Maritime work jacket construction project work package visual control method and billboard system
By coordinating the model and visualization module, the problem of mismatch between production capacity and consumption caused by information opacity in offshore jacket construction was resolved, and reasonable control of construction progress and balanced material supply were achieved, reducing construction costs and warehousing pressure.
Patent Information
- Application Number
- CN202510922568.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-04
- Publication Date
- 2025-10-17
AI Technical Summary
During the onshore construction of offshore projects, existing technologies result in non-intuitive and non-transparent production and construction information, a mismatch between production capacity and consumption, increased storage pressure, delayed construction periods, and increased construction costs.
By designing a comprehensive model, comprehensively balancing personnel factors, building material matching factors and environmental factors, a correlation data model of construction progress, material inventory and production progress is established, and a visualization module is used to display the construction, warehousing and production progress, so as to ensure that the construction progress is within a reasonable range, reasonably control the inventory and production capacity progress, and avoid warehouse overflow and insufficient material supply.
It achieves reasonable control of construction progress, avoids storage pressure and cost increase, improves data transmission efficiency, and ensures that material supply and construction are completed as expected.
Smart Images

Figure CN120806494A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the field of visual management of offshore land construction, in particular to a visual control method and Kanban system for offshore jacket construction project work package. BACKGROUND
[0002] In the process of offshore land construction, welding operation is needed for the jacket, and in this process, the actual construction progress and the production progress of the coiled pipe need to be continuously monitored, and the consumption of materials is matched with the production to achieve the purpose of supply and demand balance.
[0003] Reviewing the past work mode, project production personnel have to frequently query and process data to project interface personnel, and then inform the relevant information to the on-site production management personnel, and in this information transmission process, the characteristics of transmission are presented, which not only leads to extremely low work efficiency, but also greatly reduces the timeliness of communication and transmission. At the same time, in the whole project process, there are often situations where production capacity does not match consumption, when production capacity greatly exceeds consumption, it will cause great pressure on storage, and when production capacity greatly lags behind consumption, it will affect the construction progress of the whole jacket construction project, causing delay in the construction period, and in the specific construction environment, there will be a situation where personnel are idle due to material shortage, which leads to an increase in the overall construction cost, and in view of the above, in order to effectively solve the above series of problems, a visual control method and Kanban system for offshore jacket construction project work package are provided. SUMMARY
[0004] In view of the deficiencies of the prior art, the present application provides a visual control method and Kanban system for offshore jacket construction project work package, which solves the problem that in the existing offshore jacket construction process, production and construction information are not intuitive and transparent, resulting in mismatch between production capacity and consumption, increased storage pressure, delayed construction period and increased construction cost.
[0005] To achieve the above purpose, the present application is realized by the following technical scheme: a visual control method for offshore jacket construction project work package, comprising: S1, importing construction progress data, material inventory data and material production progress data; S2, normalizing the imported data to obtain the current construction progress, material inventory growth rate and material production speed; S3, designing three interrelated data models by designing a unified model for construction progress, material inventory growth rate and material production progress; In the construction progress model, by comprehensively balancing personnel factors, building material matching factors and environmental factors, the construction progress is in the error interval, and the construction progress is ensured to be within a reasonable range; In the inventory model, by reasonably controlling , so that , wherein indicates the maximum storage capacity of the warehouse, to avoid the occurrence of warehouse explosion; In the material production progress model, by reasonably controlling the production capacity, , so as to ensure the supply of materials, while taking into account the storage capacity.
[0006] Preferably, the construction progress formula is:
[0007] Wherein D represents personnel factors, R represents building material matching factors, and G represents environmental factors; ; indicates the error coefficient, ; The material inventory growth formula is: ; Wherein represents the material increment per unit time, represents the material consumption per unit time, represents the current inventory; The material production progress formula is: ; Wherein represents the current total material production, represents the total material demand for the whole construction period; The error interval is represented as: .
