Auxiliary steel bar planting device for fan base

By designing the fan base auxiliary reinforcement device and automatically implanting steel bars with an annular baffle and radial reinforcement unit, the problem of low bonding efficiency in fan base construction is solved, and the construction efficiency and progress are improved.

CN120575567APending Publication Date: 2025-09-02SUQIAN POWER SUPPLY COMPANY OF JIANGSU PROVINCE POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511069255.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-31
Publication Date
2025-09-02

AI Technical Summary

Technical Problem

The current fan base is ineffective in bundling steel bars during construction, which affects the construction progress.

Method used

A fan base auxiliary reinforcement device is designed, including an annular baffle, a radial reinforcement unit and a clamping assembly. The reinforcement storage box, lifting assembly and support arm are used to realize the automatic implantation of reinforcement, reducing manual scribe steps and improving the efficiency of reinforcement.

Benefits of technology

It realizes rapid implantation of radial steel bars on the fan base, saves manual marking time, improves construction efficiency, and reduces template installation time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120575567A_ABST
    Figure CN120575567A_ABST
Patent Text Reader

Abstract

The invention provides an auxiliary steel bar planting device for a fan base, and belongs to the field of fan base construction. An annular baffle is vertically and fixedly installed on the ground, and a first steel bar ring and a second steel bar ring are sequentially and fixedly installed in the annular baffle; the supporting arm is rotationally installed above the annular steel bar planting area, the steel bar storage box is fixedly installed on the supporting arm, a steel bar outlet is formed in the steel bar storage box, the lifting assembly is arranged on the supporting arm, and the clamping assembly is arranged at the lifting end of the lifting assembly. According to the steel bar planting device, a plurality of steel bars to be planted can be stored through the arranged steel bar storage box, the steel bars to be planted falling out of the steel bar storage box are clamped through the clamping assembly, and the clamped steel bars to be planted can be placed between the first steel bar ring and the second steel bar ring through the lifting assembly; a whole circle of steel bars to be planted can be placed through the rotationally-arranged supporting arm, rapid steel bar planting of the fan base in the radial direction can be achieved, the step of manual scribing is omitted, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of fan base construction, and in particular relates to an auxiliary reinforcement planting device for a fan base. Background Art

[0002] Wind turbine foundation construction is a critical step in wind power generation projects, and its quality directly impacts the stability and service life of the wind turbine. During wind turbine construction, circumferential and radial reinforcement must be tied according to the design drawings. Currently, the reinforcement tying method involves first drawing the reinforcement lines, and then workers placing the reinforcement at the marked locations. Due to the high requirements for wind turbine foundations, the number of radial and circumferential reinforcements is relatively large. Furthermore, wind turbines are typically constructed in multiple locations, making manual marking and rebar placement inefficient and impacting construction progress.

[0003] In summary, the shortcomings of the existing steel bar bundling construction method are: the number of embedded steel bars is large, the efficiency of manual marking and embedding is low, which will affect the overall construction progress. Summary of the Invention

[0004] In view of the shortcomings of the prior art described above, the purpose of the present invention is to provide a fan base auxiliary rebar planting device to solve the problem that the number of rebars planted in the prior art is large, the efficiency of manual marking and rebar planting is low, and it will affect the overall construction progress.

[0005] To achieve the above-mentioned and other related purposes, the present invention provides a wind turbine base auxiliary rebar planting device, comprising: An annular baffle, wherein the annular baffle is fixedly mounted on the ground, the centerline of the annular baffle is perpendicular to the ground, a first steel bar ring is fixedly mounted in the annular baffle, a second steel bar ring is fixedly mounted in the first steel bar ring, the axis of the annular baffle, the axis of the first steel bar ring, and the axis of the second steel bar ring coincide with each other, and the area between the first steel bar ring and the second steel bar ring is an annular reinforcement area; A radial reinforcement unit, the radial reinforcement unit includes a support arm, a steel bar storage box, a clamping assembly and a lifting assembly; the support arm is rotatably installed above the annular reinforcement area, the rotation axis of the support arm coincides with the axis of the second steel bar ring, the steel bar storage box is fixedly installed on the support arm, a number of steel bars to be embedded are placed in the steel bar storage box along the radial direction of the annular reinforcement area, the steel bar storage box is provided with a steel bar outlet, the lifting assembly is provided on the support arm, and the lifting end of the lifting assembly is provided with a clamping assembly, the steel bars to be embedded fall out from the steel bar outlet and are clamped by the clamping end of the clamping assembly, the lifting end of the lifting assembly descends and places the steel bars to be embedded clamped by the clamping end of the clamping assembly across the first steel bar ring and the second steel bar ring.

[0006] As an optional solution, the first steel bar ring and the second steel bar ring each include a plurality of vertical steel bars and a plurality of annular steel bars; The plurality of annular steel bars are arranged in sequence from top to bottom along the axis of the annular baffle; The plurality of vertical steel bars are arranged in a circular array along the axis of the annular baffle, and the annular steel bars are fixedly connected to the vertical steel bars; One end of the steel bar to be planted is against the annular baffle, one side of the steel bar to be planted is placed on the annular steel bar of the first steel bar ring, and the other side of the steel bar to be planted is placed on the annular steel bar of the second steel bar ring; The distance between the annular steel bars of the second steel bar ring supporting the steel bars to be planted and the annular steel bars of the first steel bar ring is x, and the length of the steel bars to be planted is y, where x<y.

