A hoisting construction device and method for precast panels of steel-concrete composite beams

Through the innovative design of the hoisting construction device, the rapid connection and precise hoisting of the precast panels of the steel-concrete composite beam were achieved, solving the problems of low hoisting efficiency and positional deviation, and improving construction efficiency and safety.

CN120534854BActive Publication Date: 2025-11-14HUNAN ROAD & BRIDGE CONSTR GROUP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202511037238.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-07-28
Publication Date
2025-11-14
Estimated Expiration
2045-07-28

AI Technical Summary

Technical Problem

When hoisting precast panels of steel-concrete composite beams, it is difficult to quickly connect the lifting equipment with the pre-embedded hooks, resulting in low hoisting efficiency and large positional deviations after landing, which increases the subsequent adjustment time.

Method used

The system employs a hoisting mechanism, a quick-release mechanism, a support and anti-detachment mechanism, and a control mechanism. Through the cooperation of a drive screw and a return spring, the L-shaped connecting hook can be quickly connected and disconnected. The angle can be adjusted by the control handle to ensure hoisting accuracy.

Benefits of technology

It improved hoisting efficiency, reduced subsequent adjustment time, ensured hoisting accuracy, and reduced the complexity and safety risks of manual operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120534854B_ABST
    Figure CN120534854B_ABST
Patent Text Reader

Abstract

This invention provides a hoisting and construction device and method for precast panels of reinforced concrete composite beams, relating to the field of hoisting equipment technology. It includes: a hoisting construction mechanism, a quick-release mechanism, a support and anti-detachment mechanism, and a control mechanism. The hoisting construction mechanism is located above the precast panel of the reinforced concrete composite beam. The quick-release mechanism is installed on the hoisting construction mechanism. The support and anti-detachment mechanism is installed on the hoisting construction mechanism. The control mechanism is installed on the hoisting construction mechanism. This invention allows two workers to appropriately adjust the angle of the precast panel of the reinforced concrete composite beam using two control handles, resulting in a more accurate position after the panel is lowered, thus reducing subsequent adjustment time. It solves the problem that the inconvenience of workers adjusting the angle of the precast panel leads to a large deviation in the position after lowering, increasing the subsequent adjustment time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of lifting equipment technology, and more specifically, it relates to a lifting and construction device and method for precast panels of steel-concrete composite beams. Background Technology

[0002] Precast panels for steel-concrete composite beams are typically large and heavy, making manual handling difficult and posing safety hazards. Lifting equipment can efficiently and safely complete lifting and transportation, and can be used in conjunction with cranes to achieve long-distance lifting. Therefore, lifting equipment is an important tool to ensure the construction quality, safety, and progress of precast panels for steel-concrete composite beams.

[0003] Currently, the following problems still exist during the hoisting of precast panels for steel-concrete composite beams:

[0004] 1. Generally, the pre-embedded hooks on the precast panels of steel-concrete composite beams are connected to the wire ropes on the lifting equipment by shackles. This makes it impossible to quickly connect the lifting equipment to the pre-embedded hooks on the precast panels of steel-concrete composite beams, thus reducing the lifting efficiency of the precast panels of steel-concrete composite beams.

[0005] 2. It is inconvenient for staff to adjust the angle of the precast panels of the steel-concrete composite beams appropriately, resulting in a large deviation in the position of the precast panels after they are dropped, which increases the subsequent adjustment time of the precast panels of the steel-concrete composite beams. Summary of the Invention

[0006] This disclosure relates to a hoisting and construction device and method for precast panels of steel-concrete composite beams, comprising a hoisting mechanism, a quick-release mechanism, a support and anti-detachment mechanism, and a control mechanism. When two drive screws move two connecting plates inward, four L-shaped connecting hooks move inward simultaneously under the action of four steel wire ropes. When two drive screws move two connecting plates outward, four L-shaped connecting hooks move outward simultaneously under the action of four return springs, improving the hoisting efficiency of precast panels of steel-concrete composite beams. It allows two workers to adjust the angle of the precast panels of steel-concrete composite beams appropriately using two control handles, making the position of the precast panels after descent more accurate and reducing subsequent adjustment time. It solves the problems of not being able to quickly connect the hoisting equipment to the pre-embedded hooks on the precast panels of steel-concrete composite beams and the large positional deviation of the precast panels after descent.

[0007] In a first aspect, this disclosure provides a hoisting construction device for precast steel-concrete composite beam panels, used for hoisting precast steel-concrete composite beam panels; comprising: a hoisting construction mechanism, a quick-release mechanism, a support and anti-detachment mechanism, and a control mechanism; the hoisting construction mechanism is located above the precast steel-concrete composite beam panel; the quick-release mechanism is installed on the hoisting construction mechanism and is used to separate the hoisting construction mechanism from the precast steel-concrete composite beam panel; the support and anti-detachment mechanism is installed on the hoisting construction mechanism and is used to support the hoisting construction mechanism; the control mechanism is installed on the hoisting construction mechanism and is used to control the quick-release mechanism; a lithium battery and a controller are installed on the hoisting construction mechanism, and the lithium battery is electrically connected to the controller.

