A method for refined excavation and construction of crane beams in rock walls of underground powerhouses
By employing a combined "sample frame + casing" guiding technology and methods such as layered and staggered excavation, the problems of drilling accuracy and blasting vibration in the construction of crane beams on the rock walls of underground powerhouses were solved, achieving high-precision, low-damage, and high-efficiency construction, reducing costs and improving construction quality and safety.
Patent Information
- Application Number
- CN202611334349.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-31
- Publication Date
- 2026-11-10
AI Technical Summary
Existing technologies for excavating crane beams in underground powerhouse rock walls suffer from problems such as insufficient drilling accuracy, large blasting vibrations, low construction efficiency, and severe damage to the surrounding rock, leading to unstable construction quality, increased costs, and even affecting structural stability.
The drilling direction and accuracy are controlled by a combination of "sample frame + casing" guidance technology. Combined with layered and staggered excavation, two-way light blasting, and micro-delay blasting, the excavation sequence is optimized and a dynamic monitoring and feedback mechanism is established to achieve refined construction.
It significantly improves excavation accuracy and surrounding rock integrity, reduces construction costs, increases construction efficiency, ensures the safety of rock wall crane beam structures, and is suitable for underground powerhouse construction under different geological conditions.
Smart Images

Figure CN123064484A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of underground powerhouse excavation and construction technology in the hydropower industry, and in particular to a method for refined excavation and construction of crane beams on rock walls in underground powerhouses; it is applicable to the excavation of crane beams on rock walls under different geological conditions in underground powerhouses of large and medium-sized water conservancy and hydropower projects, and is especially suitable for construction scenarios of crane beams on rock walls with high requirements for surrounding rock stability and strict control of excavation accuracy. Background Technology
[0002] The rock wall crane beam is the core load-bearing structure of the underground powerhouse. Anchored to the sloping rock face by anchor bolts, it bears the load transfer task for the bridge cranes within the powerhouse. The quality of its excavation and shaping directly determines the safety of subsequent structures, the accuracy of equipment installation, and the service life of the project. The construction environment for the underground powerhouse rock wall crane beam is complex, with limited cavern space and sensitive stress conditions on the surrounding rock. Furthermore, the excavation precision requirements for the rock platform of the rock wall crane beam are extremely high, necessitating strict control over- and under-excavation, blasting vibrations, and damage to the surrounding rock. This makes it a key and challenging aspect of underground powerhouse construction.
[0003] Currently, the excavation of crane beams in underground powerhouse rock walls mostly adopts the conventional method of "central trenching + excavation of protective layers on both sides + rock platform repair". However, the existing technology has many shortcomings: First, the drilling accuracy control is insufficient. During the construction of hand-held pneumatic drills, the drilling direction is easily deviated due to the weight of the machine and the impact force, resulting in deviations in the formation of the rock platform and even damage to the integrity of the surrounding rock. Second, the blasting parameters lack specificity and are not adjusted according to the site geological conditions. Excessive blasting vibration can easily cause the expansion of surrounding rock fissures, and over-excavation and under-excavation occur frequently. The over-excavation amount often exceeds the limit of 0.2m allowed by the specifications. Third, the excavation sequence is unreasonable. The lack of refined measures such as staggered excavation and layered controlled blasting leads to large construction interference and difficulty in controlling the progress. Fourth, there is a lack of dynamic monitoring and feedback mechanisms, making it impossible to adjust construction parameters in real time and achieve precise control of the excavation process.
[0004] While existing technologies employ methods such as the "casing method" to control drilling direction or bidirectional light blasting to improve rock platform formation, the application of a single technology makes it difficult to balance drilling accuracy, blasting effect, and construction efficiency. Furthermore, a complete and refined excavation system has not been established, leading to unstable construction quality, increased concrete backfilling volume in the later stages, higher construction costs, and even affecting the structural stability of the rock wall crane beam.
