Guide frame capable of guaranteeing construction quality of sheet pile and using method
By designing the guide frame's longitudinal beams, crossbeam components, and positioning guide components, the problems of verticality and tight connection in sheet pile construction were solved, construction quality was improved, and riverbank scouring and collapse were prevented.
Patent Information
- Application Number
- CN202511088584.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-05
- Publication Date
- 2025-10-17
AI Technical Summary
Existing technologies make it difficult to ensure that concrete sheet piles maintain verticality and tight connections during riverbank construction, especially in complex geological conditions and curved riverbank environments, making construction quality difficult to control.
A guide frame is designed, including a longitudinal beam, a crossbeam assembly and a positioning guide assembly. Positioning wheels and guide wheels are used to guide and position sheet piles to ensure that the sheet piles maintain verticality and tight connection during construction.
The verticality control of sheet piles and the close connection between adjacent sheet piles in river bank construction are realized, which improves the construction quality and prevents bank scouring and collapse.
Smart Images

Figure CN120797672A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The application belongs to the technical field of river embankment management, and particularly relates to a guide frame for ensuring the construction quality of sheet piles and a use method. BACKGROUND
[0002] River resources are rich and bring great benefits to people's life. However, due to the influence of urban construction, industrial development and agricultural activities, the river environment is deteriorating. The protection measures on the river bank are imperfect, which leads to frequent problems such as river bank collapse, floods and water pollution, and seriously threatens the safety of people's life and property and the ecological environment.
[0003] Therefore, it is necessary to design a guide frame for ensuring the construction quality of sheet piles and a use method to solve the above problems. SUMMARY
[0004] The purpose of the application is to provide a guide frame for ensuring the construction quality of sheet piles and a use method to solve the above problems and achieve the purpose of preventing bank slope erosion, collapse and seepage.
[0005] To achieve the above purpose, the application provides the following scheme: a guide frame for ensuring the construction quality of sheet piles, comprising
[0006] Two forward beams are arranged in parallel and at intervals, and a sheet pile construction space is formed between the two forward beams;
[0007] A first cross beam assembly is fixedly arranged at the top of one end of the forward beam;
[0008] A second cross beam assembly is fixedly arranged at the side wall of the other end of the forward beam;
[0009] A positioning and guiding assembly is movably arranged at the top end of the forward beam, and the positioning and guiding assembly is used for guiding and positioning the sheet pile during sheet pile construction;
[0010] The guide frame is used for guiding the sheet pile during sheet pile construction on the straight section and / or arc section of the river bank.
[0011] Based on the guide frame for ensuring the construction quality of sheet piles, the positioning and guiding assembly comprises a fixed angle steel, the side walls of the fixed angle steel are respectively fixedly connected with connecting lugs, a center shaft is fixedly connected between the two connecting lugs, the center shaft is rotatably connected with two positioning parts and one guiding part, the guiding part is located between the two positioning parts, and the guiding part is located in the sheet pile construction space.
[0012] Based on the guide frame for ensuring the construction quality of sheet piles, the positioning part comprises a positioning wheel, the positioning wheel is rotatably connected to the end of the center shaft, the forward beam is an I-beam, and the positioning wheel is rollingly arranged in the groove of the forward beam.
[0013] The guide frame for ensuring the construction quality of the sheet pile according to the application, the guide part comprises a guide wheel, the guide wheel is rotationally connected to the middle part of the central shaft, and the diameter size of the two ends of the guide wheel is larger than the diameter size of the middle part.
[0014] The guide frame for ensuring the construction quality of the sheet pile according to the application, the first cross beam assembly comprises two beam seats, the beam seats are in one-to-one correspondence with the straight beams and are fixedly arranged at the top ends of the end parts of the straight beams, and the head cross beam is fixedly connected between the top ends of the two beam seats.
[0015] The guide frame for ensuring the construction quality of the sheet pile according to the application, the second cross beam assembly comprises a tail cross beam, and the tail cross beam is fixedly connected to the end side wall of the straight beam away from the first cross beam assembly.
[0016] The guide frame for ensuring the construction quality of the sheet pile according to the application, the straight beam is fixedly connected with a supporting leg at the bottom of one end close to the second cross beam assembly.
[0017] A use method of the guide frame for ensuring the construction quality of the sheet pile, comprising the following steps:
[0018] The installation position of the guide frame is determined according to the construction position of the sheet pile;
[0019] The guide frame is transferred to the installation position and is installed and fixed;
[0020] The installation of the sheet pile is started.
