Prefabricated guardrail connection structure and assembly method with elastic guide self-locking mechanism
By employing a self-locking mechanism with elastic guidance and an axial tightening sealing structure, the contradiction between rapid assembly and high structural integrity in prefabricated guardrail connection structures has been resolved. This has enabled efficient assembly and continuous anti-collision stiffness of short-distance guardrails, improving construction efficiency and quality stability.
Patent Information
- Application Number
- CN202611144135.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-30
- Publication Date
- 2026-11-10
AI Technical Summary
Existing prefabricated guardrail connection structures cannot simultaneously achieve rapid assembly and high structural integrity. Welded connections offer strong integrity but suffer from low construction efficiency and poor quality control. Bolted connections are convenient but lack self-locking reliability. Traditional mortise and tenon structures rely on manual alignment, resulting in low efficiency. These structures cannot meet the high-efficiency, precise, and reliable construction and load-bearing requirements of short-distance guardrails.
The system employs a self-locking mechanism with elastic guidance. Through the interlocking male and female plug-in components and the axial tightening and sealing mechanism, it achieves automatic and precise alignment and active self-locking of prefabricated guardrail segments, strengthens the bending stiffness of the nodes, and improves the overall continuous stiffness of the anti-collision system.
It enables efficient assembly and vibration-resistant reinforcement of short-distance guardrails, avoids node slippage and loosening, enhances the structural anti-collision continuity and construction quality stability, and reduces the difficulty and maintenance cost of on-site high-altitude welding operations.
Smart Images

Figure CN123064103A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of road and bridge traffic safety facilities technology, and in particular to a prefabricated guardrail connection structure and assembly method with an elastic guiding self-locking mechanism. Background Technology
[0002] With the continuous advancement of urbanization, the safety protection construction standards for bridges and municipal road infrastructure are constantly improving. As a core component for mitigating driving risks and reducing accident damage, the structural reliability and construction efficiency of crash barriers directly determine the level of road operational safety. Traditional cast-in-place crash barriers require on-site reinforcement binding, formwork erection, pouring, and curing, resulting in long construction cycles, difficulties in on-site quality control, and severe traffic disruption. They are also poorly suited for urban expansion and redevelopment projects, interchange ramps, and other restricted areas. Therefore, prefabricated guardrail construction, which involves factory manufacturing and on-site assembly, has become the mainstream development direction for road protection engineering due to its advantages of standardized production, fast assembly speed, and minimal on-site disruption.
[0003] Prefabricated guardrails rely on segmental splicing for assembly. The connection structure between adjacent segments directly determines the overall load-bearing stiffness, assembly efficiency, and long-term durability. Existing connection methods all have inherent technical defects, especially in adaptability to short-distance, few-segment guardrail applications such as median strips of ramps, sides of small bridges, and partial protection at level crossings. Welded connections have good overall load-bearing performance, but the high temperature of welding can easily cause thermal cracking of concrete, residual stress in the weld can easily induce fatigue damage, and the quality stability of high-altitude welding on site is poor, resulting in high maintenance costs. Bolted connections are convenient to assemble, but the drilling accuracy requirements are strict, bolts are prone to loosening under vehicle vibration, and the point contact force transmission mode has obvious stress concentration, weak bending stiffness of the joints, and insufficient impact resistance. Traditional mortise and tenon structures rely solely on interlocking friction for force transmission, lacking automatic correction and active self-locking capabilities. Lifting and alignment rely on manual calibration, which is inefficient, and they are prone to failure problems such as tenon dislodgement and segment separation under lateral impact loads. While post-cast concrete offers excellent overall integrity, it suffers from a long curing period and is prone to cracking and water seepage at the interface between new and old concrete, thus failing to leverage the core advantages of prefabricated rapid construction.
