Roll-roll loading and hoisting integrated multipurpose transport ship for transporting complete set of high-power wind turbine generator equipment

By designing a through-type cargo hold and cargo deck structure, and equipping it with cranes and data processing modules, the problems of low space utilization, poor safety, and complex loading and unloading in the transportation of high-power wind turbine equipment have been solved, achieving an efficient and safe transportation and loading and unloading process.

CN121697789APending Publication Date: 2026-03-20JINYIN (SHANGHAI) SHIPPING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511740796.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-11-25
Publication Date
2026-03-20

AI Technical Summary

Technical Problem

Existing multi-purpose transport vessels suffer from problems such as low space utilization, low transport efficiency, poor safety, and complex and time-consuming loading and unloading processes when transporting high-power wind turbine equipment.

Method used

Design a multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment. It adopts a through-type cargo hold and cargo deck structure, and is equipped with cranes and data processing modules to achieve reasonable equipment layout and automated hoisting, reducing reliance on large port lifting equipment.

Benefits of technology

It improves the utilization rate of ship space, enhances transportation safety, simplifies the loading and unloading process, and reduces transportation costs and time costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121697789A_ABST
    Figure CN121697789A_ABST
Patent Text Reader

Abstract

The invention relates to the field of ships and ocean engineering, in particular to a roll-on and roll-off integrated multipurpose transport ship for transporting a whole set of high-power wind turbine generator equipment, which mainly comprises a ship body, the ship body is sequentially provided with a bulwark, a cargo deck, a through-type cargo hold, an inner bottom and a ship bottom from top to bottom, and the through-type cargo hold is arranged in the ship body. The through-type cargo hold is used for loading wind turbine generator host equipment, the wind turbine generator host equipment comprises a cabin, a hub, a transformer and a transmission chain, a hatch of the through-type cargo hold is located in the middle of the main deck, a through-type hatch cover is detachably installed above the hatch of the through-type cargo hold, and the top of the through-type hatch cover is flush with the top of the cargo deck; the cargo deck is used for loading a tower drum section, a single pile, a transition section and blades of wind turbine generator equipment; two cranes are arranged on a starboard of the main deck and used for hoisting and transferring wind turbine generator main machine equipment, a tower drum section, fan blades and a single pile with light weight.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of shipbuilding and marine engineering, and in particular to a roll-on / roll-off multipurpose transport vessel for transporting complete sets of high-power wind turbine equipment. Background Technology

[0002] With the continuous growth of global demand for clean energy, the wind power industry has developed rapidly. High-power wind turbine equipment, due to its advantages such as large power generation and high efficiency, has gradually become the mainstream choice for wind farm construction. However, high-power wind turbine equipment is characterized by its large size, heavy weight, and complex structure; its blades can reach lengths of over 100 meters, and its nacelle can weigh hundreds of tons. Currently, multi-purpose transport vessels can only transport individual wind turbine units, requiring the entire wind turbine equipment to be transported to port before installation can be arranged, significantly increasing the installation cycle.

[0003] Currently, traditional multi-purpose transport vessels face numerous problems when transporting high-power wind turbine equipment: (1) Due to the irregular size of wind turbine equipment, it is difficult to make reasonable layout on ships, resulting in low space utilization and low transportation efficiency. (2) During maritime transport, ships are affected by environmental factors such as wind and waves. The wind turbine equipment on the deck is prone to swaying, displacement, or even capsizing, which seriously affects transport safety. (3) Existing transport ships often need to rely on large port cranes when loading and unloading wind turbine equipment, which is complicated and time-consuming, increasing transportation and time costs. Summary of the Invention

[0004] The multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment provided in this application adopts the following technical solution: A multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment includes a hull, which is provided from top to bottom with bulwarks, a cargo deck, a through-type cargo hold, an inner bottom, and a hull bottom. The through-type cargo hold is provided inside the hull and is used to load the main equipment of the wind turbine. The main equipment of the wind turbine includes a nacelle, a hub, a transformer, and a transmission chain. The hatch of the through-type cargo hold is located in the middle of the main deck. The hatch of the through-type cargo hold is detachably equipped with a through-type hatch cover, and the top of the through-type hatch cover is flush with the top of the cargo deck. The cargo deck is used to load the tower sections, monopiles, transition sections, and blades of the wind turbine equipment. The tower sections are divided into tower section one, tower section two, tower section three, and tower section four. Two cranes are located on the starboard side of the main deck. These two cranes are used to lift and transfer the main wind turbine equipment, tower sections, wind turbine blades, and lighter monopiles.

