arch ring can be constructed. This leads to the technical problem that when faced with a construction environment with insufficient construction width such as deep water near a cliff, the steel cofferdam is not suitable for the high flow rate environment of deep water near a cliff, and the demolition period of the concrete cofferdam is long, which seriously affects the construction period of the arch ring 1# segment. Summary of the Invention

[0005] The purpose of the present invention is to provide a method for constructing an arch seat cofferdam in a cliff-side deep water area, so as to solve the technical problems mentioned above in the prior art that when the cofferdam faces a construction environment with insufficient construction width such as cliff-side deep water, the steel cofferdam is not suitable for the high flow rate environment of cliff-side deep water, and the demolition period of the concrete cofferdam is long, which seriously affects the construction period of the arch ring 1# segment.

[0006] In order to solve the above problems, the technical solution adopted by the present invention is as follows: a method for constructing an arch cofferdam in a deep water area near a cliff, characterized in that it includes the following steps:

[0007] Step 1: Construction of cofferdam foundation pit: Use survey control points and infill points to stake out the location of the cofferdam construction, determine the boundary of the cofferdam foundation pit, and excavate the cofferdam foundation pit;

[0008] Step 2: Formwork installation and pre-embedding: Use the earth cofferdam as the outer formwork to install the mold for pouring the concrete cofferdam, and pre-embed the embedded parts of the steel cofferdam in the mold;

[0009] Step 3: Pour concrete cofferdam: Pour concrete cofferdam in the mold installed in step 2;

[0010] Step 4. Setting up the steel cofferdam: Weld the steel cofferdam to the embedded parts in step 2, and set up cofferdam supports behind the steel cofferdam to complete the construction of the cofferdam.

[0011] The beneficial effects of this embodiment are:

[0012] 1. The cofferdams in the prior art are either concrete cofferdams or all-steel cofferdams. However, when facing a construction environment near a cliff, due to the deep water near the cliff and the steep slope and cliff on the front edge of the arch seat, the width of the constructible cofferdam is small, and the distance between the cofferdam and the arch seat can only be reduced, making the cofferdam and the arch seat too close. When the arch ring is constructed on the arch seat later, its 1# segment will collide with the front wall of the cofferdam, and the construction of the 1# segment cannot be completed. Therefore, in order to facilitate the construction of the 1# segment of the arch ring, the front wall needs to be demolished. However, the demolition period of the concrete cofferdam is long, which seriously affects the construction period of the 1# segment of the arch ring. Therefore, the cofferdam design of this application is a composite structure of steel cofferdam and concrete cofferdam. The cofferdam overlapping with the arch ring adopts steel cofferdam, and concrete cofferdam is adopted in other positions. After the arch seat is cast, the steel cofferdam can be quickly removed by cutting. Therefore, compared with the pure concrete cofferdam in the existing technology, it has the characteristics of rapid dismantling. In an environment with small construction space, it will not affect the construction period of the arch ring. Compared with pure steel cofferdam, this application is more suitable for deep water areas. The hydrostatic pressure in deep water areas is too large, which is a challenge for steel cofferdams. It also needs to be well protected against corrosion. Concrete has better compressive strength and is lower in cost than steel cofferdams.

[0013] Furthermore, in step 4, the steel cofferdam includes a steel plate and a channel steel provided at the rear side of the steel plate as a support, the steel plate is welded to the embedded parts, and the weld positions between the embedded parts are provided with a channel steel covering the welds.

[0014] Furthermore, an internal support of a frame structure is provided in the cofferdam.

[0015] Furthermore, N1, column construction: the columns are hoisted into place according to the designed position in the cofferdam. After all are in place, the columns are fixed to the base underwater using anti-dispersion concrete; N2, beam support construction: after the columns are fixed, beams are laid between the columns to form a frame structure. The two ends of the beams are fixedly connected to the adjacent columns. The laying order is from top to bottom. Each time a layer of beams is laid, a layer of accumulated water in the cofferdam is pumped out. This is repeated alternately until the water is finally pumped to the bottom of the foundation pit, completing the construction of all beams. The outermost layer of beams is directly fixed to the cofferdam.