[0004] In summary, existing connection structures generally suffer from technical contradictions: it is difficult to simultaneously achieve rapid assembly and high structural integrity. Welding and post-cast molding offer strong integrity but suffer from low construction efficiency and poor quality control; bolts and traditional mortise and tenon joints provide convenient assembly but have low alignment tolerance, insufficient self-locking reliability, and weak overall rigidity. The fundamental reason is that traditional structures are all passive force-bearing modes, relying on manual alignment and static friction of contact surfaces for locking, which cannot meet the high-efficiency, precise, and highly reliable construction and force-bearing requirements of short-distance prefabricated guardrails. How to achieve automatic and precise alignment and active self-locking reinforcement of prefabricated segments, improve the overall bending stiffness of nodes, and form a uniformly stressed, rigid, continuous protective structure from discrete prefabricated segments is a technical problem that urgently needs to be solved in this field. Summary of the Invention
[0005] To achieve the above objectives, the present invention provides an assembled guardrail connection structure with an elastic guiding self-locking mechanism, comprising multiple prefabricated guardrail segments spliced end to end in sequence. Each prefabricated guardrail segment includes at least a starting guardrail segment, a standard guardrail segment, and a sealing guardrail segment. The mating ends of adjacent prefabricated guardrail segments are respectively equipped with mutually interlocking elastic self-locking mechanisms. An axial tightening and sealing mechanism is provided through the interior of each prefabricated guardrail segment. The elastic self-locking mechanism includes mutually compatible male plug-in components and female plug-in grooves. The outer periphery of the male plug-in component is provided with an elastic guide component that can be radially elastically deformed. The outer side of the elastic guide component is provided with a locking protrusion. The inner wall of the female plug-in groove is provided with a locking groove that matches the locking protrusion.
[0006] Preferably, the male connector is a convex tenon, and the female connector groove is a receiving groove opened on the inner side of the guardrail docking end; the convex tenon is fixedly set in the middle of the docking side of the starting guardrail segment and the standard guardrail segment, and the receiving groove is opened inside the docking side of the adjacent standard guardrail segment and the end guardrail segment.
[0007] Preferably, elastic guide plates are symmetrically fixed on both the front and rear sides of the convex tenon, and guide lining plates are fixed on the top and bottom walls of the receiving inner groove.
[0008] Preferably, a locking protrusion is fixed on the outer side of the elastic guide plate, and locking slots are opened on the front and rear side walls of the receiving inner groove; during the docking and insertion process of the guardrail, the locking protrusion rebounds with the elastic guide plate and is locked into the locking slot, thereby realizing the lateral self-locking of adjacent guardrail segments.
[0009] Preferably, a limiting component is provided between the end of the male connector and the bottom of the female connector groove. The limiting component is used to restrict the vertical relative sliding of the guardrail segments. The limiting component includes a guide sleeve, a positioning rod, and a buffer pad. The guide sleeve is fixed to the end of the convex tenon, the positioning rod is fixed to the bottom of the receiving inner groove, and the buffer pad is provided at the front end of the positioning rod. In the assembled state, the positioning rod is slidably inserted into the inside of the guide sleeve.
[0010] Preferably, the axial tightening sealing mechanism is a post-tensioned prestressed sealing assembly, comprising multiple corrugated pipes, intercalating steel strands running through all the corrugated pipes, end anchor bases, joint seals, and tensioning locking components; corrugated pipes are respectively arranged at the top of each guardrail segment, the corrugated pipes including the starting end corrugated pipe, the intermediate corrugated pipe, and the sealing end corrugated pipe; an anchor base is provided on one side of the starting guardrail segment, and a locking component is provided at the end of the sealing end guardrail segment; and waterproof rings and outer sealing strips are respectively arranged on the mating end faces of adjacent guardrails.
[0011] Preferably, the locking assembly includes a pressure-bearing steel plate, a conical clamp, and a metal protective end cap; the pressure-bearing steel plate is fixed to the end of the end guardrail segment, the inside of the protective end cap is a conical cavity, and the conical clamp is assembled inside the protective end cap and clamps the inserted steel strand.
[0012] Preferably, each prefabricated guardrail segment has an embedded groove at its top, with a lifting ring pre-embedded in the groove; an outer protective plate is fitted to the front side of the guardrail segment, and a reflective warning strip is affixed to the top of the front side of the guardrail segment.
