Steel-concrete frame connection structure and construction method of steel-concrete frame
By using a combination of anchor bars, embedded sleeves, and tension bolts in the reinforced concrete frame, the problems of displacement of the embedded connecting plate during concrete pouring and instability of steel beam installation were solved, achieving higher positioning accuracy and construction efficiency.
Patent Information
- Application Number
- CN202611532785.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-17
AI Technical Summary
In existing reinforced concrete frames, the embedded connecting plates are prone to displacement or tilting during concrete pouring, and there are problems with instability and inaccurate connection during steel beam installation, resulting in complex construction and low efficiency.
Anchor bars and sleeves are used on the inner side of the pre-embedded connecting plate and fixed to the inner surface of the column formwork by tightening bolts. Combined with detachable positioning frame and support components, the positioning accuracy of the pre-embedded connecting plate is ensured, and guidance and support are provided during steel beam installation. The elevation is adjusted by using lifting drive components.
It improved the positioning accuracy of the pre-embedded connecting plate, reduced the phenomenon of grout entering the sleeve, simplified the installation process of the steel beam, reduced the construction complexity and workload, and ensured the accuracy and stability of the connection.
Smart Images

Figure CN123109272A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of steel-concrete frame technology, specifically relating to a steel-concrete frame connection structure and a construction method for steel-concrete frames. Background Technology
[0002] Steel-concrete frames, composed of reinforced concrete columns and steel beams, are widely used in industrial plants, public buildings, and large equipment platforms. During construction, connecting plates are usually embedded in the concrete columns. After the concrete is poured and the formwork is removed, the steel beams are hoisted between adjacent concrete columns, and the ends of the steel beams are permanently connected to the embedded connecting plates.
[0003] Existing embedded connection plates are usually fixed to the column reinforcement cage by binding or spot welding. During formwork installation, concrete pouring and vibration, the embedded connection plates are prone to displacement or tilting; if the embedded connection plate is not tightly attached to the column formwork, concrete slurry may also enter the gap between the embedded connection plate and the formwork or the inside of the sleeve, causing the embedded connection plate to sink in, the surface to be covered by concrete, or the sleeve threads to be blocked.
[0004] During steel beam installation, lifting equipment is typically required to maintain the beams in a suspended state for extended periods, while construction workers perform high-altitude positioning and connection. This presents challenges due to beam swaying and unstable temporary supports. Using scaffolding, temporary steel supports, or welded temporary pallets for support further increases the workload of erection, dismantling, and subsequent handling. Furthermore, the pre-fabricated holes on the embedded connecting plates may not accurately align with the beam end holes due to deviations in concrete construction and errors in steel beam fabrication. Summary of the Invention
[0005] This application provides a steel-concrete frame connection structure and a construction method for a steel-concrete frame, aiming to solve at least one of the above-mentioned technical problems.
[0006] One embodiment of this application provides a steel-concrete frame connection structure, mainly used for connecting concrete columns and steel beams in steel-concrete frames, characterized by comprising: An embedded connecting plate has multiple anchor bars on its inner side, and the anchor bars are fixedly connected to the steel cage in the concrete column. Multiple embedded sleeves are arranged around the inner periphery of the embedded connecting plate, and the embedded sleeves have internal threads. Multiple tension bolts, each corresponding to one of the multiple embedded sleeves, wherein the tension bolts are configured to be threadedly connected to the embedded sleeves.
[0007] The above-mentioned steel-concrete frame connection structure uses multiple embedded sleeves on the inner side of the embedded connection plate and is equipped with corresponding tension bolts. Before concrete pouring, the embedded connection plate is tightened to the inner surface of the column formwork by tension bolts to control the embedded position, ensure the positioning accuracy of the embedded connection plate, and reduce grouting into the sleeves.
[0008] In one embodiment, the pre-embedded connecting plate is rectangular with holes at its four corners, and a pre-embedded sleeve is disposed at each of the holes.
[0009] In one embodiment, the embedded sleeve must not protrude beyond the outer side of the embedded connecting plate.
[0010] In one embodiment, the steel-concrete frame connection structure further includes a detachable positioning frame. The detachable positioning frame has a through hole corresponding to the pre-embedded sleeve. The tension bolt passes through the corresponding through hole and is then connected to the pre-embedded sleeve.
[0011] In one embodiment, the steel-concrete frame connection structure further includes a support assembly, which includes a guide frame having a U-shaped groove configured to allow the steel beam to be inserted into the U-shaped groove from the opening; the support assembly is connected to multiple embedded sleeves via multiple support mounting bolts.
[0012] In one embodiment, an inclined guide surface is provided at the opening of the U-shaped groove.
[0013] In one embodiment, the supporting assembly further includes a lifting movable plate and a lifting drive component. The lifting movable plate is located within the U-shaped groove. The lifting drive component is fixedly installed at the bottom of the supporting assembly and connected to the lifting movable plate, and is used to drive the lifting movable plate to move vertically within the U-shaped groove.
[0014] In one embodiment, the bottom of the lifting movable plate is provided with multiple lifting guide rods, and the lifting guide rods are slidably connected to the guide frame in the vertical direction.
[0015] In one embodiment, the lifting movable plate is further equipped with a reaction force detection component, and a support plate is configured on the reaction force detection component, the support plate being used to support the steel beam.
[0016] In one embodiment, the steel beam is an H-beam with beam end connecting plates at both ends; the beam end connecting plates have multiple connecting through holes, and the embedded connecting plates have threaded connecting holes at corresponding positions; the beam end connecting plates and the embedded connecting plates are fixedly connected by connecting bolts.
