A method for constructing new prestressed anti-buoyancy anchors in confined spaces within existing engineering projects
By employing small electric drilling rigs and casing follow-up drilling technology within the limited space of existing underground structures, combined with segmented grouting and prestressed locking processes, the spatial adaptability and pull-out bearing capacity issues of traditional anti-buoyancy anchor construction have been solved, achieving green construction and long-term safe use.
Patent Information
- Application Number
- CN202611585856.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-14
- Publication Date
- 2026-11-17
AI Technical Summary
In the limited space of existing underground structures, traditional anti-buoyancy anchor construction suffers from large equipment size, poor spatial adaptability, easy collapse of holes in pebble layers, insufficient pull-out bearing capacity of anchors, and serious noise pollution during construction, which cannot meet the requirements for long-term safe use.
By employing miniaturized electric drilling rigs and casing follow-up hole-forming technology, segmented grouting system and prestressed locking process, combined with green construction measures, including precise point layout, water drilling to penetrate the bottom plate, casing follow-up wall protection, segmented prestressed steel reinforcement lowering, high-pressure grouting and composite layer pouring, a complete prestressed anti-buoyancy anchor structure is formed.
It achieves the goal of eliminating the need for large-scale dismantling of electromechanical pipelines within a limited space, reducing noise pollution, improving the anchoring bearing capacity and durability of anchor bolts, ensuring overall anti-buoyancy safety performance, shortening the construction period and reducing costs.
Smart Images

Figure CN123109149A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the fields of underground engineering construction and large building foundation construction, and in particular to a method for constructing new prestressed anti-buoyancy anchors in the limited space of existing projects. Background Technology
[0002] As urban groundwater recharge and restoration projects continue to advance, groundwater levels in many areas are rising year by year. A large number of existing underground buildings without pre-designed anti-buoyancy structures are experiencing problems such as arching of the foundation slab, cracking, and tilting of walls. Adding anti-buoyancy anchors is the mainstream technical approach to fundamentally solve the problem of anti-buoyancy failure in existing buildings. However, existing basements face natural constraints in construction conditions: low ceilings, dense electromechanical pipelines (most of which are in use and cannot be extensively dismantled or modified), and continuous operation of surrounding commercial businesses. Traditional anti-buoyancy anchor systems are difficult to adapt to narrow and confined spaces, and conventional construction methods in the industry generally suffer from the shortcomings of excessively large equipment size and poor spatial adaptability. Traditional drilling rigs are tall, and large drilling equipment suitable for open areas cannot enter basements for operation. Forcibly removing cables, water supply, drainage, and ventilation pipelines to make room for work will incur high costs for pipeline dismantling and restoration, significantly extend the overall construction period, and disrupt the normal operation of underground shops, highlighting a prominent conflict between economics and operation.
[0003] The lack of simultaneous casing protection in conventional anchor drilling in gravel strata is another core technical defect in the anti-buoyancy construction of existing basements. Older buildings often have gravel layers underground. Without casing during dry or water drilling, the loose gravel can easily cause large-scale borehole collapse and borehole wall collapse. Debris inside the borehole is difficult to clean, directly reducing the bond strength of the anchor section. Conventional one-time atmospheric pressure grouting can only fill the original voids in the borehole and cannot penetrate into the gravel gaps to form an integral anchoring structure. The pull-out bearing capacity of the anchor does not meet design standards. Furthermore, ordinary prestressed tendons lack a complete anti-corrosion protection system and are prone to corrosion when immersed in high-water underground environments for extended periods, significantly shortening the anchor's service life. This results in a high risk of structural leakage and anchor failure in the later stages, failing to meet the long-term safety requirements of existing buildings.
[0004] Existing anti-buoyancy anchor systems still have room for improvement in terms of force transfer and overall coordinated anti-buoyancy structural design. Traditional processes often involve a single anchor bearing the load independently, lacking supporting structures and construction procedures to transfer the load of a single anchor to the entire foundation. This makes it difficult to evenly distribute the anchor tension to the entire basement floor slab, easily leading to localized stress concentration and the risk of localized recurrence of uplift. Conventional tensioning and locking operations often require long curing periods, and some solutions lack anti-seepage structures at the anchor head nodes, making it easy for water seepage pathways to form at the junction of the anchor plate and the composite layer. Furthermore, traditional construction equipment often uses fuel-powered systems, which can generate exhaust fumes and noise in the confined environment of a basement. The lack of suitable noise reduction, ventilation, and waste disposal measures makes it difficult to meet the requirements of green construction, safe operation in confined spaces, and noise control in the surrounding commercial environment, thus limiting its overall application scenarios. Summary of the Invention
[0005] The purpose of this invention is to provide a method for constructing prestressed anti-buoyancy anchors in existing engineering projects with limited space. This method solves the problems of limited space in existing basements, inability to relocate pipelines over a large area, easy collapse of the pebble layer, dispersed stress of a single anchor, high pollution in confined spaces, and high cost, long construction period, and insufficient anti-buoyancy durability of traditional solutions.