[0021] The use method of the guide frame for ensuring the construction quality of the sheet pile according to the application, after the construction position of the sheet pile is determined, the installation position of the guide frame is determined according to the construction drawing and the measurement control point.
[0022] The use method of the guide frame for ensuring the construction quality of the sheet pile according to the application, the positioning pile is arranged at the starting point of the construction position of the sheet pile, and the first cross beam assembly is placed on the positioning pile.
[0023] Compared with the prior art, the application has the following advantages and technical effects:
[0024] The guide frame can ensure the perpendicularity during the sinking process of the sheet pile, avoid the horizontal deviation of the sheet pile along the river bank, and ensure the close connection between the adjacent sheet piles, so that the completed sheet pile has a good and stable protection effect on the river bank. BRIEF DESCRIPTION OF DRAWINGS
[0025] In order to make the technical solutions in the embodiments of the present application or the prior art clearer, the accompanying drawings needed in the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description only need to be some embodiments of the present application, and all other embodiments obtained by a person of ordinary skill in the art without creative work based on the embodiments in the present application shall fall within the protection scope of the present application.
[0026] Figure 1 The figure is a schematic diagram of the guiding frame of the present application.
[0027] 1, forward beam; 2, beam seat; 3, head beam; 4, tail beam; 5, leg; 6, fixed angle steel; 7, connecting lug; 8, center shaft; 9, positioning wheel; 10, guiding wheel. DETAILED DESCRIPTION
[0028] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the accompanying drawings in the embodiments of the present application. Obviously, the described embodiments are only some embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by a person of ordinary skill in the art without creative work shall fall within the protection scope of the present application.
[0029] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the present application will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0030] The erosion and damage of the water flow of a large river to the river bank slope surface can lead to land loss, bank slope collapse and other problems. Therefore, it is of great significance to take appropriate protection measures to protect the safety of the river bank and the surrounding environment.
[0031] In order to effectively prevent the erosion of the river bank, especially the large river or the river into the sea under the high-speed water flow, a deep concrete sheet pile is inserted at the toe of the slope or the toe of the embankment to prevent the erosion and collapse of the bank slope and prevent seepage.
[0032] The concrete sheet pile structure inserted into the bank of a river, lake or sea can effectively prevent the erosion of the river. Its characteristics are as follows: 1. strong and durable: the concrete sheet pile revetment has strong anti-erosion and bearing capacity, and can protect the river bank for a long time. 2. simple construction: the concrete sheet pile revetment is convenient to construct, can be adjusted according to the actual situation, and is suitable for various types of river banks. 3. easy to maintain: the concrete sheet pile revetment is easy to maintain, only needs to be checked and repaired regularly.
[0033] The construction method of the concrete sheet pile revetment needs the following steps:
[0034] 1. Determine the construction position: determine the construction position of the concrete sheet pile revetment according to the actual situation, and perform necessary topographic survey and design.
[0035] 2. Insert the concrete sheet pile into the design top elevation:
[0036] (1) If the ground layer in the sheet pile construction area is hard and not easy to insert and sink the sheet pile, a pilot hole can be inserted at the set construction position of the sheet pile;
[0037] (2) Then use the pile driver or pile driver to drive the sheet pile to the set elevation, and the shape, size and number of the sheet pile should be determined according to the water flow velocity and soil conditions of the river.
[0038] (3) If the ground layer is relatively soft, the pile sinking during the sheet pile insertion construction is easy, and the sheet pile can be directly hoisted and vertically positioned without pre-pilot hole, and the pile driver or pile driver is used to drive the sheet pile to the set elevation.
[0039] 3. Gap grouting between sheet piles: In order to achieve the anti-seepage effect of the concrete sheet pile, cement mortar or resin mortar is used to grout the gap between adjacent sheet piles to 0.3m below the scour line.
[0040] 4. Confirm the construction quality: Confirm the construction quality to ensure the anti-scouring and bearing capacity of the concrete sheet pile revetment.
[0041] In some special cases, in order to prevent the slope foot and the sheet pile from being washed away and damaged as much as possible, it is necessary to take a deeper sinking sheet pile to resist the corresponding anti-scouring damage and increase the stability and safety of the pile foundation.
[0042] For the construction of the super-long concrete sheet pile with deep sinking pile, the geological conditions are often complex, and there may be soft soil layer, block stone layer, "iron plate sand" layer and other unfavorable factors. These factors will increase the construction difficulty, and there may be pile sinking difficulty, pile body damage, pile deviation and other phenomena during the construction of the concrete sheet pile. Therefore, how to avoid these phenomena and ensure the perpendicularity of the sheet pile, the joint width and other parameters is one of the difficulties in the construction of the sheet pile.
