Intelligent material management method and system
By recording the basic information of building materials and the maximum number of recycling times in detail, assigning a unique identification code to each material, updating the usage status in real time and evaluating the residual value, the problems of low resource utilization and high construction costs in existing technologies are solved, and efficient management and tracking throughout the process are achieved.
Patent Information
- Application Number
- CN202510802577.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-16
- Publication Date
- 2025-09-16
AI Technical Summary
The existing material management system has shortcomings in handling the efficient recycling and tracking of recyclable construction materials. It is unable to accurately calculate and record the maximum number of recycling times of materials, and lacks dynamic adjustment and optimization of resource allocation, resulting in low resource utilization and increased construction costs.
By registering the basic information and initial status of the materials, calculating and recording the maximum number of recycling uses, assigning a unique identification code to each material, updating the number of uses and status in real time, evaluating the residual value, and deciding on the reuse or scrapping method based on the evaluation results, adjusting inventory records to reflect the latest status changes.
It significantly improves the optimal allocation and recycling efficiency of resources, reduces construction costs and resource waste, and realizes efficient management and tracking of construction materials from registration to final processing.
Smart Images

Figure CN120655209A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of smart construction sites, and specifically relates to a smart material management method and system. Background Art
[0002] In current smart construction site management, material management systems typically rely on traditional inventory management and simple barcode or QR code identification to track the status and usage of construction materials. The main solutions in existing technologies include the following aspects: Basic information registration: Record basic information of building materials, such as name, specification, quantity, etc., by manual entry or scanning of QR codes.
[0003] Inventory management: The warehouse management system (WMS) is used to store, ship and count construction materials, but there is a lack of effective tracking of the number of times the materials are recycled.
[0004] Condition monitoring: Some systems can update the usage status of materials in real time, but fail to fully incorporate the maximum number of material cycles for effective resource optimization.
[0005] Scrap processing: When materials reach the end of their service life, the system will mark them as scrapped, but there is no detailed residual value assessment mechanism, resulting in waste of resources.
[0006] Existing material management systems are inadequate for the efficient recycling and tracking of recyclable construction materials. Specifically, they are unable to accurately calculate and record the maximum number of times building materials can be recycled, and lack the ability to dynamically adjust and optimize resource allocation. This results in low resource utilization, increased construction costs, and unnecessary waste. Summary of the Invention
[0007] The purpose of the present invention is to provide an intelligent material management method and system, which realizes efficient management and tracking of construction materials from registration to final processing, significantly improves the optimal allocation and recycling efficiency of resources, reduces construction costs and resource waste, and solves the problems raised in the above background technology.
[0008] To achieve the above objectives, the present invention provides a smart material management method, comprising the following steps: Registering basic information and initial status of the material, and calculating and recording the maximum number of recycling times of the material based on the basic information; Assign an identification code to the material according to the maximum number of recycled uses and store the identification code in a database; whenever the material is used, update the number of uses in the database and mark the current status of the material; Based on the current state, checking whether a maximum number of recycling times has been reached, if not, continuing monitoring until the maximum number of recycling times has been reached, and once the maximum number of recycling times has been reached, evaluating the residual value of the material and recording the evaluation result; Based on the evaluation results, the reuse or scrapping treatment of the material is determined, the results of the treatment are fed back to the system, and the inventory records of the material are adjusted to reflect the latest status changes.
[0009] Preferably, the basic information and initial status of the registration materials include: Obtain the material identification number X, measure and record the material's size L, width W, height H, and type T based on the identification number X, and calculate the material's volume V = L*W*H; According to the type T and volume V of the material, estimate the basic value of the material BV=V*UPV, where UPV is the preset unit volume value; The identification number X, size L, width W, height H, type T, volume V and basic value BV are entered into the database to complete the registration of basic information and initial status.
[0010] Preferably, based on the basic information, the maximum number of recycling times of the material is calculated and recorded, including: Obtain the basic value BV and type T of the material, and determine the material durability coefficient D based on the material type T; Calculate the maximum number of cycles MCU = BV / D based on the base value BV and the durability coefficient D, associate the maximum number of cycles MCU with the identity identification number X, and record it in the database; Based on the maximum number of cycles MCU, the potential reuse rate of the material throughout its life cycle is evaluated and marked in the initial state record of the material.