[0005] Therefore, developing a refined excavation construction method that can achieve precise control of drilling, optimization of blasting vibration, rational excavation sequence, and dynamic monitoring throughout the process has become the key to solving the above-mentioned technical problems. Summary of the Invention
[0006] The purpose of this invention is to address the problems of low excavation accuracy, large blasting vibration, severe damage to surrounding rock, and low construction efficiency in existing technologies for underground powerhouse rock wall crane beam excavation. This invention provides a refined excavation method for underground powerhouse rock wall crane beams. By optimizing the excavation process, precisely controlling drilling parameters, customizing blasting schemes, and establishing a dynamic monitoring and feedback mechanism, this method achieves high-precision, low-damage, and high-efficiency excavation of rock wall crane beams, ensuring structural safety and construction quality while reducing construction costs.
[0007] To achieve the above objectives, the present invention adopts the following technical solution: A method for refined excavation construction of crane beams in rock walls of underground powerhouses includes the following steps: S1. Pre-splitting construction of the groove in the middle of the second floor of the main and auxiliary plant buildings; S2, the middle area of the second floor is excavated in sections; S3. Excavate the two sides of the second floor in sequence; S4, Vertical blasting hole drilling on rock platform; S5, stepped blasting excavation of the middle area of the three-layer structure; S6. The three-layered, two-sided areas are excavated in separate zones. S7. Sloping holes are drilled in the upper middle section of the rock platform area on both sides of the third layer; S8, rock platform blasting forming.
[0008] In some embodiments, the excavation of the main plant rock wall crane beam layer is carried out in "three layers and six zones"; the excavation method follows the approach of "pre-splitting and trenching in the middle first, followed by protective layers on both sides, and blasting of the rock platform in sections and zones".
[0009] In some embodiments, the excavation area is divided from top to bottom as follows: the first layer is the top arch layer; the second layer is the middle layer of the vertical side and horizontal bottom surface; and the third layer is the lower layer with the sloping surface excavated in the middle and upper part. Partition ① is the middle section of the second layer; Partition ② consists of the two sides of the second layer; Partition ③ is the middle part of the third layer; Section ④ is the upper layer of the third layer, which is excavated in layers on both sides. Section ⑤ is the lower layer excavated on both sides of the third layer; Section ⑥ is the sloping surface excavated on both sides of the upper middle part of the third layer and the area above it; Among them, the two sides of partitions ④ and ⑤ are shorter than the two sides of partition ②, and the vertical plane of partition ⑥ is flush with partition ②.
[0010] In some embodiments, the layout first marks out two opening points in the area, and then the remaining hole positions are laid out; the template is erected according to the surrounding hole positions and drilling angles.
[0011] In some embodiments, the bottom of the inclined and vertical holes is over-excavated by 3cm at the inflection point of the rock platform and 5cm at the bottom.
[0012] In some embodiments, the drilling direction and accuracy are controlled by a combined "sample holder + casing" guidance technology.
[0013] In some embodiments, the template is divided into a vertical hole template and an inclined hole template, and the template is firmly erected and firmly connected to the rock mass; The sample frame adopts a double-row scaffolding type, with guide tubes 50cm long and spaced at 25cm / 30cm (25cm for holes in the break section), and the angle between the inclined guide tubes and the vertical direction is 30°.
[0014] In some embodiments, after the lower layer of the three-layer side area is excavated, the anchor bolts are installed below the inflection point of the rock platform in the dense joint zone. The anchor bolts used in the locking joints are mortar anchor bolts to ensure the integrity of the excavation at the turning point under the rock platform.
[0015] In some embodiments, the vertical holes in the rock platform area are drilled during the drilling process in the upper layer of the three-layer side areas; after the holes are formed, PVC pipes are inserted into the holes for protection, and no explosives are loaded; the holes are blasted together after the inclined holes in the rock platform area are drilled.
[0016] In some embodiments, the drilling guide tube adopts a double-sleeve structure of steel pipe and hard rubber tube, which reduces the gap between the drill rod and the guide tube, and reduces the drifting and deviation of the drill hole caused by the shaking of the drill rod during the drilling process.