[0008] Preferably, the overall planning model is embedded with construction progress control logic to intelligently control the construction progress model, the inventory model and the material production progress model, and the specific steps are: S1, obtaining current construction progress data, material inventory data and material production progress data; S2, comparing the actual construction progress with the expected construction progress; S3, adjusting the construction speed according to the comparison result; S4, adjusting the production speed according to the material inventory; S5, ensuring that the project progress meets the construction period requirement.
[0009] Preferably, the execution strategy of S3 is: Step one, construction progress data acquisition; Step 2: Construction progress monitoring: the actual progress is compared with the threshold, quantified through a pre-designed construction schedule, and the corresponding error coefficient α is introduced; Step 3: Analyze and judge the current progress; Whether actual progress ∈ [standard progress * (1 + α), standard progress * (1 - α)] holds true; If so, it means that the current progress range is within the threshold, and the current progress is maintained; If not, it means that the current progress exceeds the threshold, and a differentiated judgment operation is performed; Actual progress ≤ standard progress * (1-α)? If so, it means that the current progress is behind the minimum schedule. In this case, the rush module is activated to improve the schedule by designing resource reinforcement strategies. If not, it means that the current progress exceeds the maximum construction period. At this time, the quality module is activated and the quality of construction is enhanced within the construction period through the design of quality improvement strategies.
[0010] Preferably, the resource enhancement strategy is based on the following formula:
[0011] By analyzing the human factors, building material matching factors and environmental factors in the current construction environment, it is found that environmental factors, as objective factors, are uncontrollable. The construction speed can be improved by increasing the number of construction personnel and at the same time increasing the number of building materials and building material-related construction equipment.
[0012] Preferably, the executable contents of the quality improvement strategy include increasing the number of related construction processes, extending the interval time between related construction steps and reducing the frequency of construction shifts of construction personnel.
[0013] Preferably, the execution strategy of S3 is: Step 1: Obtain material inventory data; Step 2: Calculate the incremental speed of consumables based on construction speed and production speed ; Step 3: Determine the current inventory increment rate whether it is established; If so, it means the inventory is within the safe range and the current progress should be maintained; If not, it means that the inventory is in a changing stage and further differentiation judgment is required; whether it is established; If so, it means that inventory is in the growth stage. At this time, we can analyze it in combination with the construction progress model. If the actual progress is less than or equal to the standard progress, we can increase the construction speed. If the actual progress is greater than the standard progress, we can reduce the production speed. If not, it means that the inventory is in the consumption stage, at this time, combined with the construction progress model for analysis, if the actual progress ≥ standard progress × (1 + α), reduce the construction speed, If the actual progress ≤ standard progress × (1-α), the material production speed is improved, and finally the construction progress adjustment is realized, and the construction progress adjustment will affect the change of material inventory, realizing the cycle control.
[0014] Preferably, when controlling the inventory, because the construction progress and the consumption of consumables are nonlinearly proportional, the consumption speed and the demand of materials are different in different construction periods, therefore, when dividing the construction progress, the progress needs to be divided according to different construction stages, and then the high-consumable stage and the low-consumable stage can be roughly classified, and the corresponding material consumption and construction progress relationship function is designed, which can be represented as:
[0015] Among them The total material demand in unit time t period is represented; The proportional coefficient obtained by normalizing the relationship function between construction progress and material consumption speed.
[0016] Preferably, because the material consumption speed is different and the material demand is different in different periods, therefore, in the inventory model and the material production progress model; When the time point of the construction progress model approaches the high-consumable stage, the production speed is improved to expand the inventory, and the material daily turnover is improved; When the time point of the construction progress model approaches the low-consumable stage, the production speed is reduced to reduce the inventory, and the material daily turnover is reduced.
[0017] Preferably, a marine offshore jacket construction project work package visual board system comprises a visualization module, the visualization module comprises a construction progress module, a warehouse module and a production progress module, the actual field quantitative work is displayed in the form of text + chart, and relevant information contents are displayed to each module person in charge, and a comprehensive overall module is designed to display overall to the main person in charge of the whole project In the visualization module; The construction progress module comprises work package workload, work package distribution plan, work package material matching state, work package limiting factor, work package completion, work package completion percentage and next construction cycle plan distribution work package quantity; The production progress module comprises a roll pipe work package construction state module intuitive display, a roll pipe work package total quantity, a roll pipe work package distribution quantity, a roll pipe welding completion total weight, a roll pipe work package completion percentage and a guide pipe rack each step roll pipe completion information.