[0006] To achieve the above objectives, this invention provides a method for constructing new prestressed anti-buoyancy anchors in confined spaces within existing engineering projects, comprising the following construction steps: S1. Construction preparation: Complete the refinement of drawings, preparation of special construction plans and hierarchical technical briefings, implement groundwater level control measures simultaneously, and mark and protect the existing electromechanical pipelines in the basement in different zones. S2. Excavation of the basement core: Small excavation and transportation equipment is used to excavate the backfill soil in the core of the basement in sections, while the internal secondary structure walls are demolished at the same time, and the site is cleared to form a continuous anchor bolt construction working surface. S3. Measurement and Positioning: Arrange anchor bolt positions according to the overall and local anti-buoyancy force requirements, mark the coordinates, hole depth and matching opening accessories of each position, and control the hole position deviation to meet the specifications. S4. Water drilling of the base plate: Match the appropriate specifications of water drill sleeve according to the thickness of the existing foundation base plate, and use water drill equipment to penetrate the base plate structure to form a vertical construction channel for anchor bolts; S5. Casing-following hole formation and cleaning: A highly improved electric down-the-hole drill rig is used, with segmented drill rods and wall-supporting steel casings drilling in sync. High-pressure airflow is used for slag removal. After the hole is completed, the hole is repeatedly cleaned to remove sediment. Various emergency handling procedures for drilling failures are also provided. S6. Lowering of reinforcement and grouting pipe: Prestressed threaded steel bars with an overall anti-corrosion protective layer are prefabricated in sections. The steel bars are matched with a central positioning component and a pile end bearing structure. After the high-pressure grouting pipe is tied and sealed at the same time, the whole structure is lowered to the bottom of the hole. S7. One-time grouting and casing recovery: Prepare cement grout according to a fixed water-cement ratio, and perform differentiated grouting for anchoring section and free section. After the grout reaches a specific hardening stage, use a special pipe pulling device to recover the protective steel casing. S8. Secondary fracturing grouting: High-pressure fracturing grouting is carried out through pre-embedded grouting pipes, and the grouting pressure is used as the main control index to complete the filling and reinforcement of the formation fractures. S9. Construction of composite layer: A composite layer with steel mesh is poured on the upper part of the foundation. Isolation sleeves are set at the anchor bolt positions, and anchoring force transmission components are pre-assembled. S10. Prestressing tensioning, locking and anchor sealing: After the grouting body and the composite concrete have reached the required strength, prestressing tensioning and locking are carried out using a matching tensioning bracket. An anti-seepage sealing structure is added to the anchor head node. Finally, filling material is poured in and the pile head is sealed to complete the anchor sealing.
[0007] Preferably, the drilling rig in S5 is a pure electric tracked down-the-hole drilling rig. The height of the drilling rig's propulsion frame is improved to address the low clearance in the basement. The drill rod and the casing are uniformly processed into short sections of equal length, enabling drilling by extending the sections one by one in the narrow vertical space. The number of sections of the casing and the drill rod remains consistent throughout the drilling process. The casing forms a physical isolation wall to offset the lateral soil pressure and groundwater seepage pressure in the loose strata, thus preventing borehole collapse.
[0008] Preferably, the prestressed threaded steel bars in S6 are entirely covered with an anti-corrosion coating. The steel bars are divided into anchorage sections and unbonded free sections. The steel bar sections are connected by special connecting sleeves. Disc-type centering supports are arranged at intervals along the entire length of the steel bar. An over-drilling sediment section is reserved at the bottom of the borehole. A circular bearing body is assembled at the bottom of the steel bar. Multiple sets of grouting holes are opened on the wall of the secondary grouting pipe, and the pipe ends and grouting holes are all sealed. The bottom end of the grouting pipe extends into the sediment section.
[0009] Preferably, the S7 primary grouting uses silicate cement to prepare cement paste, and the mixing is carried out using a standardized cylindrical mixing container. The amount of cement and mixing water is determined by volume and mass conversion. The anchoring section adopts a pressurized grouting process, and the free section adopts an atmospheric pressure grouting process. The steel sleeve removal window is controlled within the range after the initial setting and before the final setting of the cement. The sleeve can be recycled and reused after recovery.
[0010] Preferably, the S9 composite layer is equipped with a two-way steel mesh, and a hollow isolation sleeve is set at the anchor position to achieve post-tensioned non-bonded isolation. After the isolation sleeve is centrally arranged, the anchor plate and anchor nut are pre-locked to prevent the sleeve from shifting during concrete pouring.
[0011] Preferably, the S10 prestressed tensioning locking node adopts a widened anchor plate to match the large-diameter anchor pile body. Water-stop sealing components are set between the anchor plate and the composite layer, and between the anchor nut and the anchor plate to form a multi-layer anti-seepage system. Before tensioning, the anchor rod is pre-tensioned to eliminate the gap between the reinforcements. After reaching the design prestress value, the nut is locked immediately. After locking, high-strength filling material is injected through the grouting hole reserved in the anchor plate to seal the inside of the sleeve. Finally, the pile head is sealed with concrete of the same strength.
[0012] Therefore, the present invention adopts the above-mentioned method for constructing prestressed anti-buoyancy anchors in existing engineering confined spaces, and the technical effects are as follows: 1. The improved small pure electric drilling rig is suitable for the low and limited working space of the basement. It eliminates the need for large-scale dismantling and restoration of existing electromechanical pipelines, saving high pipeline dismantling and modification costs and shortening the construction period. At the same time, the electric equipment is equipped with soundproof barriers to reduce noise and exhaust pollution, without interfering with the normal operation of underground shops, thus achieving both economic and environmental benefits.
[0013] 2. The casing-following hole-forming process completely solves the problems of hole collapse and sediment residue in the pebble layer. High-pressure secondary splitting grouting allows the grout to penetrate into the gaps between the pebbles, improving the anchoring bearing capacity of the anchor bolt. The epoxy-coated prestressed steel bars, combined with the PE centering bracket, form a complete anti-corrosion system, which greatly improves the long-term underwater durability of the anchor bolt and ensures the long-term stability of the anti-buoyancy structure.