[0043] In addition, the shoreline of some rivers is mostly curved, and it is difficult to tightly sink the concrete sheet pile along the shoreline under the non-straight line. In addition, during the construction of the sheet pile, the traditional method of using the level to release the pile top elevation line and using the visual control method of the pile driver operator to control the elevation is easy to be affected by the surrounding noisy environment, and the elevation control error is large. Therefore, how to ensure the accuracy of the elevation control of the sheet pile is also a difficulty in the construction of the sheet pile.
[0044] In order to overcome various difficulties in the construction of the concrete sheet pile, ensure that the perpendicularity is always maintained during the sinking process of the inserted sheet pile, and there is no horizontal deviation along the riverbank, and the joint between adjacent sheet piles is tight, the application provides a guide frame for ensuring the construction quality of the concrete sheet pile, and is applied in the construction of the sheet pile, solves the above construction difficulties, and ensures the construction quality.
[0045] ReferenceFigure 1 As shown, the present application provides a guide frame for ensuring the quality of sheet pile construction, comprising
[0046] Two forward beams 1 are arranged in parallel and at intervals, and a sheet pile construction space is formed between the two forward beams 1.
[0047] A first cross beam assembly is fixedly arranged at the top of one end of the forward beam 1.
[0048] A second cross beam assembly is fixedly arranged on the side wall of the other end of the forward beam 1.
[0049] A positioning and guiding assembly is movably arranged at the top end of the forward beam 1, and the positioning and guiding assembly is used for guiding and positioning the sheet pile during sheet pile construction.
[0050] The guide frame is used for guiding the sheet pile during sheet pile construction of the straight section and / or the arc section of the river bank.
[0051] Further, the positioning and guiding assembly comprises a fixed angle steel 6, the side walls of the fixed angle steel 6 are respectively fixedly connected with connecting lugs 7, a center shaft 8 is fixedly connected between the two connecting lugs 7, the center shaft 8 is rotatably connected with two positioning portions and a guiding portion, the guiding portion is located between the two positioning portions, and the guiding portion is located in the sheet pile construction space.
[0052] Further, the positioning portion comprises a positioning wheel 9, the positioning wheel 9 is rotatably connected to the end of the center shaft 8, the forward beam 1 is an I-beam, and the positioning wheel 9 is rollingly arranged in the groove of the forward beam 1.
[0053] Further, the guiding portion comprises a guiding wheel 10, the guiding wheel 10 is rotatably connected to the middle of the center shaft 8, and the diameters of the two ends of the guiding wheel 10 are larger than the diameter of the middle.
[0054] Further, the first cross beam assembly comprises two beam seats 2, the beam seats 2 correspond to the forward beams 1 one by one and are fixedly arranged at the top end of the end of the forward beam 1, and a head cross beam 3 is fixedly connected between the top ends of the two beam seats 2.
[0055] Further, the second cross beam assembly comprises a tail cross beam 4, the tail cross beam 4 is fixedly connected to the side wall of the end of the forward beam 1 away from the first cross beam assembly.
[0056] Further, a leg 5 is fixedly connected to the bottom of the end of the forward beam 1 close to the second cross beam assembly.
[0057] A use method of a guide frame for ensuring the quality of sheet pile construction, comprising the following steps:
[0058] The installation position of the guide frame is determined according to the construction position of the sheet pile;
[0059] The guide frame is transferred to the installation position and is installed and fixed;
[0060] Start installing the sheet pile.
[0061] Further, after determining the construction position of the sheet pile, the installation position of the guide frame is determined according to the construction drawing and the survey control point.
[0062] Further, the positioning pile is arranged at the starting point of the sheet pile construction position, and the first cross beam assembly is placed on the positioning pile.
[0063] In order to control the accurate placement position of the guide frame, the following work needs to be done on site:
[0064] 1. During the excavation process of the guide frame placement base groove flatness, the surveyor uses the level to track the measurement;
[0065] 2. The theodolite is used for surveying and setting out the axis position of the guide frame, and the axis is rechecked after the setting out is completed;
[0066] 3. After the guide frame is erected according to the axis position line, the accuracy is rechecked and adjusted to ensure that the straightness and parallelism of the guide rail meet the design requirements.
[0067] Through the above work, the deviation of the axis of the guide frame during erection can be avoided to affect the quality of the sheet pile driving.
[0068] 4. According to the size of the pile and the distance between the two side beams, the position of the guide wheel is adjusted so that the guide wheel can play a good guiding role on the pile during driving. The guide wheel used on site needs to be flexible in rotation, without jamming, wear or damage, etc.