[0013] The present invention also provides a method for hoisting and assembling a guardrail based on the above-mentioned prefabricated guardrail connection structure with elastic guiding self-locking mechanism, comprising the following steps: Step 1: Factory prefabrication and pre-assembly: Prefabricate the starting guardrail segment, standard guardrail segment, and end guardrail segment, and simultaneously pre-embed and assemble the elastic self-locking mechanism, axial tightening and sealing mechanism, lifting ring, outer protective plate and reflective warning strip, and check the flexibility of movement and the firmness of connection of each component; Step 2: Segmented hoisting and initial alignment: The hoisting equipment grabs the guardrail segments with the hoisting rings, first fixes the starting guardrail segment, and then hoists the standard guardrail segments and the end guardrail segments in sequence, slowly moving them closer to the guardrail that is already in place, so that the convex tenon is aligned with the receiving inner groove; Step 3: Adaptive Guiding Elastic Self-Locking: As the guardrail continues to close, the convex tenon extends into the receiving inner groove, and the elastic guide plate is squeezed and contracted by the inner wall of the receiving inner groove, automatically correcting the horizontal, vertical, and corner alignment deviations; after the locking protrusion moves to the locking slot position, the elastic guide plate rebounds and makes the locking protrusion lock into the locking slot, completing the horizontal self-locking. Step 4: Axial tensioning and sealing: Anchor one end of the inserted steel strand to the anchor base of the starting guardrail segment, and extend the other end to the outside of the pressure-bearing steel plate of the sealing guardrail segment; tension the inserted steel strand to the designed tension force using tensioning equipment; the conical clamps self-lock and hold the inserted steel strand to maintain axial pre-tension pressure; the end face waterproof ring and the outer sealing strip are squeezed and deformed to fill the splice gap to achieve waterproof sealing; Step 5: On-site finishing protection: Remove the tensioning equipment and install metal protective end caps to isolate the internal anchor components; use the same grade of concrete to backfill the top groove to bury the lifting rings, and complete the overall assembly of the guardrail.
[0014] The present invention has the following beneficial effects: 1. This invention achieves efficient assembly, vibration-resistant reinforcement, and long-term sealing protection for short-distance guardrails by setting up mutually compatible male and female plug-in slots to form an elastic self-locking mechanism, combined with a segmented tensioning axial tightening and sealing structure. During the hoisting and splicing process, the elastic guide component on the radially deformable outer circumference of the male plug-in component adaptively corrects various alignment deviations, and automatically self-locks through the matching and engagement of the locking protrusion and locking groove, eliminating the need for manual edge correction, significantly improving assembly efficiency, and effectively preventing node slippage and loosening caused by vehicle reciprocating vibration. Simultaneously, the segmented tensioning mode is suitable for short-distance guardrail construction scenarios such as ramps and small bridges, eliminating the difficulty of threading ultra-long cables, and continuously tightening the sealing component through tensioning preload, effectively blocking water seepage channels in guardrail splicing gaps, preventing internal steel corrosion, and significantly improving the overall impact resistance and structural service stability of the guardrail.
[0015] 2. This invention achieves multiple optimizations by adding a guide liner and a vertical limiting component to the basic tenon-and-groove interlocking structure, resulting in reduced interlocking wear, buffering of hoisting impact, and precise control of the alignment. The guide liner effectively reduces frictional wear from repeated tenon-and-groove interlocking, improving component fitting accuracy and service life. The limiting structure, composed of guide sleeves, positioning rods, and buffer pads, forms a dual constraint system of lateral self-locking and vertical buffering, effectively offsetting the instantaneous impact load during guardrail hoisting and connection, constraining vertical misalignment of guardrail segments during operation, ensuring smooth overall guardrail alignment, and further strengthening the structural continuity of impact resistance. Simultaneously, all metal locking assemblies are pre-embedded and cast after being integrally welded in the prefabrication plant, completely avoiding on-site high-altitude welding operations and effectively ensuring component forming accuracy and construction quality stability. Attached Figure Description
[0016] Figure 1 This is a perspective view of the assembled guardrail connection structure and assembly method with elastic guiding self-locking mechanism proposed in this invention. Figure 2 This is a schematic diagram of the end guardrail segment in the assembled guardrail connection structure and assembly method with elastic guiding self-locking mechanism proposed in this invention; Figure 3 This is a schematic diagram of the lifting ring in the assembled guardrail connection structure and assembly method with elastic guiding self-locking mechanism proposed in this invention. Figure 4 This is a schematic diagram of the pressure-bearing steel plate in the prefabricated guardrail connection structure and assembly method with elastic guiding self-locking mechanism proposed in this invention.
