Construction technology for quickly erecting wharf prefabricated parts through bridge girder erection machine

By quickly lifting prefabricated longitudinal beam components and combining them with cast-in-place structures, the problem of low construction efficiency of large-area docks is solved, and efficient and safe construction results are achieved.

CN120486301APending Publication Date: 2025-08-15CHINA RAILWAY GUANGZHOU ENG GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510549271.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-28
Publication Date
2025-08-15

AI Technical Summary

Technical Problem

The existing lifting methods are difficult to efficiently adapt to large-area dock construction, and there are problems of low construction efficiency and poor stability.

Method used

The prefabricated longitudinal beam members are quickly lifted by a bridge stud, and combined with the cast-in-place structure, forming a lower cross beam and a prefabricated longitudinal beam member. Then the prefabricated panel is lifted, and the pull-up assembly and the lower support assembly are used to fix the ship-to-be-bearing member, and the rapid construction is achieved through the cast-in-place connection section.

Benefits of technology

The lifting efficiency and construction quality of prefabricated components are improved, the connection strength and construction safety are ensured, materials are saved, and construction efficiency and accuracy are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120486301A_ABST
    Figure CN120486301A_ABST
Patent Text Reader

Abstract

The invention discloses a construction process for quickly erecting wharf prefabricated parts by using a bridge girder erection machine, which comprises the following steps of: S1, sinking PHC (Prestressed High-strength Concrete) piles to form a bent frame, then constructing lower cross beams on the PHC piles, and forming a plurality of rows of lower cross beams; s2, assembling a bridge girder erection machine, supporting hydraulic supporting legs of the bridge girder erection machine on the lower cross beams, and enabling the bridge girder erection machine to move along the arrangement direction of the lower cross beams; s3, the prefabricated longitudinal beam components are hoisted through a bridge girder erection machine and placed on the lower cross beams, and the two ends of each prefabricated longitudinal beam component are placed on the two adjacent lower cross beams correspondingly; s4, an upper cross beam is constructed on the lower cross beam, so that the upper cross beam, the lower cross beam and the prefabricated longitudinal beam component form a whole; and S5, the prefabricated panels are hoisted through a bridge girder erection machine, the prefabricated panels are placed on the prefabricated longitudinal beams and the upper cross beams, and the prefabricated panels are connected with the prefabricated longitudinal beams and the upper cross beams.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of wharf construction, and in particular to a construction process for rapidly erecting prefabricated wharf components using a bridge erection machine. Background Art

[0002] During dock construction, cranes are usually installed using truck cranes, gantry cranes, floating cranes, or tower cranes. However, when the area to be constructed is large, gantry cranes and tower cranes are difficult to adapt to. Floating cranes have low lifting efficiency and are greatly affected by tidal currents, making them less stable. Truck cranes require construction of a portion of the area before they can proceed with subsequent lifting using the area already constructed, resulting in a longer construction period.

[0003] Therefore, there is an urgent need for a construction technology that can adapt to large-scale construction of docks. Summary of the Invention

[0004] The purpose of this application is to provide a construction process for quickly erecting prefabricated components of a wharf using a bridge-building machine, so as to improve the problem that the existing lifting method is difficult to efficiently adapt to wharves with larger construction areas.

[0005] In the first aspect, the present application provides a construction process for rapidly erecting prefabricated components for a dock using a bridge erection machine, which adopts the following technical solutions: A construction process for rapidly erecting prefabricated components of a wharf using a bridge erection machine comprises the following steps: S1. Sink the PHC piles to form a bent frame, and then construct lower beams on the PHC piles to form several rows of lower beams; S2. Assemble the bridge erection machine, with its hydraulic legs supported on the lower crossbeam, and the bridge erection machine capable of moving along the arrangement direction of the lower crossbeam; S3. Use a bridge erection machine to hoist the prefabricated longitudinal beam components and place the prefabricated longitudinal beam components on the lower cross beams, with both ends of each prefabricated longitudinal beam component being placed on two adjacent lower cross beams respectively; S4. Construct an upper crossbeam on the lower crossbeam so that the upper crossbeam, the lower crossbeam and the prefabricated longitudinal beam components form an integral whole; S5. Use a bridge-erecting machine to hoist the prefabricated panels, place them on the prefabricated longitudinal beams and upper cross beams, and connect the prefabricated panels with the prefabricated longitudinal beams and upper cross beams.

[0006] By adopting the above technical solution, after the cast-in-place lower crossbeam is formed, the prefabricated longitudinal beam components are quickly hoisted by a bridge-erecting machine, and then the upper crossbeam is cast in place, so that the lower crossbeam and the prefabricated longitudinal beam components are integrated. The prefabricated panels are then hoisted by the bridge-erecting machine. The combination of cast-in-place structure and prefabricated components enables rapid construction while ensuring construction quality. The bridge-erecting machine can greatly improve the hoisting efficiency of prefabricated components, and the upper crossbeam can be cast in place while the bridge-erecting machine works simultaneously, further improving construction efficiency.

[0007] Optionally, in step S4, the mooring component is hoisted, and a connecting section is cast between the mooring component and the corresponding lower crossbeam, so that the mooring component and the corresponding mooring component are integrated.

[0008] Through the above technical solution, the mooring components are prefabricated to improve construction efficiency, and then the mooring components are connected to the lower beam through cast-in-place connecting sections, which improves construction efficiency while ensuring the connection strength between the mooring components and the lower beam.