[0069] Guide frame operation requirements:
[0070] 1. Hoist the guide frame: the straightness and parallelism of the guide frame meet the design requirements;
[0071] 2. Adjust the guide frame: make the axis of the guide frame consistent with the axis of the sheet pile;
[0072] 3. Fix the guide frame: according to the stratum conditions, after the guide frame placement position is stable, the fixed piles can be inserted on both sides of the guide frame to prevent the guide frame from shifting during the insertion of the sheet pile.
[0073] For curved riverbanks, iron wedges are arranged between the inner side wall of the guide frame and the sheet pile to adjust the direction of the sheet pile, and gradually form an arc-shaped sheet pile anti-washing riverbank line.
[0074] In the description of the present application, it needs to be understood that the terms "longitudinal", "transverse", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like indicate the orientation or positional relationship shown in the drawings, and are only for the purpose of facilitating the description of the present application, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation on the present application.
[0075] The above-described embodiments are only to describe the preferred modes of the present application, and not to limit the scope of the present application, and various modifications and improvements to the technical solutions of the present application made by those skilled in the art without departing from the design spirit of the present application shall fall within the protection scope of the present application.
Claims
1. A guide frame for ensuring the quality of sheet pile construction, characterized in that: include: Two longitudinal beams (1) are arranged in parallel and at intervals, and a sheet pile construction space is formed between the two longitudinal beams (1); A first crossbeam assembly, fixedly arranged on the top of one end of the forward beam (1); A second crossbeam assembly, fixedly arranged on the other end side wall of the forward beam (1); A positioning guide assembly is movably arranged at the top end of the longitudinal beam (1), and the positioning guide assembly is used to guide and position the sheet piles during sheet pile construction; The guide frame is used to guide the sheet piles during sheet pile construction in straight sections and / or curved sections of a river bank.
2. A guide frame for ensuring the quality of sheet pile construction according to claim 1, characterized in that: The positioning guide assembly comprises a fixed angle steel (6), the two ends of the side wall of the fixed angle steel (6) are respectively fixedly connected with connecting ears (7), a central shaft (8) is fixedly connected between the two connecting ears (7), the central shaft (8) is rotatably connected to two positioning parts and a guide part, the guide part is located between the two positioning parts, and the guide part is located in the sheet pile construction space.
3. A guide frame for ensuring the quality of sheet pile construction according to claim 2, characterized in that: The positioning portion includes a positioning wheel (9), which is rotatably connected to the end of the central shaft (8); the longitudinal beam (1) is an I-beam, and the positioning wheel (9) is rollingly arranged in a groove of the longitudinal beam (1).
4. A guide frame for ensuring the quality of sheet pile construction according to claim 3, characterized in that: The guide portion comprises a guide wheel (10), the guide wheel (10) is rotatably connected to the middle of the central shaft (8), and the diameters of the two ends of the guide wheel (10) are larger than the diameter in the middle.
5. A guide frame for ensuring the quality of sheet pile construction according to claim 1, characterized in that: The first crossbeam assembly comprises two beam seats (2), the beam seats (2) corresponding one to one with the forward beam (1) and fixedly arranged at the top end of the forward beam (1), and a head crossbeam (3) fixedly connected between the top ends of the two beam seats (2).
6. A guide frame for ensuring the quality of sheet pile construction according to claim 1, characterized in that: The second crossbeam assembly comprises a tail crossbeam (4), and the tail crossbeam (4) is fixedly connected to a side wall of an end of the forward beam (1) away from the first crossbeam assembly.
7. A guide frame for ensuring the quality of sheet pile construction according to claim 1, characterized in that: A supporting leg (5) is fixedly connected to the bottom of one end of the forward beam (1) close to the second cross beam assembly.
8. A method for using the guide frame for ensuring the quality of sheet pile construction according to any one of claims 1 to 7, characterized in that: The following steps are involved: Determine the installation position of the guide frame according to the construction position of the sheet pile; Transfer the guide frame to the installation location and install and fix it; Begin installing sheet piles.
9. The method for using a guide frame for ensuring the quality of sheet pile construction according to claim 8, characterized in that: After determining the construction position of the sheet pile, determine the installation position of the guide frame according to the construction drawings and measurement control points.
10. A method for using a guide frame for ensuring the quality of sheet pile construction according to claim 9, characterized in that: Positioning piles are set at the starting point of the sheet pile construction position, and the first beam assembly is placed on the positioning piles.