[0017] Another embodiment of this application provides a construction method for a steel-concrete frame, characterized by comprising: S1. Rigid pre-embedded assembly fabrication: fabricate pre-embedded connecting plates, pre-embedded sleeves and anchor bars, fix multiple pre-embedded sleeves to the periphery of the inner side of the pre-embedded connecting plate respectively; fix multiple anchor bars to the inner pre-embedded surface of the pre-embedded connecting plate to form a rigid pre-embedded assembly. S2. Reinforcing cage installation and formwork opening: Arrange the rigid pre-embedded assembly at the design node position of the reinforcing cage, and initially connect the rigid pre-embedded assembly to the reinforcing cage; According to the position of the pre-embedded sleeve, process the formwork through hole corresponding to each pre-embedded sleeve on the column formwork; S3. Installation of positioning frame and tightening of pre-embedded assembly: Set the detachable positioning frame on the outside of the column template, pass the tightening bolts through the detachable positioning frame and the column template in sequence, and screw them into the corresponding pre-embedded sleeves; tighten each tightening bolt, and pull the pre-embedded connecting plate evenly toward the inner surface of the column template; S4. Concrete pouring and formwork removal: Pour concrete, and then vibrate and cure it; after the concrete reaches the formwork removal condition, first unscrew all the aforementioned tension bolts and remove the aforementioned detachable positioning frame, and then remove the aforementioned column formwork. S5. Support component installation: Install support components on two adjacent concrete columns. Install the support components on the outside of the pre-embedded connecting plate, so that the mounting holes of the U-shaped mounting guide on the support component correspond to the pre-embedded sleeves respectively. Pass the support mounting bolts through the corresponding mounting holes and screw them into the corresponding pre-embedded sleeves to tighten them, so that the U-shaped mounting guide is fixed on the concrete column. S6. Steel beam hoisting and guide beam lowering: Use lifting equipment to hoist the steel beam between two adjacent concrete columns, so that both ends of the steel beam are above the two installation guide frames respectively; gradually lower the steel beam so that the steel beam is supported on the support plate; S7. Steel beam elevation adjustment and connection surface fit: Control the lifting drive of the two supporting components respectively, adjust the support height at both ends of the steel beam according to the design elevation and level of the steel beam, so that the beam end connecting plates at both ends of the steel beam fit with the corresponding pre-embedded connecting plates; S8. On-site drilling and permanent connection: Mark the on-site machining hole positions on the pre-embedded connection plate according to the position of the connection hole on the beam end connection plate; drill directly through the connection hole on the beam end connection plate, and screw the permanent connection bolt through the beam end connection plate into the drill hole on the pre-embedded connection plate; S9. Load transfer and support assembly removal: Control the lifting drive to retract, causing the support plate to descend, and then remove the support assembly.
[0018] The above description is only an overview of the technical solution of this application. In order to better understand the technical means of this application and to implement it in accordance with the contents of the specification, and to make the above and other objects, features and advantages of this application more obvious and understandable, the following are specific embodiments of this application. Attached Figure Description
[0019] The accompanying drawings in this application are for illustrating preferred embodiments and to facilitate a clear understanding by those skilled in the art of various other advantages and benefits, and should not be construed as limiting the scope of this application. Furthermore, the same reference numerals denote the same parts throughout the drawings.
[0020] Figure 1 This is a three-dimensional schematic diagram of the pre-embedded connecting plate 1 in one embodiment of this application.
[0021] Figure 2 This is a three-dimensional schematic diagram of a steel-concrete frame connection structure in one embodiment of this application.
[0022] Figure 3 This is a schematic diagram of the steel-concrete frame connection structure during construction in one embodiment of this application.
[0023] Figure 4 This is a cross-sectional schematic diagram of the steel-concrete frame connection structure during construction in one embodiment of this application.
[0024] Figure 5 This is a three-dimensional schematic diagram of a concrete column in one embodiment of this application.
[0025] Figure 6 This is a schematic diagram of a support component installed on a concrete column in one embodiment of this application.
[0026] Figure 7 This is a schematic diagram of the support component being installed on the pre-embedded connecting plate in one embodiment of this application.
[0027] Figure 8 This is a schematic diagram of a guide frame in one embodiment of this application.
[0028] Figure 9 This is a schematic diagram of a support component in one embodiment of this application.
[0029] Figure 10 This is a side view of a steel beam in one embodiment of this application.
[0030] Figure 11 This is a schematic diagram of a steel-concrete frame in one embodiment of this application.
[0031] Reference numerals: 1. Embedded connecting plate; 11. Anchor bar; Embedded sleeve 2; Detachable positioning frame 3; Tighten bolt 4; Column formwork 5; 6 steel cages; Concrete column 7; Support component 8, guide frame 81, inclined guide surface 811, mounting hole 812, lifting movable plate 82, support plate 83, reaction force detection component 84, lifting drive component 85, lifting guide rod 86, support mounting bolt 87; Steel beam 9, beam end connecting plate 91. Detailed Implementation
[0032] The technical solutions in the embodiments of this application will be clearly and completely described below with reference to specific examples. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0033] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.
[0034] In the description of the embodiments of this application, "multiple" means two or more (including two), unless otherwise explicitly specified.
[0035] In the description of the embodiments of this application, the technical terms "center," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," and "circumferential" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing the embodiments of this application and simplifying the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the embodiments of this application.
[0036] In the description of the embodiments of this application, unless otherwise expressly specified and limited, technical terms such as "installation," "connection," "joining," and "fixing" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. For those skilled in the art, the specific meaning of the above terms in the embodiments of this application can be understood according to the specific circumstances.
