A construction method for installing a foundation and a column base of a steel structure by a slip method
CN120990239BActive Publication Date: 2026-08-28POWERCHINA FUJIAN ELECTRIC POWER SURVEY & DESIGN INST CO LTD
Patent Information
- Application Number
- CN202511200027.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-26
- Publication Date
- 2026-08-28
- Estimated Expiration
- 2045-08-26
AI Technical Summary
Technical Problem
[0004]本发明所要解决的技术问题是:提供一种解决因基础短柱顶部干涉而导致采用滑移法时难以在该狭窄空间内进行施工装配滑移轨道的用于滑移法安装钢结构的基础及柱脚的施工方法
Benefits of technology
[0011]本发明的有益效果在于:通过在基础短柱上以一次浇筑和二次浇筑的形式进行设计,可在一次浇筑时提供足够的滑移轨道的架设空间,避免因整体浇筑后而空间狭窄导致滑移法施工难以实现,增大施工难度及成本;在此基础上通过滑移法施工,可快速地将钢柱柱脚转移至基础短柱处进行浇筑作业;二次浇筑中通过移除滑移装置及滑移轨道以确保钢柱柱脚及基础短柱之间具有足够的浇注空间。
✦ Generated by Eureka AI based on patent content.
Smart Images

Figure CN120990239B_ABST
Abstract
The application relates to the technical field of building construction, in particular to a construction method for a foundation and a column foot of a steel structure installed by a sliding method, S1, a foundation stub is once poured, and the upper side of the foundation stub serves as a once-poured surface; S2, a sliding track is installed on the once-poured surface; S3, the steel column foot is connected with a sliding device, and then the steel column foot is integrally installed on the sliding track; the sliding device shifts the steel column foot to a predetermined foundation stub position along the sliding track; S4, the sliding device and the sliding track are removed, and then the steel column foot is connected and positioned with the once-poured surface; S5, secondary pouring is carried out between the steel column foot and the foundation stub; through the design of the once-poured and secondary-poured forms on the foundation stub, enough erection space of the sliding track can be provided during the once pouring, the sliding method construction is difficult to realize due to the narrow space after the integral pouring, and the construction difficulty and cost are increased.
Need to check novelty before this filing date? Find Prior Art
Citation Information
Patent Citations
Construction method of steel cross beam swivel structure
CN115369778A
Structure construction method and construction structure material as well as construction kit used therein
JP2013108322A