[0008] In at least some embodiments, the hoisting construction mechanism includes: a hoisting construction frame, a hook connecting frame, and L-shaped connecting hooks; the hook connecting frame is slidably installed on the hoisting construction frame, and the bottom of the hook connecting frame is in contact with the top of four screws; there are four L-shaped connecting hooks, and the four L-shaped connecting hooks are slidably installed at the bottom corner of the hoisting construction frame, and the four L-shaped connecting hooks are inserted into four pre-embedded hooks on the precast panel of the steel-concrete composite beam.

[0009] In at least some embodiments, the hoisting construction mechanism further includes: limiting baffles, circular reset rods, and reset springs; there are four limiting baffles in total, and the four limiting baffles are fixedly installed on the inner ends of four L-shaped connecting hooks; there are four circular reset rods in total, and the four circular reset rods are slidably installed on the four limiting baffles, and the four circular reset rods are also fixedly connected to the hoisting construction frame; there are four reset springs in total, and the four reset springs are sleeved on the outside of the four circular reset rods, and the four reset springs are located on the inner side of the four limiting baffles.

[0010] In at least some embodiments, the quick-release mechanism includes: a dual-head motor and a connecting plate; the dual-head motor is fixedly mounted on the hoisting construction frame, and the dual-head motor is also electrically connected to the controller; there are two connecting plates, and the two connecting plates are slidably mounted on the hoisting construction frame.

[0011] In at least some embodiments, the quick-release mechanism further includes: a drive screw and steel wire ropes; there are two drive screws, and the two drive screws are fixedly mounted on the output shaft of a dual-head motor; the threads on the two drive screws are in opposite directions, and the two drive screws are also threadedly connected to two connecting plates; there are four steel wire ropes, and the four steel wire ropes are slidably mounted inside the hoisting construction frame; the outer ends of the four steel wire ropes are fixedly connected to four L-shaped connecting hooks, and the inner ends of the four steel wire ropes are fixedly connected to two connecting plates.

[0012] In at least some embodiments, the support anti-detachment mechanism includes: a circular guide shaft and a support anti-detachment disc; there are four circular guide shafts, and the four circular guide shafts are slidably installed on the hoisting construction frame; there are four support anti-detachment discs, and the four support anti-detachment discs are fixedly installed at the bottom of the four circular guide shafts, and the bottom of the four support anti-detachment discs is in contact with the precast panel of the steel-concrete composite beam.

[0013] In at least some embodiments, the support anti-detachment mechanism further includes: limiting retaining rings and support springs; there are four limiting retaining rings in total, and the four limiting retaining rings are fixedly installed on the top of four circular guide shafts; there are four support springs in total, and the four support springs are sleeved on the outside of the four circular guide shafts, and the four support springs are located between the hoisting construction frame and the four support anti-detachment discs.

[0014] In at least some embodiments, the control mechanism includes: a U-shaped connecting seat, a rotating shaft, and a control handle; there are two U-shaped connecting seats, which are fixedly installed on the front and rear sides of the hoisting construction frame, and each of the two U-shaped connecting seats has two arc-shaped limiting holes; there are two rotating shafts, which are rotatably installed on the two U-shaped connecting seats; there are two control handles, which are fixedly installed on the outside of the two rotating shafts.

[0015] In at least some embodiments, the control mechanism further includes: angle limiting rods, reset baffles, reset springs, and control buttons; two angle limiting rods are provided, and the two angle limiting rods are fixedly installed inside the two control handles, and the two angle limiting rods are inserted into four arc-shaped limiting holes; two reset baffles are provided, and the two reset baffles are fixedly installed on the two U-shaped connecting seats, and the outer ends of the two reset baffles are in contact with the two control handles; the reset springs are fixedly installed on the two control handles; two control buttons are provided, and the two control buttons are fixedly installed inside the two U-shaped connecting seats, and the two control buttons are also electrically connected to the controller.

[0016] In another aspect, this disclosure provides a method for hoisting and installing precast panels of steel-concrete composite beams, including the following steps:

[0017] 1) Adjust the position of the hook connecting frame appropriately so that the lifting construction frame is in a balanced state after the hook connecting frame is connected to the hook on the crane. Then tighten the four screws on the lifting construction frame to ensure that the adjusted hook connecting frame does not move.