[0018] Preferably, the warehouse module comprises warehouse capacity, warehouse storage percentage, inventory cycle consumption rate dynamic diagram, inventory change prediction diagram.
[0019] The application discloses a marine jacket construction project work package visual control method and a Kanban system. 1. The marine jacket construction project work package visual Kanban system sets a unified model, develops correlation data models for construction progress, material inventory and material production progress in the unified model, balances personnel factors, building material matching factors and environmental factors in the construction progress model, so that the construction progress is within a reasonable range, the inventory growth is reasonably controlled to avoid the situation of warehouse explosion, the production capacity progress is reasonably controlled to ensure material supply, and the production, storage and consumption of materials are balanced, so that the jacket construction can be completed as expected, the supply and storage of materials are balanced, and the overall cost is reduced.
[0020] 2. The marine jacket construction project work package visual Kanban system sets a visual module, including a construction progress module, a storage module and a production progress module, adopts a text+chart form to display actual field quantitative work, displays relevant information contents to persons responsible for each module, and designs a comprehensive unified module to comprehensively display to a person in charge of the whole project, so that each aspect progress of the whole jacket construction project is intuitively displayed, data transmission efficiency is improved, and the problem of affecting project progress due to data transmission delay is avoided.
[0021] 3. The marine jacket construction project work package visual Kanban system divides the construction progress according to different construction stages, and roughly classifies the construction progress into a high-consumable stage and a low-consumable stage, designs a corresponding material consumption and construction progress relationship function in the corresponding stage, so that the storage can effectively guarantee material supply and avoid warehouse explosion in response to different construction stages.
[0022] 4. In the material production progress model, the production capacity progress is reasonably controlled, on the one hand, each process in the production scheduling stage is stable and orderly, and the whole production process is more orderly, and on the other hand, material supply is ensured, and the situation that production capacity cannot meet the consumption demand in the rapid material consumption stage is avoided. BRIEF DESCRIPTION OF DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings needed to be used in the embodiments or prior art description. Obviously, the drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other drawings can also be obtained without creative labor on the basis of these drawings.
[0024] Figure 1 The construction progress control logic flowchart of the present application; Figure 2 The functional framework diagram of the visual board system of the present application; Figure 3 The construction progress judgment execution method flowchart of the present application; Figure 4 The material inventory judgment execution method flowchart of the present application; Figure 5 The correlation model schematic diagram of the overall planning model of the present application. DETAILED DESCRIPTION
[0025] In order to make the objects, technical solutions and advantages of the embodiments of the present application more clear, the technical solutions in the embodiments of the present application are described clearly and completely. Obviously, the described embodiments are some embodiments of the present application, but not all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor are within the protection scope of the present application.
[0026] The present application provides a kind of marine guide pipe support construction project work package visual control method and board system, solve the existing marine guide pipe support construction process, there is production and construction information not intuitive transparent, thereby leading to capacity and consumption mismatch, make the problem of warehouse pressure increase, construction cycle delay and construction cost increase.
[0027] In order to better understand the above technical solutions, the above technical solutions will be described in detail in the following in conjunction with the drawings in the specification and specific embodiments.
[0028] Embodiment one, the present application discloses a kind of marine guide pipe support construction project work package visual control method, according to the drawings Figures 1-5 As shown in the figure, the following steps are included: S1, import construction progress data, material inventory data and material production progress data; S2, the imported data is normalized, so that current construction progress, material inventory growth rate and material production speed can be obtained; S3, by designing an overall planning model, the construction progress, material inventory growth rate and material production progress are designed into three interrelated data models; In the construction progress model, by comprehensively balancing personnel factors, building material matching factors and environmental factors, the construction progress is in the error interval, and the construction progress is ensured to be within a reasonable range; In the inventory model, by reasonably controlling , so that , wherein indicates the maximum storage capacity of the warehouse, to avoid the situation of warehouse explosion; In the material production progress model, by reasonably controlling the production capacity, , so as to ensure the material supply, while taking into account the storage capacity.