[0005] Preferably, the through-type cargo hold is equipped with several detachable double-layer cabinet covers. The double-layer cabinet covers can be installed vertically to locally reinforce the load according to the location of the loaded goods, or laid horizontally in the through-type cargo hold to divide the through-type cargo hold into upper and lower layers.

[0006] Preferably, the cargo deck is equipped with a cargo securing and lashing system, which includes a securing base, lashing ropes, and fastening clamps.

[0007] Preferably, both cranes are equipped with a main hook and an auxiliary hook. The main hook has a lifting capacity of 700 tons and a lifting distance of 40 meters, while the auxiliary hook has a lifting capacity of 60 tons and a lifting distance of 56 meters.

[0008] Preferably, it also includes a data processing module, which is used to automatically calculate and output the hoisting sequence of the tower sections based on the input tower section layout information and crane information; The tower layout information includes the positioning coordinates of the tower sections on the cargo deck and the tower section number, and the crane information includes the coordinate data of the two cranes.

[0009] Preferably, the loading method for the transport vessel includes the following steps: Step S1: Load the main equipment of the wind turbine into the through-type cargo compartment. The main equipment of the wind turbine includes the transformer, drive chain, nacelle and hub. Step S2: The transition section and the tower section are loaded onto the main deck in sequence, and the transition section, tower section one, tower section two, tower section three and tower section four are loaded onto the cargo deck in an upright position. Step S3: Roll-on monopiles are installed using SPMT trolleys, and the monopiles are laid flat on the cargo deck, with the monopiles set along the bow and stern of the hull. Step S4: Install blade brackets at the middle and tail of the wind turbine blades so that the wind turbine blades are stacked on the blade brackets in a top-to-bottom direction.

[0010] Preferably, step S1 includes the following steps: Step S11: Use two cranes to lift the nine through-type hatch covers off the hatch opening of the through-type cargo hold; Step S12: Arrange the second-layer cabinet cover plate as a vertical support for the movable transverse bulkhead under the through-type cover that contacts the monopile bracket and fix it. Step S13: In the space where the moving transverse bulkhead is directed toward the bow, the first layer of cargo is arranged at the bottom of the through-type cargo hold using a crane; Step S14: After the first layer of cargo is arranged, a second layer of container cover is laid in the through-type cargo hold to separate an upper space above the first layer of cargo for arranging the second layer of cargo. Step S15: Arrange the second layer of cargo in the upper space using a crane, and re-lift the hatch cover to the hatch of the through-type cargo hold.

[0011] Preferably, step S2 includes the following steps: Step S21: Transport the transition section to the dock and place it on a temporary pier for storage. Use any crane to lift the transition section bracket from the dock to the cargo deck and secure it. Use a crane to lift the transition section and move it above the transition section bracket to complete the positioning. Connect the transition section to the transition section bracket with bolts. Step S22: Transport the tower section to the dock and place temporary support blocks under the tower section. Use a crane to lift the tower bracket from the dock to the cargo deck and secure it. Connect the head and tail of the tower section to two cranes using rigging. After the hooks of the two cranes lift slightly at the same time, the crane connected to the tail of the tower section stops lifting, while the crane connected to the head of the tower section continues to lift, causing the tower to tilt and gradually adjust to an upright position. After the tower section is erected, remove the rigging from the crane connected to the tail of the tower section. Use the crane connected to the head of the tower section to move the tower section to the corresponding tower bracket and fix the tower section to the tower bracket with bolts. Step S23: After both the transition section and the tower section are loaded, the ship turns around and berths.

[0012] Preferably, step S3 includes the following steps: Step S31: Adjust the cargo deck to be level with the dock by ballast water adjustment; Step S32: Transport the monopile to the dock using an SPMT trolley and install the monopile bracket on the monopile; Step S33: Erect a gangway between the ship's side and the dock, and roll over the monopile 18 using an SPMT trolley. The SPMT trolley will then board the ship via the gangway and remain in position, securing the monopile bracket to the cargo deck.