[0009] Optionally, in step S4, a connecting section is cast through a connecting mold, and the connecting mold includes a positioning channel steel, an upper pull assembly and a lower support assembly. Two positioning channel steels are provided and are both installed on the lower crossbeam. One end of the upper pull assembly is connected to the positioning channel steel, and the other end is connected to the mooring component. One end of the lower support assembly is connected to the PHC pile, and the other end is connected to the mooring component.

[0010] Through the above technical solution, the upper pulling assembly cooperates with the lower supporting assembly to achieve temporary fixation of the mooring component so as to cast the connecting section and ensure construction safety.

[0011] Optionally, the top of the mooring component is connected to a first formwork, a second formwork and a third formwork, and a casting area for casting the connecting section is formed between the first formwork, the second formwork, the third formwork and the side wall of the lower cross beam; a lifting ring is connected to the side wall of the first formwork and the third formwork respectively, so that the mooring component can be lifted by a bridge crane; when the bridge crane lifts the mooring component, the bridge crane is connected to the two lifting rings through two lifting ropes, and the two lifting ropes are located on the outside of the two positioning channel steels.

[0012] Through the above technical solution, the first formwork, the second formwork and the third formwork are set on the mooring component, the top surface of the mooring component is used as the bottom formwork, and the side wall of the lower beam is used as the side formwork, which saves materials and ensures the accuracy of the formwork, thereby improving construction efficiency and quality.

[0013] Optionally, the lower support assembly includes a clamp, a first sleeve and a first screw, the clamp is fixedly connected to the PHC pile, one end of the first sleeve is hinged to the mooring assembly, and the other end is threadedly connected to the first screw, one end of the first screw away from the first sleeve is ball-jointed to the clamp, and a first rotating nut is fixedly connected to the first screw.

[0014] Through the above technical solution, during installation, the clamp is first fixed on the PHC pile, and then the first screw sleeve is adjusted by the first rotating nut, and then the first screw sleeve is connected to the hole reserved for the mooring component. At the same time, the first rotating nut can be further adjusted to form effective support for the mooring component.

[0015] Optionally, the pull-up assembly includes an anchor rod and an anchor, the anchor rod is fixedly connected to the mooring component, the anchor is provided on the positioning channel steel, the anchor can adjust its position relative to the positioning channel steel along the width direction of the positioning channel steel, and the anchor is used to anchor the anchor rod.

[0016] By adopting the above technical solution, the coordination between the anchor rod and the anchor device generates tension on the mooring member, so as to facilitate the coordination of the lower support assembly to form an effective support fixation. At the same time, the anchor device can adjust its position to better coordinate with the anchor rod.

[0017] Optionally, the anchor includes an anchor block, an anchor barrel and an anchor plate, the anchor block is connected to the positioning channel steel, two anchor barrels are provided, and both are hinged to the anchor block, the two anchor barrels are semicircular, the side wall of the anchor barrel is provided with a conical surface, each of the anchor barrels is provided with a plurality of anchor plates, and the plurality of anchor plates slide on the conical surface along the axis of the anchor barrel; the anchor barrel has a closed state and an open state, when the anchor barrel is in the closed state, the two anchor barrels form a cylindrical shape, and the plurality of anchor plates anchor the anchor rod, and a locking member is provided between the two anchor barrels for maintaining the anchor barrel in a closed state.

[0018] By adopting the above technical solution, after the mooring component is moved into place, the anchor barrel is moved and switched from the open state to the closed state so as to lock the anchor rod. There is no need to pass the anchor rod through the anchor barrel along the axial direction of the anchor barrel. The anchor barrel can be installed from one side of the anchor rod, thereby improving the convenience of installation.

[0019] Optionally, the locking member includes a locking cover and a locking block, the locking cover is fixedly connected to one anchor cylinder, the locking block is fixedly connected to the other anchor cylinder, the locking block is provided with a sliding groove, a slider slides in the sliding groove, the locking cover is provided with a slot for the slider to be inserted, and a compression spring is provided in the sliding groove, one end of the compression spring abuts against an end of the slider away from the slot, and the other end abuts against an end of the slide away from the slot, a shift rod is fixedly connected to the side wall of the slider, the end of the shift rod away from the slider passes through the locking block, and the locking block is provided with a shift groove for the shift rod to slide.

[0020] Through the above technical solution, after the two anchor cylinders enter the closed state, the slide groove and the card slot are aligned, and the slider is in the card slot and the slide groove at the same time, thereby locking the two anchor cylinders. The compression spring is used to prevent the slider from escaping from the card slot, and the lever is used to facilitate adjusting the position of the slider so that the slider can escaping from the card slot, thereby facilitating the separation of the two anchor cylinders and entering the open state.

[0021] Optionally, a diagonal brace is hinged on the mooring member, and one end of the diagonal brace away from the mooring member is hinged to the lower crossbeam.

[0022] Optionally, a first horizontally arranged steel bar is reserved on the side wall of the lower cross beam, and a second vertically arranged steel bar is reserved on the top surface of the mooring member, and the second steel bar is in an inverted U shape. When the mooring member is hoisted, the mooring member is hoisted until the top surface of the first template is flush with the top surface of the lower cross beam, and then the mooring member is moved laterally toward the lower cross beam until the first template and the third template abut against the lower cross beam. During the lateral movement of the mooring member, the first steel bar is inserted into the second steel bar, and the first steel bar and the second steel bar are connected by steel wire binding.