[0011] Preferably, according to the maximum number of recycling times, an identification code is assigned to the material and stored in a database, including: Obtain the maximum number of recycled uses MCU and the identification number X of the material, and determine the dynamic coefficient DC based on the maximum number of recycled uses MCU. The dynamic coefficient DC is determined by the maximum number of recycled uses and is calculated as DC=1+0.1*MCU; The dynamic coefficient DC and the identity number X are used to generate an identification code ID, the formula is ID=INT(X+DC), and the identification code ID and all relevant information of the material, including the maximum number of cycles MCU, basic value BV, and type T, are recorded in a database.
[0012] Preferably, whenever the material is used, the number of times the material is used in the database is updated, and the current status of the material is marked, including: Obtain the material's identification code ID and current usage count CU. Based on the identification code ID, retrieve all relevant information about the material in the database. Every time the material is used, increase the current usage count by the formula new CU = CU + 1. Calculate the remaining usable times of the material RCU = MCU - new CU, and mark the current status of the material according to the remaining usable times RCU. If the remaining usable times are greater than zero, mark it as in use, otherwise mark it as pending evaluation; The new usage count CU and current status are updated in the record associated with the identification code ID in the database.
[0013] Preferably, according to the current state, checking whether the maximum number of cycles has been reached, and if not, continuing monitoring until it is reached, including:
[0014] Obtain the material's identification code ID, current usage count (new CU), and maximum cyclic usage count (MCU). Based on the identification code ID, retrieve the material's current status from the database and calculate the material's remaining usage count (RCU = MCU - new CU). Check the current status. If it is marked as in use and the remaining number of uses is greater than zero, set the monitoring cycle T=1 / RCU, which means that a status check is performed at regular intervals. At the end of each monitoring cycle, obtain the current number of uses of the material again and update the remaining number of uses RCU=MCU-newCU until the remaining number of uses is equal to zero. At this time, the current status of the material is updated to pending evaluation and recorded in the database.
[0015] Preferably, once the maximum number of recycling times is reached, evaluating the residual value of the material and recording the evaluation results include: Obtain the material's identification code ID, maximum number of cycles used MCU, and current number of uses CU, and confirm that the current number of uses is equal to the maximum number of cycles used; Based on the identification code ID, the basic value BV, type T and historical usage records of the material are retrieved from the database to calculate the depreciation rate DR of the material = new CU / MCU; According to the depreciation rate, the residual value RV of the material is evaluated as RV = BV * (1-DR), and the residual value RV, the type T of the material, the state and other relevant information are recorded in the database; The status of the material is marked as evaluated, and the evaluation result is associated with the identification code ID and stored.
[0016] Preferably, based on the evaluation results, the recycling or scrapping of the material is determined, including: Obtain the identification code ID, residual value RV and type T of the material, and determine the reuse threshold RT = BV * 0.2 based on the residual value RV; comparing the residual value RV with the reuse threshold RT, and marking the material as suitable for reuse if the residual value is greater than the reuse threshold; For materials marked as suitable for reuse, calculate the estimated reuse cost RC = BV * 0.1 and compare the cost with the stated residual value; If the residual value is higher than the estimated recycling cost, updating the status of the material to recommended recycling and recording it in the database; If the residual value is lower than the reuse threshold or higher than the reuse cost but not suitable for reuse, the status of the material is updated to recommended scrapping, and the final disposal recommendation is recorded in the database.
[0017] Preferably, the results of the processing are fed back to the system, and the inventory records of the materials are adjusted to reflect the latest status changes, including: Obtain the material's identification code ID, processing method, and current inventory quantity Q; Based on the processing method, an adjustment coefficient AC is determined; if the mark is recommended for reuse, the adjustment coefficient is 0.9; if the mark is recommended for scrapping, the adjustment coefficient is 0; Updating the inventory quantity of the material according to the adjustment coefficient using the formula: new inventory quantity Q = Q * AC; associating the result of the processing method with the identification code ID of the material, and feeding back the result to the database; updating the status information of the material in the database, including the processing method and the new inventory quantity; Calculate the new inventory value of the material NV = BV * New Q and record the new inventory value in the database.