[0029] The construction progress formula is:
[0030] Wherein D represents personnel factors, R represents building material matching factors, and G represents environmental factors; ; indicates the error coefficient, ; The material inventory growth rate formula is: ; Wherein represents the material increment per unit time, represents the material consumption per unit time, represents the current inventory; The material production progress formula is: ; Wherein represents the current total production of materials, represents the total demand for materials throughout the construction period; The error interval is represented as: .
[0031] By reasonably controlling the production capacity, on the one hand, it ensures that each process in the production scheduling stage is stable and orderly, and on the other hand, it makes the entire production process more orderly, on the other hand, it ensures the material supply, avoids the situation that the production capacity cannot meet the consumption demand in the rapid material consumption stage, so as to achieve the purpose of reasonable production scheduling; By setting the overall planning model, the correlation data model of construction progress, material inventory and material production progress is developed in the overall planning model. In the construction progress model, by comprehensively balancing personnel factors, building material matching factors and environmental factors, the construction progress is within a reasonable range, and by reasonably controlling the inventory growth rate, the situation of warehouse explosion is avoided, and by reasonably controlling the production capacity, the material supply is ensured, so as to balance the production, storage and consumption of materials, ensure that the jacket construction can be completed as expected, and balance the supply and storage of materials, so as to reduce the overall cost.
[0032] At the same time in the process of inventory control, the consumption speed and demand of materials are different in different construction periods, so when dividing the construction progress, the progress needs to be divided according to different construction stages, and then it can be roughly classified into high material consumption stage and low material consumption stage, and the corresponding material consumption and construction progress relationship function is designed in the corresponding stage, so that the warehouse can effectively guarantee the material supply and avoid warehouse explosion in response to different construction stages.
[0033] In the overall planning model, the construction progress control logic is embedded to intelligently control the construction progress model, the inventory model and the material production progress model, and the specific steps are as follows: S1, obtaining current construction progress data, material inventory data and material production progress data; S2, comparing the actual construction progress with the expected construction progress; S3, adjusting the construction speed according to the comparison result; S4, adjusting the production speed according to the material inventory; S5, ensuring that the engineering progress meets the time limit requirement.
[0034] The execution strategy of S3 is as follows: Step one, construction progress data acquisition, which includes which stage the current construction is in, the personnel ratio of the current construction, the on-site situation of the related equipment, the climate condition in the next construction period, and the material supply condition in the current construction stage; Step two, construction progress monitoring, comparing the actual progress with the threshold value, quantifying through the pre-designed construction progress plan, and introducing the corresponding error coefficient α, which changes in different stages of construction, for example, in the preparation stage, the error coefficient can be set to be larger, because the construction in this stage is less affected by objective factors such as materials and environment, and the progress can be quickly improved by increasing the shift; In the pouring stage, the error coefficient needs to be set smaller, because in this stage, the poured material needs to be standardized after pouring, that is, the objective factors have a greater impact, and the progress cannot be improved by simple means. Step three, analyzing and judging the current progress; Is the actual progress ∈ [standard progress * (1+α), standard progress * (1-α)]? If yes, it means that the current progress range is within the threshold value, and the current progress is maintained; If not, it means that the current progress is out of the threshold value, and then the differential judgment operation is performed; Is the actual progress ≤ standard progress * (1-α)? If yes, it means that the current progress falls behind the minimum duration progress category, at which time the acceleration module is enabled to achieve progress improvement by designing resource reinforcement strategies, such as increasing shifts, increasing construction personnel, and increasing related equipment investment to quickly improve construction speed. If no, it means that the current progress exceeds the maximum duration progress category, at which time the quality module is enabled to achieve quality enhancement within the duration by designing quality improvement strategies, thereby further improving the standardization and overall construction quality of the entire construction operation under the premise of ensuring the duration.