[0037] See Figure 1-11 One embodiment of this application provides a steel-concrete frame connection structure, mainly used for connecting concrete columns 7 and steel beams 9 in a steel-concrete frame, including: a pre-embedded connecting plate 1, multiple pre-embedded sleeves 2, and multiple tension bolts 4. The pre-embedded connecting plate 1 has multiple anchor bars 11 on its inner side, which are fixedly connected to the reinforcing cage 6 in the concrete column 7; the multiple pre-embedded sleeves 2 are arranged around the inner side of the pre-embedded connecting plate 1, and the pre-embedded sleeves 2 have internal threads; the multiple tension bolts 4 correspond one-to-one with the multiple pre-embedded sleeves 2, and the tension bolts 4 are configured to be threadedly connected to the pre-embedded sleeves 2. The above-mentioned steel-concrete frame connection structure uses multiple pre-embedded sleeves 2 inside the pre-embedded connecting plate 1 and is equipped with corresponding tension bolts 4. Before concrete pouring, the pre-embedded connecting plate 1 is tightened to the inner surface of the column formwork 5 by tension bolts 4 (tension bolts 4 pass through holes on the column formwork 5 and are threadedly connected to the pre-embedded sleeves 2) to control the pre-embedded position, ensure the positioning accuracy of the pre-embedded connecting plate 1, and reduce grouting into the sleeves.
[0038] Specifically, such as Figure 1 As shown, the embedded connecting plate 1 is rectangular, including the outer surface facing the column formwork 5 and the inner surface facing the steel cage 6.
[0039] It should be noted that the anchor bar 11 is fixed to the embedded surface of the embedded connecting plate 1 and extends into the concrete column 7. The anchor bar 11 can be connected to the embedded connecting plate 1 by welding, threaded connection or other rigid connection methods. The anchor bar 11 is used to transfer the permanent connection load borne by the embedded connecting plate 1 and the temporary support load borne by the embedded sleeve 2 to the interior of the concrete column 7.
[0040] It should be noted that a permanent connection area is formed in the middle of the pre-embedded connecting plate 1. Before pouring, this permanent connection area does not require fixed permanent connection holes. Instead, after the steel beam 9 is hoisted and its actual position is adjusted, the connection holes are machined on-site according to the positions of the connection holes in the beam end connecting plate 91, thereby reducing the impact of pre-embedded errors and steel beam machining errors on the hole alignment.
[0041] The embedded connecting plate 1 has holes at its four corners, and four embedded sleeves 2 are preferably located at the four corners of the embedded connecting plate 1 and arranged around the permanent connection area. The axis of the embedded sleeves 2 is perpendicular or substantially perpendicular to the embedded connecting plate 1. The embedded sleeves 2 have internal threads, and their open ends face the exposed side of the embedded connecting plate 1 and communicate with the corresponding openings on the embedded connecting plate 1.
[0042] Furthermore, the embedded sleeve 2 must not protrude beyond the outer surface of the embedded connecting plate 1. In practice, the end of the embedded sleeve 2 is preferably flush or substantially flush with the outer surface of the embedded connecting plate 1, so that when the embedded connecting plate 1 is tightened on the inner surface of the column formwork 5, the embedded sleeve 2 will not push the embedded connecting plate 1 away from the column formwork 5.
[0043] It should be noted that the embedded connecting plate 1, the embedded sleeve 2 and the anchor bar 11 are assembled into a rigid whole before entering the construction site or before being installed into the steel cage 6, so as to avoid the embedded sleeve 2 moving independently relative to the embedded connecting plate 1.
[0044] In some embodiments, such as Figures 2 to 4 As shown, the steel-concrete frame connection structure also includes a detachable positioning frame 3. The detachable positioning frame 3 has through holes corresponding to the embedded sleeve 2. The tension bolt 4 passes through the corresponding through holes and is then connected to the embedded sleeve 2. The detachable positioning frame 3 is located on the outside of the column formwork 5, and its shape can be a rectangular frame, a grid-like frame, or a rigid frame composed of multiple connecting rods. It is used to increase the integrity and stability of the connection.
[0045] Specifically, through holes are machined on the column formwork 5 according to the design position of the pre-embedded connecting plate 1. The tension bolts 4 pass through the through holes of the detachable positioning frame 3 and the formwork through holes of the column formwork 5 in sequence, and are screwed into the corresponding pre-embedded sleeves 2.
[0046] After the tension bolt 4 is tightened, the detachable positioning frame 3 abuts against the outer surface of the column template 5, the embedded connecting plate 1 is tightened to the inner surface of the column template 5, and the column template 5 is clamped between the detachable positioning frame 3 and the embedded connecting plate 1.
[0047] The detachable positioning frame 3 is mainly used to distribute the load of the tension bolts 4 acting on the column formwork 5 and to maintain the relative positions between the four tensioning positions. The planar position of the detachable positioning frame 3 is mainly determined by the formwork through holes on the column formwork 5 and the construction layout position. The tension bolts 4 mainly generate a tension force perpendicular to the column formwork 5.
[0048] During installation, it is preferable to tighten the four tension bolts 4 gradually in a diagonal sequence to ensure that the embedded connecting plate 1 fits evenly against the column template 5, and to avoid tilting of the embedded connecting plate 1 caused by tightening one side completely first.
[0049] The shank of the tension bolt 4 occupies the opening of the embedded sleeve 2, and the exposed surface of the embedded connecting plate 1 is in close contact with the inner surface of the column formwork 5, thus jointly blocking the path of concrete grout into the embedded sleeve 2. The through holes on the column formwork 5 should be fitted with the tension bolt 4 with a small clearance. Depending on construction needs, a construction sealing gasket or sealant can also be installed at the bolt protrusion position on the outside of the formwork, but this sealing structure can be used as an auxiliary construction material and is not a necessary component of this device.
[0050] In some embodiments, such as Figures 6 to 9 As shown, the steel-concrete frame connection structure also includes a support assembly 8, which includes a guide frame 81 with a U-shaped groove configured to allow the steel beam 9 to be inserted into the U-shaped groove from the opening; the support assembly 8 is connected to multiple embedded sleeves 2 by multiple support mounting bolts 87.
[0051] It should be noted that the guide frame 81 includes a bottom connecting part and two side frames respectively arranged on both sides of the bottom connecting part, so that the guide frame 81 as a whole forms an open U-shaped structure at the top. A steel beam accommodating space and a connection operation space are formed between the two side frames.