[0018] In another aspect, the present invention provides a smart material management system, comprising: A material information acquisition module is used to register basic information and initial status of the material, and based on the basic information, calculate and record the maximum number of recycling times of the material; a material information updating module, configured to assign an identification code to a material according to the maximum number of cycles of use, and store the identification code in a database; and whenever the material is used, to update the number of uses in the database and mark the current status of the material; a material evaluation module, configured to check whether a maximum number of recycling times has been reached based on the current state, and if not, continue monitoring until the maximum number of recycling times has been reached; and once the maximum number of recycling times has been reached, evaluate the residual value of the material and record the evaluation result; The material adjustment module is used to determine the reuse or scrapping treatment of the material based on the evaluation results, feed the results of the treatment method back to the system, and adjust the inventory records of the material to reflect the latest status changes.
[0019] Technical effects and advantages of the present invention: Compared with the existing technology, the intelligent material management method and system proposed in the present invention have the following advantages: The present invention records the basic information and initial status of building materials in detail, calculates their maximum number of recycling uses, and assigns a unique identification code to each material, thereby achieving accurate tracking of material use. The number of uses and current status in the database are updated after each use, and continuous monitoring is carried out until the maximum number of recycling uses is reached, at which point the residual value is evaluated and the results are recorded. Based on the evaluation results, the reuse or scrapping of the material is determined, and the processing results are fed back to the system. At the same time, the inventory records are adjusted to reflect the latest status changes. This series of steps significantly improves the optimal allocation and recycling efficiency of resources, reduces construction costs and resource waste, and achieves efficient management and tracking of building materials from registration to final processing. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 This is a flow chart of a smart material management method of the present invention; Figure 2 This is a block diagram of a smart material management system of the present invention. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0022] This invention provides an intelligent material management method that achieves efficient management and tracking of construction materials from registration to final disposal, significantly improving the optimal allocation and recycling efficiency of resources, and reducing construction costs and resource waste. The details are as follows: like Figure 1 As shown, a smart material management method in this embodiment includes the following steps: Step 1: Basic information and initial status of registration materials; specifically including: Obtain the material's identification number, X, to ensure accurate identification and tracking of each material in subsequent operations. Based on this identification number, measure and record the material's dimensions (L), width (W), height (H), and type (T), and calculate its volume (V) as L*W*H. For example, if a building material has a length (L) of 2 meters, a width (W) of 1 meter, and a height (H) of 0.5 meters, its volume (V) is 2*1*0.5 = 1 cubic meter. Calculating the material's volume provides key parameters for subsequently estimating its base value.
[0023] Based on the material type T and volume V, the base value of the material is estimated as BV = V * UPV, where UPV is the preset unit volume value; this value is updated regularly based on market conditions and reflects the market value of different types of materials. For example, if the volume V of a building material is 1 cubic meter and the unit volume value UPV for this type of material is 100 yuan / cubic meter, its base value BV = 1 * 100 = 100 yuan. By combining the material's volume and unit volume value, the base value of the material is estimated, providing a basis for subsequent assessment of the material's residual value and determining its disposal method.
[0024] The identification number X, size L, width W, height H, type T, volume V and basic value BV are entered into the database to complete the registration of basic information and initial status, ensure the integrity and accuracy of the data, and facilitate subsequent management and tracking.
[0025] Step 2: Based on the basic information, calculate and record the maximum number of recycling times of the material; specifically including: Obtain the basic value (BV) and type (T) of the material, and determine the material durability coefficient (D) based on the material type (T); the basic value (BV) reflects the initial market value of the material, while the type (T) determines its physical and chemical properties, which in turn affect its durability.
[0026] Based on the base value (BV) and the durability coefficient (D), the maximum number of cycles (MCU) is calculated as BV / D. This maximum number of cycles is associated with the identification number (X) and recorded in the database. Assuming that a building material type (T) is "reinforced concrete," its durability coefficient (D) is 0.8. Determining the material's durability coefficient (D) provides a key parameter for the subsequent calculation of the maximum number of cycles (MCU), ensuring the accuracy of the assessment results.