[0014] 3. By combining the composite layer with the prestressed locking process, the independent force of a single anchor rod is transformed into the overall synergistic anti-buoyancy force of the building base slab, avoiding local stress concentration and uplift; the anchor plate is optimized and widened to improve the prestress transfer efficiency, and the matching water-stop sealing node solves the hidden danger of anchor head leakage, comprehensively improving the overall anti-buoyancy safety performance of the existing basement. Attached Figure Description
[0015] Figure 1 This is a flowchart of a construction method for adding prestressed anti-buoyancy anchors in a confined space of an existing project, according to the present invention. Figure 2 This is a schematic diagram of the exploded structure for positioning the grouting pipe in an embodiment of the present invention; Figure 3 This is a schematic diagram of anchor sealing in an embodiment of the present invention.
[0016] Figure Labels 1. Positioning frame; 2. Threaded joint; 3. PE centering bracket; 4. Steel mesh; 5. Fine aggregate concrete; 6. Steel pad; 7. Composite layer; 8. Waterproof membrane; 9. Waterstop strip; 10. Steel sleeve; 11. High-strength grouting material. Detailed Implementation
[0017] The technical solution of the present invention will be further described below with reference to the accompanying drawings and embodiments.
[0018] Unless otherwise defined, the technical or scientific terms used in this invention shall have the ordinary meaning as understood by one of ordinary skill in the art to which this invention pertains.
[0019] Example 1 like Figure 1 As shown, this invention provides a method for constructing prestressed anti-buoyancy anchors in confined spaces within existing engineering projects. Based on a space-adaptive miniaturized equipment system, it utilizes casing-following wall-protection drilling technology as the core drilling process, employs a graded grouting system to enhance anchoring performance, and uses composite layers for synergistic prestressing locking to achieve overall anti-buoyancy stress. It is complemented by node seepage prevention structures and green construction management measures, forming a complete set of prestressed anti-buoyancy anchor construction technologies adapted to confined spaces in existing engineering projects. The method includes the following steps: S1. Construction preparation: Complete the refinement of drawings, preparation of special plans and hierarchical technical briefings, and simultaneously carry out on-site groundwater level control and protection of existing pipeline markings.
[0020] Based on the geological survey report, dewatering wells or wellpoint dewatering systems are deployed to continuously monitor the groundwater level and ensure that the water level remains stable at 1.0m below the design elevation during construction, with a daily fluctuation of no more than 0.5m, to prevent water and sand inrush during the drilling process.
[0021] All existing electromechanical pipelines in the basement should be fully marked, and the pipeline routes and ranges should be marked with colored paint. A warning zone should be set up within 1 meter around the pipelines. Before construction, protective measures such as wrapping and shielding should be taken for the pipelines. Heavy equipment operations and excavation operations are strictly prohibited in the warning zone.
[0022] S2. Excavation of the basement core: Using miniaturized excavation and transportation equipment, the basement core backfill soil is excavated in sections and the secondary structural walls are demolished to expose the foundation slab and form a continuous working surface.
[0023] For existing basements with independent foundations and waterproof slabs, or partial raft foundations, a backfill soil layer exists between the foundation and the building surface. Before construction, this backfill soil must be excavated to expose the foundation structure surface. Due to basement height limitations, a 15-type mini excavator with a 2m [unclear - possibly a height or height] is selected. 3 The volumetric agricultural tricycle is used for excavation and earthwork transportation, and its size is suitable for low-ceilinged spaces and narrow passages.
[0024] Excavation work began from one side of the basement and progressed gradually, forming a continuous work surface. Once the work conditions were met, subsequent surveying and drilling processes were interspersed to shorten the overall construction period. To ensure the integrity of the anchor bolt equipment operating space and the subsequent composite layers, all secondary structural walls of the basement were demolished simultaneously, and construction waste was cleared to create a flat and continuous working surface.
[0025] S3. Measurement and Positioning: Arrange anchor bolt positions while taking into account both overall and local anti-buoyancy requirements, mark coordinates, hole depth and corresponding casing parameters, and control hole position deviation within the allowable range.
[0026] The anchor bolt layout takes into account both overall and local anti-buoyancy requirements, and adopts a concentrated point, mesh, or uniform arrangement. The anchor bolt spacing is not less than 8 times the diameter of the anchor body and not less than 1.5m. The diameter of the anchor body in this construction method is 180mm, and the design spacing is controlled within the range of 2.1m-2.7m to meet the stress requirements of the specifications.
[0027] Draw an anchor bolt location layout diagram, marking the coordinates, design hole depth, corresponding foundation thickness, and matching sleeve length for each point. On-site, using fixed components such as column edges and structural wall edges as reference points, use a steel tape measure to measure and lay out the lines according to the pile point diagram. Mark the anchor bolt location control lines on the ground and number each point, noting the corresponding water drill sleeve length to avoid incorrect use during construction. Strictly control the allowable deviation of the hole position to ±50mm during construction.
[0028] S4. Water drilling: Select a water drill sleeve of the corresponding length according to the thickness of the base plate to penetrate the base plate structure and form an anchor bolt construction channel.
[0029] Before anchor bolt installation, a water drill is used to penetrate the existing foundation slab to create a drilling channel. For anchor bolts with a diameter of 180mm, a 200mm diameter water drill is selected, leaving a margin for sleeve installation. Depending on the thickness of the waterproofing slab and raft foundation, two lengths of water drill sleeves are selected: a 500mm long sleeve is suitable for drilling holes in waterproofing slab structures with a thickness of 300mm or less, and a 900mm long sleeve is suitable for drilling holes in raft foundation structures with a thickness of 700mm or less. Drilling must penetrate the structural layer, the bedding layer, the waterproofing layer, and the waterproofing protective layer. During drilling, the drilling speed is controlled, the drill is kept vertical, and damage to the surrounding foundation structure is avoided. After drilling, debris at the hole opening is cleaned, the hole position and diameter are checked, and temporary protection is applied to the hole opening.