[0023] By adopting the above technical solution, the mooring component is first hoisted in the vertical direction and then moved horizontally, which can improve the placement accuracy of the mooring component. At the same time, it is convenient to put the second steel bar on the first steel bar. The connection between the second steel bar and the first steel bar can cooperate with the diagonal rod to further improve the connection reliability and stability between the connecting section and the lower beam and the mooring component.

[0024] In summary, this application includes at least one of the following beneficial technical effects: 1. After the cast-in-place lower crossbeam is formed, the prefabricated longitudinal beam components are quickly hoisted using a bridge-erecting machine, and then the upper crossbeam is cast in-place, so that the lower crossbeam and the prefabricated longitudinal beam components form a whole. The prefabricated panels are then hoisted using the bridge-erecting machine. The combination of cast-in-place structure and prefabricated components enables rapid construction while ensuring construction quality. The bridge-erecting machine can significantly improve the hoisting efficiency of prefabricated components, and the bridge-erecting machine can work simultaneously while the upper crossbeam is cast in-place, further improving construction efficiency. 2. The use of prefabricated mooring components can improve construction efficiency. The mooring components are then connected to the lower beam through cast-in-place connecting sections, which improves construction efficiency while ensuring the connection strength between the mooring components and the lower beam; 3. The upper pull assembly cooperates with the lower support assembly to achieve temporary fixation of the mooring components so that the connecting section can be poured to ensure construction safety; 4. Place the first formwork, the second formwork, and the third formwork on the berthing member, using the top surface of the berthing member as the bottom formwork and the side wall of the lower crossbeam as the side formwork, saving materials while ensuring the accuracy of the formwork, improving construction efficiency and quality; 5. During installation, first fix the clamp on the PHC pile, then adjust the distance of the first screw sleeve by turning the first screw sleeve, and then connect the first screw sleeve to the hole reserved in the mooring component. At the same time, you can continue to adjust the first screw sleeve to form an effective support for the mooring component. 6. Through the coordination of the anchor rod and the anchor, a tensile force is generated on the mooring component, so that the lower support assembly cooperates and forms an effective support fixation. At the same time, the anchor can be adjusted to better cooperate with the anchor rod; 7. After the mooring member is moved into position, the anchor barrel is moved and switched from the open state to the closed state to lock the anchor rod. There is no need to pass the anchor rod through the anchor barrel along the axial direction. The anchor barrel can be installed from one side of the anchor rod, which improves the convenience of installation. 8. When the two anchor cylinders enter the closed state, the chute and the clamping slot are aligned, and the slider is in both the clamping slot and the chute, thereby locking the two anchor cylinders. The compression spring is used to prevent the slider from leaving the clamping slot, and the lever is used to adjust the position of the slider so that the slider can leave the clamping slot, thereby facilitating the separation of the two anchor cylinders into the open state. 9. First hoist the mooring component in the vertical direction, and then move the component horizontally. This can improve the placement accuracy of the mooring component and make it easier to put the second steel bar on the first steel bar. The connection between the second steel bar and the first steel bar can cooperate with the diagonal rod to further improve the connection reliability and stability between the connecting section and the lower beam and the mooring component. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 The present invention is a schematic diagram of a construction process for rapidly erecting prefabricated components of a wharf using a bridge erection machine, showing the erection of a lower crossbeam.

[0026] Figure 2 The present invention is a schematic diagram of a construction process for rapidly erecting prefabricated wharf components using a bridge erection machine, showing the erection of prefabricated longitudinal beam components.

[0027] Figure 3 The present invention is a schematic diagram of the construction of an upper crossbeam in a construction process for rapidly erecting prefabricated components of a wharf using a bridge erection machine.

[0028] Figure 4 It is a schematic diagram of erecting prefabricated panels in a construction process for rapidly erecting prefabricated components of a wharf using a bridge erection machine in the present invention.

[0029] Figure 5 The present invention is a schematic diagram of a construction process for rapidly erecting prefabricated dock components using a bridge erection machine, which illustrates the erection of mooring components.

[0030] Figure 6 It is a three-dimensional schematic diagram of the connection mold in the present invention.

[0031] Figure 7 It is a three-dimensional schematic diagram embodying the first steel bar and the second steel bar in the present invention.

[0032] Figure 8 yes Figure 6 A partial enlarged view of part A in the middle.

[0033] Figure 9 It is a structural schematic diagram of the anchor in the present invention.

[0034] Figure 10 It is a schematic cross-sectional view of the locking member in the present invention.

[0035] Figure 11 It is a three-dimensional schematic diagram of a part of the bridge erecting machine in the present invention.

[0036] Figure 12 It is a cross-sectional schematic diagram of the clamp in the first embodiment of the present invention.

[0037] Figure 13 It is a schematic diagram showing the cross section of the prefabricated longitudinal beam component in the present invention.

[0038] Figure 14 It is a three-dimensional schematic diagram of the clamp in the second embodiment of the present invention.

[0039] Figure 15 It is a schematic diagram of step S1 in a lifting process according to the present invention.

[0040] Figure 16 It is a schematic diagram of step S2 in a lifting process according to the present invention.

[0041] Figure 17 It is a schematic diagram of step S3 in a lifting process according to the present invention.

[0042] Figure 18 It is a schematic diagram of step S4 in a lifting process according to the present invention.