[0052] The U-shaped mounting guide frame 81 is provided with four mounting holes 812, and the positions of the four mounting holes 812 correspond to the four embedded sleeves 2 at the four corners of the embedded connecting plate 1.
[0053] When installing the support assembly 8, the support mounting bolts 87 are passed through the mounting holes 812 and screwed into the corresponding pre-embedded sleeves 2, so that the U-shaped installation guide frame 81 is fixed on the concrete column 7. The four support mounting bolts 87 jointly bear the vertical load, overturning moment and installation eccentric load of the support assembly 8.
[0054] Mounting hole 812 is simply a through hole provided on the U-shaped mounting guide 81, and support mounting bolt 87 is an independent fastener that passes through mounting hole 812 and is threadedly connected to the pre-embedded sleeve 2. This avoids confusion between mounting hole 812 and support mounting bolt 87.
[0055] The middle area of the U-shaped mounting guide 81 remains open, so that after the supporting assembly 8 is installed on the embedded connecting plate 1, the permanent connection area of the embedded connecting plate 1 is still exposed between the two side frames. The beam end connecting plate 91 can pass through or enter this open area and directly fit against the embedded connecting plate 1 without being obstructed by the U-shaped mounting guide 81.
[0056] Furthermore, an inclined guide surface 811 is provided at the opening of the U-shaped groove. The two inclined guide surfaces 811 gradually converge from top to bottom toward the space to accommodate the steel beam, forming a flared inlet that is wider at the top and narrower at the bottom, which facilitates the installation of the steel beam 9.
[0057] When the steel beam 9 is hoisted and lowered by the lifting equipment, if there is a certain lateral deviation between the end of the steel beam 9 and the supporting component 8, the lower flange of the steel beam 9 or the beam end connecting plate 91 can first contact the inclined guide surface 811 and slide along the inclined guide surface 811 towards the middle of the U-shaped mounting guide frame 81, thereby entering above the supporting plate 83.
[0058] It should be noted that the inclined guide surface 811 is mainly used for rough guidance and collision prevention during the steel beam hoisting process, and does not constitute a precision adjustment mechanism for the steel beam in the X or Y direction. The horizontal position of the steel beam is still determined by the hoisting equipment, construction surveying, and the dimensions of the steel beam itself.
[0059] In some embodiments, the support assembly 8 further includes a lifting movable plate 82 and a lifting drive 85. The lifting movable plate 82 is located in the U-shaped groove. The lifting drive 85 is fixedly installed at the bottom of the support assembly 8 and connected to the lifting movable plate 82, and is used to drive the lifting movable plate 82 to move vertically in the U-shaped groove.
[0060] Specifically, the lifting drive component 85 can be a hydraulic cylinder, an electric push rod, a mechanical screw lifting mechanism, or other drive devices capable of outputting vertical thrust.
[0061] When the lifting drive component 85 extends, it pushes the lifting movable plate 82 to move upward; when the lifting drive component 85 retracts, the lifting movable plate 82 moves downward.
[0062] Furthermore, the lifting movable plate 82 forms a vertical sliding engagement with the U-shaped mounting guide frame 81 through multiple lifting guide rods 86. The lifting guide rods 86 are used to withstand the lateral forces during the lifting process and limit the tilt of the lifting movable plate 82, so that the lifting movable plate 82, the reaction force detection component 84, and the support plate 83 maintain a stable vertical lifting trajectory.
[0063] The lifting mechanism in this scheme is mainly used to adjust the installation elevation of steel beam 9 and to bear the vertical load of the steel beam.
[0064] In some embodiments, the lifting movable plate 82 is further provided with a reaction force detection element 84, and a support plate 83 is provided on the reaction force detection element 84. The support plate 83 is used to support the steel beam 9.
[0065] Specifically, the support plate 83 is positioned above the lifting movable plate 82, and its upper surface is used to support the lower flange of the steel beam 9. The support plate 83 has a corresponding support area along the width direction of the steel beam 9 to avoid excessive concentration of support reaction force.
[0066] The reaction force detection element 84 is set between the support plate 83 and the lifting movable plate 82, and preferably adopts a pressure-type weighing sensor, a pressure-type force sensor or other detection element that can detect vertical pressure.
[0067] One, two, or more reaction force detection elements 84 can be set. When multiple reaction force detection elements 84 are set, they are arranged at intervals along the width or length of the support plate 83. This can detect the total support reaction force and determine whether the steel beam 9 is eccentrically loaded based on the detection values of different reaction force detection elements 84.
[0068] The load formed by the steel beam 9 is sequentially transferred to the concrete column 7 through the support plate 83, the reaction force detection piece 84, the lifting movable plate 82, the lifting drive piece 85, the U-shaped installation guide frame 81, the support installation bolt 87, the embedded sleeve 2, the embedded connecting plate 1, and the anchor bar 11.
[0069] During the hoisting process, when the support reaction force detected by the reaction force detection component 84 reaches the predetermined range and remains stable, it indicates that the steel beam 9 has been reliably supported by the support component 8. The hoisting equipment can release the wire rope load appropriately according to the construction plan, but necessary hoisting safety measures should still be retained before the permanent connection is completed.
[0070] In some embodiments, the steel beam 9 is an H-beam, with beam end connecting plates 91 at both ends; the beam end connecting plate 91 has multiple connecting through holes, and the pre-embedded connecting plate 1 has threaded connecting holes at corresponding positions; the beam end connecting plate 91 and the pre-embedded connecting plate 1 are fixedly connected by connecting bolts.