[0035] In the resource reinforcement strategy, the following formula is used:
[0036] By analyzing the personnel factors, building material matching factors, and environmental factors in the current construction environment, the environmental factors, as objective factors, are uncontrollable, and the construction speed can be improved by increasing the number of construction personnel and simultaneously increasing the number of building materials and related construction equipment.
[0037] The executable contents in the quality improvement strategy include: 1. Increasing the number of related construction processes, such as increasing the finishing cycle of related construction equipment, repeating the work in key construction areas 2-3 times, and setting different construction precision parameters for different materials; 2. Extending the gap time of related construction steps, such as appropriately extending the cooling and solidification time during pipe welding or concrete structure pouring, extending the temperature control to 150+10 degrees Celsius for 30 minutes in the welding process for high-carbon steel pipes, adjusting the slow cooling time after stainless steel welding to natural cooling for 48 hours to ensure component strength, extending the form removal time of mass concrete to 85% of the design strength, and extending the steam curing period to 10 days from 7 days during winter construction; 3. Reducing the construction shift frequency of construction personnel, such as changing from a three-shift system to a two-shift system to reduce work time, while supporting the establishment of a fatigue monitoring system to assess worker status in real time, implementing cross-operation management, setting AB corner rotation system for key positions, implementing "work-rest" work system for complex processes, and establishing a training system to improve single operation efficiency.
[0038] The execution strategy of S3 is: Step 1: Material inventory data acquisition; Step 2: Derive the incremental speed of consumables based on construction speed and production speed ; Step 3: If yes, it means that the inventory is within a safe range, and the current progress is maintained; If no, it means that the inventory is in a changing phase, and further differentiated judgment is made whether or not; if yes, it means that the inventory is in the growth stage, at this time, combined with the construction progress model, if the actual progress ≤ standard progress, the construction speed is increased, if the actual progress > standard progress, the production speed is reduced; if no, it means that the inventory is in the consumption stage, at this time, combined with the construction progress model, if the actual progress ≥ standard progress × (1+α), the construction speed is reduced, if the actual progress ≤ standard progress × (1-α), the material production speed is increased, and finally the construction progress adjustment is realized, and the construction progress adjustment will affect the change of material inventory, realizing the cycle control.
[0039] When controlling the inventory, due to the non-linear proportion of construction progress and consumable consumption, the consumption speed and demand of materials are different in different construction cycles, therefore, when dividing the construction progress, the progress needs to be divided according to different construction stages, which can be roughly classified as high-consumable stage and low-consumable stage, and the corresponding material consumption and construction progress relationship function is designed in the corresponding stage, which can be expressed as:
[0040] wherein represents the total material demand in unit time t cycle; is the proportional coefficient obtained by normalizing the relationship function between construction progress and material consumption speed.
[0041] Because the material consumption speed is different and the material demand is different in different cycles, therefore, in the inventory model and material production progress model; when the time point of the construction progress model approaches the high-consumable stage, the production speed is increased to expand the inventory, and the material daily turnover is increased; when the time point of the construction progress model approaches the low-consumable stage, the production speed is reduced to reduce the inventory, and the material daily turnover is reduced.
[0042] Working principle; the offshore jacket construction project work package visual control method, by setting a unified model, respectively in the unified model, the correlation data model development of construction progress, material inventory and material production progress, in the construction progress model, by comprehensively balancing personnel factors, building material matching factors and environmental factors, so that the construction progress is in a reasonable range, at the same time, by reasonably controlling the inventory growth rate, so as to avoid the situation of burst warehouse, by reasonably controlling the production capacity progress, so as to ensure the material supply, in this way, the production, storage and consumption of materials are balanced, at the same time of ensuring that the jacket construction can be completed as expected, the supply and storage of materials are balanced, so as to reduce the overall cost; At the same time in the process of inventory control, the consumption speed and demand of materials are different in different construction periods, so when dividing the construction progress, the progress needs to be divided according to different construction stages, and can be roughly classified as high-consumption stage and low-consumption stage, and the corresponding material consumption and construction progress relationship function is designed in the corresponding stage, so that the warehouse can effectively guarantee the material supply and avoid warehouse explosion in response to different construction stages.