[0018] 2) Use a crane to move the hoisting construction frame above the precast panel of the steel-concrete composite beam to be hoisted, and then slightly adjust the position of the hoisting construction frame so that the hoisting construction frame and the precast panel of the steel-concrete composite beam are on the same center plane;

[0019] 3) Two staff members simultaneously press down on the control handle and wait for the dual-head motor to complete its operation;

[0020] 4) The precast panels of the steel-concrete composite beam are moved to the designated position by a crane. Before they are lowered, the staff adjusts the angle of the precast panels of the steel-concrete composite beam appropriately using two control handles.

[0021] 5) The staff will press down on the two control handles again and wait for the dual-head motor to finish working.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] 1. This invention allows workers to easily adjust the position of the hook connecting frame, ensuring that the hoisting frame is basically balanced after the hook connecting frame contacts the hook; it also facilitates adjustment of the hook connecting frame using four limit screws; when adjusting the hook connecting frame, workers can first connect the hook connecting frame to the hook, and then move the hook connecting frame upwards using the hook, which helps workers observe the tilt of the hoisting frame and accurately adjust the position of the hook connecting frame based on the tilt.

[0024] Furthermore, when the two drive screws move the two connecting plates inward, the four L-shaped connecting hooks move inward simultaneously under the action of the four steel wire ropes, realizing the rapid separation of the four L-shaped connecting hooks from the four pre-embedded hooks on the precast panel of the steel-concrete composite beam; when the two drive screws move the two connecting plates outward, the four L-shaped connecting hooks move outward simultaneously under the action of the four return springs, realizing the rapid connection of the four L-shaped connecting hooks from the four pre-embedded hooks on the precast panel of the steel-concrete composite beam, thus improving the hoisting efficiency of the precast panel of the steel-concrete composite beam.

[0025] 2. The four supporting springs of this invention provide support for the hoisting construction frame, ensuring that after the four L-shaped connecting hooks are connected to the four pre-embedded hooks on the precast panel of the steel-concrete composite beam, the four L-shaped connecting hooks can always be in contact with the four pre-embedded hooks on the precast panel of the steel-concrete composite beam, thus preventing the four L-shaped connecting hooks from separating from the four pre-embedded hooks on the precast panel of the steel-concrete composite beam during hoisting.

[0026] 3. This invention allows two workers to adjust the angle of the precast steel-concrete composite beam panel appropriately using two control handles, making the position of the precast steel-concrete composite beam panel more accurate after it is lowered, which helps to reduce the subsequent adjustment time of the precast steel-concrete composite beam panel; the setting of two reset baffles and reset springs provides an elastic positioning effect for the two control handles, preventing the two control handles from swinging during the hoisting of the precast steel-concrete composite beam panel.

[0027] In addition, when the four L-shaped connecting hooks need to be connected or disconnected from the four pre-embedded hooks on the precast panel of the steel-concrete composite beam, the workers need to press down on the two control handles. When the two control handles are pressed down, the two control handles do not change angle or change only slightly under the action of the return spring, so that the hoisting construction frame will drive the four L-shaped connecting hooks to move down simultaneously. When the elastic force of the four support springs after compression is greater than the tension of the return spring, the hoisting construction frame stops moving outward, causing the two control handles to change angle.

[0028] In addition, when the two angle limit rods move to the other end of the four arc-shaped limit holes, the two angle limit rods can press the two control buttons in the two U-shaped connecting seats; when the two control buttons are in the pressed state, the controller controls the double-head motor to rotate forward for a period of time; when the two control buttons are pressed again, the controller controls the double-head motor to rotate in reverse for a period of time, so that when the hoisting construction frame drives the four L-shaped connecting hooks to move downward to the designated position, the double-head motor can work automatically. Attached Figure Description

[0029] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings of the embodiments will be briefly described below.

[0030] The accompanying drawings described below are only related to some embodiments of the invention and are not intended to limit the invention.

[0031] In the attached diagram:

[0032] Figure 1 A structural schematic diagram of the present invention and the precast panel of the steel-concrete composite beam is shown;

[0033] Figure 2 It shows Figure 1 A schematic diagram of the longitudinal center section structure;

[0034] Figure 3 It shows Figure 2 A magnified schematic diagram of a portion of region A in the middle;

[0035] Figure 4 A structural schematic diagram of the hoisting construction mechanism and the quick-release mechanism is shown;

[0036] Figure 5 It shows Figure 4 A magnified schematic diagram of a portion of region B in the middle;

[0037] Figure 6 It shows Figure 4 A magnified schematic diagram of a portion of region C in the middle;

[0038] Figure 7 A structural schematic diagram of the hoisting construction frame and the support anti-detachment mechanism is shown;

[0039] Figure 8 A schematic diagram of the control mechanism is shown;

[0040] Figure 9 It shows Figure 2 A magnified schematic diagram of a portion of region D in the middle;

[0041] Figure 10 It shows Figure 8 A magnified schematic diagram of a portion of region E in the middle.