[0013] Preferably, step S4 includes the following steps: Step S41: Install a blade tail bracket at the tail of the wind turbine blade and a blade middle bracket at the middle of the wind turbine blade. Step S42: Transport the wind turbine blades to the dock in sequence; Step S43: Connect any crane to the blade tail bracket lug and the blade middle bracket lug using slings, and use the crane to lift the wind turbine blade to the position, and then tie the blade tail bracket and the blade middle bracket to the cargo deck. Step S44: Stack the wind turbine blades from bottom to top using a crane. The tooling connects and fixes the tail bracket of the blade to the tail bracket of the blade, and connects and fixes the middle bracket of the blade to the middle bracket of the blade. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of Embodiment 1 of this application used to illustrate the overall structure of the transport ship.

[0015] Figure 2 This is a schematic diagram of the cargo deck plan structure of a ship, as shown in Embodiment 1 of this application.

[0016] Figure 3 This is a schematic diagram of Embodiment 1 of this application used to illustrate the internal structure of a through-type cargo hold.

[0017] Figure 4 This application's embodiment 1 is used to illustrate the arrangement of the monopile, transition section, tower section 1, tower section 2, tower section 3, tower section 4, and wind turbine blades on the cargo deck of the transport ship after the through-type cargo hold is loaded.

[0018] Figure 5 This is a schematic diagram illustrating the structure of wind turbine blades mounted on a ship's hull, as described in this application.

[0019] Explanation of reference numerals in the attached drawings: 1. Hull; 2. Inner bottom; 3. Cargo deck; 4. Crane; 5. Through-type cargo hold; 51. Through-type hatch cover; 52. Second-level cabinet cover; 10. Monopile; 20. Wind turbine blade; 30. Tower section. Detailed Implementation

[0020] The following combination Figures 1-5 This application will be described in further detail.

[0021] Example 1 This application discloses a multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment. (Refer to...) Figures 1-2 The vessel mainly consists of a hull 1, which, from top to bottom, includes bulwarks, a cargo deck 3, a through-type cargo hold 5, an inner bottom 2, and a hull bottom. The hull 1 is also equipped with an advanced power system and propulsion device. The power system has sufficient power to ensure stable speed and good maneuverability even in complex sea conditions when transporting wind turbine equipment.

[0022] The through-type cargo hold 5 is located in the middle of the interior of the hull 1. This through-type cargo hold 5 can also be used as a ballast water tank. During the loading of various parts of the wind turbine equipment, the height of the cargo deck surface can be adjusted through the ballast water system built into the hull 1. At the same time, the ballast water distribution can also be adjusted through the ballast water system to keep the hull 1 stable during loading.

[0023] The through-type cargo hold 5 is equipped with 18 removable second-level container covers 52. These second-level container covers 52, installed horizontally, divide the through-type cargo hold 5 into upper and lower levels to facilitate the loading of different types of cargo. Simultaneously, the second-level container covers 52 can be installed vertically as movable transverse bulkheads to provide localized load reinforcement based on cargo location. The installation method of the second-level container covers 52 can be adjusted according to actual usage needs, and the number of second-level container covers 52 can also be adjusted according to the dimensions of the through-type cargo hold 5.

[0024] The through-type cargo compartment 5 is also equipped with temperature control, dehumidification and shock absorption facilities, which can provide a suitable storage environment for the transformer, transmission chain, nacelle and hub of the wind turbine equipment, and reduce the occurrence of damage to the above components during transportation.

[0025] It should be noted that, in this embodiment, 6 of the 18 second-layer cabinet cover plates 52 have strong load-bearing capacity. The second-layer cabinet cover plates 52 with strong load-bearing capacity can be installed on the cargo deck 3 as the edge structure of the cargo deck 3 to increase the cargo carrying area of ​​the cargo deck 3 on the hull 1.

[0026] Please refer to Figure 3 In this embodiment of the application, nine through-type hatch covers 51 are installed on the hatch of the through-type cargo hold 5. The nine through-type hatch covers 51 are arranged sequentially along the length direction above the hatch of the through-type cargo hold 5, covering the internal space of the through-type cargo hold 5. The top surface of the through-type hatch covers 51 is flush with the top surface of the cargo deck.