[0043] In the figure, 1, PHC pile; 2, lower crossbeam; 21, first steel bar; 22, connecting section; 3, bridge erection machine; 31, bridge frame; 32, hydraulic support leg; 33, mobile frame; 34, crane; 35, spreader; 36, connecting assembly; 361, second screw sleeve; 362, second screw rod; 363, second rotating nut; 37, jack; 38, assembly block; 39, clamp; 391, first assembly plate; 392, inclined clamp; 393, vertical surface; 394, second assembly plate; 395, sling; 4, prefabricated longitudinal beam component; 5, prefabricated panel; 6, upper crossbeam; 7, mooring component; 71, first formwork; 72, second formwork; 73, third formwork; 74, inclined tie rod; 75, 8. Second steel bar; 8. Connecting mold; 81. Positioning channel steel; 811. I-beam; 812. Embedded screw; 813. Fixed block; 82. Pull-up assembly; 821. Anchor block; 8211. Moving rod; 832. Anchor cylinder; 8321. Conical surface; 8322. T-slot; 833. Anchor plate; 8331. T-block; 834. Anchor rod; 835. Locking piece; 8351. Locking cover; 8352. Locking block; 8353. Slide; 8354. Slider; 8355. Compression spring; 8356. Push rod; 8357. Push groove; 8358. Card slot; 84. Lower support assembly; 841. Hoop; 842. First screw sleeve; 843. First screw; 844. First rotating nut. DETAILED DESCRIPTION

[0044] The present invention will now be described in further detail with reference to the accompanying drawings, which are simplified schematic diagrams that illustrate the basic structure of the present invention in a schematic manner.

[0045] In the description of the present invention, it should be understood that the terms "center," "longitudinal," "transverse," "length," "width," "thickness," "upper," "lower," "front," "back," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," "circumferential," and the like, indicating positions or relationships, are based on the positions or relationships shown in the accompanying drawings and are intended solely to facilitate the description of the present invention and simplify the description. They are not intended to indicate or imply that the devices or components referred to must have, be constructed, or operate in a specific orientation, and therefore should not be construed as limiting the present invention. Furthermore, features defined as "first" or "second" may explicitly or implicitly include one or more of such features. In the description of the present invention, unless otherwise specified, "plurality" means two or more. In the description of the present invention, it should be noted that, unless otherwise specified or limited, the terms "mounted," "connected," and "connected" should be broadly understood, for example, to mean fixed, removable, or integral; mechanically or electrically connected; directly or indirectly through an intermediary; or internally connected between two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0046] Example 1 A construction process for quickly erecting prefabricated components of a wharf using a bridge erection machine, referring to Figure 1 To Figure ,4, the following steps are included: S1, sinking the PHC piles 1 to form a bent frame, and then constructing the lower cross beams 2 on the PHC piles 1 to form several rows of lower cross beams 2; S2, assembling the bridge erection machine 3, the hydraulic legs 32 of the bridge erection machine 3 are supported on the lower crossbeam 2, and the bridge erection machine 3 can move along the arrangement direction of the lower crossbeam 2; S3, hoisting the prefabricated longitudinal beam components 4 by the bridge erection machine 3, placing the prefabricated longitudinal beam components 4 on the lower cross beam 2, with both ends of each prefabricated longitudinal beam component 4 respectively placed on two adjacent lower cross beams 2; S4. Construction: Construct the upper crossbeam 6 (the yellow part in the figure is the upper crossbeam 6) on the lower crossbeam 2, so that the upper crossbeam 6, the lower crossbeam 2 and the prefabricated longitudinal beam member 4 form a whole; S5. Hoist the prefabricated panel 5 by the bridge-erecting machine 3, place the prefabricated panel 5 on the prefabricated longitudinal beam and the upper cross beam 6, and connect the prefabricated panel 5 with the prefabricated longitudinal beam and the upper cross beam 6.

[0047] After the cast-in-place lower crossbeam 2 is formed, the prefabricated longitudinal beam component 4 is quickly hoisted by using the bridge-erecting machine 3, and then the upper crossbeam 6 is cast in place, so that the lower crossbeam 2 and the prefabricated longitudinal beam component 4 are formed into one body, and then the prefabricated panel 5 is hoisted by the bridge-erecting machine 3. The combination of cast-in-place structure and prefabricated components can achieve rapid construction while ensuring construction quality. The bridge-erecting machine 3 can greatly improve the hoisting efficiency of prefabricated components, and the bridge-erecting machine 3 can work simultaneously while the upper crossbeam 6 is cast in place, further improving construction efficiency.

[0048] Specifically, in step S4, the mooring member 7 is hoisted, and a connecting section 22 is cast between the mooring member 7 and the corresponding lower crossbeam 2 to form an integral body with the mooring member 7. The mooring member 7 is prefabricated to improve construction efficiency. The mooring member 7 is then connected to the lower crossbeam 2 via the cast-in-place connecting section 22, thereby improving construction efficiency while ensuring the connection strength between the mooring member 7 and the lower crossbeam 2.