[0017] Compared with the prior art, the present invention provides a method for refined excavation and construction of crane beams in rock walls of underground powerhouses, which has the following beneficial effects.
[0018] 1. This invention significantly improves excavation accuracy: Through the combined guiding technology of "sample frame + casing", the drilling direction and accuracy are effectively controlled, the borehole position deviation is controlled within ±20mm, the borehole angle deviation is not greater than ±3°, the over-excavation of the rock platform is controlled within 0.2m, the blasting half-hole rate reaches more than 97%, the rock platform forming quality meets the design and specification requirements, reduces the amount of concrete backfilling in the later stage, and reduces construction costs.
[0019] 2. This invention effectively controls surrounding rock damage: By employing layered and staggered excavation, bidirectional blasting, and micro-delay blasting techniques, combined with personalized blasting parameters, the impact of blasting vibration on the surrounding rock is effectively reduced, preventing the generation of blasting fractures and the expansion of existing structural cracks, ensuring the integrity and stability of the surrounding rock, reducing the amount of support work, and improving construction safety.
[0020] 3. This invention significantly improves construction efficiency: It optimizes the excavation sequence by adopting a method of staggered trenching in the middle and follow-up construction of protective layers on both sides, reducing construction interference; it determines the optimal parameters through blasting tests to avoid rework caused by blind construction; and it enables real-time adjustment of construction parameters through a dynamic monitoring and feedback mechanism to ensure smooth construction progress. Compared with traditional methods, the construction schedule can be advanced by more than 20 days, significantly improving construction efficiency.
[0021] 4. This invention effectively reduces construction costs: it reduces the amount of concrete used for over-excavation and backfilling, the amount of support work, and rework costs, while also reducing the intensity of manual labor and the input of construction personnel. Based on calculations using similar project data in the literature, it can directly save more than 300,000 yuan in construction costs, demonstrating significant economic benefits.
[0022] 5. This invention has wide applicability: It is applicable to the excavation of crane beams on rock walls in underground powerhouses of large and medium-sized water conservancy and hydropower projects with different geological conditions (Class I, Class II, and Class III surrounding rock, and locally Class IV and Class V surrounding rock after treatment). The construction parameters can be flexibly adjusted according to the site geological conditions and the size of the powerhouse. It has strong versatility and good promotion and application value.
[0023] Other advantages, objectives and features of the invention will be set forth in part in the description which follows; and in part will be apparent to those skilled in the art upon examination of the following description; or may be learned from practice of the invention. Attached Figure Description
[0024] Figure 1 This is a flowchart of the present invention.
[0025] Figure 2 This is a schematic diagram of the excavation of the crane beam layer on the rock wall of the factory building.
[0026] Figure 3 A schematic diagram of the vertical hole pattern frame setup.
[0027] Figure 4 A schematic diagram of the vertical hole pattern frame erection for area ⑤.
[0028] Figure 5 A schematic diagram of the erection of the inclined hole template.
[0029] Figure 6 This is a schematic diagram of the vertical hole template for zone ⑥.
[0030] Figure 7 for Figure 6 Enlarged detailed views of points A and B in the middle.
[0031] Figure 8 This is a schematic diagram of the inclined hole template in zone ⑥.
[0032] Figure 9 Photos of the prototype construction.
[0033] Figure 10 Photo 1 shows the completed excavation.
[0034] Figure 11 Photo 2 shows the completed excavation. Detailed Implementation
[0035] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.
[0036] Reference Figure 1-11 A refined excavation construction method for crane beams on the rock walls of underground powerhouses is proposed. The excavation of the crane beam layers on the rock walls of the main powerhouse is carried out in three layers and six zones. The excavation method follows the approach of "pre-splitting and trenching in the middle first, followed by protective layers on both sides, and blasting in sections and zones on the rock platform".