[0071] like Figure 10 and Figure 11 As shown, the steel beam 9 includes a web, an upper flange, and a lower flange, with beam end connecting plates 91 fixedly installed at both ends. The beam end connecting plates 91 are preferably perpendicular or substantially perpendicular to the axis of the steel beam 9 and are connected to the web and flanges of the steel beam 9 by welding. The design length of the steel beam 9 is adapted to the node spacing between the two concrete columns 7. The horizontal position of the steel beam 9 and the beam end spacing are mainly controlled by the steel beam fabrication dimensions, concrete column positioning, and hoisting by lifting equipment. After the steel beam 9 is hoisted between the two concrete columns 7, both ends of it enter the U-shaped installation guide frame 81 of the corresponding support component 8, and the lower flange of the steel beam 9 is supported on the support plate 83.
[0072] Control the lifting drive 85 of the two supporting components 8 to adjust the height and level of both ends of the steel beam 9, so that the two beam end connecting plates 91 are respectively attached to the corresponding pre-embedded connecting plates 1. Before attachment, concrete laitance, rust, burrs and other protrusions on the surface of the pre-embedded connecting plates 1 should be removed to avoid the formation of non-design gaps between the beam end connecting plates 91 and the pre-embedded connecting plates 1.
[0073] It should be noted that the permanent connection area of the pre-embedded connecting plate 1 can remain as an intact plate surface without holes before concrete pouring. After the steel beam 9 is hoisted, its height is adjusted, and the beam end connecting plate 91 is attached to the pre-embedded connecting plate 1, connection holes are then machined on-site on the pre-embedded connecting plate 1 according to the actual position of the beam end connecting plate 91.
[0074] In one embodiment, a connecting through hole is pre-formed on the beam end connecting plate 91. After the beam end connecting plate 91 is attached to the embedded connecting plate 1, the connecting through hole on the beam end connecting plate 91 is used as a drilling guide to drill and tap a threaded connecting hole on the embedded connecting plate 1 in the field. The permanent connecting bolt passes through the connecting through hole on the beam end connecting plate 91 and is screwed into the threaded connecting hole of the embedded connecting plate 1.
[0075] It should be noted that the embedded connecting plate 1 should have a plate thickness and effective thread engagement length that meet the requirements for threaded connection strength. The thickness of the embedded connecting plate 1, the diameter of the hole to be machined on site, the thread specification, and the number of bolts should be determined based on structural calculations of the shear force, axial force, and bending moment borne by the node.
[0076] In another embodiment, after drilling holes on the pre-embedded connecting plate 1 on site, anchor holes can be drilled into the concrete column 7, and the beam end connecting plate 91 and the pre-embedded connecting plate 1 can be clamped and connected by a post-installed anchoring connector that meets the structural design requirements.
[0077] It should be noted that, according to design requirements, after the threaded fastening connection is completed, the joint between the beam end connecting plate 91 and the pre-embedded connecting plate 1 can be welded so that the threaded fastening connection and welding together form a permanent connection.
[0078] The location of the on-site processing connection hole should be in the permanent connection area of the pre-embedded connection plate 1, and should avoid the pre-embedded sleeve 2 located at the four corners, the anchor bar 11 on the back of the pre-embedded connection plate 1, and the main load-bearing steel bars in the concrete column 7.
[0079] By machining the connection holes on-site after the beam end connecting plate 91 and the pre-embedded connecting plate 1 have been fitted and positioned, it is not necessary to ensure that the pre-made holes on the pre-embedded connecting plate 1 and the connection holes on the beam end connecting plate 91 are strictly aligned before hoisting. This can absorb a certain range of pre-embedded construction deviations and steel beam processing deviations.
[0080] It should be noted that after the beam end connecting plate 91 and the pre-embedded connecting plate 1 are permanently connected and pass inspection, the lifting drive component 85 is retracted, causing the lifting movable plate 82, reaction force detection component 84, and support plate 83 to move downwards. As the support plate 83 descends, the load on the steel beam 9 is gradually transferred from the support component 8 to the permanent connection node. Construction personnel can confirm that the support reaction force on the support component 8 has been significantly reduced or eliminated based on the detection value of the reaction force detection component 84. After the external equipment takes necessary anti-fall support measures for the support component 8, the support mounting bolt 87 is unscrewed from the pre-embedded sleeve 2, separating the U-shaped installation guide frame 81 from the concrete column 7. Since the top of the U-shaped installation guide frame 81 is an open structure, the dismantled support component 8 does not need to be pulled out along the length of the steel beam 9, but can be moved directly downwards, allowing the two side frames to detach from both sides of the steel beam 9. The support component 8 can then be transferred to the next steel beam installation node for reuse.
[0081] See Figure 1-11 Another embodiment of this application provides a construction method for a reinforced concrete frame, characterized by comprising: S1, Rigid Embedded Assembly Fabrication Fabricate pre-embedded connecting plate 1, pre-embedded sleeve 2, and anchor bar 11 according to the design location of the steel-concrete frame node.
[0082] Four embedded sleeves 2 are fixed at the four corners of the embedded connecting plate 1, so that the open end of each embedded sleeve 2 is flush or nearly flush with the exposed surface of the embedded connecting plate 1. Anchor bars 11 are fixed to the embedded surface of the embedded connecting plate 1 to form a rigid embedded assembly.
[0083] Check the flatness of the pre-embedded connecting plate 1, the relative positions of the four pre-embedded sleeves 2 and the integrity of the internal threads, and determine the field drilling connection area in the middle of the pre-embedded connecting plate 1.
[0084] S2. Reinforcing cage installation and formwork opening The rigid pre-embedded assembly is placed at the designed node position of the reinforcing cage 6, so that the anchor bars 11 extend into the interior of the reinforcing cage 6. The rigid pre-embedded assembly can be initially held on the reinforcing cage 6 by binding.
[0085] Based on the design positions of the embedded sleeves 2, template through holes corresponding to the four embedded sleeves 2 are machined on the column template 5. The positions of the template through holes also serve as the positioning references for the planar positions of the embedded connecting plate 1.
[0086] S3, Positioning frame installation and pre-embedded assembly tightening The detachable positioning frame 3 is set on the outside of the column template 5, so that the through hole on the detachable positioning frame 3, the template through hole on the column template 5, and the opening of the pre-embedded sleeve 2 correspond to each other.