[0017] Legend: 1. Initial guardrail segment; 2. Standard guardrail segment; 3. End guardrail segment; 4. Elastic self-locking mechanism; 401. Protruding tenon; 402. Receiving inner groove; 403. Elastic guide plate; 404. Guide inner liner; 405. Locking protrusion; 406. Locking slot; 407. Limiting component; 4071. Guide sleeve; 4072. Positioning rod; 4073. Buffer pad; 5. Axial tension Tight sealing mechanism; 501, starting end corrugated pipe; 502, intermediate corrugated pipe; 503, sealing end corrugated pipe; 504, inserted steel strand; 505, anchor base; 506, end face waterproof ring; 507, outer sealing strip; 508, locking assembly; 5081, pressure-bearing steel plate; 5082, conical clamp; 5083, protective end cap; 6, lifting ring; 7, outer protective plate; 8, reflective warning strip. Detailed Implementation
[0018] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0019] Example 1 Please refer to Figures 1 to 4. This embodiment discloses an assembled guardrail connection structure with an elastic guiding self-locking mechanism, which includes multiple prefabricated guardrail segments spliced end to end. Each prefabricated guardrail segment includes at least a starting guardrail segment 1, a standard guardrail segment 2, and a sealing guardrail segment 3. Elastic self-locking mechanisms 4 are matched and matched on the inner side of the joint between two adjacent guardrail segments. An axial tightening and sealing mechanism 5 is arranged longitudinally inside each guardrail segment.
[0020] The elastic self-locking mechanism 4 includes a convex tenon 401 and a receiving inner groove 402 that are adapted to each other. The outer periphery of the convex tenon 401 is provided with an elastic guide plate 403 that can be radially elastically deformed. A locking protrusion 405 is provided on the outer side of the elastic guide plate 403. A locking groove 406 matching the locking protrusion 405 is opened on the inner wall of the receiving inner groove 402.
[0021] The axial tightening and sealing mechanism 5 adopts a segmented tensioning mode, with the interlaced steel strands 504 arranged in independent tensioning sections. Each interlaced steel strand only passes through the guardrail segment within the same section, making it suitable for short-distance highway guardrail construction such as ramps and small bridges.
[0022] This solution achieves convenient assembly of short-distance guardrails and robust vibration resistance at the joints through the above-mentioned connection structure; it relies on the elastic guide plate 403 for adaptive guidance and correction during the hoisting process, and the locking protrusion 405 automatically engages with the locking slot 406 to achieve lateral locking, eliminating the need for manual pushing and pulling correction at the edge, greatly improving assembly efficiency and eliminating the safety hazards of high-altitude calibration; and it relies on the axial tightening and sealing mechanism 5 for segmented tensioning.
[0023] Example 2 To reduce wear on the tenon and mortise joints, correct vertical alignment deviations, constrain vertical misalignment after guardrail splicing, buffer the impact of hoisting and docking, and ensure the smooth alignment of the entire guardrail line, a guide and buffer structure is added to the elastic self-locking mechanism based on Example 1.
[0024] A convex tenon 401 is fixedly installed on the inner middle of the joint of the starting guardrail segment 1 and the standard guardrail segment 2. A receiving groove 402 is formed on the inner side of the joint of the adjacent standard guardrail segment 2 and the end guardrail segment 3. Guide inner lining plates 404 are fixed on the top and bottom walls of the receiving groove 402. The convex tenon 401, the elastic guide plate 403, and the locking protrusion 405 are pre-assembled and welded into an integrated embedded unit, which is fixed during the casting of the guardrail.
[0025] A limiting component 407 is provided between the end of the convex tenon 401 and the bottom of the receiving inner groove 402. The limiting component includes a guide sleeve 4071, a positioning rod 4072 and a buffer pad 4073. The guide sleeve 4071 is fixed to the end of the convex tenon 401, the positioning rod 4072 is fixed to the bottom of the receiving inner groove 402, and after assembly, the positioning rod 4072 is slidably inserted into the inside of the guide sleeve 4071. The buffer pad 4073 is provided at the front end of the positioning rod 4072.
[0026] When the guardrail is connected and plugged in, the locking protrusion 405 rebounds and engages with the locking slot 406 along with the elastic guide plate 403, and the positioning rod 4072 and the guide sleeve 4071 are connected and limited simultaneously.
[0027] The 404 guide liner can reduce friction loss during insertion and assist in correcting vertical alignment deviations; all metal assemblies are pre-embedded and cast after welding in the prefabrication workshop, eliminating on-site high-altitude welding operations and ensuring stable processing quality; the lateral self-locking combined with vertical buffer limit double constraint offsets the impact load of hoisting, limits the vertical misalignment of guardrail segments after the road is opened to traffic, and further improves the overall continuity of anti-collision force.