[0049] More specifically, refer to Figures 5 to 10 When pouring the connecting section 22, the connecting section 22 is poured through the connecting mold 8. The connecting mold 8 includes a positioning channel steel 81, an upper pull assembly 82 and a lower support assembly 84. Two positioning channel steels 81 are provided, and both are installed on the lower crossbeam 2. One end of the upper pull assembly 82 is connected to the positioning channel steel 81, and the other end is connected to the mooring member 7. One end of the lower support assembly 84 is connected to the PHC pile 1, and the other end is connected to the mooring member 7. The upper pull assembly 82 cooperates with the lower support assembly 84 to achieve temporary fixation of the mooring member 7, so that the connecting section 22 can be poured to ensure construction safety. The positioning channel steel 81 and the lower crossbeam 2 are temporarily provided with an I-beam 811. At the same time, the positioning channel steel 81 is connected to the embedded screw 812 on the lower crossbeam 2 through a nut to achieve the fixation of the positioning channel steel 81.

[0050] The top of the docking member 7 is connected to a first formwork 71, a second formwork 72, and a third formwork 73. A casting area for casting the connecting section 22 is formed between the first formwork 71, the second formwork 72, the third formwork 73, and the side wall of the lower cross beam 2. A lifting ring is connected to the side wall of each of the first formwork 71 and the third formwork 73, so that the docking member 7 can be hoisted by the bridge erection machine 3. When the bridge erection machine 3 hoists the docking member 7, the bridge erection machine 3 is connected to the two lifting rings through two lifting ropes, and the two lifting ropes are located on the outside of the two positioning channel steels 81. The first formwork 71, the second formwork 72, and the third formwork 73 are set on the docking member 7, and the top surface of the docking member 7 is used as the bottom formwork, and the side wall of the lower cross beam 2 is used as the side formwork, which saves materials, ensures the accuracy of the formwork, and improves construction efficiency and quality.

[0051] The lower support assembly 84 includes a clamp 841, a first screw sleeve 842 and a first screw rod 843. The clamp 841 is fixedly connected to the PHC pile 1. One end of the first screw sleeve 842 is hinged to the mooring assembly, and the other end is threadedly connected to the first screw rod 843. The end of the first screw rod 843 away from the first screw sleeve 842 is ball-jointed with the clamp 841. The first screw rod 843 is fixedly connected to the first rotating nut 844. During installation, the clamp 841 is first fixedly installed on the PHC pile 1, and then the first rotating nut 844 is used to adjust the distance between the first screw sleeve 842 and the first screw sleeve 842. The first screw sleeve 842 is then connected to the hole reserved for the mooring member 7. At the same time, the first rotating nut 844 can be further adjusted to form an effective support for the mooring member 7.

[0052] The pull-up assembly 82 includes an anchor rod 834 and an anchor. The anchor rod 834 is fixedly connected to the mooring member 7. The anchor is provided on the positioning channel steel 81. The anchor can be adjusted relative to the positioning channel steel 81 along the width direction of the positioning channel steel 81. The anchor is used to anchor the anchor rod 834. The cooperation between the anchor rod 834 and the anchor generates a pulling force on the mooring member 7, so that the lower support assembly 84 cooperates to form an effective support and fixation. At the same time, the anchor can be adjusted to better cooperate with the anchor rod 834.

[0053] The anchor system includes an anchor block 821, an anchor cylinder 832, and anchor plates 833. The anchor block 821 is connected to the positioning channel steel 81. Two anchor cylinders 832 are provided, both hingedly connected to the anchor block 821. A movable rod 8211 is fixedly connected to the anchor block 821, and a fixed block 813 is fixedly connected to the positioning channel steel 81. The movable rod 8211 is inserted through the fixed block 813, and a bolt is threaded onto the fixed block 813 to lock the movable rod 8211. Both anchor cylinders 832 are semicircular in shape, with a tapered surface 8321 on their sidewalls. Each anchor cylinder 832 is equipped with multiple anchor plates 833. These multiple anchor plates 833 slide along the axis of the anchor cylinder 832 on the tapered surface 8321, and the outer walls of the anchor plates 833 are aligned with the tapered surface 8321 of the anchor cylinder 832. A T-shaped block 8331 is fixedly connected to the outer wall of the anchor plate 833. A T-shaped slot 8322 is provided on the conical surface 8321 of the anchor barrel 832 for the T-shaped slider 8354 to slide, allowing the anchor plate 833 to slide relative to the anchor barrel 832. The anchor barrel 832 has a closed state and an open state. When the anchor barrel 832 is in the closed state, the two anchor barrels 832 form a cylindrical shape, and the multiple anchor plates 833 anchor the anchor rod 834. A locking member 835 is provided between the two anchor barrels 832 to maintain the closed state of the anchor barrels 832. After the mooring member 7 is moved into position, the anchor barrel 832 is moved again and switched from the open state to the closed state to lock the anchor rod 834. The anchor rod 834 does not need to be passed through the anchor barrel 832 along its axial direction. The anchor barrel 832 can be installed from one side of the anchor rod 834, improving installation convenience.