[0027] Please refer to Figure 1 and Figure 2 To facilitate the transport and loading of wind turbine equipment, in this embodiment, two cranes 4 are installed on the starboard side of the cargo deck 3. The two cranes 4 can perform single-lift operations or tandem lifting operations. Both cranes 4 are equipped with a main hook and an auxiliary hook. The main hook has a lifting capacity of 700 tons and a lifting distance of 40 meters, while the auxiliary hook has a lifting capacity of 60 tons and a lifting distance of 56 meters. The main hook can be used to lift large and heavy wind turbine equipment components, while the auxiliary hook can be used to lift small parts of the wind turbine equipment.

[0028] Since the ship hull 1 has its own crane 4 on the deck, it can transfer and lift the various components of the wind turbine equipment without the need for the large crane 4 in the port, which can save transportation costs and time costs.

[0029] In this embodiment, the main wind turbine equipment is disassembled into the nacelle, hub, transformer, drive train, monopile 10, transition section, tower section 30, and wind turbine blades 20 for loading. The tower section 30 includes tower section one, tower section two, tower section three, and tower section four. Among them, the nacelle, hub, transformer, and drive train constitute the main wind turbine equipment, which are hoisted into the through-type cargo hold 5 by two cranes 4 for loading. In addition, the through-type cargo hold can also be used to store other precision equipment and instruments of the wind turbine equipment. The monopile 10, transition section, tower section one, tower section two, tower section three, tower section four, and wind turbine blades 20 are all loaded on the cargo deck 3.

[0030] It should be noted that, please refer to Figure 4 and Figure 5 In this embodiment, the transition section, tower section 1, tower section 2, tower section 3, and tower section 4 are all vertically mounted. The transition section, tower section 1, tower section 2, tower section 3, and tower section 4 have a high center of gravity and strict requirements for acceleration. Therefore, the transition section, tower section 1, tower section 2, tower section 3, and tower section 4 are arranged on the cargo deck 3 near the bow. In order to save space, the wind turbine blades 20 are stacked and arranged on the cargo deck 3 near the port side. The heavy and horizontally placed monopile 10 is arranged in the rear part of the cargo deck 3.

[0031] In order to securely fix the monopile 10, transition section, tower section 1, tower section 2, tower section 3, tower section 4, and blades to the cargo deck and prevent equipment displacement or damage due to ship swaying during transportation, in this embodiment, the surface of the cargo deck 3 is provided with a special cargo fixing and lashing system, which consists of a fixing base, lashing ropes, and fastening clamps.

[0032] It should be noted that in this embodiment, the transition section is transported vertically to the dock by a transport vehicle, while the first, second, third, and fourth tower sections are all transported horizontally to the dock by a transport vehicle.

[0033] This embodiment also proposes a loading method for a roll-on / roll-off (Ro-Ro) multi-purpose transport vessel that integrates the transport of complete sets of high-power wind turbine equipment. It mainly includes the following steps: Step S1: Load the main equipment of the wind turbine into the through-type cargo nacelle 5. The main equipment of the wind turbine includes a transformer, transmission chain, nacelle and hub. Step S2: The transition section and the tower section 30 are loaded onto the cargo deck 3 in sequence, and the transition section, tower section 1, tower section 2, tower section 3 and tower section 4 are loaded onto the cargo deck 3 in an upright position. Step S3: Roll up the monopile 10 using the SPMT trolley, lay the monopile 10 flat on the cargo deck 3, and set the monopile 10 along the bow and stern direction of the hull 1. Step S4: Install blade brackets at the middle and tail of the fan blades 20, so that the fan blades 20 are stacked on the blade brackets in a top-to-bottom direction.

[0034] Step S1 includes the following steps: Step S11: Use two cranes 4 to lift the nine through-type hatch covers 51 away from the hatch opening of the through-type cargo hold 5. Step S12: Arrange the second-layer cabinet cover plate 52 as a vertical support for the movable transverse bulkhead under the through-type cover 51 that contacts the single pile 10 bracket and fix it. Step S13: In the space where the moving transverse bulkhead is directed toward the bow, the first layer of cargo is arranged at the bottom of the through-type cargo hold 5 using a crane. Step S14: After the first layer of cargo is arranged, a second layer of cabinet cover 52 is laid in the through-type cargo hold 5 to separate an upper space above the first layer of cargo for arranging the second layer of cargo. Step S15: Arrange the second layer of cargo in the upper space using crane 4, and re-lift the hatch cover to the hatch of the through-type cargo hold 5.