[0027] Based on the maximum number of cycles (MCU), the potential reuse rate of the material throughout its life cycle is assessed and marked in the material's initial state record, allowing the system to fully understand the recyclability potential of each material. This marking facilitates subsequent resource optimization and reuse decisions.
[0028] Step 3: assigning an identification code to the material according to the maximum number of recycling uses and storing it in a database; specifically comprising: Obtain the material's maximum number of cycles (MCU) and identification number (X). Based on the maximum number of cycles (MCU), determine the dynamic coefficient (DC). The dynamic coefficient (DC) is determined by the maximum number of cycles (MCU) and is calculated using the formula DC = 1 + 0.1 * MCU. The dynamic coefficient (DC) is a factor determined based on the material's maximum number of cycles (MCU) to increase the uniqueness and distinction of the identification code. The formula DC = 1 + 0.1 * MCU indicates that the dynamic coefficient equals 1 plus the maximum number of cycles multiplied by 0.1.
[0029] Assuming the maximum number of MCU cycles for a building material is 125, its dynamic coefficient DC = 1 + 0.1 * 125 = 13.5. By calculating the dynamic coefficient DC, the identification code not only relies on the material's identity number X but also incorporates the material's maximum number of cycles, increasing the uniqueness of the identification code and improving management accuracy.
[0030] The dynamic coefficient DC and the identification number X are used to generate an identification code ID using the formula ID = INT(X + DC). This ensures that each material has a unique identification code, facilitating subsequent management and tracking. For example, if the identification number X of a building material is 12345 and the dynamic coefficient DC is 13.5, its identification code ID = INT(12345 + 13.5) = 12358. By generating a unique identification code ID, each material is uniquely identified in the system, facilitating subsequent usage status updates, monitoring, and reuse decisions.
[0031] The identification code ID and all relevant information of the material, including the maximum number of cycles MCU, basic value BV, and type T, are recorded in the database. This information provides solid data support for subsequent resource optimization, usage status updates, and reuse decisions.
[0032] Step 4: Whenever the material is used, update the usage count in the database and mark the current status of the material; specifically including: Obtain the material's identification code ID and current usage count CU. The identification code ID ensures the uniqueness of each material, while the current usage count CU is used to track the actual usage of the material.
[0033] Based on the identification code ID, all relevant information about the material (such as the maximum number of cycles, MCU, base value, BV, type, etc.) is retrieved from the database. This ensures complete information when updating usage counts and status, thereby improving management accuracy. Each time a material is used, the current usage count is incremented using the formula: New CU = CU + 1. This helps accurately record the material's usage frequency. For example, if a building material has a current usage count of 5 times, when it is used again, the new usage count is New CU = 5 + 1 = 6 times. By incrementing the current usage count, the system accurately records the material's actual usage, facilitating subsequent management and decision-making.
[0034] Calculate the remaining usable count (RCU) of a material using MCU minus the new CU. Assuming a building material has a maximum reusable count (MCU) of 125 and a current usage count (new CU) of 6, its remaining usable count (RCU) equals 125 minus 6, which is 119. By calculating the remaining usable count, the system can understand the material's remaining useful life in real time, providing a basis for subsequent status marking and management. Based on the remaining usable count (RCU), the material's current status is marked. If the remaining usable count is greater than zero, it is marked as "in use"; otherwise, it is marked as "pending evaluation." This status marking facilitates subsequent resource optimization and reuse decisions. Assuming a building material has a remaining usable count (RCU) of 119, it is marked as "in use"; if the remaining usable count is 0, it is marked as "pending evaluation."
[0035] The new usage count (CU) and current status are updated in the record associated with the identification code ID in the database to ensure that the data in the system is always up to date and accurate.