[0007] As an optional solution, the clamping assembly includes two clamping modules, and the two clamping modules are symmetrically arranged relative to the steel bar outlet; The clamping modules each include a mounting plate, a clamping plate, a base plate and a spring; The mounting plate is provided on the lifting end of the lifting assembly, and the mounting plate is located below the bottom end surface of the support arm; The clamping plate is slidably mounted on the mounting plate, wherein the sliding direction of the clamping plate is perpendicular to the axial direction of the second steel bar ring, and the sliding direction of the clamping plate is also perpendicular to the length direction of the support arm; The bottom plate is slidably mounted on the bottom end surface of the clamping plate, one end of the spring is fixedly connected to the bottom plate, and the other end of the spring is fixedly connected to the clamping plate, and the compression direction of the spring is parallel to the sliding direction of the bottom wall; When the bottom plates of the two clamping modules move toward each other, the side walls of the bottom plates of the two clamping modules come into contact with each other and can be used to support the steel bars to be planted; The clamping plates of the two clamping modules move toward each other to form a clamping space, and clamp the steel bars to be embedded.

[0008] As an optional solution, a slide groove is provided on the upper end surface of the base plate, the guide direction of the slide groove is parallel to the sliding direction of the clamping plate, the slider is fixedly mounted on the bottom end surface of the clamping plate, and the slider is slidably connected to the slide groove; The spring is located in the slide groove, one end of the spring is fixedly connected to the slide groove, and the other end of the spring is fixedly connected to the slider.

[0009] As an optional solution, the number of the clamping assemblies is at least two, and the at least two clamping assemblies are arranged sequentially along the length direction of the support arm.

[0010] As an optional solution, the lifting assembly includes two lifting modules, and the two lifting modules correspond one to one with the two clamping modules respectively; The lifting modules each include a movable plate and a lifting frame; The movable plate is movably arranged on the support arm, and the moving direction of the movable plate is parallel to the length direction of the support arm; The lifting frame is slidably mounted on the movable plate, and the sliding direction of the lifting frame is parallel to the axial direction of the annular rebar planting area; The mounting plate is arranged on the bottom end surface of the lifting frame.

[0011] As an optional solution, the mounting plate is rotatably mounted on the bottom end surface of the lifting frame, and the rotation axis of the mounting plate is parallel to the sliding direction of the clamping plate.

[0012] As an optional solution, the number of the lifting assemblies is the same as the number of the clamping assemblies, and the lifting assemblies correspond one to one to the clamping assemblies.

[0013] As an optional solution, the steel bar storage box includes a box body, a guide channel main plate, a first guide channel, a second guide channel, a connecting groove and a through groove; The box is fixedly mounted on the support arm; The guide channel main plate is located below the box body, and the upper end surface of the guide channel main plate passes through the inner and outer walls of the box body upward; The first guide channel is provided in the guide channel main body plate, the upper end surface of the first guide channel extends upward through the upper end surface of the guide channel main body plate and communicates with the box body, the first guide channel is rectangular, the width of the first guide channel is a, the diameter of the steel bar to be planted is b, b≤a<2b, the length of the first guide channel is greater than or equal to the length of the steel bar to be planted is m, the length of the steel bar to be planted is n, and m≥n; The second guide channel is provided in the guide channel main plate. The second guide channel is identical to the first guide channel and is parallel to the first guide channel. The bottom end surface of the second guide channel extends downward and passes through the bottom end surface of the guide channel main plate. The communicating groove is provided in the main plate of the guide channel, one end of the communicating groove is connected to the bottom of the first guide channel, and the other end of the communicating groove is connected to the second guide channel, and the bottom end surface of the communicating groove and the bottom end surface of the first guide channel are located on the same plane; The through groove is opened on the support arm and passes through the upper end surface and the bottom end surface of the support arm. The steel bars to be embedded pass through the first guide channel, the connecting groove, the second guide channel and the through groove in sequence from the box body and fall onto the clamping end of the clamping assembly.

[0014] As an optional solution, the steel bar storage box further includes a receiving slot and a pushing block; The receiving groove is provided in the main plate of the guide channel, the receiving groove is connected to the first guide channel, and the receiving groove and the communicating groove are respectively located on two opposite sides of the first guide channel; The pushing block is slidably connected to the accommodating groove, the sliding direction of the pushing block is parallel to the center line direction of the communicating groove, the plane where the upper end surface of the pushing block is located is a first plane, and the first plane is located between the axis of the bottommost steel bar to be planted and the outer wall of the penultimate steel bar to be planted; The length of the pushing block along the width direction of the first guide channel is greater than the width value of the first guide channel. The pushing block slides and pushes the steel bars to be embedded at the bottom of the first guide channel from the first guide channel through the connecting groove and into the second guide channel.