[0016] Furthermore, in step a, four sensors are set on the cofferdam as reference sensors, and three of the reference sensors are adjusted to be on the same horizontal plane as the reference plane using the Beidou system; in step b, the columns are hoisted into place by a crane so that the columns are in contact with the base bedrock, and sensors are installed on the upper ends of the columns as positioning sensors, and the positioning sensors are adjusted so that they are on the reference plane; in step c, sensors are installed on the lower ends of the columns along the vertical lines of the columns as inclination sensors, and the distances between the positioning sensors, the inclination sensors and the three reference sensors on the reference plane are used to determine whether the columns are vertical, and after verticalization, the columns are fixed to the cofferdam or other adjacent columns using connecting rods to ensure that the columns remain vertical; in step d, after all the columns in the cofferdam are installed vertically using step c, the bottom of the columns are fixed to the bedrock using bottom sealing concrete to form a flat foundation pit bottom foundation.

[0017] Furthermore, the inner support can serve as a construction channel for subsequent arch seat construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a structural diagram of the arch seat construction of the present invention. Figure 2 This is a schematic structural diagram of the front wall of the cofferdam of the present invention. Figure 3 This is a schematic diagram of the mold casting of the present invention. Figure 4 It is a schematic diagram of the connection structure between the beam and the cofferdam of the present invention. DETAILED DESCRIPTION

[0019] The following is further described in detail through specific implementation methods:

[0020] The reference numerals in the drawings of the specification include: arch seat 1, cofferdam 2, front wall 21, side wall 22, back wall 23, and inner support 3.

[0021] Example 1

[0022] The construction method of the arch cofferdam in the deep water area near the cliff includes the following steps:

[0023] A method for constructing a cantilever cast arch bridge arch seat in a cliff-side deep water area comprises the following steps:

[0024] Step S1, constructing a cofferdam: extending outward from the designed arch seat construction position to construct a cofferdam, the cofferdam being a steel-concrete structure with a steel cofferdam as the front wall;

[0025] This application is mainly used to build arch abutments of arch bridges in deep water areas near cliffs beside rivers, such as Figure 1 As shown, due to the limitation of the deep water near the cliff, there is a cliff not far from the front side of the arch seat 1, and the construction space is small. Therefore, the width of the cofferdam 2 that can be built is limited, and the distance between the arch seat 1 and the cofferdam 2 is very short. There is not enough space for construction work, and there is not enough width space to build the cofferdam. In addition, the water level of the reservoir has a high water level period. Since it is impossible to complete all construction in a low water level period, the height of the cofferdam is forced to be raised to above the water level line of the high water level period. However, when it is necessary to construct an arch ring on the arch seat in the later stage, the 1# segment of the arch ring will collide with the front wall of the cofferdam. Therefore, it is impossible to construct directly, and the front wall needs to be demolished to construct the 1# segment of the arch ring. Therefore, the present application has developed a construction method for an arch seat cofferdam in a deep water area near a cliff, and its specific construction steps are introduced in detail:

[0026] The cofferdam 2 of this application is designed as a steel-concrete composite cofferdam, and its structure is as follows Figure 1 As shown, the main part of the cofferdam 2 is composed of a front wall 21 (close to the water flow side), a side wall 22, and a back wall 23. The main structure of the side wall 22 and the back wall 23 is a concrete structure, and the front wall 21 is set in front of the arch seat. The front wall of the cofferdam of this application adopts a composite structure of a concrete foundation combined with a steel cofferdam, such as Figure 2 As shown, it includes front wall I and front wall II, of which front wall I is a concrete cofferdam and front wall II is a steel cofferdam. The steel structure of front wall II can be directly cut and removed during the construction of arch ring 1# segment, and the removal is quick, so it does not affect the construction of arch ring 1# segment. Its construction method is as follows:

[0027] Step 1: Cofferdam foundation pit construction: During a low water level period before the target low water level period, use survey control points and infill points to stake out the cofferdam construction location, determine the cofferdam foundation pit boundary, and reserve 1-2m of construction space for excavating the cofferdam foundation pit;

[0028] During a low water period prior to the target low water period, the cofferdam design foundation position was staked out using survey control points and infill points. This was performed using a total station to confirm that the cofferdam foundation pit construction area was consistent with the design. During the low water period, the cofferdam was constructed when the water level was relatively low, making it easier to construct. Steel cofferdams have relatively weaker anti-overturning capabilities, and the water pressure during the low water period was relatively low, preventing damage to the cofferdam during the construction period.

[0029] When construction begins, the excavation method needs to be adjusted according to the water level, which is divided into two parts. First, when the elevation of the excavation is above the water level, the construction no longer considers the water level changes in the morning and evening of the day. It is consistent with land construction and directly uses conventional methods such as excavators and blasting for excavation. Second, when the elevation of the excavation is lower than the water level, construction is carried out by setting up an earth cofferdam. Use an excavator to excavate the foundation pit until the bedrock surface is reached. No blasting is performed, and the loose stones in the foundation pit are cleaned up in time to ensure that the base is free of mud, slag and various construction waste. If the foundation pit is left for a long time after excavation due to other external factors, mud and sand will remain at the bottom. A high-power mud suction device needs to be used to clean it to ensure that the base is a large area of bedrock surface. The cofferdam foundation pit construction requires the base inside the cofferdam to be constructed at the same time.

[0030] When the excavation elevation is below the water level, an earthen cofferdam is set up according to the water level changes. The earthen cofferdam is mainly made of earthbags, and the size of the filled earthbags is approximately 60x15cm. When the water depth of the foundation pit is less than 2m, a double row of earthbag cofferdams (approximately 1.2m wide) is set up. When the water depth of the foundation pit is between 2-4m, a four row of earthbag cofferdams (approximately 2.4m wide) is set up. Due to the severe water seepage in the earthen cofferdam, red clay is selected as much as possible, and special waterproof materials such as leak-proof agents are used to seal the gaps between the earthbag layers to reduce water seepage. The foundation pit adopts a layer-by-layer excavation construction method.

[0031] After the excavation of the foundation pit is completed, the plane position, size and base elevation of the base need to be quality inspected to ensure that the plane position meets the design requirements and meets the needs of foundation construction operations; the base elevation is allowed to deviate, and the deviation is based on the geological conditions of the base, and all reach the bedrock surface, and ensure that the geological conditions and bearing capacity of the base are consistent with the design.

[0032] Step 2: Formwork installation and pre-embedding: Use the earth cofferdam as the outer formwork to install the mold for pouring the concrete cofferdam, and pre-embed the embedded parts of the steel cofferdam in the mold;

[0033] Since the cofferdam structure of the present application is a steel-concrete composite cofferdam, its concrete cofferdam includes its side walls, back walls and part of the front wall. The pouring of the concrete cofferdam is divided into two parts. First, when pouring on land (such as the back wall), the formwork uses a large-area steel formwork and is constructed according to ordinary concrete construction methods. Second, when pouring underwater, when the foundation of the cofferdam is below the water level, the earth cofferdam in step 1 is used as the outer water-facing side formwork for construction. The steel-concrete composite cofferdam of the present application only installs the back wall, side wall and front wall of the front wall I in the formwork. After installation, it is necessary to embed the embedded parts of the steel cofferdam at the connecting end face of the front wall II and the front wall I to ensure that part of the embedded parts is cast in the front wall I and part leaks out of the front wall I to form an end that can be connected to the front wall II. It is worth noting that the embedded parts need to be firmly fixed and will not tilt during the pouring process. The embedded parts can be fixed to the bottom of the base or to the formwork. The material and thickness of the steel cofferdam embedded parts are exactly the same as those of the front wall II steel cofferdam.