[0037] A method for refined excavation construction of crane beams on rock walls in underground powerhouses includes the following steps: S1. Pre-splitting construction of the groove in the middle of the second floor of the main and auxiliary plant buildings; S2, the middle area of the second floor (area ①) is excavated in sections; S3. Excavate the two sides of the second layer (areas ② on both sides) in sequence; S4, Vertical blasting hole drilling on rock platform; S5, Step-by-step blasting excavation of the intermediate area (zone ③) of the three-layer structure; S6. The two sides of the third layer (zones ④ and ⑤) are excavated in layers and zones; S7. Sloping holes are drilled in the upper part of the rock platform area (section ⑥) on both sides of the third layer; S8, rock platform blasting forming.
[0038] like Figure 2 As shown; In the division of the excavation area, from top to bottom, they are as follows: First layer, vaulted top layer; The second layer is the middle layer with vertical sides and horizontal bottom. The third layer is the lower layer with a sloping surface excavated in the middle and upper part.
[0039] Partition ① is the middle section of the second layer; Partition ② consists of the two sides of the second layer; Partition ③ is the middle part of the third layer; Section ④ is the upper layer of the third layer, which is excavated in layers on both sides. Section ⑤ is the lower layer excavated on both sides of the third layer; Zone ⑥ is the rock platform area formed by the upper and middle excavated slopes on both sides of the third layer and the area above them.
[0040] Among them, the two sides of partitions ④ and ⑤ are shorter than the two sides of partition ②, and the vertical plane of partition ⑥ is flush with that of partition ②; that is, when excavating areas ④ and ⑤, a portion at both ends is left unexcavated as partition ⑥; after the excavation of partition ⑥ is completed, a flush vertical plane and a slope are formed, constituting a rock platform.
[0041] In some embodiments, the focus is on controlling the accuracy of the layout of the holes around the rock wall crane beam.
[0042] Specifically, the layout process begins by marking out two opening points in the area, followed by the layout of the remaining hole positions. The template frame is then erected based on the surrounding hole positions and drilling angles. After the template frames for the vertical and inclined holes on the rock wall crane beam are erected, the surveyors must verify and accept the template frame positioning tubes to ensure accurate positioning.
[0043] In some embodiments, to prevent under-excavation in the rock platform area of the rock wall crane beam, the bottom of the hole at the lower inflection point of the rock platform is over-excavated by 3cm, and the bottom of the inclined and vertical holes is over-excavated by 5cm.
[0044] Please refer to the following: Figure 9 Photos, Figure 6 The diagram, and Figure 7 correspond Figure 6 Detailed enlarged views A and B show the local areas; over-excavation is controlled to ensure construction accuracy.
[0045] In some embodiments, the drilling direction and accuracy are controlled by the combined guiding technology of "sample frame + casing", the drilling position deviation is controlled within ±20mm, and the drilling angle deviation is not greater than ±3°.
[0046] like Figures 3-9 As shown; the template is divided into vertical hole template and inclined hole template. The template erection and positioning guide pipe are all made of φ48 steel pipe. The template is erected firmly and is firmly connected to the rock mass by anchor bolts.
[0047] The sample frame adopts a double-row scaffolding type, with guide tubes 50cm long and spaced at 25cm / 30cm (25cm for holes in the broken section), and the angle between the inclined guide tubes and the vertical direction is 30°; construction is not carried out without the sample frame erected, and drilling is not carried out without the sample frame being inspected.
[0048] In some embodiments, after the excavation of the lower layer (rock wall crane beam zone ⑤) of the three-layer side area is completed, lock anchor bolts are installed below the inflection point of the rock platform in the dense joint zone. The lock anchor bolts are located 0.2m below the inflection point, and are made of mortar. They are 22mm in diameter, 3.0m long, penetrate 2.85m into the rock, and are spaced 1.0m apart, thereby ensuring the integrity of the excavation at the inflection point of the rock platform.
[0049] like Figure 3 , 6As shown; the vertical holes in the rock platform area (rock wall crane beam rock platform ⑥ area) are drilled during the drilling process in the upper layer (④ area) of the three-layer side area; after the holes are formed, PVC pipes are inserted into the holes for protection, and no explosives are loaded; after the inclined holes in the rock platform area (⑥ area) are drilled, they are blasted together.