[0087] Pass the tension bolts 4 sequentially through the detachable positioning frame 3 and the column template 5, and screw them into the embedded sleeve 2. Tighten the four tension bolts 4 in a diagonal and phased manner, and then pull the embedded connecting plate 1 evenly toward the column template 5.
[0088] Check whether the embedded connecting plate 1 is completely attached to the inner surface of the column formwork 5, whether the detachable positioning frame 3 is stable, and the tightness of the four tension bolts 4. This step only involves tensioning in the direction perpendicular to the column formwork 5, without adjusting in the X or Y direction through the detachable positioning frame 3.
[0089] S4. Concrete pouring and formwork removal While keeping the detachable positioning frame 3 and the tension bolts 4 in the installed state, pour concrete and vibrate and cure it according to the construction requirements.
[0090] After the concrete reaches the demolding condition, first unscrew the tension bolts 4 and remove the detachable positioning frame 3, then remove the column formwork 5, so that the openings of the embedded connecting plate 1 and the embedded sleeve 2 are exposed.
[0091] Clean the residual laitance on the surface of the embedded connecting plate 1, and check the exposed position, flatness and thread condition of the embedded connecting plate 1 and the embedded sleeve 2.
[0092] The reinforcing cage 6 is set within the casting space enclosed by the column formwork 5. The rigid pre-embedded assembly is located outside the reinforcing cage 6 or partially inserted inside the reinforcing cage 6, and its anchor bars 11 extend into the interior of the reinforcing cage 6.
[0093] The rigid pre-embedded assembly can be temporarily tied to the steel cage 6 to limit its swaying during the pouring process; its final position and formwork status are mainly maintained by the detachable positioning frame 3 and the tension bolts 4.
[0094] During concrete pouring and vibration, the lateral pressure of the concrete on the embedded connecting plate 1 can be transmitted to the detachable positioning frame 3 and column formwork 5 through the tension bolt 4, thereby reducing the possibility of the embedded connecting plate 1 retreating into the column or tilting.
[0095] After the concrete reaches the specified strength, first unscrew the tension bolt 4 from the embedded sleeve 2, and then remove the detachable positioning frame 3 and column formwork 5. After demolding, the embedded connecting plate 1 is exposed on the surface of the concrete column 7, and its exposed surface is flush or basically flush with the surface of the concrete column 7. The openings of the four embedded sleeves 2 can be used directly from the outside of the concrete column 7.
[0096] S5, Support Component Installation Move the support component 8 to the outside of the pre-embedded connecting plate 1 so that the four through holes on the U-shaped mounting guide frame 81 correspond to the four pre-embedded sleeves 2 respectively.
[0097] Pass the four support mounting bolts 87 through the through holes and screw them into the pre-embedded sleeves 2. Tighten them gradually in a diagonal sequence to reliably fix the U-shaped mounting guide frame 81 onto the concrete column 7.
[0098] Install the support components 8 on the two concrete columns 7 at both ends of the steel beam 9, and check the initial height of the two support plates 83.
[0099] S6 and H-beam hoisting and beam lowering Using lifting equipment, the steel beam 9 is hoisted between the two concrete columns 7, so that both ends of the steel beam 9 are located above the two supporting components 8.
[0100] Gradually lower the steel beam 9. If there is a lateral deviation at the end of the steel beam, the corresponding part of the steel beam 9 will contact the inclined guide surface 811 and enter the middle of the U-shaped installation guide frame 81 under the guidance of the inclined guide surface 811.
[0101] Continue lowering steel beam 9 until its lower flange rests on support plate 83. After confirming that reaction force detection device 84 has generated a stable reaction force signal, release the load on the steel beam appropriately using the lifting equipment.
[0102] S7. Steel beam elevation adjustment and connection surface fitting The lifting drive components 85 at both ends of the steel beam 9 are controlled respectively to make the lifting movable plate 82, the reaction force detection component 84 and the support plate 83 move vertically along the lifting guide rod 86.
[0103] Based on the design elevation, levelness, and test results of the reaction force test piece 84 of the steel beam, adjust the support height at both ends of the steel beam so that the beam end connecting plate 91 fits into the corresponding pre-embedded connecting plate 1.
[0104] This step involves vertical lifting and lowering adjustment only via the support assembly 8. The lateral and longitudinal positions of the steel beam 9 are roughly positioned using lifting equipment and manual assistance; the support assembly 8 does not have an active longitudinal or lateral adjustment mechanism for the steel beam.
[0105] S8, Field Drilling and Permanent Connection With the beam end connecting plate 91 and the embedded connecting plate 1 in close contact, and the steel beam 9 stably supported by the supporting component 8, mark the on-site machining hole positions on the embedded connecting plate 1 according to the position of the connecting hole on the beam end connecting plate 91.
[0106] Drill holes directly through the connecting holes on the beam end connecting plate 91, or mark the hole positions and temporarily create a drilling operation gap, and process the connecting holes in the permanent connection area of the pre-embedded connecting plate 1.
[0107] When using on-site drilling and tapping, the permanent connection bolts are passed through the beam end connecting plate 91 and screwed into the threaded connection holes on the pre-embedded connecting plate 1. When using post-installed anchoring, anchoring holes are formed according to the structural design requirements, and the corresponding anchoring connectors are installed.
[0108] After the threads are tightened, the beam end connecting plate 91 and the embedded connecting plate 1 are welded according to the node design requirements. After all permanent connections are completed, the thread tightening status, weld quality, and fit between the beam end connecting plate 91 and the embedded connecting plate 1 are checked.
[0109] S9. Load transfer and removal of supporting components The lifting drive component 85 is retracted, causing the support plate 83 to descend. The detection value of the reaction force detection component 84 is observed to confirm that the load of the steel beam 9 has been transferred to the permanent connection node.