[0015] The present invention provides a method for planting reinforcement bars of a fan base auxiliary reinforcement bar planting device as follows: A plurality of steel bars to be planted are stored in a steel bar storage box, and the steel bars to be planted dropped out of the steel bar storage box are clamped by a clamping assembly. The clamped steel bars to be planted are placed between the first steel bar ring and the second steel bar ring by a lifting assembly, and a whole circle of steel bars to be planted can be placed by rotating a support arm; By rotating the mounting plate and installing it on the lifting frame, the clamped steel bars to be planted are rotated. When placing the steel bars to be planted, the steel bars to be planted can be first rotated to be inclined in the direction of the second steel bar ring, and then one end of the steel bar to be planted can be placed on the ring steel bar of the second steel bar ring, and the steel bar to be planted can be inserted into the second steel bar ring, and then one end of the steel bar to be planted can be rotated downward and placed on the ring steel bar of the first steel bar ring, so that the steel bar to be planted can be placed between the ring steel bars of the first steel bar ring and the ring steel bars of the second steel bar ring; By setting the first guide channel, the second guide channel, the connecting groove and the pushing block, when the pushing block slides, only the steel bars to be embedded in the bottom of the first guide channel can be pushed out of the first guide channel, thereby enabling the embedding of steel bars one by one, which is convenient for rapid loading.

[0016] As described above, the fan base auxiliary reinforcement planting device proposed by the present invention has at least the following beneficial effects: 1. The present application provides a steel bar storage box that can store multiple steel bars to be planted. The steel bars to be planted that fall out of the steel bar storage box are clamped by a clamping assembly. The clamped steel bars to be planted can be placed between the first steel bar ring and the second steel bar ring by a lifting assembly. The steel bars to be planted can be placed in a whole circle by rotating the support arm, which can realize rapid radial planting of the wind turbine base, save the step of manual marking, and improve construction efficiency. 2. The annular baffle provided in this application can be used as an external formwork for concrete pouring after the reinforcement construction is completed, thereby reducing the installation time of the formwork and improving construction efficiency; 3. The present application provides the first guide channel, the second guide channel, the connecting groove and the pushing block. When the pushing block slides, only the rebar to be planted at the bottom of the first guide channel can be pushed out of the first guide channel, thereby enabling the planting of rebars one by one, facilitating rapid loading. 4. The present application rotates the mounting plate and installs it on the lifting frame, so that the clamped steel bars to be embedded can be rotated. When placing the steel bars to be embedded, the steel bars to be embedded can be first rotated to tilt toward the second steel bar ring, and then one end of the steel bars to be embedded can be placed on the ring steel bars of the second steel bar ring, and the steel bars to be embedded can be inserted into the second steel bar ring, and then one end of the steel bars to be embedded can be rotated downward and placed on the ring steel bars of the first steel bar ring, so that the steel bars to be embedded can be placed between the ring steel bars of the first steel bar ring and the ring steel bars of the second steel bar ring, thereby improving the embedding efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 Shown is a schematic structural diagram of the present invention; Figure 2 Shown as the present invention Figure 1 A local enlarged view of point A in FIG; Figure 3 Shown is a cross-sectional view of the radial reinforcement unit of the present invention; Figure 4 Shown as the present invention Figure 3 A local enlarged view of point B in FIG; Figure 5 Shown as the present invention Figure 3 A local enlarged view of point C in FIG; Figure 6 Shown is a schematic structural diagram of a first steel bar ring and a second steel bar ring of the present invention; Figure 7 Shown is a schematic structural diagram of a second steel bar ring of the present invention; Figure 8 Shown is a schematic structural diagram of the clamping assembly of the present invention; Figure 9 It is a schematic diagram showing the installation of the clamping plate and the base plate of the present invention.

[0018] In the figure: 101, annular baffle; 102, first steel ring; 103, second steel ring; 111. Vertical reinforcement; 112. Circular reinforcement; 201, support arm; 202, steel bars to be planted; 211, mounting plate; 212, clamping plate; 213, bottom plate; 214, slider; 215, slide groove; 216, spring; 221, movable plate; 222, lifting frame; 231, box body; 232, guide channel main plate; 233, first guide channel; 234, second guide channel; 235, connecting groove; 236, through groove; 237, receiving groove; 238, pushing block; 301. Second plane; 302. Rod body. DETAILED DESCRIPTION

[0019] The following describes the implementation of the present invention through specific embodiments. People skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification.

[0020] See also Figures 1 to 9 . It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention. Therefore, they have no substantive technical significance. Any modification of the structure, change in the proportional relationship or adjustment of the size should still fall within the scope of the technical content disclosed by the present invention without affecting the efficacy and purpose that can be achieved by the present invention. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. Changes or adjustments in their relative relationships should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.

[0021] The following embodiments are for illustration only and can be combined with each other, and are not limited to the contents presented in the following single embodiments.