[0030] S5. Casing follow-up hole formation and cleaning: A modified pure electric down-the-hole drill rig is used, with 1m short drill rods and casings advancing section by section. The steel casing is pressed in simultaneously with hydraulic pressure to protect the wall, and high-pressure air is used to remove slag. After the hole is completed, the sediment inside the hole is thoroughly cleaned.
[0031] To adapt to the limited space and enclosed environment of the basement, a pure electric tracked hydraulic down-the-hole drill rig was selected, which emits no fuel exhaust gas, ensuring indoor air quality. Each drill rig is equipped with an air compressor to clean up the gravel and debris generated during drilling. Addressing the tendency of gravel layers to collapse, a casing-following drilling technique was employed. The core principle is "simultaneous casing isolation and active borehole wall protection," which uses steel casing to isolate the borehole wall soil, offsetting the lateral pressure of loose soil layers and groundwater seepage pressure, thus ensuring the integrity of the borehole.
[0032] To address the minimum 2.6m height restriction for basements, the height of the drilling rig's propulsion frame was modified: the original conventional propulsion frame was approximately 5m high, while the modified frame is 2.4m high, allowing for a 200mm operating margin for the torque rotary head to be raised; the matching drill rods and steel casings are all machined to 1m in length to accommodate the propulsion frame's stroke range. Corresponding to an effective pile length of 11m, each unit is equipped with 11 sections of steel casing with an inner diameter of 180mm and 12 sections of 1m-long drill rods to meet the requirements of drilling section by section. The drilling rig has a power of 90kW, and the drilling time for a single anchor bolt ranges from 50 to 90 minutes depending on the geological complexity.
[0033] Before drilling begins, adjust the hydraulic supports in all four directions of the drilling rig to stabilize the machine body and calibrate the verticality of the borehole, ensuring that the allowable deviation of the verticality is less than 1%. During drilling, the drill bit breaks up the gravel formation, while the high-pressure airflow generated by the air compressor blows the debris out of the hole along the casing. The drilling rig's own hydraulic system simultaneously presses the steel casing into the formation, and the outer wall of the casing makes close contact with the soil in the borehole to form a protective wall.
[0034] The steel casing is connected section by section, each section pressed into the casing to a depth of 1m. Two sections are connected by tightening threads. Before connecting the casing, lubricant is applied to the threads to facilitate disassembly and removal later. A release agent is applied to the inner wall of the casing to reduce pulling resistance. The drill rod extension is connected in the same way as the casing. After raising the drill bit motor to a height of 2m, the threaded drill rod is connected using a torque wrench. During drilling, the number of casing and drill rod sections is always kept the same to ensure the entire pile length is protected by the casing, eliminating the risk of borehole collapse.
[0035] Once the drilling reaches the designed depth, the outer sleeve stops advancing, and the last section of drill rod is connected. The drill rod is repeatedly rotated and impacted, and high-pressure air is used to clean all remaining pebbles and debris from the hole until no obvious waste is discharged from the hole opening. Only after confirming that the sediment at the bottom of the hole meets the requirements can the next process be carried out.
[0036] To address the four common emergencies encountered during drilling operations in gravel formations—stuck drill bit, drill bit detachment, difficulty in removing slag, and casing detachment—a closed-loop, end-to-end response plan has been developed. Regarding the handling of stuck drill bits, the causes of stuck drill bits are mostly insufficient drilling power supply, drilling pressure overload, and deviation of the drill hole verticality. Throughout the construction process, the drilling rhythm should be strictly controlled at a uniform speed, and the drill hole verticality should be calibrated at a fixed frequency. In the event of sudden stuck drill bits, the drilling operation should be gradually restored by repeatedly pulling the drill rod at low speed and making multiple small impacts. It is strictly forbidden to force pressure drilling, which may cause secondary failures in the hole.
[0037] Regarding the handling of drill bit detachment, drill bits are high-frequency and easily damaged components. Before drilling, a full-dimensional appearance integrity inspection must be completed. If there are any defects in the cutting edge or missing corners, a brand new drill bit must be replaced immediately. If a drill bit suddenly detaches during construction, all connecting drill rods in the hole must be pulled out and disassembled section by section, and a compliant new drill bit must be replaced before restarting the drilling operation.
[0038] Regarding the handling of difficult slag removal, as the drilling depth continues to increase, the resistance to slag removal in the hole also increases. During construction, the single drilling progress is strictly controlled, and a multi-stage slag removal process is adopted to avoid excessive slag accumulation in the hole and blockage of the channel. After the drilling depth exceeds the threshold, the air compressor's air supply intensity is increased simultaneously to enhance the efficiency of conveying and removing drill cuttings in the hole.
[0039] Regarding the handling of casing detachment, the friction between the extended casing and the surrounding pebble layer increases significantly, which can easily lead to the failure of the pipe section thread to come off. All casing connections use high-strength special threads and the threading interval is increased to ensure the firmness of the pipe section connection from the source. In the event of a sudden casing detachment, all casings are pulled out and re-tightened immediately. Work is resumed only after there are no hidden dangers.
[0040] S6. Lowering prestressed steel bars and secondary grouting pipes: Use segmented epoxy-coated prestressed threaded steel bars, equipped with centering supports and pile end bearings, and simultaneously lower the secondary grouting pipes with sealed grouting holes to the bottom of the hole.
[0041] The prestressing tendons for this project will uniformly use PSB1080 grade prestressed concrete threaded steel bars, with a design tensile strength of 900MPa and a mandatory requirement that the measured ultimate tensile strength be no less than 1230MPa. After the steel bars arrive on site, a strictly witnessed sampling and retesting process will be implemented, and all test indicators must meet the following standards: yield strength ≥ 1080MPa, tensile strength ≥ 1230MPa, total elongation at maximum force ≥ 4.5%, and elongation after fracture ≥ 6%, thus controlling the mechanical properties of the raw materials from the source.