[0028] Example 3 To provide long-term corrosion protection for tension anchors, enhance the multi-layer sealing effect of joints, and ensure the smoothness and uniformity of the outer surface of the guardrail, the structure of the axial tightening and sealing mechanism 5 is refined based on Example 1.
[0029] The axial tightening sealing mechanism 5 is a post-tensioned prestressed sealing assembly, which includes a starting end bellows 501, an intermediate bellows 502, a sealing end bellows 503, an inserted steel strand 504, an anchor base 505, an end face waterproof ring 506, an outer sealing strip 507, and a locking assembly 508.
[0030] The starting guardrail segment 1 has a pre-fabricated embedded installation groove in the upper middle part of the outer side of the guardrail, and the anchor base 505 is pre-embedded in the groove; the starting end corrugated pipe 501 is pre-embedded at the top of the starting guardrail segment 1, the middle corrugated pipe 502 is pre-embedded at the top of the standard guardrail segment 2, and the sealing end corrugated pipe 503 is pre-embedded at the top of the sealing end guardrail segment 3. The corrugated pipes are spliced to form a through channel for the steel strand 504 to pass through; the inner end faces of the adjacent guardrails are respectively matched and pasted with end face waterproof rings 506 and outer sealing strips 507.
[0031] The outer right end of the guardrail segment 3 has a pre-reserved embedded installation groove, within which the locking component 508 is arranged. The locking component 508 includes a pressure-bearing steel plate 5081, a conical clamp 5082, and a metal protective end cap 5083. The protective end cap 5083 is detachably installed on the outside of the installation groove. The corrugated pipe, anchor base 505, and pressure-bearing steel plate 5081 are integrally cast with the guardrail reinforcement cage. After tensioning and installation of the locking component 508, the outer installation groove of the guardrail is sealed and smoothed in layers with repair concrete to conceal the internal metal anchors. After tensioning, the splicing sealant is continuously tightened to seal the joint seepage channels and prevent internal steel reinforcement corrosion.
[0032] The embedded mounting groove at the end, combined with the detachable protective end cap 5083, provides long-term corrosion protection for the interlaced steel strands 504 and the anchor base 505. The double-layer sealing gasket is tightly squeezed by the tensioning pre-tightening force, which greatly improves the waterproof and durable performance of the joint. After the end is completed, it is uniformly sealed and leveled, taking into account both component protection and the smoothness of the road appearance.
[0033] Example 4 To integrate hoisting, collision avoidance, and driving warning functions, and to meet the on-site requirements for segmented disassembly and reassembly of guardrails, additional auxiliary components and matching disassembly and reassembly structures are added based on any of the aforementioned embodiments.
[0034] Each precast guardrail segment has an embedded groove on its top surface, with a lifting ring 6 pre-embedded in the groove; an outer protective plate 7 is installed on the outside of the guardrail, and a reflective warning strip 8 is affixed to the top of the outside of the guardrail. The lifting ring 6 is hidden in the groove on the top surface and can be backfilled with concrete of the same grade after hoisting.
[0035] A small push hole is made on the side wall of the receiving inner groove 402, corresponding to the locking groove 406, extending through the outer side of the guardrail. A detachable sealing plug is provided on the outside of the small hole. The assembly adopts a segmented tensioning mode, which can be used for single-section or multi-section overall alignment and pushing installation. If it is necessary to disassemble the guardrail assembly, remove the sealing plug on the outside of the small hole, and use a steel bar push rod to push the locking protrusion 405 into the small hole to release the locking constraint of the elastic self-locking mechanism 4, so as to realize the separation of the guardrail segments. After disassembly and reassembly, clean the channel, apply an anti-rust coating, and reposition the sealing plug to prevent mud and rainwater from entering and corroding the internal metal parts.
[0036] The concealed lifting ring 6 facilitates on-site lifting operations; the outer protective plate 7 protects against minor vehicle scratches; the reflective warning strip 8 clearly delineates lane boundaries, improving road driving safety; no additional auxiliary facilities are required afterward, resulting in higher prefabrication integration; the jacking hole provides convenient disassembly and assembly channels.