[0110] By using an external lifting device to support the support component 8, the four support mounting bolts 87 are removed in sequence to separate the support component 8 from the pre-embedded sleeve 2.
[0111] Control the support assembly 8 to move downwards, causing the U-shaped installation guide frame 81 to detach from both sides of the steel beam 9, and then transfer the support assembly 8 to the next node.
[0112] S10. Installation and quality verification of continuous steel beams Install the next steel beam 9 sequentially along the length or height of the reinforced concrete frame, repeating the process of installing the support component 8, hoisting the steel beam, vertical adjustment, on-site drilling, permanent connection, and dismantling the support component.
[0113] During construction, the position and exposed flatness of the pre-embedded connecting plate 1, the tightness of the support installation bolts 87, the test value of the reaction force test piece 84, the elevation and levelness of the steel beam 9, and the quality of the permanent node connection should be checked.
[0114] In summary, this application has the following beneficial effects: (1) By assembling the pre-embedded connecting plate 1, the four corner pre-embedded sleeves 2 and the anchor bar 11 into a rigid pre-embedded assembly, and using the detachable positioning frame 3 and the tension bolt 4 set on the outside of the column formwork 5, the pre-embedded connecting plate 1 is directly tightened to the inner surface of the column formwork 5, which solves the problem that the pre-embedded connecting plate is easy to retreat into the column, tilt or be covered by the concrete slurry layer during concrete pouring and vibration, and improves the positional accuracy, exposed flatness and node construction quality of the pre-embedded connecting plate 1.
[0115] (2) By making the open end of the pre-embedded sleeve 2 flush with the exposed surface of the pre-embedded connecting plate 1, and by using the tension bolt 4 to occupy the opening of the pre-embedded sleeve 2, while making the pre-embedded connecting plate 1 close to the column formwork 5, the flow channel of concrete slurry into the pre-embedded sleeve 2 is reduced, thus solving the problem of slurry blockage at the opening of the sleeve and difficulty in installing bolts after demolding.
[0116] (3) By connecting the same set of pre-embedded sleeves 2 to the detachable positioning frame 3 before concrete pouring and connecting the support component 8 after concrete demolding, the pre-embedded sleeves 2 can sequentially bear the pre-embedded positioning interface and the temporary support interface of the steel beam, thus solving the problems of separate setting of the pre-embedded positioning structure and the steel beam support structure, complex node construction and large workload of temporary support installation, and realizing the reuse of the same pre-embedded interface in different construction stages.
[0117] (4) By setting the U-shaped installation guide frame 81 as an open structure at the top and forming an operating space between the two side frames that can expose the permanent connection area of the pre-embedded connection plate 1, the steel beam 9 can enter the support component 8 from above, the beam end connection plate 91 can directly fit with the pre-embedded connection plate 1, and the support component 8 can be disengaged from the steel beam after the permanent connection is completed. This solves the problem that the closed support structure is easy to block the permanent node and difficult to remove after the connection is completed.
[0118] (5) By setting an inclined guide surface 811 with opposite arrangement on the top of the U-shaped installation guide frame 81, a steel beam inlet with a wide top and narrow bottom is formed, so that the steel beam 9 being hoisted and lowered can be guided to the support plate 83 when there is a certain lateral deviation, thereby reducing the risk of rigid collision between the end of the steel beam and the concrete column 7, the pre-embedded connecting plate 1 and the support component 8.
[0119] (6) The lifting movable plate 82, the reaction force detection piece 84 and the support plate 83 are driven to rise and fall vertically by the lifting drive component 85, and the lifting guide rod 86 is used to limit the tilt of the lifting movable plate 82, so that the support component 8 can complete the elevation adjustment and stable support of the steel beam 9 without setting a complex three-way adjustment mechanism, simplifying the structure of the support component 8 and adapting to the installation conditions where the length of the steel beam and the column spacing are basically matched.
[0120] (7) By setting a reaction force detection piece 84 between the support plate 83 and the lifting movable plate 82, the vertical support reaction force of the steel beam 9 acting on the support component 8 can be directly detected, which solves the problem that it is difficult to judge whether the steel beam has been stably lowered, whether there is an off-center load, and whether the load has been transferred after the permanent connection is completed by relying solely on manual observation, thereby improving the judgment and safety of the steel beam hoisting, connection and support component dismantling process.
[0121] (8) After the beam end connecting plate 91 and the pre-embedded connecting plate 1 are actually fitted and positioned, the connecting hole is processed on the pre-embedded connecting plate 1 according to the position of the beam end connecting plate 91. This solves the problem that the precast hole is difficult to accurately correspond after the accumulation of concrete column construction deviation, pre-embedded plate positioning deviation and steel beam processing error. It can also form a permanent node by thread fastening or by combining thread fastening and welding.
[0122] (9) By following the construction process of “pre-embedded positioning - concrete pouring - installation of supporting components with the same sleeve - vertical adjustment of steel beam - on-site drilling for permanent connection - downward removal of supporting components”, the quality control of concrete construction, temporary support of steel beam and permanent node installation are continuously connected, reducing the long-term suspension of steel beam, scaffolding erection and temporary support plate welding, and improving the construction efficiency of steel-concrete frame nodes and the reuse rate of supporting components.
[0123] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this application, and not to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of this application, and they should all be covered within the scope of the claims and specification of this application. In particular, as long as there is no contradiction or conflict, the various technical features mentioned in the various embodiments can be combined in any way. This application is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims
1. A construction device for the outer side of a municipal bridge railing, mainly used for connecting concrete columns (7) and steel beams (9) in a reinforced concrete frame, characterized in that, include: An embedded connecting plate (1) has multiple anchor bars (11) on its inner side, and the anchor bars (11) are fixedly connected to the steel cage (6) in the concrete column (7). Multiple embedded sleeves (2) are arranged around the inner periphery of the embedded connecting plate (1), and the embedded sleeves (2) have internal threads; Multiple tension bolts (4) are provided, each of which corresponds to one of the multiple embedded sleeves (2). The tension bolts (4) are configured to be threadedly connected to the embedded sleeves (2).