[0042] List of reference numerals in the attached diagram:

[0043] 100. Precast panels for steel-concrete composite beams;

[0044] 200. Lifting and installation mechanism; 201. Lifting and installation frame; 202. Hook connecting frame; 203. L-shaped connecting hook; 204. Limiting baffle; 205. Circular reset rod; 206. Reset spring;

[0045] 300. Quick release mechanism; 301. Dual-head motor; 302. Connecting plate; 303. Drive screw; 304. Steel wire rope;

[0046] 400. Anti-detachment support mechanism; 401. Circular guide shaft; 402. Anti-detachment support disc; 403. Limiting retaining ring; 404. Support spring;

[0047] 500. Control mechanism; 501. U-shaped connecting seat; 5011. Arc-shaped limiting hole; 502. Rotating shaft; 503. Control handle; 504. Angle limiting rod; 505. Reset baffle; 506. Reset tension spring; 507. Control button;

[0048] 600, lithium battery; 700, controller. Detailed Implementation

[0049] To make the objectives, solutions, and advantages of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Unless otherwise stated, the terms used herein have their ordinary meanings in the art. The same reference numerals in the drawings represent the same parts.

[0050] Example: Please refer to Figures 1 to 10As shown: This invention provides a hoisting construction device for precast steel-concrete composite beam panels, used for hoisting precast steel-concrete composite beam panels 100; it includes: a hoisting construction mechanism 200, a quick-release mechanism 300, a support and anti-detachment mechanism 400, and a control mechanism 500; the hoisting construction mechanism 200 is located above the precast steel-concrete composite beam panel 100; the quick-release mechanism 300 is installed on the hoisting construction mechanism 200 and is used to separate the hoisting construction mechanism 200 from the precast steel-concrete composite beam panel 100; the support and anti-detachment mechanism 400 is installed on the hoisting construction mechanism 200 and is used to support the hoisting construction mechanism 200; the control mechanism 500 is installed on the hoisting construction mechanism 200 and is used to control the quick-release mechanism 300; a lithium battery 600 and a controller 700 are installed on the hoisting construction mechanism 200, and the lithium battery 600 and the controller 700 are electrically connected.

[0051] In this embodiment of the disclosure, such as Figures 3 to 6 As shown, the hoisting construction mechanism 200 includes: a hoisting construction frame 201, a hook connecting frame 202, and L-shaped connecting hooks 203; the hook connecting frame 202 is slidably installed on the hoisting construction frame 201, and the bottom of the hook connecting frame 202 is in contact with the tops of four screws; there are four L-shaped connecting hooks 203, and the four L-shaped connecting hooks 203 are slidably installed at the bottom corner of the hoisting construction frame 201, and the four L-shaped connecting hooks 203 are inserted into four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam; the hoisting construction mechanism 200 also includes: a limiting baffle 204, The system includes a circular reset rod 205 and a reset spring 206; four limiting baffles 204 are provided, and the four limiting baffles 204 are fixedly installed on the inner ends of four L-shaped connecting hooks 203; four circular reset rods 205 are provided, and the four circular reset rods 205 are slidably installed on the four limiting baffles 204, and the four circular reset rods 205 are also fixedly connected to the hoisting construction frame 201; four reset springs 206 are provided, and the four reset springs 206 are sleeved on the outside of the four circular reset rods 205, and the four reset springs 206 are located on the inner side of the four limiting baffles 204;

[0052] The quick-release mechanism 300 includes: a dual-head motor 301 and a connecting plate 302; the dual-head motor 301 is fixedly installed on the hoisting construction frame 201, and the dual-head motor 301 is also electrically connected to the controller 700; there are two connecting plates 302, and the two connecting plates 302 are slidably installed on the hoisting construction frame 201; the quick-release mechanism 300 also includes: a drive screw 303 and a wire rope 304; there are two drive screws 303, and the two drive screws 303 are fixedly installed on the output shaft of the dual-head motor 301; the threads on the two drive screws 303 are in opposite directions, and the two drive screws 303 are also threadedly connected to the two connecting plates 302; there are four wire ropes 304, and the four wire ropes 304 are slidably installed inside the hoisting construction frame 201; the outer ends of the four wire ropes 304 are fixedly connected to four L-shaped connecting hooks 203, and the inner ends of the four wire ropes 304 are fixedly connected to the two connecting plates 302;

[0053] Its specific functions are as follows: Because the hook connecting frame 202 is slidably installed on the hoisting construction frame 201, it is convenient for the staff to adjust the position of the hook connecting frame 202 appropriately, ensuring that the hoisting construction frame 201 is basically in a balanced state after the hook connecting frame 202 contacts the hook; and because the bottom of the hook connecting frame 202 contacts the top of the four screws, it is convenient to adjust the hook connecting frame 202 by limiting the position of the four screws; when adjusting the hook connecting frame 202, the staff can first connect the hook connecting frame 202 to the hook, and then move the hook connecting frame 202 upward through the hook, which is conducive to the staff to observe the tilt of the hoisting construction frame 201 and to accurately adjust the position of the hook connecting frame 202 according to the tilt.