[0050] like Figure 5 , 8 As shown in Figures 9 and 9; after the excavation of the lower layer (zone 5) of the three-layer side area of the rock platform area (zone 6) is completed, the inclined sample frame is erected for drilling.
[0051] Preferably, a YT28 hand drill is used for drilling; the hole diameter is Φ42, and the hole spacing is 30cm (25cm for the pre-consolidation grouting area).
[0052] The drilling guide pipe for the rock platform adopts a double-sleeve structure of Φ48 steel pipe with a wall thickness of 3mm and Φ30 hard rubber pipe, which reduces the gap between the drill rod and the guide pipe and reduces the drift and deviation of the drill due to the shaking of the drill rod during the drilling process.
[0053] like Figure 10 , 11 As shown in the actual work photos, the molding quality is excellent.
[0054] The "method for refined excavation of crane beams on rock walls in underground powerhouses" provided in this application has been successfully applied to the excavation of the sidewall of the second floor, i.e., the rock anchor beam floor, in an underground powerhouse in Hebei Province.
[0055] Please refer to the attached diagram; the main powerhouse of this pumped storage power station consists of an installation area, main equipment room, and auxiliary powerhouse, arranged in a straight line. The total length of the underground powerhouse is 164m, the maximum excavation height is 54.5m, the upper excavation width is 26.5m, and the lower excavation width is 25m. The rock anchor beam is 144m long, 1.65m wide, and 2.53m high, with an elevation of 143.230~140.700m. The upper inflection point elevation is 141.330m, the lower inflection point elevation is 140.7m, and the angle between the rock platform slope and the vertical direction is 30°.
[0056] This invention significantly improves excavation accuracy: through the combined guiding technology of "sample frame + casing", the drilling direction and accuracy are effectively controlled, the borehole position deviation is controlled within ±20mm, the borehole angle deviation is no more than ±3°, the over-excavation of the rock platform is controlled within 0.2m, the blasting half-hole rate reaches more than 97%, the rock platform forming quality meets the design and specification requirements, reduces the amount of concrete backfilling in the later stage, and reduces construction costs.
[0057] This invention effectively controls surrounding rock damage: by employing techniques such as layered and staggered excavation, bidirectional blasting, and micro-delay blasting, combined with personalized blasting parameters, it effectively reduces the impact of blasting vibration on the surrounding rock, avoids the generation of blasting fractures and the expansion of existing structural cracks, ensures the integrity and stability of the surrounding rock, reduces the amount of support work, and improves construction safety.
[0058] This invention significantly improves construction efficiency: it optimizes the excavation sequence by using a method of staggered trenching in the middle and follow-up construction of protective layers on both sides to reduce construction interference; it determines the optimal parameters through blasting tests to avoid rework caused by blind construction; and it uses a dynamic monitoring and feedback mechanism to adjust construction parameters in real time to ensure smooth construction progress. Compared with traditional methods, the construction schedule can be advanced by more than 20 days, significantly improving construction efficiency.
[0059] This invention effectively reduces construction costs by reducing the amount of concrete used for over-excavation and backfilling, the amount of support work, and rework costs. It also reduces the intensity of manual labor and the number of construction personnel. Based on calculations using similar project data, it can directly save more than 300,000 yuan in construction costs, demonstrating significant economic benefits.
[0060] This invention has wide applicability: it is applicable to the excavation of crane beams on rock walls in underground powerhouses of large and medium-sized water conservancy and hydropower projects under different geological conditions (Class I, Class II, and Class III surrounding rock, and locally Class IV and Class V surrounding rock after treatment). The construction parameters can be flexibly adjusted according to the site geological conditions and the size of the powerhouse. It has strong versatility and good promotion and application value.
[0061] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present invention, based on the technical solution and inventive concept of the present invention, should be covered within the scope of protection of the present invention.
[0062] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Moreover, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.
[0063] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.