2. The construction device for the outer side of a municipal bridge railing as described in claim 1, characterized in that: The pre-embedded connecting plate (1) is rectangular and has holes at the four corners. Each hole is equipped with a pre-embedded sleeve (2). The pre-embedded sleeve (2) shall not protrude from the outer side of the pre-embedded connecting plate (1).
3. The construction device for the outer side of a municipal bridge railing as described in claim 2, characterized in that: The steel-concrete frame connection structure also includes a detachable positioning frame (3). The detachable positioning frame (3) has a through hole at the corresponding position of the pre-embedded sleeve (2). The tension bolt (4) passes through the corresponding through hole and is then connected to the pre-embedded sleeve (2).
4. The construction device for the outer side of a municipal bridge railing as described in claim 1, characterized in that: The steel-concrete frame connection structure also includes a support assembly (8), which includes a guide frame (81) having a U-shaped groove configured to allow the steel beam (9) to be inserted into the U-shaped groove from the opening; the support assembly (8) is connected to multiple embedded sleeves (2) by multiple support mounting bolts (87).
5. The construction device for the outer side of a municipal bridge railing as described in claim 4, characterized in that: An inclined guide surface (811) is provided at the opening of the U-shaped groove.
6. The construction device for the outer side of a municipal bridge railing as described in claim 4, characterized in that: The supporting component (8) further includes a lifting movable plate (82) and a lifting drive component (85). The lifting movable plate (82) is located in the U-shaped groove. The lifting drive component (85) is fixedly installed at the bottom of the supporting component (8) and connected to the lifting movable plate (82) for driving the lifting movable plate (82) to move vertically in the U-shaped groove.
7. The construction device for the outer side of a municipal bridge railing as described in claim 6, characterized in that: The bottom of the lifting movable plate (82) is equipped with multiple lifting guide rods (86), and the lifting guide rods (86) are slidably connected to the guide frame (81) in the vertical direction.
8. The construction device for the outer side of a municipal bridge railing as described in claim 7, characterized in that: The lifting movable plate (82) is also equipped with a reaction force detection component (84), and the reaction force detection component (84) is equipped with a support plate (83), which is used to support the steel beam (9).
9. The construction device for the outer side of a municipal bridge railing as described in claim 1, characterized in that: The steel beam (9) is an H-beam, and both ends are equipped with beam end connecting plates (91); the beam end connecting plate (91) is provided with multiple connecting through holes, and the pre-embedded connecting plate (1) is provided with threaded connecting holes at corresponding positions. The beam end connecting plate (91) and the pre-embedded connecting plate (1) are fixedly connected by connecting bolts.
10. A construction method for a steel-concrete frame, characterized in that, include: S1. Rigid pre-embedded assembly fabrication: fabricate pre-embedded connecting plate (1), pre-embedded sleeve (2) and anchor bar (11), fix multiple pre-embedded sleeves (2) to the periphery of the inner side of the pre-embedded connecting plate (1) respectively; fix multiple anchor bars (11) to the inner pre-embedded surface of the pre-embedded connecting plate (1) to form a rigid pre-embedded assembly. S2, Reinforcing cage installation and template opening: Arrange the rigid pre-embedded assembly at the design node position of the reinforcing cage (6) and initially connect the rigid pre-embedded assembly to the reinforcing cage (6); According to the position of the pre-embedded sleeve (2), process template through holes corresponding to each pre-embedded sleeve (2) on the column template (5); S3. Installation of positioning frame and tightening of pre-embedded assembly: Set the detachable positioning frame (3) on the outside of the column template (5), pass the tightening bolt (4) through the detachable positioning frame (3) and the column template (5) in sequence, and screw it into the corresponding pre-embedded sleeve (2); tighten each tightening bolt (4), and pull the pre-embedded connecting plate (1) evenly toward the inner surface of the column template (5); S4. Concrete pouring and formwork removal: Pour concrete, and vibrate and cure it; after the concrete reaches the formwork removal conditions, first unscrew the tension bolts (4) and remove the detachable positioning frame (3), and then remove the column formwork (5). S5. Installation of support components: Install support components (8) on two adjacent concrete columns (7), install the support components (8) on the outside of the pre-embedded connecting plate (1), so that the mounting holes (812) of the U-shaped mounting guide frame (81) on the support components (8) correspond to the pre-embedded sleeve (2); pass the support mounting bolts (87) through the corresponding mounting holes (812) and screw them into the corresponding pre-embedded sleeves (2) to tighten them, so that the U-shaped mounting guide frame (81) is fixed on the concrete column (7); S6. Steel beam hoisting and guide beam lowering: Use lifting equipment to hoist the steel beam (9) between two adjacent concrete columns (7), so that both ends of the steel beam (9) are above the two installation guide frames (81); gradually lower the steel beam (9) so that the steel beam (9) is supported on the support plate (83); S7. Steel beam elevation adjustment and connection surface fitting: Control the lifting drive (85) of the two supporting components (8) respectively, adjust the support height of both ends of the steel beam (9) according to the design elevation and level of the steel beam, so that the beam end connecting plate (91) at both ends of the steel beam (9) fits with the corresponding pre-embedded connecting plate (1); S8. On-site drilling and permanent connection: According to the position of the connection hole on the beam end connection plate (91), mark the on-site processing hole position on the pre-embedded connection plate (1); drill directly through the connection hole on the beam end connection plate (91), and screw the permanent connection bolt through the beam end connection plate (91) and into the drill hole on the pre-embedded connection plate (1); S9. Load transfer and support assembly removal: Control the lifting drive (85) to retract, so that the support plate (83) is lowered, and then remove the support assembly (8).