[0054] Furthermore, because the four steel wire ropes 304 are slidably installed inside the hoisting construction frame 201, and the outer ends of the four steel wire ropes 304 are fixedly connected to the four L-shaped connecting hooks 203, and the inner ends of the four steel wire ropes 304 are fixedly connected to the two connecting plates 302, when the two drive screws 303 drive the two connecting plates 302 to move inward, the four L-shaped connecting hooks 203 can move inward simultaneously under the action of the four steel wire ropes 304, realizing the rapid separation of the four L-shaped connecting hooks 203 from the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam; and because the four circular reset... Rod 205 is slidably mounted on four limiting baffles 204, and four return springs 206 are sleeved on the outside of the four circular return rods 205, and the four return springs 206 are located inside the four limiting baffles 204. When the two drive screws 303 drive the two connecting plates 302 to move outward, the four L-shaped connecting hooks 203 move outward simultaneously under the action of the four return springs 206, realizing the rapid connection between the four L-shaped connecting hooks 203 and the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, thereby improving the hoisting efficiency of the precast panel 100 of the steel-concrete composite beam.

[0055] In this embodiment of the disclosure, such as Figure 7 and Figure 9 As shown, the anti-detachment support mechanism 400 includes: circular guide shafts 401 and anti-detachment support discs 402; there are four circular guide shafts 401, and the four circular guide shafts 401 are slidably installed on the hoisting construction frame 201; there are four anti-detachment support discs 402, and the four anti-detachment support discs 402 are fixedly installed at the bottom of the four circular guide shafts 401, and the bottom of the four anti-detachment support discs 402 is in contact with the precast panel 100 of the steel-concrete composite beam; the anti-detachment support mechanism 400 also includes: limiting retaining rings 403 and support springs 404; there are four limiting retaining rings 403, and the four limiting retaining rings 403 are fixedly installed at the top of the four circular guide shafts 401; there are four support springs 404, and the four support springs 404 are sleeved on the outside of the four circular guide shafts 401, and the four support springs 404 are located between the hoisting construction frame 201 and the four anti-detachment support discs 402;

[0056] Its specific function is as follows: Since the four support anti-detachment discs 402 are fixedly installed at the bottom of the four circular guide shafts 401, and the bottom of the four support anti-detachment discs 402 is in contact with the precast panel 100 of the steel-concrete composite beam, and the four support springs 404 are located between the hoisting construction frame 201 and the four support anti-detachment discs 402, they play a supporting role for the hoisting construction frame 201. This ensures that after the four L-shaped connecting hooks 203 are connected to the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, the four L-shaped connecting hooks 203 can always be in contact with the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, thus preventing the four L-shaped connecting hooks 203 from separating from the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam during hoisting.

[0057] In this embodiment of the disclosure, such as Figures 8 to 10As shown, the control mechanism 500 includes: a U-shaped connecting seat 501, a rotating shaft 502, and a control handle 503; two U-shaped connecting seats 501 are provided, and the two U-shaped connecting seats 501 are fixedly installed on the front and rear sides of the hoisting construction frame 201, and two arc-shaped limiting holes 5011 are respectively opened on the two U-shaped connecting seats 501; two rotating shafts 502 are provided, and the two rotating shafts 502 are rotatably installed on the two U-shaped connecting seats 501; two control handles 503 are provided, and the two control handles 503 are fixedly installed on the outside of the two rotating shafts 502; the control mechanism 500 also includes: an angle limiting rod 504, a reset baffle 505, a reset tension spring 506, and a control button 507. Two angle limiting rods 504 are provided, and the two angle limiting rods 504 are fixedly installed inside the two control handles 503, and the two angle limiting rods 504 are inserted into the four arc-shaped limiting holes 5011; two reset baffles 505 are provided, and the two reset baffles 505 are fixedly installed on the two U-shaped connecting seats 501, and the outer ends of the two reset baffles 505 are in contact with the two control handles 503; a reset tension spring 506 is fixedly installed on the two control handles 503; two control buttons 507 are provided, and the two control buttons 507 are fixedly installed inside the two U-shaped connecting seats 501, and the two control buttons 507 are also electrically connected to the controller 700;