[0035] Step S2 includes the following steps: Step S21: Transport the transition section to the dock and place it on a temporary pier for storage. Use any crane 4 to lift the transition section bracket from the dock to the cargo deck 3 and complete the binding. Use the crane 4 to lift the transition section and move it above the transition section bracket to complete the positioning. Connect the transition section to the transition section bracket with bolts. Step S22: Transport the tower section 30 to the dock and place temporary support blocks under the tower section 30. Use any crane 4 to lift the tower bracket from the dock to the cargo deck 3 and secure it. Connect the head and tail of the tower section 30 to two cranes 4 using rigging. After the hooks of the two cranes 4 are raised slightly at the same time, the crane 4 connected to the tail of the tower section 30 stops lifting, while the crane 4 connected to the head of the tower section 30 continues to lift, causing the tower to tilt and gradually adjust to an upright position. After the tower section 30 is erected, remove the rigging from the crane 4 connected to the tail of the tower section 30. Use the crane 4 connected to the head of the tower section 30 to move the tower section 30 to the corresponding tower bracket and fix the tower section 30 to the tower bracket with bolts. After step S23, when the transition section and tower section 30 are both loaded, the ship turns around and berths.

[0036] Step S3 includes the following steps: Step S31: Adjust the cargo deck 3 to be flush with the dock by adjusting the ballast water load; Step S32: Transport the monopile 10 to the dock using an SPMT trolley and install the monopile 10 bracket on the monopile 10. Step S33: Erect a gangway between the ship's side and the dock, and roll over the monopile 10 using an SPMT trolley. The SPMT trolley will then board the ship via the gangway and remain in position. The monopile 10 bracket will be secured to the cargo deck 3.

[0037] It should be noted that in some other embodiments, in step S3, some of the lighter monopiles can also be lifted by two cranes on the cargo deck together, which will not be limited or elaborated here.

[0038] Step S4 includes the following steps: Step S41: Install a blade tail bracket at the tail of the fan blade 20 and a blade middle bracket at the middle of the fan blade 20. Step S42: Transport the wind turbine blades 20 to the dock in sequence; Step S43: Connect any crane 4 to the blade tail bracket lug and the blade middle bracket lug using slings, and use the crane 4 to lift the wind turbine blade 20 to the position, and tie the blade tail bracket and the blade middle bracket to the cargo deck 3. Step S44: Stack the wind turbine blades 20 by crane 4 in a bottom-up stacking manner, connect and fix the blade tail bracket to the blade tail bracket, and connect and fix the blade middle bracket to the blade middle bracket.

[0039] Example 2 In this embodiment, the transport vessel also includes a data processing module located in the control compartment. The data output terminal of the data processing module is connected to a display screen inside the compartment. The data processing module can automatically calculate the hoisting sequence of the tower section 30 based on the input layout information of the tower section 30 and the information of the crane 4, and display the result on the display screen.

[0040] The tower section 30 layout information includes the positioning coordinates of the tower section 30 on the cargo deck 3 and the tower section 30 number. The crane 4 information includes the coordinate data of the two cranes 4.

[0041] In this embodiment, a two-dimensional coordinate system is established on the surface of the cargo deck 3 with the starboard side of the hull 1 as the X-axis and the edge of the cargo deck 3 near the stern as the Y-axis. Before loading, relevant technicians pre-plan the loading positions of the tower sections 30 based on the safety distance of the tower sections 30, the width of the wind turbine blades 20, and the positions of the two cranes 4 on the cargo deck 3, and pre-number the tower sections 30 to be loaded at each position.

[0042] It should be noted that the safety distance is determined based on the space occupied by the cargo securing and lashing system on cargo deck 3 and the space interval requirements between adjacent cargo securing and lashing systems.