[0034] Step 3: Pour concrete cofferdam: Pour concrete cofferdam in the mold installed in step 2;

[0035] The concrete cofferdam is poured in layers as a whole, and the thickness of each pouring shall not exceed 2m to prevent the earth cofferdam template on the water side from collapsing. The template for layered pouring is constructed by flipping the mold. The construction method of flipping the mold is as follows: Figure 3 As shown, first use a 2m formwork to cast three layers of standard section cofferdam concrete. When the three layers of standard section cofferdam concrete are cast, and the concrete strength and curing period reach the conditions for removing the formwork, only the formwork of the lower two standard section cofferdam concrete is removed, and the 2m formwork of the top standard section is left on the wall and is not removed, serving as the basic formwork for the second casting of the cofferdam wall formwork. The removed formwork is used to continue casting the cofferdam wall upwards. It must be removed in pieces during removal, and each removal must ensure that the removed formwork is the lowest layer of formwork. After the surface of the removed formwork is cleaned and coated with a release agent, it is lifted by a crane and installed in the position to be installed. After the installation is completed and the bottom is cleaned, the next layer of concrete is poured until the wall of the concrete cofferdam of this application is poured. During the entire process, the water in the cofferdam is not pumped out, and only the water in the cofferdam wall casting formwork is pumped out to pour the concrete.

[0036] Step 4: Setting up the steel cofferdam: Weld the steel cofferdam to the embedded parts in step 2, and set up cofferdam supports behind the steel cofferdam to complete the cofferdam construction;

[0037] After pouring is completed, the steel plate of the steel cofferdam is welded to the leaked end of the embedded parts in the front wall I. The strength of the weld must meet the pressure resistance and anti-seepage requirements in the construction environment. After welding is completed, channel steels must be set at equal intervals on the back side of the steel plate (the side away from the water body) as the rear support of the steel plate to ensure that the steel plate can provide sufficient pressure resistance. In order to ensure that there is no water seepage accident at the welding position of the embedded parts and the steel plate, when setting the channel steel as the rear support of the steel plate, it is necessary to ensure that a channel steel must be set at the weld position to cover the weld. After covering, the contact edge of the channel steel and the steel plate is also sealed by dense welding to ensure that the quality of the weld can withstand sufficient water pressure. Other channel steels and steel plates are also fixed by welding. After the construction of the channel steel and steel plates is completed, the front wall II is formed.

[0038] In this embodiment, in order to ensure the stability of the cofferdam, the structure of the front wall II steel cofferdam is composed of 20mm steel plate + 20a channel steel, the channel steels are evenly spaced, and the spacing of the evenly spaced channel steels is 1m.

[0039] Step S2, setting up internal supports: carrying out internal support construction and pumping water inside the cofferdam simultaneously in the built cofferdam. When the internal support construction is completed, the river water inside the cofferdam is just pumped out;

[0040] Due to the characteristics of this application being close to a cliff and deep water, the original ground at the front edge of the arch seat is a steep slope and cliff, resulting in insufficient width of the cofferdam foundation, and thus insufficient anti-overturning capacity of the cofferdam wall itself. Under the static pressure of high water levels, there is a risk of crushing the cofferdam. Therefore, internal supports must be added inside the cofferdam to support the cofferdam. The internal support adopts a frame structure, which includes a number of beams and columns. The columns are made of steel pipe structure, and the beams are made of I-beam structure. The I-beams and columns are used to form an integral frame inside the cofferdam to support the cofferdam. The cofferdam is fully paved so that the static pressure on the front wall can be transmitted to the back wall through the frame. The static pressure of the upper side wall and the static pressure of the lower side wall are offset by each other through the frame, making it impossible for the front wall and the side wall to be crushed by the static pressure of deep water.