[0058] Its specific functions are as follows: Since the two U-shaped connecting seats 501 are fixedly installed on the front and rear sides of the hoisting construction frame 201, and the two rotating shafts 502 are rotatably installed on the two U-shaped connecting seats 501, and the two control handles 503 are fixedly installed on the outside of the two rotating shafts 502, it is convenient for two workers to adjust the angle of the precast steel-concrete composite beam panel 100 appropriately through the two control handles 503, so that the position of the precast steel-concrete composite beam panel 100 after falling is more accurate, which helps to reduce the subsequent adjustment time of the precast steel-concrete composite beam panel 100; and since the two reset baffles 505 are fixedly installed on the two U-shaped connecting seats 501, and the outer ends of the two reset baffles 505 are in contact with the two control handles 503, and the reset tension spring 506 is fixedly installed on the two control handles 503, it plays an elastic positioning role for the two control handles 503, preventing the two control handles 503 from swinging during the hoisting of the precast steel-concrete composite beam panel 100;

[0059] Furthermore, when the four L-shaped connecting hooks 203 need to be connected or disconnected from the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, the operator needs to press down on the two control handles 503. When the two control handles 503 are pressed down, under the action of the return spring 506, the two control handles 503 do not change their angle or only change their angle slightly, causing the hoisting construction frame 201 to drive the four L-shaped connecting hooks 203 to move downward simultaneously; when the elastic force of the four support springs 404 after compression is greater than the tension of the return spring 506... When the force is applied, the hoisting construction frame 201 stops moving outward, causing the two control handles 503 to change angle; since the two control buttons 507 are fixedly installed inside the two U-shaped connecting seats 501, and the two control buttons 507 are electrically connected to the controller 700, and the dual-head motor 301 is also electrically connected to the controller 700, when the two angle limit rods 504 move to the other end of the four arc-shaped limit holes 5011, the two angle limit rods 504 can press the two control buttons 507 in the two U-shaped connecting seats 501;

[0060] In addition, when the two control buttons 507 are pressed, the controller 700 controls the dual-head motor 301 to rotate forward for a period of time; when the two control buttons 507 are pressed again, the controller 700 controls the dual-head motor 301 to rotate in reverse for a period of time, so that when the hoisting construction frame 201 drives the four L-shaped connecting hooks 203 to move downward to the designated position, the dual-head motor 301 can work automatically.

[0061] This invention provides a method for hoisting and installing precast panels of steel-concrete composite beams, comprising the following steps:

[0062] 1) Adjust the position of the hook connecting frame 202 appropriately so that the lifting construction frame 201 is in a balanced state after the hook connecting frame 202 is connected to the hook on the crane. Then tighten the four screws on the lifting construction frame 201 to ensure that the adjusted hook connecting frame 202 does not move.

[0063] 2) Use a crane to move the hoisting construction frame 201 above the precast steel-concrete composite beam panel 100 to be hoisted, and then slightly adjust the position of the hoisting construction frame 201 so that the hoisting construction frame 201 and the precast steel-concrete composite beam panel 100 are on the same central plane.

[0064] 3) Two staff members simultaneously press down on control handle 503 and wait for the dual-head motor 301 to complete its operation;

[0065] 4) The precast steel-concrete composite beam panel 100 is moved to the designated position by a crane. Before it is lowered, the staff adjusts the angle of the precast steel-concrete composite beam panel 100 appropriately using two control handles 503.

[0066] 5) The staff will press down on the two control handles 503 again and wait for the dual-head motor 301 to finish working.

[0067] The specific usage and function of this embodiment are as follows:

[0068] When using this invention, firstly, adjust the position of the hook connecting frame 202 appropriately so that after the hook connecting frame 202 is connected to the hook on the crane, the hoisting construction frame 201 is in a balanced state. When adjusting the hook connecting frame 202, the operator can first connect the hook connecting frame 202 to the hook, and then move the hook connecting frame 202 upwards through the hook. This allows the operator to observe the tilt of the hoisting construction frame 201 and accurately adjust the position of the hook connecting frame 202 according to the tilt. Afterwards, tighten the four screws on the hoisting construction frame 201 to ensure that the adjusted hook connecting frame 202 is in a stable position. 02. No movement occurs; the hoisting construction frame 201 is moved by a crane to above the precast steel-concrete composite beam panel 100 to be hoisted, and then the position of the hoisting construction frame 201 is slightly adjusted so that the hoisting construction frame 201 and the precast steel-concrete composite beam panel 100 are on the same center plane; two workers simultaneously press down the control handle 503. When the two control buttons 507 are in the pressed state, the controller 700 controls the double-head motor 301 to rotate forward for a period of time. When the two drive screws 303 drive the two connecting plates 302 to move outward, the four L-shaped connecting hooks 203 are in the four Under the action of the return spring 206, they move outward simultaneously, realizing the rapid connection between the four L-shaped connecting hooks 203 and the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, waiting for the double-head motor 301 to complete its work; the precast panel 100 of the steel-concrete composite beam is moved to the designated position by the crane. Before falling, the operator adjusts the angle of the precast panel 100 of the steel-concrete composite beam appropriately through the two control handles 503, so that the position of the precast panel 100 of the steel-concrete composite beam is more accurate after falling, which helps to reduce the subsequent adjustment time of the precast panel 100 of the steel-concrete composite beam; when hoisted to the designated position... The staff pressed down the two control handles 503 again. When the two control buttons 507 were pressed again, the controller 700 controlled the dual-head motor 301 to reverse for a period of time. When the two drive screws 303 drove the two connecting plates 302 to move inward, the four L-shaped connecting hooks 203 could move inward simultaneously under the action of the four steel wire ropes 304. This achieved the rapid separation of the four L-shaped connecting hooks 203 from the four pre-embedded hooks on the precast panel 100 of the steel-concrete composite beam, improving the hoisting efficiency of the precast panel 100 of the steel-concrete composite beam. The staff then waited for the dual-head motor 301 to finish its work.