[0036] Step 5: Based on the current status, check whether the maximum number of cycles has been reached. If not, continue monitoring until it is reached. Specifically, the steps include: The system obtains the material's identification code ID, current usage count (New CU), and maximum cycle usage count (MCU). Based on this ID, the system retrieves the material's current status (e.g., "in use" or "pending evaluation") from the database, ensuring that the system can make appropriate decisions and management operations based on the material's actual usage. The remaining usable count (RCU) is calculated as MCU - New CU, meaning the number of times a material can still be used is calculated by subtracting the current usage count. For example, if the maximum cycle usage count (MCU) of a building material is 125 and the current usage count (New CU) is 6, then its remaining usable count (RCU) = 125 - 6 = 119. By calculating the remaining usable count, the system can understand the material's remaining service life in real time, providing a basis for subsequent status marking and management.
[0037] Check the current status. If it's marked as in use and the remaining number of uses is greater than zero, set the monitoring cycle T = 1 / RCU, indicating a status check at regular intervals. This formula helps the system dynamically adjust the monitoring frequency, ensuring more frequent monitoring of high-use materials. For example, if the remaining number of uses (RCU) for a building material is 119, then its monitoring cycle T = 1 / 119 ≈ 0.0084 (units of time). This means the system will perform a status check approximately every 0.0084 units of time.
[0038] At the end of each monitoring cycle, the current usage count of the material is obtained again, and the remaining usable count RCU=MCU-new CU is updated until the remaining usable count is equal to zero. When the remaining usable count is equal to zero, the system automatically updates the current status of the material to "pending evaluation" and records it in the database.
[0039] Step 6: Once the maximum number of recycling times is reached, assess the residual value of the material and record the assessment results; specifically, include: Obtain the material's identification code, maximum number of cycles (MCU), and current number of cycles (new CU). Verify that the current number of cycles equals the maximum number of cycles. If this is the case, the material requires residual value assessment. For example, suppose the identification code of a building material is 12358, the maximum number of cycles (MCU) is 125, and the current number of cycles (new CU) is 125.
[0040] Based on the material's identification code (ID), the system retrieves the material's base value (BV), type (T), and historical usage history from the database and calculates the material's depreciation rate (DR) = New CU / MCU. This represents the material's depreciation calculated by dividing its current usage by its maximum number of cycles. This helps quantify the material's value loss. For example, if a building material's current usage (New CU) is 125 and its maximum number of cycles (MCU) is 125, its depreciation rate (DR) = 125 / 125 = 1. By calculating the depreciation rate, the system can quantify the material's value loss and provide a basis for subsequent residual value assessment.
[0041] Based on the depreciation rate, the residual value (RV) of the material is assessed as BV*(1-DR). This represents the calculation of the material's residual value by multiplying the base value by (1 minus the depreciation rate). This helps assess the material's actual value at the end of its lifecycle. The residual value (RV) is recorded in the database along with the material's type (T), condition, and other relevant information. By calculating the residual value, the system can determine the material's actual value at the end of its lifecycle, providing a basis for subsequent resource optimization and reuse decisions.
[0042] Mark the status of the material as "assessed" and store the assessment results in association with the identification code ID to ensure that the system can accurately track the assessment status of each material, facilitating subsequent management and decision-making.
[0043] Step 7: Based on the assessment results, decide on the material's reuse or disposal method; specifically, including: The system obtains the material's identification code ID, residual value RV, and type T. Based on the residual value RV, it determines a reuse threshold RT = BV * 0.2. This threshold is determined by multiplying the material's base value by 0.2. This threshold is used to determine whether the material has sufficient residual value for reuse. For example, if the base value BV of a building material is 100 yuan, its reuse threshold RT = 100 * 0.2 = 20 yuan. By calculating the reuse threshold, the system can set a standard for determining whether a material is worth reusing, thereby improving resource reuse.
[0044] By comparing the residual value (RV) with the reuse threshold (RT), if the residual value is greater than the reuse threshold, the material is marked as "suitable for reuse." This marking helps in subsequent resource optimization and reuse decisions. For example, if the residual value (RV) of a building material is 30 yuan and the reuse threshold (RT) is 20 yuan, the material is marked as "suitable for reuse." For materials marked as suitable for reuse, the estimated reuse cost (RC) is calculated as BV*0.1 and compared with the residual value, which means estimating the additional cost required for reuse by multiplying the base value of the material by 0.1. This helps assess the practical feasibility of reuse.