[0041] The construction method of the cofferdam internal support is as follows:

[0042] N1. Column construction: hoist the columns into place according to the designed position within the cofferdam. Once all are in place, use anti-dispersion concrete to fix the columns to the base underwater.

[0043] Since the steel-concrete composite cofferdam of this application does not use concrete for bottom sealing during its construction, the bottom of the foundation pit is an uneven bedrock surface. When the columns are directly hoisted into the foundation pit and installed on the bedrock, they cannot be vertical. If the columns are not vertical, the internal structure of the frame formed will be a number of parallelogram structures. When the parallelogram structure is subjected to lateral pressure, it is easy to deform. This makes the overall support strength of the internal support insufficient and unable to provide reliable support for the cofferdam. In order to ensure that the formed internal support can provide reliable support strength, it is necessary to ensure that the columns are vertical. This application uses a steel pipe positioning construction method for the cofferdam columns to ensure the vertical installation of the columns. The specific construction method is as follows:

[0044] Step a: Set four sensors on the cofferdam as reference sensors, and use the BeiDou system to adjust three of the reference sensors to the same horizontal plane as the reference plane;

[0045] After the cofferdam is constructed, a circle is constructed with the center of the cofferdam as the center. At the intersection of the arc and the cofferdam, sensors are installed at any three points as reference sensors. When installing the reference sensors, a level (a laser level) can be used to align the three sensors. The reference sensors must be able to independently measure distances between each other or connect to the Beidou system, using the system to align the three sensors. Therefore, the reference sensors need to perform two functions: first, measure distances between each other, and second, communicate with the Beidou system. A combination solution is available: a Beidou positioning module + a ranging sensor, such as the Sinan T300 Beidou module + the SICK DL100 laser ranging sensor. Alternatively, an integrated device (with built-in ranging and Beidou positioning) can be used, such as the Huace Navigation i70 Pro. Use a level and Beidou system to ensure that the three reference sensors are on the same horizontal plane, and use this horizontal plane as the reference plane. After the three sensors on the reference plane are set up, set the fourth reference sensor vertically above any sensor. Use this fourth reference sensor to cooperate with the reference plane to establish a coordinate system inside the cofferdam.

[0046] Step b: using a crane to hoist the column into place so that the column contacts the base bedrock, and installing a sensor as a positioning sensor on the upper end of the column, and adjusting the positioning sensor so that it is on the reference plane;

[0047] The columns are installed underwater. Before hoisting the columns, sediment removal equipment is used to clear the foundation pit, exposing the bedrock surface. This ensures that the bottom of the columns will contact the bedrock surface at the bottom of the pit when hoisted into position. After the columns are hoisted into position, sensors are installed at their upper ends as positioning sensors. The positioning sensors must be selected in the same manner as the reference sensors. Therefore, the positioning sensors can directly measure distances with the reference sensors, or they can use the BeiDou system. Using three reference sensors on the reference surface to define a plane, a coordinate system is established with a fourth reference sensor. Direct distance measurements can be made between the positioning sensors to obtain the positioning sensor's coordinates. Using the plane equation Ax + By + Cz + D = 0, the positioning sensor is ensured to be on the reference surface, and the coordinates of the hoisted position within the cofferdam are consistent with the designed position coordinates. Alternatively, the BeiDou system can be used to directly confirm that the positioning sensor is on the reference surface and accurately positioned.

[0048] Step c: Install a sensor as an inclination sensor at the lower end of the column along the vertical line of the column, and use the distance between the positioning sensor, the inclination sensor, and the three reference sensors on the reference surface to determine whether the column is vertical. After verticalization, use a connecting rod to fix the column to the cofferdam or other adjacent columns to ensure that the column remains vertical;

[0049] When installing the tilt sensor, ensure that the line connecting the tilt sensor and the positioning sensor is perpendicular to the column's centerline. During actual installation, before hoisting the column, draw a straight line perpendicular to the column's centerline and install the positioning sensor and tilt sensor directly on either end of the line. When the lower end of the column contacts the bedrock, the column may be completely submerged due to the unevenness of the bedrock surface. To do this, weld angle iron along a line perpendicular to the column's centerline and install the positioning sensor on the angle iron.