[0069] The following points should be noted in this article:

[0070] 1. The accompanying drawings of the embodiments disclosed herein only relate to the structures involved in the embodiments disclosed herein; other structures can be referred to in general design.

[0071] 2. Where there is no conflict, the embodiments of this disclosure and the features in the embodiments can be combined with each other to obtain new embodiments.

[0072] The above are merely specific embodiments of this disclosure, but the scope of protection of this disclosure is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this disclosure should be included within the scope of protection of this disclosure. Therefore, the scope of protection of this disclosure should be determined by the scope of the claims.

Claims

1. A hoisting and installation device for precast panels of steel-concrete composite beams, used for hoisting precast panels (100) of steel-concrete composite beams; comprising: The system comprises a hoisting construction mechanism (200), a quick-release mechanism (300), a support and anti-detachment mechanism (400), and a control mechanism (500); characterized in that the hoisting construction mechanism (200) is located above the precast panel (100) of the steel-concrete composite beam; the quick-release mechanism (300) is installed on the hoisting construction mechanism (200), and the quick-release mechanism (300) is used to separate the hoisting construction mechanism (200) from the precast panel (100) of the steel-concrete composite beam; the support and anti-detachment mechanism (4 ... precast panel (200), and the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (100); the support and anti-detachment mechanism (400) is installed on the precast panel (200), and the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (100); the support and anti-detachment mechanism (400) is installed on the precast panel (200), and the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (100); the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (100); the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (100); the quick-release mechanism (400) is used to separate the hoisting construction mechanism (200) from the precast panel (10 The detachment mechanism (400) is installed on the hoisting construction mechanism (200), and the anti-detachment support mechanism (400) is used to support the hoisting construction mechanism (200); the control mechanism (500) is installed on the hoisting construction mechanism (200), and the control mechanism (500) is used to control the quick detachment mechanism (300); the hoisting construction mechanism (200) is equipped with a lithium battery (600) and a controller (700), and the lithium battery (600) is electrically connected to the controller (700); The hoisting construction mechanism (200) includes: a hoisting construction frame (201) and an L-shaped connecting hook (203); the quick release mechanism (300) includes: a connecting plate (302) and a wire rope (304); there are two connecting plates (302), and the two connecting plates (302) are slidably installed on the hoisting construction frame (201); there are four wire ropes (304), and the four wire ropes (304) are slidably installed inside the hoisting construction frame (201); the outer ends of the four wire ropes (304) are fixedly connected to the four L-shaped connecting hooks (203), and the inner ends of the four wire ropes (304) are fixedly connected to the two connecting plates (302); The control mechanism (500) includes: a U-shaped connector (501), a rotating shaft (502), a control handle (503), an angle limiting rod (504), a reset spring (506), and a control button (507); there are two control handles (503), and the two control handles (503) are fixedly installed on the outside of the two rotating shafts (502); there are two angle limiting rods (504), and the two angle limiting rods (504) are fixedly installed inside the two control handles (503); the reset spring (506) is fixedly installed on the two control handles (503); there are two control buttons (507), and the two control buttons (507) are fixedly installed inside the two U-shaped connectors (501), and the two control buttons (507) are also electrically connected to the controller (700).

2. The precast panel hoisting construction device for steel-concrete composite beams according to claim 1, characterized in that, The hoisting construction mechanism (200) further includes: a hook connecting frame (202); the hook connecting frame (202) is slidably installed on the hoisting construction frame (201), and the bottom of the hook connecting frame (202) is in contact with the top of four screws; there are four L-shaped connecting hooks (203), and the four L-shaped connecting hooks (203) are slidably installed at the bottom corner of the hoisting construction frame (201), and the four L-shaped connecting hooks (203) are inserted into four pre-embedded hooks on the precast panel (100) of the steel-concrete composite beam.

3. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 2, characterized in that, The hoisting construction mechanism (200) further includes: a limiting baffle (204), a circular reset rod (205), and a reset spring (206); there are four limiting baffles (204), and the four limiting baffles (204) are fixedly installed on the inner ends of four L-shaped connecting hooks (203); there are four circular reset rods (205), and the four circular reset rods (205) are slidably installed on the four limiting baffles (204), and the four circular reset rods (205) are also fixedly connected to the hoisting construction frame (201); there are four reset springs (206), and the four reset springs (206) are sleeved on the outside of the four circular reset rods (205), and the four reset springs (206) are located on the inner side of the four limiting baffles (204).

4. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 2, characterized in that, The quick unhooking mechanism (300) further includes a dual-head motor (301); the dual-head motor (301) is fixedly installed on the hoisting construction frame (201), and the dual-head motor (301) is also electrically connected to the controller (700).

5. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 4, characterized in that, The quick unhooking mechanism (300) further includes: a drive screw (303); there are two drive screws (303), and the two drive screws (303) are fixedly installed on the output shaft of the dual-head motor (301); the threads on the two drive screws (303) are opposite in direction, and the two drive screws (303) are also threadedly connected to two connecting plates (302).

6. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 2, characterized in that, The support anti-detachment mechanism (400) includes: a circular guide shaft (401) and a support anti-detachment disc (402); there are four circular guide shafts (401), and the four circular guide shafts (401) are slidably installed on the hoisting construction frame (201); there are four support anti-detachment discs (402), and the four support anti-detachment discs (402) are fixedly installed at the bottom of the four circular guide shafts (401), and the bottom of the four support anti-detachment discs (402) is in contact with the precast panel (100) of the steel-concrete composite beam.

7. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 6, characterized in that, The support anti-detachment mechanism (400) further includes: a limiting retaining ring (403) and a support spring (404); there are four limiting retaining rings (403), and the four limiting retaining rings (403) are fixedly installed on the top of the four circular guide shafts (401); there are four support springs (404), and the four support springs (404) are sleeved on the outside of the four circular guide shafts (401), and the four support springs (404) are located between the hoisting construction frame (201) and the four support anti-detachment discs (402).

8. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 4, characterized in that, There are two U-shaped connecting seats (501), and the two U-shaped connecting seats (501) are fixedly installed on the front and rear sides of the hoisting construction frame (201), and two arc-shaped limiting holes (5011) are opened on the two U-shaped connecting seats (501) respectively; there are two rotating shafts (502), and the two rotating shafts (502) are rotatably installed on the two U-shaped connecting seats (501).

9. The precast panel hoisting and construction device for steel-concrete composite beams according to claim 8, characterized in that, The control mechanism (500) further includes: a reset baffle (505); two angle limiting rods (504) are inserted into four arc-shaped limiting holes (5011); there are two reset baffles (505), and the two reset baffles (505) are fixedly installed on two U-shaped connecting seats (501), and the outer ends of the two reset baffles (505) are in contact with two control handles (503).

10. A method for hoisting and installing precast panels of a steel-concrete composite beam, using the hoisting and installation device for precast panels of a steel-concrete composite beam as described in claim 8, characterized in that... The steps are as follows: 1) Adjust the position of the hook connecting frame (202) appropriately so that the hook connecting frame (202) is connected to the hook on the crane and the hoisting construction frame (201) is in a balanced state. Then tighten the four screws on the hoisting construction frame (201) to ensure that the adjusted hook connecting frame (202) does not move. 2) Use a crane to move the hoisting construction frame (201) above the precast panel (100) of the steel-concrete composite beam to be hoisted, and then slightly adjust the position of the hoisting construction frame (201) so that the hoisting construction frame (201) and the precast panel (100) of the steel-concrete composite beam are on the same central plane. 3) Two staff members simultaneously press down on the control handle (503) and wait for the dual-head motor (301) to complete its operation; 4) The precast panel (100) of the steel-concrete composite beam is moved to the designated position by a crane. Before it is lowered, the staff adjusts the angle of the precast panel (100) of the steel-concrete composite beam appropriately by using two control handles (503). 5) The staff will press down on the two control handles (503) again and wait for the dual-head motor (301) to finish working.

Citation Information

Patent Citations

  • Fabricated outer wall hoisting equipment

    CN119503610A

  • Tool clamp for carrying hand fork lift

    CN217708543U

  • A lifting auxiliary lifting device for facilitating the flipping of concrete prefabricated wall panels

    CN222714932U