[0045] Assuming the base value (BV) of a building material is 100 yuan, its estimated reuse cost (RC) = 100*0.1 = 10 yuan. By calculating the estimated reuse cost, the system can evaluate the actual cost of reuse and compare it with the residual value to determine the economic feasibility of reuse. If the residual value is higher than the estimated reuse cost, the material's status is updated to "Recommended for Reuse" and recorded in the database. This status mark facilitates subsequent resource management and reuse operations. For example, if the residual value (RV) of a building material is 30 yuan and the estimated reuse cost (RC) is 10 yuan, the material's status is updated to "Recommended for Reuse."
[0046] If the residual value (RV) falls below the reuse threshold, or if it exceeds the reuse cost but is unsuitable for reuse, the material's status is updated to "Scrap Recommended," and the final disposal recommendation is recorded in the database. This status marking facilitates subsequent resource management and disposal decisions. For example, if the residual value (RV) of a construction material is 15 yuan (below the reuse threshold of 20 yuan), the material's status is updated to "Scrap Recommended."
[0047] Step 8: Feedback the results of the processing method to the system and adjust the inventory records of the materials to reflect the latest status changes; specifically including: Obtain the material's identification code ID, disposal method (such as "reuse recommended" or "scrap recommended"), and current inventory quantity Q; the identification code ID ensures the uniqueness of each material, while the disposal method and current inventory quantity are used to determine the specific operation of inventory adjustment.
[0048] The adjustment factor (AC) is determined based on the disposal method and is used to adjust the material's inventory quantity. If a material is marked "Recommended for Reuse," the adjustment factor is 0.9, indicating that it still has a high reuse value, and the inventory quantity is reduced but not completely eliminated. If a material is marked "Scrap Recommended," the adjustment factor is 0, indicating that the material no longer has any use value, and the inventory quantity is cleared.
[0049] For example, if the disposal method for a building material is "recommended for reuse," the adjustment coefficient AC is 0.9; if the disposal method is "scrapping recommended," the adjustment coefficient AC is 0. By determining the adjustment coefficient, the system can dynamically adjust inventory quantities based on the material's disposal method, ensuring accurate and effective inventory management.
[0050] The material's inventory quantity is updated based on the adjustment factor. The formula is New Inventory Quantity Q = Q * AC, which means the inventory quantity is updated by multiplying the current inventory quantity by the adjustment factor. This helps accurately adjust inventory based on the material's disposal method. For example, if the current inventory quantity Q of a building material is 100 units and the disposal method is "Recommend Reuse," the adjustment factor AC = 0.9, and the new inventory quantity Q = 100 * 0.9 = 90 units. If the disposal method is "Scrap Recommended," the adjustment factor AC = 0, and the new inventory quantity Q = 100 * 0 = 0 units.
[0051] The results of the treatment method are associated with the material's ID and fed back to the database to update the material's status information (such as the treatment method and the new inventory quantity), ensuring that the data in the system is always up-to-date and accurate. This provides reliable data support for subsequent resource management and decision-making.
[0052] Calculate the material's new inventory value (NV) = BV * New Q and record it in the database. The formula NV = BV * New Q calculates the material's new inventory value by multiplying the material's base value by the new inventory quantity. This helps assess the material's remaining economic value throughout its lifecycle.
[0053] For example, if the base value (BV) of a building material is 100 yuan and the new inventory quantity (Q) is 90 units, then its new inventory value (NV) is 100*90 = 9,000 yuan. If the new inventory quantity (Q) is 0 units, then the new inventory value (NV) is 100*0 = 0 yuan. By calculating the new inventory value, the system can determine the actual economic value of the material at the end of its life cycle, providing a basis for subsequent resource optimization and financial decision-making.
[0054] On the other hand, the present invention proposes a smart material management system, such as Figure 2 As shown, including: A material information acquisition module is used to register basic information and initial status of the material, and based on the basic information, calculate and record the maximum number of recycling times of the material; a material information updating module, configured to assign an identification code to a material according to the maximum number of cycles of use, and store the identification code in a database; and whenever the material is used, to update the number of uses in the database and mark the current status of the material; a material evaluation module, configured to check whether a maximum number of recycling times has been reached based on the current state, and if not, continue monitoring until the maximum number of recycling times has been reached; and once the maximum number of recycling times has been reached, evaluate the residual value of the material and record the evaluation result; The material adjustment module is used to determine the reuse or scrapping treatment of the material based on the evaluation results, feed the results of the treatment method back to the system, and adjust the inventory records of the material to reflect the latest status changes.