[0043] The data processing module automatically calculates the hoisting sequence of tower section 30 based on the layout information of tower section 30 and the information of crane 4. The data processing method includes the following steps: Step A: Calculate the blockage factor of each tower segment 30 in the layout. The blockage factor is a score used to evaluate the blockage caused by the tower segment 30 to the adjacent tower segments 30. Step B: Calculate the hoisting priority for each tower section 30 based on the blockage coefficient; Step C: Output the loading order of tower sections 30 in descending order of priority, and display the loading order on the display.

[0044] In step A, the specific method for calculating the blockage coefficient of tower section 30 is as follows: Step A1: Define the hoisting shielding sector area of ​​tower segment 30Ti: For each tower segment 30Ti, calculate the vector Vi from tower Q to tower segment 30Ti; determine the sector angle by rotating vector Vi clockwise by θ2 and counterclockwise by θ2, where θ is the sector angle of the hoisting shielding sector area, and θ is an empirical parameter (θ is 30° in this embodiment); use the maximum hoisting distance of crane 4 as the radius of the hoisting shielding sector area; Step A2: Determine whether the remaining tower sections 30 are located within the hoisting shielding sector area of ​​tower section 30Ti by checking the angle and distance. Step A3: Calculate the number of tower sections 30 located within the hoisting shielding sector area of ​​tower section 30Ti. The number of tower sections 30 located within the hoisting shielding sector area of ​​tower section 30Ti is the blockage degree of tower section 30Ti.

[0045] In step A2, the angle check for the remaining tower sections 30 is as follows: calculate the vector Vj between the crane 4Q and the tower section 30Tj, calculate the angle between Vi and Vj, and if the angle between Vi and Vj is less than θ2, then it is determined that the tower section 30Tj is located within the hoisting shielding sector of the tower section 30Ti; otherwise, the tower section 30Tj is not located within the hoisting shielding sector of the tower section 30Ti.

[0046] In step A2, the distance check for the remaining tower sections 30 is as follows: calculate the straight-line distance Li between tower section 30Ti and crane 4Q, and calculate the straight-line distance Lj between tower section 30Tj and crane 4Q. If Lj > Li, it means that the path for hoisting Tj must pass through the area where Ti is located, so Ti will block Tj; if Lj < Li, then the opposite is true.

[0047] For tower section 30Ti, if there is blockage in angle check and / or distance check, it is determined that tower section 30Ti is blocking tower section 30Tj. The number of Tj can reflect the blockage coefficient of tower section 30Ti. For tower section 30 with a higher blockage coefficient, it is prioritized for hoisting and loading, which can improve the efficiency of loading tower section 30.

[0048] The above are all preferred embodiments of this application and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A multi-purpose transport vessel integrating roll-on / roll-off and hoisting for transporting complete sets of high-power wind turbine equipment, characterized in that... The vessel includes a hull, which, from top to bottom, consists of bulwarks, a cargo deck, a through-type cargo hold, an inner bottom, and a hull bottom. The through-type cargo hold is used to load the main equipment of a wind turbine generator set. The main equipment of the wind turbine generator set includes a nacelle, a hub, a transformer, and a transmission chain. The hatch of the through-type cargo hold is located in the middle of the main deck. The hatch of the through-type cargo hold is detachably fitted with a through-type hatch cover, and the top of the through-type hatch cover is flush with the top of the cargo deck. The cargo deck is used to load the tower sections, monopiles, transition sections, and blades of the wind turbine equipment. The tower sections are divided into tower section one, tower section two, tower section three, and tower section four. Two cranes are located on the starboard side of the main deck. These two cranes are used to lift and transfer the main wind turbine equipment, tower sections, wind turbine blades, and lighter monopiles.

2. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 1, characterized in that, The through-type cargo hold is equipped with several detachable double-layer cabinet covers. These double-layer cabinet covers can be installed vertically to provide localized load reinforcement or laid horizontally within the through-type cargo hold to divide it into upper and lower layers, depending on the location of the loaded cargo.

3. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 2, characterized in that, The cargo deck is equipped with a cargo securing and lashing system, which includes a securing base, lashing ropes, and fastening clamps.

4. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment as described in claim 3, characterized in that... Both cranes are equipped with a main hook and an auxiliary hook. The main hook has a lifting capacity of 700 tons and a lifting distance of 40 meters, while the auxiliary hook has a lifting capacity of 60 tons and a lifting distance of 56 meters.

5. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 4, characterized in that, It also includes a data processing module, which is used to automatically calculate and output the hoisting sequence of the tower sections based on the input tower section layout information and crane information; The tower layout information includes the positioning coordinates of the tower sections on the main deck and the tower section number, and the crane information includes the coordinate data of the two cranes.

6. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 4, characterized in that, The loading method for transport vessels includes the following steps: Step S1: Load the main equipment of the wind turbine into the through-type cargo compartment. The main equipment of the wind turbine includes the transformer, drive chain, nacelle and hub. Step S2: The transition section and the tower section are loaded onto the cargo deck in sequence, and the transition section, tower section one, tower section two, tower section three and tower section four are loaded onto the cargo deck in an upright position. Step S3: Roll-on monopiles are installed using SPMT trolleys, and the monopiles are laid flat on the cargo deck, with the monopiles set along the bow and stern of the hull. Step S4: Install blade brackets at the middle and tail of the wind turbine blades so that the wind turbine blades are stacked on the blade brackets in a top-to-bottom direction.

7. A roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment as described in claim 6, characterized in that... Step S1 includes the following steps: Step S11: Use two cranes to lift the nine through-type hatch covers off the hatch opening of the through-type cargo hold; Step S12: Arrange the second-layer cabinet cover plate as a vertical support for the movable transverse bulkhead under the through-type cover that contacts the monopile bracket and fix it. Step S13: In the space where the moving transverse bulkhead is directed toward the bow, the first layer of cargo is arranged at the bottom of the through-type cargo hold using a crane; Step S14: After the first layer of cargo is arranged, a second layer of container cover is laid in the through-type cargo hold to separate an upper space above the first layer of cargo for arranging the second layer of cargo. Step S15: Arrange the second layer of cargo in the upper space using a crane, and re-lift the hatch cover to the hatch of the through-type cargo hold.

8. The roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 7, characterized in that, Step S2 includes the following steps: Step S21: Transport the transition section to the dock and store it on a temporary pier. Use a crane to lift the transition section bracket from the dock to the cargo deck and secure it. Use a crane to lift the transition section and move it above the transition section bracket to complete the positioning. Connect the transition section to the transition section bracket with bolts. Step S22: Transport the tower section to the dock and place temporary support blocks under the tower section. Use a crane to lift the tower bracket from the dock to the cargo deck and secure it. Connect the head and tail of the tower section to two cranes using rigging. After the hooks of the two cranes lift slightly at the same time, the crane connected to the tail of the tower section stops lifting, while the crane connected to the head of the tower section continues to lift, causing the tower to tilt and gradually adjust to an upright position. After the tower section is erected, remove the rigging from the crane connected to the tail of the tower section. Use the crane connected to the head of the tower section to move the tower section to the corresponding tower bracket and fix the tower section to the tower bracket with bolts. Step S23: After both the transition section and the tower section are loaded, the ship turns around and berths.

9. A roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment as described in claim 8, characterized in that, Step S3 includes the following steps: Step S31: Adjust the cargo deck to be level with the dock by ballast water adjustment; Step S32: Transport the monopile to the dock using an SPMT trolley and install the monopile bracket on the monopile; Step S33: Erect a gangway between the ship's side and the dock, and roll on the monopile using an SPMT trolley. The SPMT trolley moves onto the ship via the gangway and lowers the monopile into position. The monopile bracket is then secured to the cargo deck.

10. A roll-on / roll-off (Ro-Ro) and hoisting integrated multi-purpose transport vessel for transporting complete sets of high-power wind turbine equipment according to claim 9, characterized in that, Step S4 includes the following steps: Step S41: Install a blade tail bracket at the tail of the wind turbine blade and a blade middle bracket at the middle of the wind turbine blade. Step S42: Transport the wind turbine blades to the dock in sequence; Step S43: Connect the two crane auxiliary hooks to the blade tail bracket lug and the blade middle bracket lug respectively using slings, and use the crane to lift the wind turbine blade to the position, and tie the blade tail bracket and the blade middle bracket to the cargo deck. Step S44: Stack the wind turbine blades from bottom to top using a crane, connect and fix the tail brackets of the blades to each other, and connect and fix the middle brackets of the blades to each other.