[0054] The locking piece 835 includes a locking cover 8351 and a locking block 8352. The locking cover 8351 is fixedly connected to one anchor cylinder 832, and the locking block 8352 is fixedly connected to the other anchor cylinder 832. A sliding groove 8353 is provided on the locking block 8352, and a slider 8354 slides in the sliding groove 8353. The locking cover 8351 is provided with a slot 8358 for the slider 8354 to be inserted, and a compression spring 8355 is provided in the sliding groove 8353. One end of the compression spring 8355 abuts against the end of the slider 8354 away from the slot 8358, and the other end abuts against the end of the sliding groove 8353 away from the slot 8358. A detent rod 8356 is fixedly connected to the side wall of the slider 8354, and the end of the detent rod 8356 away from the slider 8354 passes through the locking block 8352, and the locking block 8352 is provided with a detent groove 8357 for the detent rod 8356 to slide. After the two anchor cylinders 832 enter the closed state, the slide groove 8353 is aligned with the card slot 8358, and the slider 8354 is in the card slot 8358 and the slide groove 8353 at the same time, thereby locking the two anchor cylinders 832. The compression spring 8355 is used to prevent the slider 8354 from disengaging from the card slot 8358, and the lever 8356 is used to facilitate the adjustment of the position of the slider 8354 so that the slider 8354 disengages from the card slot 8358, thereby facilitating the separation of the two anchor cylinders 832 and entering the open state.

[0055] In addition, a diagonal brace 74 is hingedly connected to the mooring member 7. The end of the diagonal brace 74, which is away from the mooring member 7, is hingedly connected to the side wall of the lower crossbeam 2. The diagonal brace 74 can further enhance the stability of the mooring member 7. At the same time, the diagonal brace 74 also serves as the skeleton of the connecting section 22, improving the strength and reliability of the connection between the connecting section 22, the lower crossbeam 2, and the mooring member 7. After construction is completed, the positioning channel steel 81 and the upper pull assembly 82 are removed, but the lower support assembly 84 is not removed.

[0056] It should be noted that a horizontally arranged first steel bar 21 is reserved on the side wall of the lower cross beam 2, and a vertically arranged second steel bar 75 is reserved on the top surface of the docking member 7. The second steel bar 75 is in an inverted U shape. When the docking member 7 is hoisted, the docking member 7 is hoisted until the top surface of the first template 71 is flush with the top surface of the lower cross beam 2, and then the docking member 7 is moved horizontally toward the lower cross beam 2 until the first template 71 and the third template 73 abut against the lower cross beam 2. During the horizontal movement of the docking member 7, the first steel bar 21 is inserted into the second steel bar 75, and the first steel bar 21 and the second steel bar 75 are connected by steel wire binding. First hoisting the docking member 7 in the vertical direction and then moving the member horizontally can improve the placement accuracy of the docking member 7 and facilitate the second steel bar 75 to be put on the first steel bar 21. The connection between the second steel bar 75 and the first steel bar 21 can cooperate with the inclined rod 74 to further improve the reliability and stability of the connection between the connecting section 22 and the lower cross beam 2 and the docking member 7.

[0057] A high-efficiency quick-assembly and disassembly bridge-erecting machine for docks, used in the above-mentioned construction process of quickly erecting prefabricated components of docks using a bridge-erecting machine 3, referring to Figures 11 to 13 The bridge 31 includes a bridge frame 31 and hydraulic legs 32 fixedly connected to the bridge frame 31. The hydraulic legs 32 are provided in four groups. The bridge frame 31 can move horizontally relative to the hydraulic legs 32. A mobile frame 33 is provided on the bridge frame 31. The mobile frame 33 can move relative to the bridge frame 31 along the length direction of the bridge frame 31. A crane 34 is provided on the mobile frame 33. The crane 34 can move relative to the mobile frame 33 along the width direction of the bridge frame 31. A sling 35 is connected to the hook of the crane 34. The sling 35 is connected to the mobile vehicle through a connecting assembly 36. The sling 35 is provided with a detachable module for connecting with different clamps 39. The hydraulic legs 32 can be placed on the lower crossbeam 2, which facilitates the movement of the bridge erection machine 3 on the lower crossbeam 2, thereby achieving stable and reliable lifting on the water surface. At the same time, the detachable module can be connected with different clamps 39 to adapt to different prefabricated components, further improving the lifting efficiency and safety.

[0058] Specifically, the connecting assembly 36 includes a second screw sleeve 361, a second screw rod 362 and a second rotating nut 363. One end of the second screw sleeve 361 is hinged to the movable frame 33, and the other end is threadedly connected to the second screw rod 362. The end of the second screw rod 362 away from the second screw sleeve 361 is ball-jointed to the sling 35, and the second rotating nut 363 is fixedly connected to the second screw rod 362. During operation, rotating the second rotating nut 363 drives the second screw rod 362 to rotate, thereby making the second screw rod 362 and the second screw sleeve 361 cooperate to respectively tighten the sling 35 and the movable frame 33, and then cooperate with the hook of the crane 34 to achieve reliable fixation of the sling 35, reduce the possibility of the sling 35 shaking during operation, and thus improve the lifting accuracy. During lifting, the movable frame 33 realizes the movement of the sling 35, and the hydraulic support leg 32 realizes the lifting of the sling 35.

[0059] The detachable module includes two sets of jacks 37, with the output ends of the two sets of jacks 37 arranged in opposite directions. The output ends of the two sets of jacks 37 are fixedly connected to assembly blocks 38, which are used to connect to different clamps 39. The jacks 37 facilitate the movement of the clamps 39 to adapt to different components and clamping requirements.