[0022] See also Figures 1 to 9 The present invention provides a fan base auxiliary reinforcement device, which includes: An annular baffle 101, wherein the annular baffle 101 is fixedly mounted on the ground, and a center line of the annular baffle 101 is perpendicular to the ground; The annular baffle 101 can be a whole or can be composed of a plurality of annular baffle petals. The plurality of annular baffle petals are arranged in a circular array along the axis of the annular baffle 101, and adjacent annular baffle petals are fixedly connected end to end. The outer wall of the annular baffle petals is also fixedly installed with reinforcing ribs to strengthen the strength of the annular baffle 101. A first steel ring 102 is fixedly installed in the annular baffle 101, and a second steel ring 103 is fixedly installed in the first steel ring 102. The first steel ring 102 and the second steel ring 103 are both fixedly installed on the ground. The axis of the annular baffle 101, the axis of the first steel ring 102 and the axis of the second steel ring 103 coincide with each other. The area between the first steel ring 102 and the second steel ring 103 is an annular reinforcement area. The first steel bar ring 102 and the second steel bar ring 103 each include a plurality of vertical steel bars 111 and a plurality of annular steel bars 112; The plurality of annular steel bars 112 are sequentially arranged from top to bottom along the axis of the annular baffle 101; The plurality of vertical steel bars 111 are arranged in a circular array along the axis of the annular baffle 101, and the annular steel bars 112 are fixedly connected to the vertical steel bars 111. The fixing between the annular steel bars 112 and the vertical steel bars 111 can be tied with wire or welded. The vertical steel bars 111 can be located inside or outside the annular steel bars 112. One end of the to-be-planted steel bar 202 is against the annular baffle 101, one side of the to-be-planted steel bar 202 is placed on the annular steel bar of the first steel bar ring 102, and the other side of the to-be-planted steel bar 202 is placed on the annular steel bar of the second steel bar ring 103; The distance between the annular steel bars of the second steel bar ring 103 supporting the steel bar to be planted 202 and the annular steel bars of the first steel bar ring 102 is x, and the length of the steel bar to be planted 202 is y, where x<y; Here, taking the example that the vertical steel bars of the first steel ring 102 are located inside the annular steel bars of the first steel ring 102, the inner wall of the annular baffle 101 fits in with the annular steel bars of the first steel ring 102, or there is a gap between the inner wall of the annular baffle 101 and the annular steel bars of the first steel ring 102, and the gap may be smaller than the radius of the second steel ring 103; The first steel bar ring 102 and the second steel bar ring 103 can be woven in advance in a factory and directly transported to the construction site, or they can be woven on site. In order to further improve the construction efficiency, the first steel bar ring 102 and the second steel bar ring 103 are generally woven in advance in a factory. The inner wall of the annular baffle 101 may be perpendicular to the ground, or may be inclined inwards and form an acute angle with the ground, or may be inclined outwards and form an obtuse angle with the ground; A radial rebar planting unit, comprising a support arm 201, a rebar storage box, a clamping assembly, and a lifting assembly; the support arm 201 is rotatably mounted above the annular rebar planting area, and the rotation axis of the support arm 201 coincides with the axis of the second rebar ring 103; A main support column is provided in the second steel bar ring 103, and the main support column is fixedly installed on the ground. The upper part of the main support column extends above the second steel bar ring 103, and a rotating column is rotatably installed on the upper part of the main support column. The axis of the rotating column coincides with the axis of the second steel bar ring 103. One end of the support arm 201 is rotatably connected to the top of the rotating column. A first motor is fixedly installed on the main support column, and the first motor drives the rotating column to rotate through a gear set. The other end of the support arm 201 is fixedly connected to an auxiliary support column, and the auxiliary support column is located outside the annular baffle 101. A tire is rotatably installed on the bottom end surface of the auxiliary support column, and the tire rolls on the ground. A second motor is also fixedly installed on the auxiliary support column, and the second motor drives the tire to rotate to assist the main support column in rotating; The steel bar storage box is fixedly mounted on the support arm 201, and a number of steel bars 202 to be embedded are placed in the steel bar storage box along the radial direction of the annular embedded reinforcement area. The steel bar storage box is provided with a steel bar outlet, and the lifting assembly is provided on the support arm 201. The lifting end of the lifting assembly is provided with a clamping assembly. The steel bars 202 to be embedded fall out from the steel bar outlet and are clamped by the clamping end of the clamping assembly. The lifting end of the lifting assembly descends and places the steel bars 202 to be embedded clamped by the clamping end of the clamping assembly across between the first steel bar ring 102 and the second steel bar ring 103.

[0023] When radial steel bars need to be placed, the steel bars 202 to be embedded fall out from the steel bar outlet of the steel bar storage box and are clamped by the clamping end of the clamping assembly. The lifting end of the lifting assembly descends and places the steel bars 202 to be embedded clamped by the clamping end of the clamping assembly across the first steel bar ring 102 and the second steel bar ring 103.

[0024] In this embodiment, the number of the radial anchoring units is at least two, and the at least two radial anchoring units are arranged in a circular array around the rotation axis of the support arm 201. By setting up multiple radial anchoring units, a fast diameter can be achieved and the construction speed can be accelerated.

