A method and system for planning the conversion route of a decommissioned generator into a camera.

By establishing a health assessment index system and a three-dimensional decision-making model for the subsystems of retired generating units, the health and performance satisfaction of each subsystem are quantitatively assessed, solving the problem of investment optimization when converting retired generating units into synchronous condensers, and achieving the most economical conversion scheme.

CN123121704APending Publication Date: 2026-11-17XIAN THERMAL POWER RES INST CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611214210.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-11
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The lack of systematic decision-making methods in existing technologies makes it difficult to optimize investment when converting decommissioned generator sets into synchronous condensers, and the design of each subsystem is not compatible with the operating conditions of the synchronous condenser.

Method used

Establish a health assessment index system for each subsystem of the decommissioned unit, quantitatively assess the health and performance satisfaction of each subsystem, construct a three-dimensional decision-making model that includes equipment health, technical performance and retrofit cost, calculate the comprehensive evaluation value, and determine the optimal retrofit route.

Benefits of technology

This approach ensures optimal overall investment economics for the renovation plan while meeting technical standards, avoiding blind decision-making, and optimizing the investment payback period and internal rate of return through full life-cycle economic assessment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123121704A_ABST
    Figure CN123121704A_ABST
Patent Text Reader

Abstract

This invention provides a method and system for planning the conversion route of decommissioned generators into synchronous condensers. The method includes: establishing a health assessment index system for each subsystem of the decommissioned unit; quantitatively assessing each subsystem to obtain a health score; determining the performance requirements of each subsystem based on the operating technical specifications of the synchronous condenser; calculating the performance satisfaction score of each subsystem based on the gap between its current performance and the required performance; constructing a decision model based on the performance satisfaction scores of each subsystem, incorporating three elements: equipment health, technical performance, and conversion cost; calculating a comprehensive evaluation value for each subsystem; and determining the optimal conversion route for each subsystem based on the comprehensive evaluation value, thus forming a conversion plan. This transforms complex engineering, technical, and economic decisions into a quantifiable, calculable, and verifiable standardized process, achieving optimal economic efficiency for overall investment and avoiding blind decision-making.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of power supply technology and relates to a method and system for planning the conversion route of a decommissioned generator into a synchronous condenser. Background Technology

[0002] Converting retired thermal power units into synchronous condensers is an effective way to revitalize idle assets and enhance the reactive power support capacity of the power grid. Moreover, the cost of renovating existing units is far lower than that of building new synchronous condensers. The cost of renovating a 150MW generator is only 20%-30% of that of building a new one.

[0003] Upgrading decommissioned generating units involves complex technical decisions. The design of the original unit's various subsystems is not compatible with the operating conditions of the synchronous condenser, and the lack of a systematic decision-making method makes it difficult to achieve the optimal economic efficiency of the upgrade.

[0004] There are two existing cases of generators being converted into synchronous condensers in China. In-service generator units were modified to also function as synchronous condensers. The original generator's lubrication system, cooling system, and control system were designed for power generation, which is quite different from the operating condition of a synchronous condenser, which operates in pure reactive power.

[0005] Existing technologies are for retrofitting in-service units, which is fundamentally different from the most economical technical route for extending the life of retired units by adjusting the camera. For retired units, there is currently no mature method to systematically decide on the reuse, retrofitting, or new construction of each subsystem, making it impossible to achieve optimal investment. Summary of the Invention

[0006] The purpose of this invention is to provide a method and system for planning the conversion route of retired generators into synchronous condensers, so as to solve the problem of lack of systematic decision-making methods and difficulty in achieving investment optimization in the conversion of existing retired units.

[0007] To achieve the above objectives, the present invention adopts the following technical solution: In a first aspect, the present invention provides a method for planning the conversion route of a decommissioned generator into a camera, comprising: Establish a health assessment index system for each subsystem of the decommissioned unit, conduct quantitative assessments of each subsystem, and obtain a health score for each subsystem; Based on the technical specifications for synchronous condenser operation, the performance requirements of each subsystem are determined, and the performance satisfaction score of each subsystem is calculated based on the gap between the existing performance and the required performance. Based on the performance satisfaction scores of each subsystem, a decision model is constructed that includes three elements: equipment health, technical performance, and transformation cost. A comprehensive evaluation value is then calculated for each of the subsystems. Based on the comprehensive evaluation value, the optimal transformation route for each subsystem is determined, and a transformation plan is formed.

[0008] Furthermore, the establishment of a health assessment index system for each subsystem of the decommissioned unit, the quantitative assessment of each subsystem, and the resulting health score for each subsystem include: The decommissioned generator unit is divided into subsystems: generator body, excitation system, lubrication system, cooling system and control system. A health assessment index is established for each subsystem. Each index is scored from 0 to 10, with 0 being complete failure and 10 being brand new. The health score H of each subsystem is calculated by weighting.