[0042] To accommodate the height limitations of the basement, the reinforcing bars were prefabricated in 2m sections. Each anchor rod had 5 effective load-bearing sections, with an additional 1m long operating section reserved at the top of the pile specifically for subsequent prestressing tensioning, locking, and anchor sealing operations. Each section of reinforcing bar was joined using a dedicated prestressed connecting sleeve, with a total sleeve length of 180mm. The screw-in depth of the reinforcing bars at both ends was controlled to 90mm. Before connection, limit markings were marked on the ends of the reinforcing bars to ensure accurate screw-in depth. Simultaneously, the cut surfaces of the reinforcing bar ends were ground smooth to remove burrs and sharp edges to prevent jamming during the connection process.
[0043] The entire prestressed tendon is divided into two functional sections: an 8m anchorage section and a 3m free section. The free section is covered with heat shrink tubing to achieve a completely bond-free design. The outer surface of the entire rebar is uniformly covered with an epoxy anti-corrosion coating with a coating thickness of ≥240μm. Special tests on coating thickness and continuity are carried out simultaneously upon arrival at the site to ensure the durability and corrosion resistance of the rebar under long-term groundwater erosion.
[0044] PE conical disc centering supports are installed along the entire length of the prestressed steel bar, with the spacing strictly controlled at 2m / support. The effective outer diameter of the support is set at 110mm. This ensures that the steel bar is centered throughout the entire length and meets the requirements for the thickness of the concrete protective layer of the pile body. It also avoids the risk of pile breakage caused by excessively large support size.
[0045] A 200mm thick over-drilling sediment containment section is pre-installed at the bottom of the pile. This area, where no prestressed steel reinforcement is placed, is specifically designed to accommodate the small amount of sediment remaining after drilling, ensuring that the effective load-bearing length of the anchorage section is not encroached upon by the sediment. A 120mm diameter steel circular bearing is installed at the bottom of the reinforcement, effectively expanding the load-bearing contact area at the pile end and significantly enhancing the end-bearing anchorage effect of the anchorage section.
[0046] like Figure 2 As shown, to accommodate the low ceiling height of the basement, the prestressed steel bars are prefabricated in sections. Adjacent sections are connected one by one using threaded joints 2 and special connecting sleeves to ensure the coaxiality and tensile strength of the steel bars. PE centering supports 3 are arranged at intervals along the length of the steel bars, with a disc-shaped structure supporting the steel bars circumferentially between the steel bars and the hole wall to ensure that the steel bars are centered throughout the entire process. This ensures that the protective layer thickness is uniform after grouting and avoids the hole from collapsing due to friction with the hole wall during the lowering process. The secondary grouting pipe is tied and fixed to the prestressed steel bars as a whole by the positioning frame 1 to maintain the axial position stability of the pipe and to ensure that the pipe end extends accurately to the sediment section at the bottom of the pile, providing a reliable path for subsequent high-pressure fracturing grouting.
[0047] The secondary grouting pipe is made of PE pipe material with excellent high pressure resistance and chemical stability. The specifications can be selected according to the on-site grouting requirements, such as 20mm, 25mm, or 32mm. The overall pressure bearing capacity of the pipe material must reach more than 2.0MPa to meet the requirements of high-pressure grouting operations. Grout outlet holes are drilled on the pipe wall at intervals of 300mm-400mm. The bottom end of the pipe and all grout outlet holes are sealed with transparent waterproof tape to completely avoid the problem of grout backflow into the pipe and causing pipeline blockage during the primary grouting process.
[0048] After the secondary grouting pipe is tied and fixed as a whole with the prestressed steel bars, it is lowered into the hole simultaneously. The pipe end extends into the sediment section at the bottom of the pile, and the bottom elevation of the pipe is controlled to be 50mm higher than the bottom of the pile. This ensures that during subsequent high-pressure grouting operations, the grout can be smoothly injected into the anchorage area at the bottom of the borehole, achieving effective grouting reinforcement of the entire anchorage section.
[0049] S7. One-time grouting and casing removal: Prepare cement grout according to the designed water-cement ratio, perform pressurized grouting in the anchoring section and normal pressure grouting in the free section, and remove the steel casing for recycling after the grout has initially set and before it has fully set.
[0050] Cement grout was prepared using P.O42.5 ordinary Portland cement with a water-cement ratio of 0.5. The design strength of the grout was not less than 30 MPa. A cylindrical mixing drum with a diameter of 1 m and a height of 1 m was used on site. The grout height was controlled to be below 0.8 m during each mixing to prevent overflow. The total grout volume was calculated using the following formula: ; Substitution , ,have to: ; Based on the relationship between volume and mass: ; in, ;Depending on the water-cement ratio ,have to Substitute into the volume formula Calculations yielded That is, each bucket of slurry should be filled with 16 bags of 50kg cement and water should be added to a height of 0.8m to meet the water-cement ratio requirement of 0.5.
[0051] The grouting pipe is lowered separately without being tied to the reinforcing steel and is pulled out after grouting is completed. Grouting is controlled in sections: the anchoring section uses pressurized grouting, with the grouting pressure controlled between 0.8MPa and 1.5MPa, utilizing the high density of cement grout to replace the mud and water in the hole; the free section uses atmospheric pressure grouting. When the grout emerging from the hole has the same properties as freshly mixed grout, grouting continues for 2 minutes to ensure complete replacement of the mud in the hole. The grouting height is controlled below the structural cushion layer; the portion above the cushion layer will be filled with high-strength grout after prestressing is completed.