[0025] In this embodiment, please refer to Figures 1 to 9 , the clamping assembly includes two clamping modules, and the two clamping modules are symmetrically arranged relative to the steel bar outlet; The clamping modules each include a mounting plate 211, a clamping plate 212, a base plate 213 and a spring 216; The mounting plate 211 is provided on the lifting end of the lifting assembly, and the mounting plate 211 is located below the bottom end surface of the support arm 201; The clamping plate 212 is slidably mounted on the mounting plate 211 , and the sliding direction of the clamping plate 212 is perpendicular to the axial direction of the second steel ring 103 , and the sliding direction of the clamping plate 212 is also perpendicular to the length direction of the support arm 201 ; A sliding rod is fixedly mounted on the clamping plate 212, and the sliding rod slides through the mounting plate 211. A first hydraulic cylinder is also fixedly mounted on the mounting plate 211, and the telescopic end of the first hydraulic cylinder is fixedly connected to the clamping plate 212. The guiding direction of the sliding rod and the telescopic direction of the first hydraulic cylinder are both parallel to the sliding direction of the clamping plate 212. In order to increase the clamping force of the clamping plate 212 on the rebar 202 to be planted, a rubber block can be fixedly installed on the surface of the clamping plate 212 that clamps the rebar 202 to be planted, so as to increase the friction between the clamping plate 212 and the rebar 202 to be planted; The bottom plate 213 is slidably mounted on the bottom end surface of the clamping plate 212, and the clamping plate 212 is located in the middle of the bottom plate 213. One end of the spring 216 is fixedly connected to the bottom plate 213, and the other end of the spring 216 is fixedly connected to the clamping plate 212. The compression direction of the spring 216 is parallel to the sliding direction of the bottom wall. The sliding connection between the bottom plate 213 and the clamping plate 212 can be that the upper end surface of the bottom plate 213 is provided with a slide groove 215, the guide direction of the slide groove 215 is parallel to the sliding direction of the clamping plate 212, and the slider 214 is fixedly mounted on the bottom end surface of the clamping plate 212, and the slider 214 is slidably connected to the slide groove 215; The spring 216 is located in the slide groove 215, one end of the spring 216 is fixedly connected to the slide groove 215, and the other end of the spring 216 is fixedly connected to the slider 214; when the bottom plates of the two clamping modules move toward each other, the side walls of the bottom plates of the two clamping modules contact each other and can be used to support the steel bars 202 to be planted; The plane where the side walls of the bottom plates of the two clamping modules contact each other is the contact surface, and the rotation axis of the support arm 201 is located on the contact surface; The clamping plates of the two clamping modules move toward each other to form a clamping space, and clamp the steel bars 202 to be embedded.

[0026] Starting the first hydraulic cylinder can drive the clamping plate 212 to move toward the middle, thereby also driving the bottom plate 213 to move toward the middle. At this time, the side walls of the bottom plates of the two clamping modules will contact each other, so that the upper end surfaces of the bottom plates of the two clamping modules can be pieced together into a whole surface. When the embedded steel bars 202 fall onto it, the first hydraulic cylinder continues to start so that the clamping plates of the two clamping modules can clamp the embedded steel bars 202.

[0027] In this embodiment, please refer to Figures 1 to 9The number of the clamping assemblies is at least two, and at least two of the clamping assemblies are arranged in sequence along the length direction of the support arm 201.

[0028] The number of the lifting assemblies is the same as the number of the clamping assemblies, and the lifting assemblies correspond one to one with the clamping assemblies. By providing multiple clamping assemblies, when the rebar 202 to be planted falls out of the rebar outlet, the bottom plates of the multiple clamping assemblies can support both ends of the rebar 202 to be planted, thereby ensuring the stability of the clamping.

[0029] In this embodiment, please refer to Figures 1 to 9 , the lifting assembly includes two lifting modules, and the two lifting modules correspond to the two clamping modules respectively; The lifting modules each include a moving plate 221 and a lifting frame 222; The movable plate 221 is movably arranged on the support arm 201, and the moving direction of the movable plate 221 is parallel to the length direction of the support arm 201; Here, the movable plate 221 is slidably mounted on the side wall of the support arm 201. A third motor is fixedly mounted on the support arm 201. A lead screw is rotatably mounted on the support arm 201. The third motor drives the lead screw to rotate. The movable plate 221 is threadedly connected to the lead screw. The rotation axis direction of the lead screw is parallel to the sliding direction of the movable plate 221. The lifting frame 222 is slidably mounted on the movable plate 221 , and the sliding direction of the lifting frame 222 is parallel to the axial direction of the annular rebar planting area; One side of the movable plate 221 extends out of the support arm 201, and the lifting frame 222 is slidably mounted on the protruding portion of the support arm 201 of the movable plate 221. The movable plate 221 is fixedly mounted with a fourth motor, and the lifting frame 222 is fixedly mounted with a rack. The guide direction of the rack is parallel to the sliding direction of the lifting frame 222. A gear is fixedly mounted on the fourth motor, and the gear is meshed with the rack. When the fourth motor is started, the lifting frame 222 can be driven to move up and down through the meshing of the gear and rack. The mounting plate 211 is disposed on the bottom end surface of the lifting frame 222 .

[0030] In this embodiment, please refer to Figures 1 to 9 The mounting plate 211 is rotatably mounted on the bottom end surface of the lifting frame 222 , and the rotation axis of the mounting plate 211 is parallel to the sliding direction of the clamping plate 212 .