Claims
1. A method for refined excavation and construction of crane beams in rock walls of underground powerhouses, characterized in that, Includes the following steps: S1. Pre-splitting construction of the groove in the middle of the second floor of the main and auxiliary plant buildings; S2, the middle area of the second floor is excavated in sections; S3. Excavate the two sides of the second floor in sequence; S4, Vertical blasting hole drilling on rock platform; S5, stepped blasting excavation of the middle area of the three-layer structure; S6. The three-layered, two-sided areas are excavated in separate zones. S7. Sloping holes are drilled in the upper middle section of the rock platform area on both sides of the third layer; S8, rock platform blasting forming.
2. The method for refined excavation construction of crane beams in underground powerhouse rock walls according to claim 1, characterized in that, The excavation of the main plant's rock wall crane beam layer was carried out in "three layers and six zones"; the excavation method followed the approach of "pre-splitting and trenching in the middle first, followed by protective layers on both sides, and blasting of the rock platform in sections and zones".
3. The method for refined excavation construction of crane beams on rock walls of underground powerhouses according to claim 1 or 2, characterized in that, In the division of the excavation area, from top to bottom, they are: the first layer, the top arch layer; The second layer is the middle layer with vertical sides and horizontal bottom; the third layer is the lower layer with an sloping surface excavated in the upper middle part. Partition ① is the middle section of the second layer; Partition ② consists of the two sides of the second layer; Partition ③ is the middle part of the third layer; Section ④ is the upper layer of the third layer, which is excavated in layers on both sides. Section ⑤ is the lower layer excavated on both sides of the third layer; Section ⑥ is the sloping surface excavated on both sides of the upper middle part of the third layer and the area above it; Among them, the two sides of partitions ④ and ⑤ are shorter than the two sides of partition ②, and the vertical plane of partition ⑥ is flush with partition ②.
4. The method for refined excavation construction of crane beams on rock walls of underground powerhouses according to claim 1, characterized in that, First, lay out the two opening points in this area, and then lay out the remaining hole positions; set up the template according to the hole positions and drilling angles of the surrounding holes.
5. The method for refined excavation construction of crane beams in underground powerhouse rock walls according to claim 1, characterized in that, Over-excavate 3cm downwards at the inflection point of the rock platform, and over-excavate 5cm at the bottom of the inclined and vertical holes.
6. The method for refined excavation construction of crane beams in rock walls of underground powerhouses according to claim 1 or 4, characterized in that, The drilling direction and accuracy are controlled by the combined guidance technology of "sample frame + casing".
7. The method for refined excavation construction of crane beams in rock walls of underground powerhouses according to claim 1, 4, or 6, characterized in that, The sample frame is divided into vertical hole sample frame and inclined hole sample frame. The sample frame is firmly erected and firmly connected to the rock mass. The sample frame adopts a double-row scaffolding type, with guide tubes 50cm long and spaced at 25cm / 30cm intervals. The angle between the inclined guide tubes and the vertical direction is 30°.
8. The method for refined excavation construction of crane beams in underground powerhouse rock walls according to claim 1, characterized in that, After the lower layer excavation of the three-layer side areas is completed, anchor bolt construction will be carried out below the inflection point of the rock platform in the dense joint zone. The anchor bolts used in the locking joints are mortar anchor bolts to ensure the integrity of the excavation at the turning point under the rock platform.
9. The method for refined excavation construction of crane beams on rock walls of underground powerhouses according to claim 1, characterized in that, In step S4: The vertical holes in the rock platform area were drilled during the drilling process in the upper layer of the three-layer side areas; After drilling, a PVC pipe is inserted into the hole for protection, but no explosive is loaded. The blasting will be carried out together after the inclined holes in the rock platform area are completed.
10. The method for refined excavation construction of crane beams on rock walls of underground powerhouses according to claim 1, characterized in that, The drilling guide tube adopts a double-sleeve structure of steel pipe and hard rubber tube, which reduces the gap between the drill rod and the guide tube, and reduces the drift and deviation of the drill due to the shaking of the drill rod during the drilling process.