Roof settlement joint anti-seepage construction method

By using the single-sided cantilevered cover plate construction method, the problem of seepage prevention in the roof settlement joints was solved, achieving a zero-leakage effect, avoiding the defects of traditional methods, and improving construction efficiency and waterproof stability.

CN120797904APending Publication Date: 2025-10-17GUI ZHOU JIAN GONG JI TUAN DI BA JIAN ZHU GONG CHENG GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510985209.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-17
Publication Date
2025-10-17

AI Technical Summary

Technical Problem

The traditional waterproofing treatment method for roof settlement joints has poor anti-leakage stability, the metal plates are prone to falling off and peeling off, and the concrete cover plates are prone to cracking due to uneven settlement and stretching, resulting in leakage of the exterior walls at the settlement joints of the entire building.

Method used

The single-sided cantilevered cover plate construction method is adopted, including roof measurement and layout, cantilevered cover plate formwork installation, cover plate concrete pouring, sealing and waterproofing layer installation, ensuring that the height and slope of the cover plate and settlement joint curb meet the requirements, using building sealant for sealing, and covering with a waterproofing layer.

Benefits of technology

It achieves zero leakage at roof settlement joints, avoiding the cracking and warping of cover plates in traditional methods, reducing maintenance costs and time, and improving construction progress and waterproofing effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120797904A_ABST
    Figure CN120797904A_ABST
Patent Text Reader

Abstract

The invention discloses a roof settlement joint anti-seepage construction method which comprises the following steps: step 1, roof surveying and setting out, step 2, single-side overhanging cover plate template installation, step 3, single-side overhanging cover plate and settlement joint plugging, and step 4, waterproof layer arrangement. The whole construction method is simple, easy to operate and high in durability, continuous construction can be conducted after a main body structure settlement joint reverse ridge is completed, the situation that the cover plate is pulled to be cracked due to uneven settlement of a building is avoided, meanwhile, the construction progress is accelerated, the way that rainwater flows into the settlement joint is cut off, and the zero-leakage function is achieved; leakage caused by cracking of a traditional concrete cover plate and warping of a metal cover plate can be effectively prevented, repair caused by leakage is prevented, and investment of maintenance materials, manpower and the like is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the field of roofing waterproof construction method, in particular to a roofing settlement joint anti-leakage construction method. BACKGROUND

[0002] The leakage rate of roofing engineering, especially at the settlement joint position, is relatively high. Once leakage occurs, it not only affects the use function of the owner, but also causes economic loss to the owner's indoor decoration. Generally, the settlement joint waterproof treatment structure of the roofing of the building engineering adopts the traditional method of using metal cover plate and concrete cover plate. This method has poor anti-leakage stability, the metal plate is easy to fall off and curl, the concrete cover plate is easy to stretch and crack due to uneven settlement, and the "leakage" phenomenon occurs, resulting in the leakage of the outer wall at the settlement joint of the whole building. SUMMARY

[0003] The present application relates to the field of roofing waterproof construction method, in particular to a roofing settlement joint anti-leakage construction method.

[0004] The technical scheme of the present application is a roofing settlement joint anti-leakage construction method, comprising the following steps:

[0005] Step one, roofing measurement and line laying, after the completion of the roofing scaffold support and the template installation, the roofing measurement and line laying is carried out, the water and electricity pre-buried and the settlement joint position are measured and positioned, at the same time, in order to ensure the one-time forming of the roofing and the settlement joint main structure, the roofing reinforcement and the settlement joint reinforcement are bound, and the one-side cantilever cover plate reinforcement is pre-buried, after the pre-buried water and electricity, the formwork installation of the settlement joint is carried out;

[0006] Step two, one-side cantilever cover plate template installation, the one-side cantilever cover plate template is installed, the slope from the root to the end is found, the root and the end are provided with the drip line, then the reinforcement is made, the template installation is completed, and the cover plate concrete is poured;

[0007] Step three, one-side cantilever cover plate and settlement joint plugging, after the one-side cantilever cover plate is maintained to reach the design strength, the formwork is removed and cleaned, and then the one-side cantilever cover plate and the reverse ridge top are injected with the building sealant for plugging after drying

[0008] Step four, setting of the waterproof layer, a layer of waterproof layer is covered on the formed one-side cantilever cover plate, so as to improve the overall waterproof effect.

[0009] Further, in the step one, the height of the settlement joint reverse ridge after the formwork installation is greater than or equal to 200mm.

[0010] Further, the slope from the root to the end is greater than or equal to 5%.

[0011] Compared with the prior art, the application has the advantages of simple overall construction method, easy operation, strong durability, continuous construction after the completion of the main structure settlement joint ridge, no influence of uneven settlement of the building on the cracking of the cover plate, accelerated construction progress, no way for rainwater to flow into the settlement joint, zero leakage function, prevention of leakage caused by cracking of the traditional concrete cover plate and buckling of the metal cover plate, prevention of repair caused by leakage, and reduction of investment in maintenance materials and labor. BRIEF DESCRIPTION OF DRAWINGS

[0012] Figure 1 is a construction method flowchart of the application;

[0013] Figure 2 is a roof settlement joint anti-leakage treatment sectional view of the application;

[0014] Figure 3 is a one-side cantilever cover plate flow path working principle sectional view. DETAILED DESCRIPTION

[0015] The technical solutions in the embodiments of the application will be clearly and completely described below with reference to the drawings in the embodiments of the application. Obviously, the described embodiments are only part of the embodiments of the application, rather than all the embodiments of the application. Based on the embodiments in the application, all other embodiments obtained by those skilled in the art without creative work fall within the protection scope of the application.

[0016] It should be noted that all directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the application are only used to explain the relative positional relationship, movement condition, etc. between components in a certain posture (as shown in the drawings), and if the certain posture changes, the directional indications also change accordingly.