[0043] In embodiment two, the offshore jacket construction project work package visualization board system is provided, which comprises a visualization module, the visualization module comprises a construction progress module, a warehouse module and a production progress module, the actual field quantitative work is displayed in the form of text+chart, and the relevant information content is displayed to the person in charge of each module, and a comprehensive overall module is designed to comprehensively display to the person in charge of the whole project.
[0044] By setting the visualization module, including the construction progress module, the warehouse module and the production progress module, the actual field quantitative work is displayed in the form of text+chart, and the relevant information content is displayed to the person in charge of each module, and a comprehensive overall module is designed to comprehensively display to the person in charge of the whole project, so as to intuitively display the progress of each aspect of the whole jacket construction project, improve the data transmission efficiency, and avoid the problem of affecting the project progress due to data transmission delay.
[0045] In the visualization module, The construction progress module comprises work package workload, work package distribution plan, work package material matching state, work package limiting factor, work package completion condition, work package completion percentage and next construction cycle plan distribution work package quantity; The production progress module comprises a roll pipe work package construction state module intuitive display, a roll pipe work package total quantity, a roll pipe work package distribution quantity, a roll pipe welding completion total weight, a roll pipe work package completion percentage and a jacket each step roll pipe completion condition information.
[0046] The warehouse module comprises warehouse capacity, warehouse storage percentage, inventory cycle consumption rate dynamic diagram and inventory change prediction diagram.
[0047] Working principle; by setting the visualization module, including the construction progress module, the warehouse module and the production progress module, the actual field quantitative work is displayed in the form of text+chart, and the relevant information content is displayed to the person in charge of each module, and a comprehensive overall module is designed to comprehensively display to the person in charge of the whole project, so as to intuitively display the progress of each aspect of the whole jacket construction project, improve the data transmission efficiency, and avoid the problem of affecting the project progress due to data transmission delay.
[0048] The above shows and describes the basic principles and main features of the present application and the advantages of the present application. Those skilled in the art should understand that the present application is not limited to the above embodiments, and the above embodiments and descriptions in the specification are only to illustrate the principles of the present application. Without departing from the spirit and scope of the present application, various changes and improvements can be made to the present application, and these changes and improvements all fall within the scope of the claimed present application. The scope of protection of the present application is defined by the appended claims and their equivalents.
Claims
1. A visual control method for work packages in an offshore jacket construction project, characterized in that: The following steps are involved: S1. Import construction progress data, material inventory data, and material production progress data; S2. Normalize the imported data to obtain the current construction progress, material inventory growth rate, and material production speed; S3. Design three interrelated data models for construction progress, material inventory growth rate, and material production progress through a comprehensive model; In the construction progress model, by comprehensively balancing personnel factors, building material matching factors and environmental factors, the construction progress is kept within the error range, ensuring that the construction progress is within a reasonable range; In the inventory model, through reasonable control , thus making ,in Indicates the maximum storage capacity of the warehouse to avoid warehouse overflow; In the material production schedule model, by reasonably controlling the production capacity schedule, , thereby ensuring material supply while taking into account warehousing capacity.
2. The method for visual control of work packages for an offshore jacket construction project according to claim 1, characterized in that: The construction progress formula is: Among them, D represents human factors, R represents building material matching factors, and G represents environmental factors; ; represents the error coefficient, ; The formula for material inventory growth rate is: ; in represents the material unit time increment, Indicates the material consumption per unit time, Indicates the current inventory level; The material production schedule formula is: ; in Indicates the current total material production, Indicates the total material demand during the entire construction period; The error interval is expressed as: .
3. The method for visual control of work packages for an offshore jacket construction project according to claim 1, characterized in that: The overall planning model is embedded with construction progress control logic to intelligently regulate the construction progress model, inventory model and material production progress model. The specific steps are as follows: S1. Obtain current construction progress data, material inventory data, and material production progress data; S2. Compare the actual construction progress with the expected construction progress; S3. Adjust the construction speed according to the comparison results; S4. Adjust production speed according to material inventory; S5. Ensure that the project progress meets the construction period requirements.