[0037] Assembly method This invention also provides a construction method for hoisting, assembling, and connecting guardrails that are compatible with any of the above-mentioned structures, comprising the following steps: Step 1: Factory Prefabrication and Assembly: Prefabricate and pour the starting guardrail segment 1, standard guardrail segment 2, and end guardrail segment 3. Simultaneously embed elastic self-locking mechanism 4, axial tightening and sealing mechanism 5, and lifting ring 6 during the pouring stage. The anchors at both ends of the prefabricated guardrail are embedded in the installation grooves. The outer protective plate 7 and reflective warning strip 8 are assembled after prefabrication. Before leaving the factory, inspect the elastic guide plate 403 for its resilience, corrugated pipe connectivity, and tenon and groove fit dimensions to form standardized prefabricated units.
[0038] Step 2, preliminary alignment of segmented hoisting: Using the hoisting ring 6, hoist the guardrail segments. First, fix the starting guardrail segment 1, and then hoist each standard guardrail segment 2 and the end guardrail segment 3 in sequence, slowly bringing them together so that the convex tenon 401 is aligned with the opening of the receiving inner groove 402 to complete the preliminary positioning.
[0039] Step 3, Adaptive Guiding Elastic Self-Locking: As the guardrail continues to close, the convex tenon 401 extends into the receiving inner groove 402. The elastic guide plate 403 is compressed and contracted by the inner wall of the receiving inner groove 402, automatically correcting lateral, vertical, and angular alignment deviations. After the locking protrusion 405 moves to the locking slot 406, the elastic guide plate 403 rebounds, causing the locking protrusion 405 to engage with the locking slot 406, completing the lateral self-locking. Preferably, while the convex tenon 401 extends into the receiving inner groove 402, the positioning rod 4072 is simultaneously inserted into the guide sleeve 4071, and the buffer pad 4073 absorbs the docking impact and restricts vertical misalignment.
[0040] Step 4, Section Tensioning and Sealing: Anchor one end of the inserted steel strand 504 to the anchor base 505 in the installation groove outside the starting guardrail, and the other end passes through the bearing steel plate 5081 outside the sealing guardrail; after tensioning to the designed tension force, the conical clamp 5082 self-locks and clamps the inserted steel strand 504 to maintain the axial pre-tightening pressure, and the end waterproof ring 506 and the outer sealing strip 507 squeeze and fill the splicing gap to achieve overall sealing and reinforcement.
[0041] Step 5: On-site finishing protection construction: After tensioning and locking, install the metal protective end cap 5083, use repair concrete to seal the installation grooves at both ends of the outer side of the guardrail and smooth it; backfill the top surface groove with concrete of the same grade to bury the lifting ring 6; check the integrity of the outer protective plate 7 and reflective warning strip 8, and complete the assembly and reinforcement construction of the entire guardrail section.
[0042] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A prefabricated guardrail connection structure with an elastic guiding self-locking mechanism, characterized in that: The system comprises multiple prefabricated guardrail segments that are sequentially spliced together end to end. Each prefabricated guardrail segment includes at least a starting guardrail segment (1), a standard guardrail segment (2), and a sealing guardrail segment (3). The connecting ends of two adjacent prefabricated guardrail segments are respectively equipped with mutually interlocking elastic self-locking mechanisms (4). Each prefabricated guardrail segment is internally provided with an axial tightening and sealing mechanism (5). The elastic self-locking mechanism (4) includes mutually compatible male plug-in components and female plug-in grooves. The male plug-in component has an elastic guide component that can be radially elastically deformed on its outer periphery. The elastic guide component has a locking protrusion on its outer side. The inner wall of the female plug-in groove has a locking groove that matches the locking protrusion.
2. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 1, characterized in that: The male connector is a convex tenon (401), and the female connector groove is a receiving inner groove (402) opened on the inner side of the guardrail docking end; the convex tenon (401) is fixedly set in the middle of the docking side of the starting guardrail segment (1) and the standard guardrail segment (2), and the receiving inner groove (402) is opened in the inner side of the docking side of the adjacent standard guardrail segment (2) and the end guardrail segment (3).
3. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 2, characterized in that: The convex tenon (401) has elastic guide plates (403) fixed symmetrically on both the front and rear sides, and the top and bottom walls of the receiving groove (402) are both fixed with guide lining plates (404).
4. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 3, characterized in that: The elastic guide plate (403) has a fixed locking protrusion (405) on its outer side, and the receiving inner groove (402) has locking slots (406) on its front and rear side walls. During the connection and insertion of the guardrail, the locking protrusion (405) rebounds with the elastic guide plate (403) and is inserted into the locking slot (406), thereby realizing the lateral self-locking of adjacent guardrail segments.
5. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 1, characterized in that: A limiting component (407) is provided between the end of the male connector and the bottom of the female connector groove. The limiting component (407) is used to limit the vertical relative sliding of the guardrail segments. The limiting component (407) includes a guide sleeve (4071), a positioning rod (4072), and a buffer pad (4073). The guide sleeve (4071) is fixed to the end of the convex tenon (401), the positioning rod (4072) is fixed to the bottom of the receiving inner groove (402), and the buffer pad (4073) is provided at the front end of the positioning rod (4072). In the assembled state, the positioning rod (4072) is slidably inserted into the inside of the guide sleeve (4071).
6. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 1, characterized in that: The axial tightening sealing mechanism (5) is a post-tensioned prestressed sealing assembly, which includes multiple corrugated pipes, a through steel strand (504) that runs through all the corrugated pipes, an end anchor base (505), a joint seal and a tension locking assembly (508); corrugated pipes are respectively arranged at the top of each guardrail segment, and the corrugated pipes include the starting end corrugated pipe (501), the middle corrugated pipe (502), and the sealing end corrugated pipe (503); an anchor base (505) is set on one side of the starting guardrail segment (1), and a locking assembly (508) is set at the end of the sealing end guardrail segment (3). The end waterproof ring (506) and the outer sealing strip (507) are respectively arranged on the joint end face of the adjacent guardrails.
7. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 6, characterized in that: The locking assembly (508) includes a pressure-bearing steel plate (5081), a conical clamp (5082), and a metal protective end cap (5083); the pressure-bearing steel plate (5081) is fixed to the end of the end guardrail segment (3), the protective end cap (5083) has a conical inner cavity, and the conical clamp (5082) is assembled in the protective end cap (5083) and clamps the inserted steel strand (504).
8. The assembled guardrail connection structure with elastic guiding self-locking mechanism according to claim 1, characterized in that: Each prefabricated guardrail segment has an embedded groove at the top, and a lifting ring (6) is pre-embedded in the groove; an outer protective plate (7) is installed on the front side of the guardrail segment, and a reflective warning strip (8) is pasted on the top of the front side of the guardrail segment.
9. A method for hoisting and assembling a prefabricated guardrail connection structure with an elastic guiding self-locking mechanism as described in any one of claims 1 to 8, characterized in that, Includes the following steps: Step 1, Factory prefabrication and pre-assembly: Prefabricate the starting guardrail segment (1), standard guardrail segment (2), and end guardrail segment (3), and simultaneously pre-embed and assemble the elastic self-locking mechanism (4), axial tightening and sealing mechanism (5), lifting ring (6), outer protective plate (7) and reflective warning strip (8), and check the flexibility of movement and the firmness of connection of each component; Step 2, preliminary alignment of segmented hoisting: The hoisting equipment grabs the guardrail segments through the hoisting ring (6), first fixes the starting guardrail segment (1), and then hoists the standard guardrail segment (2) and the end guardrail segment (3) in sequence, slowly moving them closer to the guardrail that has been in place, so that the convex tenon (401) is aligned with the receiving inner groove (402). Step 3, Adaptive Guiding Elastic Self-Locking: As the guardrail continues to close, the convex tenon (401) extends into the receiving inner groove (402), and the elastic guide plate (403) is squeezed and contracted by the inner wall of the receiving inner groove (402), automatically correcting the horizontal, vertical, and corner alignment deviations; after the locking protrusion (405) moves to the locking slot (406) position, the elastic guide plate (403) rebounds, causing the locking protrusion (405) to engage with the locking slot (406), completing the horizontal self-locking; Step 4, Axial tensioning and sealing: Anchor one end of the inserted steel strand (504) to the anchor base (505) of the starting guardrail segment (1), and extend the other end to the outside of the pressure plate (5081) of the sealing guardrail segment (3); the tensioning equipment tensions the inserted steel strand (504) to the designed tension force, the conical clamp (5082) self-locks and holds the inserted steel strand (504) to maintain the axial pre-tightening pressure, and the end face waterproof ring (506) and the outer sealing strip (507) are squeezed and deformed to fill the splicing gap to achieve waterproof sealing; Step 5, On-site finishing protection: Remove the tensioning fixtures and install metal protective end caps (5083) to isolate the internal anchor components; use the same grade of concrete to backfill the top groove to bury the lifting rings (6), and complete the overall assembly of the guardrail.