[0017] In addition, the description of “first”, “second” and the like in the application is only for the purpose of description, and cannot be understood as indicating or implying the relative importance of the indicated technical features or implicitly indicating the number of the indicated technical features. Therefore, the features defined as “first”, “second” can explicitly or implicitly include at least one of the features. In addition, the technical solutions of each embodiment can be combined with each other, but it must be based on the realization of those skilled in the art, and when the combination of technical solutions appears contradictory or unachievable, it should be considered that the combination of technical solutions does not exist, and is not within the protection scope required by the application.

[0018] Reference Figures 1-3In the present application, a construction method for preventing leakage of a roof settlement joint comprises the following steps: Step 1, roof measurement and line laying, after completion of roof scaffold support and template installation, measurement and positioning of roof water and electricity pre-burial and settlement joint position are carried out, and at the same time, in order to ensure one-time forming of the roof and the main structure of the settlement joint, roof reinforcement and settlement joint reinforcement are bound, and one-side overhanging cover plate reinforcement is pre-buried, after pre-burial of water and electricity, formwork installation of the settlement joint is carried out; the settlement joint is installed by formwork, after installation of the formwork, the height of the settlement joint counterfort is greater than or equal to 200 mm, and the reinforcement is completely installed and the water and electricity pre-burial is completed, after completion of the formwork installation, acceptance is carried out, and after acceptance, roof concrete is poured.

[0019] Step 2, one-side overhanging cover plate template installation, one-side overhanging cover plate 4 template is installed, the one-side overhanging cover plate 4 is arranged on the overhanging support 5, and the slope from the root part B to the end part A is arranged, the root part and the end part are arranged with a drip line, the drip line comprises an overhanging end drip line 1 and an overhanging support drip line 2, then reinforcement is made, template installation is completed, cover plate concrete is poured, and C30 fine stone concrete is used for pouring of the concrete. The one-side overhanging cover plate solves the problem of cracking and leakage caused by uneven settlement of two buildings in the traditional concrete cover plate; the principle of the one-side overhanging cover plate is to both block rain by the cover plate and completely separate the two buildings without any connection, so as to achieve the purpose of preventing cracking and leakage; the one-side overhanging cover plate solves the drawbacks of leakage caused by warping deformation of the traditional metal cover plate, so as to achieve the purpose of preventing cracking and leakage; and the cost of the cast-in-place one-side concrete cover plate is much lower than the procurement and installation cost of the metal cover plate, so as to achieve the purpose of cost saving.

[0020] Step 3, sealing of the one-side overhanging cover plate and the settlement joint 7, after the one-side overhanging cover plate reaches the design strength after maintenance, the formwork is removed and cleaned, and after drying, the one-side overhanging cover plate and the counterfort top are injected with building sealant 3 for sealing.

[0021] Step 4, setting of a waterproof layer, a waterproof layer is arranged on the formed one-side overhanging cover plate, so as to improve the overall waterproof effect.

[0022] Specifically, the slope from the root part to the end part is greater than or equal to 5%. And for the actual materials and equipment, refer to Table 1-Table 2.

[0023] Table 1: materials

[0024] Serial number Material name Model Specification Unit Quantity Remark 1 Steel bar HRB400 8mm KG According to actual needs Cover force steel bar 2 Steel bar HPB300 8mm KG According to actual needs Cover distribution steel bar 3 Formwork 15*1830*915 ㎡ According to actual needs Cover formwork 4 Wood square 40*80*2000 m³ According to actual needs Cover formwork 5 Building sealant Support According to actual needs Plugging 6 Concrete Fine stone concrete C30 m³ According to actual needs Cover pouring

[0025] Table 2: appliances and equipment

[0026] Serial number Main equipment name Specification model Quantity Purpose 1 Tower crane 6013 1 set Hoist material 2 Disc saw 1 set Wood square, formwork blanking 3 Steel bar bending machine 1 set Steel bar blanking 4 Concrete hopper 1 set Hoist concrete 5 Welder 1 set Steel bar welding

[0027] In addition to the preferred embodiments described above, other embodiments of the application will become apparent to those skilled in the art from the following description, which is given by way of example only.

Claims

1. A construction method for preventing leakage of roof settlement joints, characterized in that: The following steps are included: Step 1: Roof measurement and layout. After the roof scaffolding support and formwork installation are completed, roof measurement and layout are carried out. The roof water and electricity pre-embedded and settlement joint positions are measured and positioned. At the same time, in order to ensure the one-time forming of the main structure of the roof and settlement joint, the roof steel bars and settlement joint steel bars are tied. At the same time, the single-side cantilever cover steel bars are pre-embedded. After the water and electricity are pre-embedded, the settlement joint formwork is installed. Step 2: Install the single-sided cantilever cover plate formwork. Install the single-sided cantilever cover plate formwork, find the slope from the root to the end, set drip lines at the root and end, then make the steel bars, complete the formwork installation, and pour the cover plate concrete; Step 3: Seal the single-sided cantilever cover plate and the settlement joint. After the single-sided cantilever cover plate reaches the design strength after curing, it is cleaned after demoulding. After drying, the single-sided cantilever cover plate and the top of the anti-slope are sealed with building sealant. Step 4: Setting up the waterproof layer. Cover the formed single-sided cantilever cover with a waterproof layer to improve the overall waterproof effect.

2. A construction method for preventing leakage of roof settlement joints according to claim 1, characterized in that: In the step 1, the settlement joint is installed with a hanging formwork, and after the hanging formwork is installed, the height of the settlement joint is greater than or equal to 200 mm.

3. A construction method for preventing leakage of roof settlement joints according to claim 1 or 2, characterized in that: In the step 2, the slope from the root to the end is greater than or equal to 5%.