[0031] A fifth motor is fixedly mounted on the bottom of the lifting frame 222 , and an output shaft of the fifth motor is fixedly connected to the mounting plate 211 .

[0032] Before the rebar 202 to be planted falls out of the rebar outlet, the first hydraulic cylinders of all the clamping assemblies are started, so that the bottom plates of the two clamping modules can be spliced ​​together. At this time, the distance between the clamping plates of the two clamping modules is greater than the diameter of the rebar 202 to be planted. After the rebar 202 to be planted falls out of the rebar outlet, the two ends of the rebar 202 to be planted can be supported by the bottom plates of all the clamping assemblies. At this time, continue to start the first hydraulic cylinder of one of the clamping assemblies, which can drive the clamping blocks of the two clamping modules to continue to move inward, thereby clamping the rebar 202 to be planted. At this time, since the bottom plates of the two clamping modules conflict with each other, the bottom plates of the clamping modules will not continue to move inward, and then start the fourth motor to drive the lifting frame 222 to descend. At this time, start the fifth motor to rotate clockwise and tilt the rebar 202 to be planted inward, that is, the height of the end of the rebar 202 to be planted close to the second rebar ring 103 is lower than the height of the end of the rebar 202 to be planted close to the first rebar When the lifting frame 222 is lowered, the lifting frame 222 is lowered, and the lifting frame 222 is lowered, so that the lifting frame 222 is lowered, and the lifting frame 222 is lowered.

[0033] In this embodiment, a through hole can also be opened on the bottom end surface of the slide groove 215, and the through hole passes through the bottom end surface of the slide groove 215 and the bottom end surface of the bottom plate 213. The bottom end surface of the slider 214 is fixedly connected to the rod body 302, and the rod body 302 extends downward and extends to the bottom of the bottom plate 213. Through the set rod body 302, when the steel bar 202 to be embedded is placed between the first steel bar ring 102 and the second steel bar ring 103, the position of the steel bar 202 to be embedded can be corrected by the rod body 302 moving toward each other.

[0034] In this embodiment, please refer to Figures 1 to 9 The steel bar storage box includes a box body 231, a guide channel main plate 232, a first guide channel 233, a second guide channel 234, a connecting groove 235 and a through groove 236; The box 231 is fixedly mounted on the support arm 201 and is located above the support plate. The upper portion of the box 231 is open to facilitate placement of the steel bars 202 to be embedded in the box 231. The guide channel main plate 232 is located below the box body 231, and the upper end surface of the guide channel main plate 232 passes through the inner and outer walls of the box body 231 upward; The first guide channel 233 is provided in the guide channel main plate 232. The upper end surface of the first guide channel 233 extends upward through the upper end surface of the guide channel main plate 232 and communicates with the box body 231. The first guide channel 233 is rectangular. The width of the first guide channel 233 is a. The diameter of the to-be-planted reinforcement bar 202 is b, where b≤a<2b. The length of the first guide channel 233 is greater than or equal to the length m of the to-be-planted reinforcement bar 202. The length of the to-be-planted reinforcement bar 202 is n, where m≥n. This arrangement allows multiple steel bars to be planted to be arranged in a row, that is, the individual steel bars to be planted can be stacked in the first guide channel 233 from bottom to top. The second guide channel 234 is provided in the guide channel main plate 232. The second guide channel 234 is identical to the first guide channel 233 and is parallel to the first guide channel 233. The bottom end surface of the second guide channel 234 extends downward and passes through the bottom end surface of the guide channel main plate 232. The connecting groove 235 is formed in the guide channel main plate 232. One end of the connecting groove 235 is connected to the bottom of the first guide channel 233, and the other end of the connecting groove 235 is connected to the second guide channel 234. The bottom end surface of the connecting groove 235 and the bottom end surface of the first guide channel 233 are located on the same plane. The through-slot 236 is provided on the support arm 201 and passes through the upper end surface and the bottom end surface of the support arm 201. The rebar 202 to be planted passes through the first guide channel 233, the connecting groove 235, the second guide channel 234 and the through-slot 236 in sequence from the box body 231 and falls onto the clamping end of the clamping assembly. That is, the bottom of the through-slot 236 is the rebar outlet. The steel bar storage box further includes a receiving slot 237 and a pushing block 238; The receiving groove 237 is provided in the guide channel main plate 232 , one end of the receiving groove 237 is connected to the first guide channel 233 , and the receiving groove 237 and the communicating groove 235 are respectively located on opposite sides of the first guide channel 233 ; The other end of the receiving groove 237 extends outward and penetrates the outer wall of the guide channel main plate 232. The pushing block 238 is slidably connected to the receiving groove 237. The sliding direction of the pushing block 238 is parallel to the center line direction of the connecting groove 235. The second hydraulic cylinder is fixedly mounted on the support arm 201. The telescopic end of the second hydraulic cylinder is fixedly connected to a connecting rod. The connecting rod passes through the receiving groove 237 and is fixedly connected to the pushing block 238. The plane where the upper end surface of the pushing block 238 lies is a first plane, and the first plane is located between the axis of the bottommost steel bar to be planted and the outer wall of the penultimate steel bar to be planted; The length of the pushing block 238 along the width direction of the first guide channel 233 is greater than the width value of the first guide channel 233. The pushing block 238 slides and pushes the steel bars to be embedded at the bottom of the first guide channel 233 from the first guide channel 233 through the connecting groove 235 and into the second guide channel 234.