[0050] The tilt sensor and the reference sensor have the same model. Therefore, the distance between the tilt sensor, the reference sensor and the positioning sensor can be tested, and they can also be connected to the Beidou system to determine the position.

[0051] Using the positioning sensor, tilt sensor, and three reference sensors on the reference surface, we can determine the distance a between the tilt sensor and the positioning sensor; the distances b1, b2, and b3 between the positioning sensor and the four reference sensors; and the distances c1, c2, and c3 between the tilt sensor and the reference sensors. As long as a, b1, and c1, a, b2, and c2 are all Pythagorean trigonometric, the columns will be vertical. Beidou positioning can also be used to connect to each sensor to perform distance calculations and determine the values of a, b, and c. Ensure the columns are vertical. After ensuring the columns are vertical, use connecting rods to secure them to the cofferdam. The column installation sequence is as follows: first install the circle of columns closest to the cofferdam. After this circle of columns is installed, proceed in a circular pattern toward the center of the cofferdam. Secure the outermost circle of columns to the cofferdam, and then secure the inner circle of columns to the adjacent columns until installation is complete.

[0052] Step d: After all the columns in the cofferdam are vertically installed using step c, the bottom of the columns are fixed to the bedrock using bottom sealing concrete to form a flat foundation pit bottom foundation.

[0053] Before using concrete bottom seal construction, it is necessary to confirm that the columns are vertical again. The bottom seal concrete is constructed underwater using C40 underwater anti-dispersion concrete. During construction, the bottom sediment and mud are cleaned again to ensure that the thickness of the sediment at the bottom of the arch seat is not greater than 1cm before pouring concrete. Concrete pouring must be carried out in a timely manner to avoid mud sedimentation. During construction, a boom pump is used for pouring, and a crane is used to lift the conduit and hopper. The conduit and hopper can be moved in water. When lowering the conduit, it must first be inserted into the bottom of the foundation pit, and then raised 30-50cm as concrete construction space. Divers roughly control the elevation of the concrete to ensure that the concrete pouring elevation is basically consistent. After pouring is completed, the column and the bedrock form a fixed structure, its stability is enhanced, and it meets the requirements for internal support settings.

[0054] During the entire column positioning construction, the coordinates are mainly provided by distance measurement between sensors, and the data transmitted by the Beidou system is used as an early warning aid.

[0055] N2. Beam support construction: After the columns are fixed, beams are laid between the columns to form a frame structure. The two ends of the beams are fixedly connected to the adjacent columns. The laying order is from top to bottom. Each time a layer of beams is laid, a layer of accumulated water in the cofferdam is pumped out. This is repeated alternately until the water is finally pumped to the bottom of the foundation pit. The construction of all beams is completed, and the outermost layer of beams is directly fixed to the cofferdam.

[0056] After the columns are secured with concrete at the bottom, I-beams are used as crossbeams between them to form the overall frame structure. Construction proceeds from top to bottom, from the center outward to the sides, first vertically and then horizontally. Because there is water in the foundation pit, the I-beams can be installed while pumping water. During the first pumping, the first layer of I-beams is installed. Once the first layer is installed, the water is pumped again and the second layer is installed. This cycle is repeated until the water is pumped down to the bottom of the pit, completing the installation of all I-beams. Once all crossbeams are installed, the internal supports will completely fill the cofferdam space.

[0057] Step S3, casting the arch seat: after the internal support is set up, the arch seat casting is completed before the target low water level period.