[0055] In addition, the above-mentioned material information acquisition module, material information update module, material evaluation module, and material adjustment module are also used to implement other steps of the above-mentioned intelligent material management method when executed, which are not described one by one here.
[0056] In summary, this invention achieves precise tracking of material usage by recording the basic information and initial status of building materials in detail, calculating their maximum number of recycling cycles, and assigning a unique identification code to each material. After each use, the database updates the number of uses and current status. Monitoring continues until the maximum number of recycling cycles is reached, at which point the remaining value is assessed and recorded. Based on this assessment, the system determines whether the material should be reused or scrapped, and the resulting disposal is fed back to the system. Inventory records are also adjusted to reflect the latest status changes.
[0057] This series of steps significantly improves the optimal allocation and recycling efficiency of resources, reduces construction costs and resource waste, and realizes efficient management and tracking of construction materials from registration to final processing.
[0058] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A smart material management method, characterized in that: The following steps are involved: Registering basic information and initial status of the material, and calculating and recording the maximum number of recycling times of the material based on the basic information; Assign an identification code to the material according to the maximum number of recycled uses and store the identification code in a database; whenever the material is used, update the number of uses in the database and mark the current status of the material; Based on the current state, checking whether a maximum number of recycling times has been reached, if not, continuing monitoring until the maximum number of recycling times has been reached, and once the maximum number of recycling times has been reached, evaluating the residual value of the material and recording the evaluation result; Based on the evaluation results, the reuse or scrapping treatment of the material is determined, the results of the treatment are fed back to the system, and the inventory records of the material are adjusted to reflect the latest status changes.
2. A smart material management method according to claim 1, characterized in that: The basic information and initial status of the registration materials include: Obtain the material identification number X, measure and record the material's size L, width W, height H, and type T based on the identification number X, and calculate the material's volume V = L*W*H; According to the type T and volume V of the material, estimate the basic value of the material BV=V*UPV, where UPV is the preset unit volume value; The identification number X, size L, width W, height H, type T, volume V and basic value BV are entered into the database to complete the registration of basic information and initial status.
3. A smart material management method according to claim 2, characterized in that: Based on the basic information, calculate and record the maximum number of recycling times of the material, including: Obtain the basic value BV and type T of the material, and determine the material durability coefficient D based on the material type T; Calculate the maximum number of cycles MCU = BV / D based on the base value BV and the durability coefficient D, associate the maximum number of cycles MCU with the identity identification number X, and record it in the database; Based on the maximum number of cycles MCU, the potential reuse rate of the material throughout its life cycle is evaluated and marked in the initial state record of the material.
4. A smart material management method according to claim 3, characterized in that: According to the maximum number of recycling uses, an identification code is assigned to the material and stored in a database, including: Obtain the maximum number of recycled uses MCU and the identification number X of the material, and determine the dynamic coefficient DC based on the maximum number of recycled uses MCU. The dynamic coefficient DC is determined by the maximum number of recycled uses and is calculated as DC=1+0.1*MCU; The dynamic coefficient DC and the identity number X are used to generate an identification code ID, the formula is ID=INT(X+DC), and the identification code ID and all relevant information of the material, including the maximum number of cycles MCU, basic value BV, and type T, are recorded in a database.
5. A smart material management method according to claim 4, characterized in that: Whenever the material is used, the number of times it is used in the database is updated, and the current status of the material is marked, including: Obtain the material's identification code ID and current usage count CU. Based on the identification code ID, retrieve all relevant information about the material in the database. Every time the material is used, increase the current usage count by the formula new CU = CU + 1. Calculate the remaining usable times of the material RCU = MCU - new CU, and mark the current status of the material according to the remaining usable times RCU. If the remaining usable times are greater than zero, mark it as in use, otherwise mark it as pending evaluation; The new usage count CU and current status are updated in the record associated with the identification code ID in the database.