[0052] The steel casing serves to ensure the formation of the pile body. The initial setting time of the cement is 45 minutes, and the final setting time is 6.5 hours. The casing should be removed after the initial setting and before the final setting of the cement. However, when removing the casing, the state of the cement grout should be observed in advance. It is most appropriate to remove the casing when it has lost its fluidity. Therefore, the removal time of the steel casing should be controlled between 2 and 4 hours. At this time, the state of the cement grout ensures that the cement in the pile body does not overflow into the gravel layer, and also ensures that the conditions for secondary grout injection are met. The removal of the steel casing cannot be done manually and requires the use of a professional casing removal machine. Furthermore, the removed casing needs to be disassembled manually for use in subsequent anchor bolt construction.
[0053] S8. Secondary splitting grouting: High-pressure cement grout is injected through a secondary grouting pipe to split the primary grouting body and allow the grout to seep into the gaps of the pebble layer. The grouting pressure is used as the control standard.
[0054] Secondary grouting is high-pressure fracturing grouting. Its purpose is to create fracturing cracks in the grout formed during the primary grouting under high pressure. The grout is then forced into the surrounding gravel layer under pressure, forming an integral anchoring structure between the anchor bolt and the stratum, significantly improving pull-out bearing capacity. Due to the large differences in permeability in gravel strata, grouting quality is not controlled by the grout volume, but rather by the grouting pressure. The grouting pressure should be controlled above 1.5 MPa, and stabilized for 5 minutes after reaching the design pressure to ensure sufficient grout diffusion. Secondary grouting is performed immediately after casing removal, utilizing the incomplete hardening of the grout to enhance the fracturing effect.
[0055] S9. Construction of composite layer: Lay out steel mesh and pour concrete for composite layer. Pre-set steel sleeves at anchor positions to isolate the post-tensioned area and pre-fix anchor plates and nuts.
[0056] Since the anti-buoyancy anchors are all single anchors bearing the buoyancy load, it is necessary to transform the single buoyancy load of all anchors into an integrated buoyancy load through unbonded connection between the anti-buoyancy anchors and the composite layer and prestressed locking. The thickness of the newly constructed composite layer in this project is 100mm-150mm, with a single layer of bidirectional steel mesh inside. The construction of the composite layer is completed after the concrete is poured.
[0057] Before constructing the composite layer, the prestressed steel bars of the anti-buoyancy anchors need to be bonded within the composite layer, and the prestressing is applied using the post-tensioning method. Therefore, concrete cannot be poured into this part of the pile body; a steel sleeve is required for effective isolation, and the steel sleeve must be able to withstand the load of the post-tensioning method. In this project, a steel sleeve with an outer diameter of 100mm and a wall thickness of 8mm was selected. After the prestressing is locked, high-strength grout is injected internally for sealing.
[0058] The sleeve should be placed in the center. After placing the sleeve, lock the anchor plate and anchor nut to ensure that the sleeve will not shift during the concrete pouring process.
[0059] S10. Prestressing Locking and Anchoring: After the strength of the grout and composite layer reaches the standard, prestress is applied and locked using a special tensioning bracket to complete the joint seepage prevention treatment and anchoring construction.
[0060] The prestressed locking joint consists of an anchor plate and anchor nuts. The anchor plate is located above the composite layer and requires a hole in its center through which the prestressed steel reinforcement passes. The anchor nuts are locked onto the prestressed steel reinforcement after prestressing is applied, thus locking the prestress. Secondly, because the post-tensioning method and the prestressed steel reinforcement within the composite layer have bonding requirements, and the newly added steel sleeve and the composite layer concrete are made of different materials, there is a risk of leakage. Therefore, a water-swellable sealing strip needs to be added between the anchor plate and the composite layer, and a polytetrafluoroethylene gasket needs to be added between the anchor nuts and the anchor plate to prevent leakage.
[0061] PSB1080 level The anchor plate used for the 36 prestressed steel bars should be 110mm wide and 20mm thick. However, because the diameter of the anti-buoyancy anchor pile is 180mm, the 110mm wide anchor plate cannot meet the prestress transfer requirements. Based on on-site tests and calculations by the design unit, the anchor plate was replaced with a 200mm wide and 20mm thick plate while meeting the anchor plate warpage calculation requirements, thus effectively solving the prestress transfer function of the anchor plate.
[0062] The purpose of prestressing locking is to apply an upward pull-out force to the completed anti-buoyancy anchors. The reaction force generated by the anti-buoyancy anchors controls the entire foundation, preventing structural displacement under the buoyancy of groundwater and thus ensuring structural safety and stability. Prestressing locking can only be carried out 28 days after the completion of the anti-buoyancy anchor construction, after both the pile body strength and the composite layer concrete strength have reached 100%.
[0063] For prestressing, jacks equipped with pressure gauges are selected. The tensioning equipment used in this project is similar to that used for slope protection pile anchors, but jack support brackets need to be prefabricated. Furthermore, a set of anchor plates and anchor nuts are required for fixing the prestressed steel bars. Secondly, the prestressing locking value for this project needs to reach 420kN. The material used for the support brackets is the same prestressed steel bar used in anti-buoyancy anchors, which meets both the jack requirements and the 420kN load requirement.
[0064] Before prestressing, align the center of the fabricated support with the prestressing steel bars. Then, place the jacks on top of the prestressing steel bars and secure them with anchor plates and nuts. After starting the equipment, constantly monitor the stability of the support and the tension values. Once the values meet the design requirements, stop tensioning and immediately lock the anchor nuts. After ensuring the anchor nuts are securely tightened, the prestressing locking process is complete.