[0058] Since all construction work on Section 1# needs to be completed within the target low water level window, the arch seat casting construction must be completed during the high water level period, and at the latest before the high water level drops to the low water level period. Arch seat casting construction: Determine the arch seat construction position within the cofferdam where the internal support structure is completed in S2. Use the internal support frame structure as a construction channel to cast the arch seat. Cast the internal support directly into the arch seat where the arch seat and the internal support overlap.

[0059] Based on the designed arch seat position, the arch seat construction location is determined and the arch seat casting construction is carried out. The arch seat casting construction includes the steps of reinforcing steel and cooling pipe laying, formwork installation, concrete pouring, formwork removal, and concrete curing. Because the internal support is a frame structure, the space between the frames can be used for construction. Therefore, steel plates can be laid on the internal support beams to form a layered construction platform, through which construction can be carried out.

[0060] Rebar construction and cooling pipe laying: After the bottom is sealed, the arch seat reinforcement is set in the foundation pit, and the cooling pipe is installed. If the cooling pipe conflicts with the arch seat reinforcement, the cooling pipe is moved to ensure the shape of the arch seat reinforcement.

[0061] The arch seat reinforcement is formed by one-time binding. During the reinforcement binding process, a rigid skeleton must be installed first, and some temporary supports must be added as needed to ensure that the reinforcement binding can be straight and straight without deformation. The reinforcement binding is divided into blocks and bound from one end to the other to ensure that personnel can construct in the three-way reinforcement binding. During the reinforcement binding process, some positioning reinforcements must be spot welded firmly to avoid large deformation of the lower reinforcement when constructing the upper reinforcement. For the embedded reinforcement of the junction pier and arch ring, a positioning frame should be used to ensure the accurate position of the embedded reinforcement.

[0062] In order to reduce the hydration heat generated during the construction of the arch seat concrete and prevent temperature difference cracks in the concrete, a circulating cooling water pipe is installed in the arch seat. The circulating cooling pipe uses an ordinary welded steel pipe with good thermal conductivity and a certain strength. The steel pipe itself has great strength and rigidity. It is welded to the arch seat steel bar (including the rigid skeleton) during installation. If necessary, it is assisted by erection steel bars to ensure the forming effect of the cooling pipe, but the arch seat steel bar must not be moved. In case of conflict, the cooling pipe position must be moved to ensure the shape of the arch seat steel bar. The arch seat cooling pipe is set at every 0.8m, and the spacing between the cooling pipes on the same layer is 60cm. The cooling pipes of the two adjacent layers are set vertically.

[0063] Formwork installation: Use lifting equipment to lift the arch seat casting formwork to the arch seat installation position, insert it between the beams, fix the formwork to the columns, and use the internal support as the fixed structure of the formwork to facilitate the installation of the formwork. The formwork needs to be customized so that it can perfectly fit into the space of the internal support frame.

[0064] Concrete pouring: Use a concrete pump to pour the arch seat concrete. The strength of the poured concrete must meet the requirements of C40 large-volume concrete. The slump of the concrete mix ratio should be designed to be between 16cm-20cm. The initial setting time of the concrete is 5-6 hours, and the final setting time is 13-14 hours.

[0065] Formwork removal and concrete curing: After pouring the concrete in S5, when the concrete strength reaches 4-5Mpa, the formwork can be removed by crane. After the formwork is removed, water should be sprinkled on the concrete surface for curing.

[0066] The entire process should follow the temperature control standards for large-volume concrete, and cooling pipes should be used to ensure that the hydration heat is well released and that the cast arch seat meets the design standards.

[0067] Step S4, 1# segment arch construction: dismantle the steel structure and complete the 1# segment construction during the target low water level period.