[0035] Starting the second hydraulic cylinder can drive the pushing block 238 to move toward the first guide channel 233, thereby pushing the bottommost steel bar to be embedded into the connecting groove 235. At this time, the second to last steel bar to be embedded will be blocked by the upper end face of the pushing block 238, so that only one steel bar to be embedded can be pushed out. The pushing block 238 continues to move, allowing the steel bar to be embedded 202 in the connecting groove 235 to enter the second guide channel 234, and allowing the steel bar to be embedded 202 to fall out of the through groove 236 onto the bottom plate 213 of the clamping assembly.

[0036] In this embodiment, the same plane where the bottom end surface of the connecting groove 235 and the bottom end surface of the first guide channel 233 are located is the second plane 301. The second plane 301 is an inclined plane. The height of the second plane 301 on the side close to the second guide channel 234 is h, and the height of the second plane 301 on the side close to the first guide channel 233 is k, and h is greater than k.

[0037] The above embodiments are merely illustrative of the principles and effects of the present invention and are not intended to limit the present invention. Anyone skilled in the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by one of ordinary skill in the art without departing from the spirit and technical principles disclosed herein are intended to be covered by the claims of the present invention.

Claims

1. A fan base auxiliary reinforcement device, characterized in that: An auxiliary rebar planting device is provided, and the auxiliary rebar planting device includes: An annular baffle, wherein the annular baffle is fixedly mounted on the ground, the centerline of the annular baffle is perpendicular to the ground, a first steel bar ring is fixedly mounted in the annular baffle, a second steel bar ring is fixedly mounted in the first steel bar ring, the axis of the annular baffle, the axis of the first steel bar ring, and the axis of the second steel bar ring coincide with each other, and the area between the first steel bar ring and the second steel bar ring is an annular reinforcement area; A radial reinforcement unit, the radial reinforcement unit includes a support arm, a steel bar storage box, a clamping assembly and a lifting assembly; the support arm is rotatably installed above the annular reinforcement area, the rotation axis of the support arm coincides with the axis of the second steel bar ring, the steel bar storage box is fixedly installed on the support arm, a number of steel bars to be embedded are placed in the steel bar storage box along the radial direction of the annular reinforcement area, the steel bar storage box is provided with a steel bar outlet, the lifting assembly is provided on the support arm, and the lifting end of the lifting assembly is provided with a clamping assembly, the steel bars to be embedded fall out from the steel bar outlet and are clamped by the clamping end of the clamping assembly, the lifting end of the lifting assembly descends and places the steel bars to be embedded clamped by the clamping end of the clamping assembly across the first steel bar ring and the second steel bar ring.

2. The auxiliary reinforcement planting device for a fan base according to claim 1 is characterized in that: The first steel bar ring and the second steel bar ring each include a plurality of vertical steel bars and a plurality of annular steel bars; The plurality of annular steel bars are arranged in sequence from top to bottom along the axis of the annular baffle; The plurality of vertical steel bars are arranged in a circular array along the axis of the annular baffle, and the annular steel bars are fixedly connected to the vertical steel bars; One end of the steel bar to be planted is against the annular baffle, one side of the steel bar to be planted is placed on the annular steel bar of the first steel bar ring, and the other side of the steel bar to be planted is placed on the annular steel bar of the second steel bar ring; The distance between the annular steel bars of the second steel bar ring supporting the steel bars to be planted and the annular steel bars of the first steel bar ring is x, and the length of the steel bars to be planted is y, where x<y.

3. The auxiliary reinforcement planting device for a fan base according to claim 1, characterized in that: The clamping assembly includes two clamping modules, and the two clamping modules are symmetrically arranged relative to the steel bar outlet; The clamping modules each include a mounting plate, a clamping plate, a base plate and a spring; The mounting plate is provided on the lifting end of the lifting assembly, and the mounting plate is located below the bottom end surface of the support arm; The clamping plate is slidably mounted on the mounting plate, wherein the sliding direction of the clamping plate is perpendicular to the axial direction of the second steel bar ring, and the sliding direction of the clamping plate is also perpendicular to the length direction of the support arm; The bottom plate is slidably mounted on the bottom end surface of the clamping plate, one end of the spring is fixedly connected to the bottom plate, and the other end of the spring is fixedly connected to the clamping plate, and the compression direction of the spring is parallel to the sliding direction of the bottom wall; When the bottom plates of the two clamping modules move toward each other, the side walls of the bottom plates of the two clamping modules come into contact with each other and can be used to support the steel bars to be planted; The clamping plates of the two clamping modules move toward each other to form a clamping space, and clamp the steel bars to be embedded.

4. The auxiliary reinforcement planting device for a fan base according to claim 3 is characterized in that: The upper end surface of the bottom plate is provided with a slide groove, the guide direction of the slide groove is parallel to the sliding direction of the clamping plate, the slider is fixedly mounted on the bottom end surface of the clamping plate, and the slider is slidably connected to the slide groove; The spring is located in the slide groove, one end of the spring is fixedly connected to the slide groove, and the other end of the spring is fixedly connected to the slider.