[0065] like Figure 3 As shown, the existing waterproof slab 8 above the foundation slab serves as the original seepage prevention structure and forms the basis of the slab's waterproofing system. A composite layer 7 with embedded steel mesh 4 is poured on top of it, which can evenly distribute the pull-out force of a single anchor rod to the entire slab area, achieving a transformation from independent force on a single anchor to overall collaborative anti-buoyancy. Steel sleeves 10 are pre-embedded at the corresponding anchor rod positions, forming an unbonded isolation for the free section of the prestressed steel reinforcement, ensuring the effective stroke of post-tensioning, and also serving as a cavity for subsequent filling materials.
[0066] During tensioning and locking, a steel pad 6 is installed on the top surface of the composite layer. The increased contact area allows for the uniform transfer of prestress to the composite layer, preventing localized stress concentration and concrete damage. A waterstop strip 9 is installed at the interface between the steel pad and the composite layer. Its water-swelling properties fill the interface gaps, blocking groundwater seepage along the pile body and forming a seepage barrier around the anchor head. After prestressing locking is completed, high-strength grout 11 is injected into the steel sleeve through the pre-drilled holes in the anchor plate. This densely fills the internal voids of the sleeve and wraps the reinforcing steel in the anchoring section, enhancing the overall integrity and sealing performance of the joint. Finally, fine aggregate concrete 5 is used to seal and smooth the top of the pile head, making the anchor head flush with the surface of the composite layer, completing the complete sealing and protection.
[0067] Before prestressing locking, two 20mm grouting holes need to be drilled on the anchor plate according to the location of the newly added steel sleeve; one is for grouting and the other is for venting. After prestressing locking, excess prestressing steel bars are cut off, leaving 20mm of the prestressing steel bars exposed above the anchor nut. Then, high-strength grout is injected. After the grout is filled, the grouting holes are sealed with structural sealant. Finally, the anti-buoyancy anchor head is sealed with concrete of the same strength as the composite layer.
[0068] The actual application effect of this method was verified by taking the structural reinforcement project of B1-B3 of a certain Huazhong Center as an application scenario.
[0069] The basement ceiling has a complex network of pipes, all of which are in use, making large-scale demolition impossible; the groundwater level in the area remains high, and the strata are mainly composed of gravel, making the drilling process prone to collapse; the first basement level houses normally operating shops, requiring strict control of noise and dust emissions during construction; the basement has a minimum clear height of only 2.6m, making it impossible for conventional large drilling equipment to directly access the site.
[0070] The anchor body diameter is 180mm, the effective pile length is 11m, and the anchor spacing is controlled within the range of 2.1m-2.7m; the prestressed steel bars are PSB1080 grade. 36 threaded steel bars with an epoxy coating thickness ≥240μm; anchor rods are divided into an 8m anchorage section and a 3m free section; the design locking force is 420kN; the grout strength is ≥30MPa; and the thickness of the composite layer at the top of the pile is set to 100mm-150mm.
[0071] The improved 2.4m high-mounted electric drilling rig, paired with 1m short-section casing drill rods, perfectly adapts to the 2.6m low clearance working environment, and no large-scale dismantling of existing pipelines was carried out throughout the process. The casing follow-up drilling process was used throughout the process, completely solving the hidden danger of hole collapse in the pebble layer, and the hole qualification rate reached 100%. After the secondary splitting grouting was completed, the pull-out bearing capacity test results of all anchor bolts met the design requirements, and the bearing capacity surplus coefficient reached more than 1.2. The pure electric construction equipment, combined with the closed soundproof enclosure measures, ensured that the construction noise and dust emissions fully complied with environmental protection standards, and did not interfere with the normal operation of the shops on the first basement floor.
[0072] This construction method directly avoids the dismantling and restoration of a large number of existing pipelines, saving a total of over one million yuan in pipeline dismantling and restoration costs. Compared with the traditional drainage pressure limiting construction scheme, it eliminates the need for sewage treatment, labor and electricity consumption corresponding to large daily discharge of rainwater, significantly reducing daily operation and maintenance costs. Once the construction method is invested in, it does not require long-term continuous operation and maintenance, resulting in outstanding comprehensive economic benefits throughout its entire life cycle.
[0073] Therefore, this invention adopts the above-mentioned construction method for adding prestressed anti-buoyancy anchors in the limited space of existing engineering projects. First, preliminary preparations are completed through drawing surveys, dewatering and positioning control, and pipeline protection. Then, small excavation equipment is used to excavate the core, backfill, and demolish the secondary structure. After precise point marking and water drilling to penetrate the bottom slab, a modified low-height pure electric crawler drilling rig with a 1m short-section casing is used to advance the wall protection and drilling. Simultaneously, measures are implemented to handle sudden geological problems such as stuck drill and pipe detachment. Subsequently, segmented epoxy anti-corrosion prestressed steel bars and high-pressure PE secondary grouting pipes are lowered. Based on a precise mixing formula, a 0.5 water-cement ratio cement slurry is prepared for a single pressurized grouting. The steel casing is recovered during the initial to final setting interval, and high-pressure fracturing grouting of 1.5MPa or higher is immediately carried out. Then, a 100-150mm thick composite layer with steel mesh is poured to achieve overall load transfer. With widened and optimized anchor plates and water-stop sealing components, seepage-proof tensioning nodes are formed. After the strength of the grout and composite layer fully meets the standards, 420kN prestress is applied for locking and high-strength grouting material is used to seal the anchor. This method avoids the cost of dismantling and modifying a large number of pipelines, reduces noise and exhaust pollution, and solves defects such as pebble layer collapse, insufficient anchor durability, local floating, and anchor head leakage. It can complete the anti-floating reinforcement construction of the basement of the existing building without interfering with the operation of the underground shops.