[0060] The clamp 39 includes two sets of first assembly plates 391 and inclined clamping plates 392. Each set of first assembly plates 391 and inclined clamping plates 392 is associated with a corresponding set of jacks 37. The first assembly plates 391 are detachably connected to the corresponding assembly blocks 38, while the inclined clamping plates 392 are fixedly connected to the corresponding first assembly plates 391. The inclined clamping plates 392 are designed to mate with the inclined portions of the prefabricated longitudinal beam members 4. The inclined clamping plates 392 mate with the inclined portions of the prefabricated longitudinal beam members 4, thereby improving the stability and reliability of the hoisting of the prefabricated longitudinal beam members 4, thereby enhancing the safety and accuracy of the hoisting. A vertical surface 393 is provided on the end of the inclined clamping plate 392, distal from the first assembly plates 391. The vertical surface 393 is designed to mate with the prefabricated longitudinal beam members 4. The vertical surface 393 facilitates matement with the side walls of the prefabricated longitudinal beam members 4, thereby facilitating the clamping of the prefabricated longitudinal beam members 4 and reducing the possibility of shaking during the hoisting process.

[0061] A hoisting process, based on the above-mentioned quick assembly and disassembly type efficient bridge erecting machine for dock, referring to Figures 15 to 18 , including the following steps: S1, assembling bridge erection machine 3; S2, move the bridge erection machine 33 so that two sets of hydraulic legs 32 of the bridge erection machine 3 are located on the lower crossbeam 2, define the area between the two sets of hydraulic legs 32 and the shore as the lifting area, and use the bridge erection machine 3 to lift the prefabricated longitudinal beam component 4 to the lifting area; S3, continue to move the bridge erection machine 3, so that the bridge erection machine 3 moves as a whole in a direction away from the shore, thereby expanding the lifting area, and then continue to lift the prefabricated longitudinal beam component 4 to the newly added lifting area; S4. Repeat steps S2 and S3 until all prefabricated longitudinal beam components 4 are hoisted.

[0062] S5. After the upper crossbeam 6 is cast, the clamp 39 on the detachable module is replaced, and the prefabricated panel 5 is hoisted by the bridge-building machine 3, and the prefabricated panel 5 is placed on two adjacent lower crossbeams 2, so that the prefabricated panel 5 is located between the two prefabricated longitudinal beam components 4, and at the same time, the prefabricated panel 5 is located between the two upper crossbeams 6.

[0063] By moving the bridge-building machine 3 on the lower beam 2, stable and reliable lifting on the water surface can be achieved. At the same time, the detachable module can be connected with different clamps 39 to adapt to different prefabricated components, further improving the lifting efficiency and safety.

[0064] Specifically, in step S1, when assembling the bridge frame 31, three main beams are first assembled, and then the bridge frame 31 is moved away from the shore. New main beams are then installed on the shore, and the bridge frame 31 is then moved again, and this process is repeated until all the main beams of the bridge frame 31 are installed. Installing new main beams on the shore is more convenient and safer. By continuously moving the bridge frame 31 forward to provide installation space for the new main beams, the bridge frame 31 can be assembled in a smaller space, further ensuring the convenience of construction.

[0065] In step S3 , after the bridge erection machine 3 is completely separated from the shore, the upper crossbeam 6 is cast synchronously on the rear side. When the bridge erection machine 3 hoists the prefabricated panel 5 , the hydraulic support legs 32 are supported on the prefabricated longitudinal beam component 4 or the upper crossbeam 6 .

[0066] Example 2 Reference Figure 14 The fixture 39 includes a second assembly plate 394 and slings 395. The second assembly plate 394 is detachably connected to the assembly block 38. Two second assembly plates 394 are provided, and each second assembly plate 394 is provided with two slings 395. The four slings 395 are used to connect to the four lifting points on the prefabricated panel 5. The four slings 395 facilitate the secure lifting of the prefabricated panel 5, improving the safety and lifting accuracy of the prefabricated panel 5.

[0067] The examples of this specific embodiment are all preferred embodiments of this application and are not intended to limit the scope of protection of this application. Identical components are represented by the same reference numerals. Therefore, any equivalent changes made based on the structure, shape, and principle of this application should be included in the scope of protection of this application.

Claims

1. A construction process for rapidly erecting prefabricated components of a wharf using a bridge erection machine, characterized in that: The steps include: S1, sinking the PHC piles (1) to form a bent frame, then constructing the lower cross beams (2) on the PHC piles (1), and forming the lower cross beams (2) into several rows; S2. Assembling a bridge erection machine (3), wherein the hydraulic legs of the bridge erection machine (3) are supported on the lower crossbeam (2), and the bridge erection machine (3) is capable of moving along the arrangement direction of the lower crossbeam (2); S3, hoisting the prefabricated longitudinal beam components (4) by means of a bridge erection machine (3), placing the prefabricated longitudinal beam components (4) on the lower cross beam (2), with both ends of each prefabricated longitudinal beam component (4) respectively placed on two adjacent lower cross beams (2); S4, constructing an upper crossbeam (6) on the lower crossbeam (2), so that the upper crossbeam (6), the lower crossbeam (2) and the prefabricated longitudinal beam member (4) form a whole; S5. The prefabricated panel (5) is hoisted by a bridge erection machine (3), the prefabricated panel (5) is placed on the prefabricated longitudinal beam and the upper cross beam (6), and the prefabricated panel (5) is connected to the prefabricated longitudinal beam and the upper cross beam (6).

2. The construction process for rapidly erecting prefabricated dock components using a bridge erection machine according to claim 1, characterized in that: In step S4, the mooring component (7) is hoisted, and a connecting section (22) is cast between the mooring component (7) and the corresponding lower crossbeam (2) so that the mooring component (7) and the corresponding mooring component (7) are integrated.