6. A smart material management method according to claim 5, characterized in that: Based on the current state, check whether the maximum number of cycles has been reached. If not, continue monitoring until it is reached, including: Obtain the material's identification code ID, current usage count (new CU), and maximum cyclic usage count (MCU). Based on the identification code ID, retrieve the material's current status from the database and calculate the material's remaining usage count (RCU = MCU - new CU). Check the current status. If it is marked as in use and the remaining number of uses is greater than zero, set the monitoring cycle T=1 / RCU, which means that a status check is performed at regular intervals. At the end of each monitoring cycle, obtain the current number of uses of the material again and update the remaining number of uses RCU=MCU-newCU until the remaining number of uses is equal to zero. At this time, the current status of the material is updated to pending evaluation and recorded in the database.
7. A smart material management method according to claim 6, characterized in that: Once the maximum number of recycling times is reached, the residual value of the material is assessed and the assessment results are recorded, including: Obtain the material's identification code ID, maximum number of cycles used MCU, and current number of uses CU, and confirm that the current number of uses is equal to the maximum number of cycles used; Based on the identification code ID, the basic value BV, type T and historical usage records of the material are retrieved from the database to calculate the depreciation rate DR of the material = new CU / MCU; According to the depreciation rate, the residual value RV of the material is evaluated as RV = BV * (1-DR), and the residual value RV, the type T of the material, the state and other relevant information are recorded in the database; The status of the material is marked as evaluated, and the evaluation result is associated with the identification code ID and stored.
8. A smart material management method according to claim 7, characterized in that: Based on the assessment results, decide on the material's reuse or disposal method, including: Obtain the identification code ID, residual value RV and type T of the material, and determine the reuse threshold RT = BV * 0.2 based on the residual value RV; comparing the residual value RV with the reuse threshold RT, and marking the material as suitable for reuse if the residual value is greater than the reuse threshold; For materials marked as suitable for reuse, calculate the estimated reuse cost RC = BV * 0.1 and compare the cost with the stated residual value; If the residual value is higher than the estimated recycling cost, updating the status of the material to recommended recycling and recording it in the database; If the residual value is lower than the reuse threshold or higher than the reuse cost but not suitable for reuse, the status of the material is updated to recommended scrapping, and the final disposal recommendation is recorded in the database.
9. A smart material management method according to claim 8, characterized in that: Feed the results of the above process back to the system and adjust the inventory records of the materials to reflect the latest status changes, including: Obtain the material's identification code ID, processing method, and current inventory quantity Q; Based on the processing method, an adjustment coefficient AC is determined; if the mark is recommended for reuse, the adjustment coefficient is 0.9; if the mark is recommended for scrapping, the adjustment coefficient is 0; Updating the inventory quantity of the material according to the adjustment coefficient using the formula: new inventory quantity Q = Q * AC; associating the result of the processing method with the identification code ID of the material, and feeding back the result to the database; updating the status information of the material in the database, including the processing method and the new inventory quantity; Calculate the new inventory value of the material NV = BV * New Q and record the new inventory value in the database.
10. A smart material management system for implementing the method according to any one of claims 1 to 9, characterized in that: include: A material information acquisition module is used to register basic information and initial status of the material, and based on the basic information, calculate and record the maximum number of recycling times of the material; a material information updating module, configured to assign an identification code to a material according to the maximum number of cycles of use, and store the identification code in a database; and whenever the material is used, to update the number of uses in the database and mark the current status of the material; a material evaluation module, configured to check whether a maximum number of recycling times has been reached based on the current state, and if not, continue monitoring until the maximum number of recycling times has been reached; and once the maximum number of recycling times has been reached, evaluate the residual value of the material and record the evaluation result; The material adjustment module is used to determine the reuse or scrapping treatment of the material based on the evaluation results, feed the results of the treatment method back to the system, and adjust the inventory records of the material to reflect the latest status changes.
Citation Information
Patent Citations
Material supervision and management system based on data analysis
CN119313014A
Cyclic application management and control system for capital construction materials
CN119313260A
Recycling management method, system and device for digital logistics packaging materials
CN119539532A
Intelligent processing and manufacturing management system
CN119850025A
KR20230014389A