[0074] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the technical solutions of the present invention, and these modifications or equivalent substitutions cannot cause the modified technical solutions to deviate from the spirit and scope of the technical solutions of the present invention.
Claims
1. A method for constructing new prestressed anti-buoyancy anchors in a confined space within an existing engineering project, characterized in that, The construction steps include the following: S1. Construction preparation: Complete the refinement of drawings, preparation of special construction plans and hierarchical technical briefings, implement groundwater level control measures simultaneously, and mark and protect the existing electromechanical pipelines in the basement in different zones. S2. Excavation of the basement core: Small excavation and transportation equipment is used to excavate the backfill soil in the core of the basement in sections, while the internal secondary structure walls are demolished at the same time, and the site is cleared to form a continuous anchor bolt construction working surface. S3. Measurement and Positioning: Arrange anchor bolt positions according to the overall and local anti-buoyancy force requirements, mark the coordinates, hole depth and matching opening accessories of each position, and control the hole position deviation to meet the specifications. S4. Water drilling of the base plate: Match the appropriate specifications of water drill sleeve according to the thickness of the existing foundation base plate, and use water drill equipment to penetrate the base plate structure to form a vertical construction channel for anchor bolts; S5. Casing-following hole formation and cleaning: A highly improved electric down-the-hole drill rig is used, with segmented drill rods and wall-supporting steel casings drilling in sync. High-pressure airflow is used for slag removal. After the hole is completed, the hole is repeatedly cleaned to remove sediment. Various emergency handling procedures for drilling failures are also provided. S6. Lowering of reinforcement and grouting pipe: Prestressed threaded steel bars with an overall anti-corrosion protective layer are prefabricated in sections. The steel bars are matched with a central positioning component and a pile end bearing structure. After the high-pressure grouting pipe is tied and sealed at the same time, the whole structure is lowered to the bottom of the hole. S7. One-time grouting and casing recovery: Prepare cement grout according to a fixed water-cement ratio, and perform differentiated grouting for anchoring section and free section. After the grout reaches a specific hardening stage, use a special pipe pulling device to recover the protective steel casing. S8. Secondary fracturing grouting: High-pressure fracturing grouting is carried out through pre-embedded grouting pipes, and the grouting pressure is used as the main control index to complete the filling and reinforcement of the formation fractures. S9. Construction of composite layer: A composite layer with steel mesh is poured on the upper part of the foundation. Isolation sleeves are set at the anchor bolt positions, and anchoring force transmission components are pre-assembled. S10. Prestressing tensioning, locking and anchor sealing: After the grouting body and the composite concrete have reached the required strength, prestressing tensioning and locking are carried out using a matching tensioning bracket. An anti-seepage sealing structure is added to the anchor head node. Finally, filling material is poured in and the pile head is sealed to complete the anchor sealing.
2. The method for constructing new prestressed anti-buoyancy anchors in a confined space of an existing project according to claim 1, characterized in that, The S5 drilling rig is a pure electric tracked down-the-hole drilling rig. The height of the drilling rig's propulsion frame has been improved to address the low clearance in basements. The drill rod and the casing steel pipe are uniformly processed into short sections of equal length, enabling drilling by extending the sections one by one in narrow vertical spaces. The number of sections of the casing steel pipe and the drill rod remains consistent throughout the drilling process. The casing steel pipe forms a physical isolation wall to offset the lateral soil pressure and groundwater seepage pressure of loose strata, thus preventing borehole collapse.
3. The method for constructing new prestressed anti-buoyancy anchors in a confined space of an existing project according to claim 1, characterized in that, The prestressed threaded steel bars in S6 are entirely covered with an anti-corrosion coating. The steel bars are divided into anchorage sections and unbonded free sections. The steel bar sections are connected by special connecting sleeves. Disc-type centering supports are arranged at intervals along the length of the steel bar. An over-drilling sediment section is reserved at the bottom of the borehole. A circular bearing body is assembled at the bottom of the steel bar. Multiple sets of grouting holes are opened on the wall of the secondary grouting pipe, and the pipe ends and grouting holes are all sealed. The bottom end of the grouting pipe extends into the sediment section.
4. The method for constructing new prestressed anti-buoyancy anchors in a confined space of an existing project according to claim 1, characterized in that, S7 grouting uses silicate cement to prepare cement paste, and standardized cylindrical mixing containers are used for mixing. The amount of cement and mixing water is determined by volume and mass conversion. The anchoring section adopts pressurized grouting process, and the free section adopts atmospheric pressure grouting process. The steel sleeve removal window is controlled within the range after the initial setting and before the final setting of cement. The sleeve can be recycled and reused.
5. The method for constructing new prestressed anti-buoyancy anchors in a confined space of an existing project according to claim 1, characterized in that, The S9 composite layer is internally equipped with a two-way steel mesh, and hollow isolation sleeves are set at the anchor positions to achieve post-tensioned non-bonded isolation. After the isolation sleeve is centrally positioned, the anchor plate and anchor nut are pre-locked to prevent the sleeve from shifting during concrete pouring.
6. The method for constructing new prestressed anti-buoyancy anchors in a confined space of an existing project according to claim 1, characterized in that, The S10 prestressed tensioning locking node adopts a widened anchor plate to match the large-diameter anchor pile body. Water-stop sealing components are set between the anchor plate and the composite layer, and between the anchor nut and the anchor plate to form a multi-layer anti-seepage system. Before tensioning, the anchor rod is pre-tensioned to eliminate the gap between the reinforcement. After reaching the design prestress value, the nut is locked immediately. After locking, high-strength filling material is injected through the grouting hole reserved in the anchor plate to seal the inside of the sleeve. Finally, the pile head is sealed with concrete of the same strength.