4. The method for visual control of work packages for offshore jacket construction projects according to claim 3, characterized in that: The execution strategy of S3 is: Step 1: Acquire construction progress data; Step 2: Construction progress monitoring: the actual progress is compared with the threshold, quantified through a pre-designed construction schedule, and the corresponding error coefficient α is introduced; Step 3: Analyze and judge the current progress; Whether actual progress ∈ [standard progress * (1 + α), standard progress * (1 - α)] holds true; If so, it means that the current progress range is within the threshold, and the current progress is maintained; If not, it means that the current progress exceeds the threshold, and a differentiated judgment operation is performed; Actual progress ≤ standard progress * (1-α)? If so, it means that the current progress is behind the minimum schedule. In this case, the rush module is activated to improve the schedule by designing resource reinforcement strategies. If not, it means that the current progress exceeds the maximum construction period. At this time, the quality module is activated and the quality of construction is enhanced within the construction period through the design of quality improvement strategies.
5. The method for visual control of work packages for an offshore jacket construction project according to claim 4, characterized in that: In the resource enhancement strategy, according to the following formula: By analyzing the human factors, building material matching factors and environmental factors in the current construction environment, it is found that environmental factors, as objective factors, are uncontrollable. The construction speed can be improved by increasing the number of construction personnel and at the same time increasing the number of building materials and building material-related construction equipment.
6. The method for visual control of work packages for an offshore jacket construction project according to claim 4, characterized in that: The executable contents of the quality improvement strategy include increasing the number of related construction processes, extending the interval time between related construction steps and reducing the frequency of construction shifts of construction personnel.
7. The method for visual control of work packages for an offshore jacket construction project according to claim 3, characterized in that: The execution strategy of S3 is: Step 1: Obtain material inventory data; Step 2: Calculate the incremental speed of consumables based on construction speed and production speed ; Step 3: Determine the current inventory increment rate whether it is established; If so, it means the inventory is within the safe range and the current progress should be maintained; If not, it means that the inventory is in a changing stage and further differentiation judgment is required. whether it is established; If so, it means that inventory is in the growth stage. At this time, we can analyze it in combination with the construction progress model. If the actual progress is less than or equal to the standard progress, we can increase the construction speed. If the actual progress is greater than the standard progress, we can reduce the production speed. If not, it means that the inventory is in the consumption stage. At this time, we analyze it in combination with the construction progress model. If the actual progress ≥ standard progress × (1 + α), we will reduce the construction speed. If the actual progress is ≤ standard progress × (1-α), the material production speed will be increased, and the construction progress will eventually be adjusted. At the same time, the construction progress adjustment will affect the changes in material inventory, thus achieving cyclic control.
8. The method and kanban system for visual control of work packages in an offshore jacket construction project according to claim 7, characterized in that: When conducting inventory control, since the construction progress and consumables consumption are in a nonlinear ratio, the consumption rate and demand for materials are different in different construction cycles. Therefore, when dividing the construction progress, it is necessary to divide the progress according to different construction stages, which can be roughly classified into high-consumables stage and low-consumables stage. In the corresponding stage, the corresponding material consumption and construction progress relationship function is designed, which can be expressed as; in It represents the total material demand per unit time period t; It is the proportional coefficient obtained by normalizing the relationship function between construction progress and material consumption rate.
9. The method for visual control of work packages for an offshore jacket construction project according to claim 8, characterized in that: Because the material consumption rate is different and the material required quantity is different in different cycles, in the inventory model and material production schedule model; When the construction schedule model approaches the high-consumption stage, increase production speed to expand inventory and improve daily material turnover; When the time point of the construction schedule model approaches the low-consumables stage, inventory is reduced by slowing down the production speed while reducing the daily material turnover.
10. A visual dashboard system for work packages in an offshore jacket construction project, used to implement the control method according to any one of claims 1 to 9, characterized in that: It includes a visualization module, which includes a construction progress module, a warehousing module and a production progress module. It uses text + charts to display the actual field quantitative work, and displays relevant information content to the person in charge of each module. At the same time, a comprehensive coordination module is designed to provide an overall display to the main person in charge of the entire project.