3. The construction process for rapidly erecting prefabricated dock components using a bridge erection machine according to claim 2, characterized in that: In step S4, the connecting section (22) is cast through a connecting mold (8), and the connecting mold (8) includes a positioning channel steel (81), an upper pull component (82) and a lower support component (84). Two positioning channel steels (81) are provided and are both installed on the lower crossbeam (2). One end of the upper pull component (82) is connected to the positioning channel steel (81), and the other end is connected to the mooring component (7). One end of the lower support component (84) is connected to the PHC pile (1), and the other end is connected to the mooring component (7).

4. The construction process for rapidly erecting prefabricated wharf components using a bridge erection machine according to claim 3, characterized in that: The top of the mooring member (7) is connected to a first template (71), a second template (72) and a third template (73); a casting area for casting the connecting section (22) is formed between the first template (71), the second template (72), the third template (73) and the side wall of the lower cross beam (2); A lifting ring is connected to the side walls of the first template (71) and the third template (73) respectively, so as to facilitate the lifting of the mooring component (7) by a bridge erection machine (3); When the bridge erection machine (3) is lifting the mooring component (7), the bridge erection machine (3) is connected to two lifting rings via two lifting ropes, and the two lifting ropes are located outside the two positioning channel steels (81).

5. The construction process for rapidly erecting prefabricated dock components using a bridge erection machine according to claim 4, characterized in that: The lower support assembly (84) comprises a hoop (841), a first screw sleeve (842) and a first screw rod (843); the hoop (841) is fixedly connected to the PHC pile (1); one end of the first screw sleeve (842) is hinged to the mooring assembly, and the other end is threadedly connected to the first screw rod (843); one end of the first screw rod (843) away from the first screw sleeve (842) is spherically hinged to the hoop (841); and a first rotating nut (844) is fixedly connected to the first screw rod (843).

6. The construction process for rapidly erecting prefabricated wharf components using a bridge erection machine according to claim 5, characterized in that: The pull-up assembly (82) includes an anchor rod (834) and an anchor. The anchor rod (834) is fixedly connected to the mooring component (7). The anchor is provided on the positioning channel steel (81). The anchor can adjust its position relative to the positioning channel steel (81) along the width direction of the positioning channel steel (81). The anchor is used to anchor the anchor rod (834).

7. The construction process for rapidly erecting prefabricated dock components using a bridge erection machine according to claim 6, characterized in that: The anchor comprises an anchor block (821), an anchor cylinder (832) and an anchor plate (833), wherein the anchor block (821) is connected to the positioning channel steel (81), two anchor cylinders (832) are provided, and both are hinged to the anchor block (821), and the two anchor cylinders (832) are semicircular, and a conical surface (8321) is provided on the side wall of the anchor cylinder (832), and each anchor cylinder (832) is provided with a plurality of anchor plates (833), and the plurality of anchor plates (833) slide on the conical surface (8321) along the axis of the anchor cylinder (832); The anchor cylinder (832) has a closed state and an open state. When the anchor cylinder (832) is in the closed state, the two anchor cylinders (832) form a cylindrical shape, and the plurality of anchor plates (833) anchor the anchor rod (834). A locking member (835) is provided between the two anchor cylinders (832) for maintaining the anchor cylinder (832) in the closed state.

8. The construction process for rapidly erecting prefabricated wharf components using a bridge erection machine according to claim 7, characterized in that: The locking member (835) includes a locking cover (8351) and a locking block (8352). The locking cover (8351) is fixedly connected to one anchor cylinder (832). The locking block (8352) is fixedly connected to the other anchor cylinder (832). A sliding groove (8353) is provided on the locking block (8352). A slider (8354) slides in the sliding groove (8353). A card slot (8358) for inserting the slider (8354) is provided on the locking cover (8351). The sliding groove (8353) is provided with a card slot (8358) for inserting the slider (8354). ) is provided with a compression spring (8355), one end of the compression spring (8355) abuts against the end of the slider (8354) away from the slot (8358), and the other end abuts against the end of the slide groove (8353) away from the slot (8358), and a shift rod (8356) is fixedly connected to the side wall of the slider (8354), and the end of the shift rod (8356) away from the slider (8354) passes through the locking block (8352), and the locking block (8352) is provided with a shift groove (8357) for the shift rod (8356) to slide.

9. The construction process for rapidly erecting prefabricated wharf components using a bridge erection machine according to claim 7, characterized in that: The mooring member (7) is hinged with an inclined tie rod (74), and one end of the inclined tie rod (74) away from the mooring member (7) is hinged with the lower cross beam (2).

10. The construction process for rapidly erecting prefabricated wharf components using a bridge erection machine according to claim 7, characterized in that: A first horizontally arranged steel bar (21) is reserved on the side wall of the lower cross beam (2), and a second vertically arranged steel bar (75) is reserved on the top surface of the berthing member (7), wherein the second steel bar (75) is in an inverted U shape. When the berthing member (7) is hoisted, the berthing member (7) is hoisted until the top surface of the first template (71) is flush with the top surface of the lower cross beam (2), and then the berthing member (7) is moved laterally toward the lower cross beam (2) until the first template (71) and the third template (73) are in contact with the lower cross beam (2). During the lateral movement of the berthing member (7), the first steel bar (21) is inserted into the second steel bar (75), and the first steel bar (21) and the second steel bar (75) are connected by steel wire binding.