5. The auxiliary reinforcement planting device for a fan base according to claim 3 is characterized in that: The number of the clamping assemblies is at least two, and the at least two clamping assemblies are arranged in sequence along the length direction of the support arm.

6. The auxiliary reinforcement planting device for a fan base according to claim 3, characterized in that: The lifting assembly includes two lifting modules, and the two lifting modules correspond to the two clamping modules one by one; The lifting modules each include a movable plate and a lifting frame; The movable plate is movably arranged on the support arm, and the moving direction of the movable plate is parallel to the length direction of the support arm; The lifting frame is slidably mounted on the movable plate, and the sliding direction of the lifting frame is parallel to the axial direction of the annular rebar planting area; The mounting plate is arranged on the bottom end surface of the lifting frame.

7. The auxiliary reinforcing bar planting device for a fan base according to claim 6, characterized in that: The mounting plate is rotatably mounted on the bottom end surface of the lifting frame, and the rotation axis of the mounting plate is parallel to the sliding direction of the clamping plate.

8. The auxiliary reinforcement planting device for a fan base according to claim 5, characterized in that: The number of the lifting assemblies is the same as the number of the clamping assemblies, and the lifting assemblies correspond to the clamping assemblies in a one-to-one manner.

9. The auxiliary reinforcement planting device for a fan base according to claim 1, characterized in that: The steel bar storage box includes a box body, a guide channel main plate, a first guide channel, a second guide channel, a connecting groove and a through groove; The box is fixedly mounted on the support arm; The guide channel main plate is located below the box body, and the upper end surface of the guide channel main plate passes through the inner and outer walls of the box body upward; The first guide channel is provided in the guide channel main body plate, the upper end surface of the first guide channel extends upward through the upper end surface of the guide channel main body plate and communicates with the box body, the first guide channel is rectangular, the width of the first guide channel is a, the diameter of the steel bar to be planted is b, b≤a<2b, the length of the first guide channel is greater than or equal to the length of the steel bar to be planted is m, the length of the steel bar to be planted is n, and m≥n; The second guide channel is provided in the guide channel main plate. The second guide channel is identical to the first guide channel and is parallel to the first guide channel. The bottom end surface of the second guide channel extends downward and passes through the bottom end surface of the guide channel main plate. The communicating groove is provided in the main plate of the guide channel, one end of the communicating groove is connected to the bottom of the first guide channel, and the other end of the communicating groove is connected to the second guide channel, and the bottom end surface of the communicating groove and the bottom end surface of the first guide channel are located on the same plane; The through groove is opened on the support arm and passes through the upper end surface and the bottom end surface of the support arm. The steel bars to be embedded pass through the first guide channel, the connecting groove, the second guide channel and the through groove in sequence from the box body and fall onto the clamping end of the clamping assembly.

10. The auxiliary reinforcement planting device for a fan base according to claim 9, characterized in that: The steel bar storage box also includes a receiving slot and a pushing block; The receiving groove is provided in the main plate of the guide channel, the receiving groove is connected to the first guide channel, and the receiving groove and the communicating groove are respectively located on two opposite sides of the first guide channel; The pushing block is slidably connected to the accommodating groove, the sliding direction of the pushing block is parallel to the center line direction of the communicating groove, the plane where the upper end surface of the pushing block is located is a first plane, and the first plane is located between the axis of the bottommost steel bar to be planted and the outer wall of the penultimate steel bar to be planted; The length of the pushing block along the width direction of the first guide channel is greater than the width value of the first guide channel. The pushing block slides and pushes the steel bars to be embedded at the bottom of the first guide channel from the first guide channel through the connecting groove and into the second guide channel.

11. A method for planting reinforcement bars using the auxiliary reinforcement bar planting device for a fan base according to any one of claims 1 to 10, characterized in that: A plurality of steel bars to be planted are stored in a steel bar storage box, and the steel bars to be planted dropped out of the steel bar storage box are clamped by a clamping assembly. The clamped steel bars to be planted are placed between the first steel bar ring and the second steel bar ring by a lifting assembly, and a whole circle of steel bars to be planted can be placed by rotating a support arm; By rotating the mounting plate and installing it on the lifting frame, the clamped steel bars to be planted are rotated. When placing the steel bars to be planted, the steel bars to be planted can be first rotated to be inclined in the direction of the second steel bar ring, and then one end of the steel bar to be planted can be placed on the ring steel bar of the second steel bar ring, and the steel bar to be planted can be inserted into the second steel bar ring, and then one end of the steel bar to be planted can be rotated downward and placed on the ring steel bar of the first steel bar ring, so that the steel bar to be planted can be placed between the ring steel bars of the first steel bar ring and the ring steel bars of the second steel bar ring; By setting the first guide channel, the second guide channel, the connecting groove and the pushing block, when the pushing block slides, only the steel bars to be embedded in the bottom of the first guide channel can be pushed out of the first guide channel, thereby enabling the embedding of steel bars one by one, which is convenient for rapid loading.