[0068] After the construction of the arch seat is completed, wait for the arrival of the target low water level period. When the water level line of the high water level period gradually drops, the steel structure of the front wall of the cofferdam exposed above the water level line can be quickly cut with a cutting machine. When the water level line reaches the low water level period, the demolition of the front wall of the cofferdam is just completed, freeing up the construction space for the 1# section. It is also possible to use a cutting machine to quickly remove the front wall of the cofferdam after the low water level period. The construction of the 1# section is consistent with the existing technology, and the construction is carried out by quickly pouring the formwork. It is worth noting that the construction of the 1# section needs to be completed before the high water level period arrives to avoid the water level rising and flowing back into the cofferdam, causing the construction of the 1# section to be underwater and then interrupted.

[0069] The above is only an embodiment of the present invention, and the common knowledge such as the specific structure and characteristics of the scheme is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the structure of the present invention, several variations and improvements can be made, which should also be regarded as the scope of protection of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. The construction method of arch cofferdam in deep water area near cliff is characterized by: The following steps are involved: Step 1: Construction of cofferdam foundation pit: Use survey control points and infill points to stake out the location of the cofferdam construction, determine the boundary of the cofferdam foundation pit, and excavate the cofferdam foundation pit; Step 2: Formwork installation and pre-embedding: Use the earth cofferdam as the outer formwork to install the mold for pouring the concrete cofferdam, and pre-embed the embedded parts of the steel cofferdam in the mold; Step 3: Pour concrete cofferdam: Pour concrete cofferdam in the mold installed in step 2; Step 4. Setting up the steel cofferdam: Weld the steel cofferdam to the embedded parts in step 2, and set up cofferdam supports behind the steel cofferdam to complete the construction of the cofferdam.

2. The method for constructing an abutment cofferdam in a deep-water area near a cliff according to claim 1, characterized in that: In step 4, the steel cofferdam includes a steel plate and a channel steel provided at the rear side of the steel plate as a support. The steel plate is welded to the embedded parts, and the welds between the embedded parts are provided with a channel steel covering the welds.

3. The method for constructing an abutment cofferdam in a cliff-side deep-water area according to claim 2, characterized in that: An internal support of a frame structure is provided in the cofferdam.

4. The method for constructing an abutment cofferdam in a cliff-side deep-water area according to claim 3, characterized in that: The inner support includes columns and beams, and the construction method includes the following steps: N1. Column construction: hoist the columns into place according to the designed position within the cofferdam. Once all are in place, use anti-dispersion concrete to fix the columns to the base underwater. N2. Beam support construction: After the columns are fixed, beams are laid between the columns to form a frame structure. The two ends of the beams are fixedly connected to the adjacent columns. The laying order is from top to bottom. Each time a layer of beams is laid, a layer of accumulated water in the cofferdam is pumped out. This is repeated alternately until the water is finally pumped to the bottom of the foundation pit. The construction of all beams is completed, and the outermost layer of beams is directly fixed to the cofferdam.

5. The method for constructing an abutment cofferdam in a deep-water area near a cliff according to claim 4, characterized in that: The column positioning construction method comprises the following steps: Step a: Set four sensors on the cofferdam as reference sensors, and use the Beidou system to adjust three of the reference sensors to the same horizontal plane as the reference plane; Step b: using a crane to hoist the column into place so that the column contacts the base bedrock, and installing a sensor as a positioning sensor on the upper end of the column, and adjusting the positioning sensor so that it is on the reference plane; Step c: Install a sensor as an inclination sensor at the lower end of the column along the vertical line of the column, and use the distance between the positioning sensor, the inclination sensor, and the three reference sensors on the reference surface to determine whether the column is vertical. After verticalization, use a connecting rod to fix the column to the cofferdam or other adjacent columns to ensure that the column remains vertical; Step d: After all the columns in the cofferdam are vertically installed using step c, the bottom of the columns are fixed to the bedrock using bottom sealing concrete to form a flat foundation pit bottom foundation.

6. The method for constructing an abutment cofferdam in a deep-water area near a cliff according to claim 5, characterized in that: The inner support can be used as a construction channel for subsequent arch seat construction.