[0009] Furthermore, health assessment indicators are established for each subsystem, including: Generator body: stator winding insulation resistance, dielectric loss factor, partial discharge, rotor inter-turn short circuit condition, core insulation resistance, bearing wear; Excitation system: aging degree of rectifier components, wear of demagnetizing switch contacts, insulation resistance of excitation transformer, and service life of control board components; Lubricating oil system: oil pump motor insulation, oil pump efficiency, pipeline corrosion, oil cooler heat exchange efficiency, oil tank cleanliness; Cooling system: water pump efficiency, cooling tower packing aging, heat sink corrosion, fan vibration value; Control system: DCS controller load rate, I / O module channel integrity rate, communication bus bit error rate, operator station response time.

[0010] Furthermore, based on the technical specifications for synchronous condenser operation, the performance requirements of each subsystem are determined, and the performance satisfaction score of each subsystem is calculated based on the gap between its current performance and the required performance, including: Taking a certain generating unit as an example, the technical requirements for its subsystems when converted to synchronous condenser operation include: Generator body: reactive power regulation capacity ≥118Mvar, stator overload capacity 3.5 times / 15s, rotor overload capacity 2.5 times / 15s; Excitation system: delay time ≤ 0.02s, strong excitation rise time ≤ 0.02s, strong deceleration fall time ≤ 0.025s; Lubricating oil system: oil supply pressure 0.1-0.25MPa, oil supply temperature 40-45℃, oil pump standby rate 100%; Cooling system: Cooling water flow rate, inlet and outlet temperature rise, and heat exchange efficiency meet the rated loss heat dissipation requirements of the synchronous condenser; Control system: Response time, control accuracy, and human-machine interaction functions meet the operating requirements of the synchronous condenser; Based on the gap between the existing performance and the required performance of each subsystem, calculate the performance satisfaction score P, ranging from 0 to 10, with 10 indicating complete satisfaction.

[0011] Furthermore, a decision model is constructed based on the performance satisfaction scores of each subsystem, incorporating three elements: equipment health, technical performance, and modification cost. A comprehensive evaluation value is calculated for each subsystem, including: Calculate the comprehensive evaluation value corresponding to the reuse plan, renovation plan, and new construction plan for each of the subsystems. Establish a three-dimensional decision space and define the comprehensive evaluation value F: F = αH + βP + γC Wherein, H is the health score (0-10), P is the performance satisfaction score (0-10), C is the cost score, and the cost score is normalized based on the renovation cost, with lower costs resulting in higher scores. α, β, and γ are weighting coefficients, and α+β+γ=1.

[0012] Furthermore, the values ​​of α, β, and γ are determined based on the project objectives: if the goal is to maximize the reuse of existing materials, α is chosen to be high; if the goal is to achieve technical performance standards, β is chosen to be high; if the goal is to minimize investment, γ is chosen to be high.

[0013] Furthermore, determining the optimal modification route for each subsystem based on the comprehensive evaluation value to form a modification plan includes: The aforementioned reuse scheme refers to the direct retention and use of the subsystem without any processing. The aforementioned modification plan refers to the overhaul, component replacement, or performance upgrade of the subsystem. The new plan refers to completely replacing the atomic system with new equipment.

[0014] For each subsystem, compare the values ​​of Freuse, Fmodify, and Fnew, and take the route corresponding to the maximum value as the optimal modification route for that subsystem.

[0015] Calculate the total initial investment for the overall renovation plan; Calculate the payback period and internal rate of return based on the projected revenue from synchronous condenser operation. If the investment payback period exceeds the set threshold or the internal rate of return is lower than the benchmark value, the weighting coefficients are adjusted and the optimization is repeated until the economic requirements are met.

[0016] Secondly, the present invention provides a route planning system for converting retired generators into camera converters, comprising: The quantitative assessment module is used to establish a health assessment index system for each subsystem of the decommissioned unit, to conduct quantitative assessment of each subsystem, and to obtain the health score of each subsystem. The satisfaction calculation module is used to determine the performance requirements that each subsystem needs to achieve based on the technical specifications of the synchronous condenser operation, and to calculate the performance satisfaction score of each subsystem based on the gap between the existing performance and the required performance. The comprehensive calculation module is used to construct a decision model that includes three elements: equipment health, technical performance, and transformation cost, based on the performance satisfaction scores of each subsystem, and to calculate the comprehensive evaluation value for each subsystem. The output module is used to determine the optimal transformation route for each subsystem based on the comprehensive evaluation value, and to form a transformation plan.

[0017] Thirdly, the present invention provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the steps of the method for planning the conversion route of a decommissioned generator to a camera.

[0018] Fourthly, the present invention provides a computer-readable storage medium storing a computer program, which, when executed by a processor, implements the steps of the method for planning the conversion route of a decommissioned generator to a camera.

[0019] Compared with the prior art, the present invention has the following technical effects: This application transforms the decision-making process from fuzzy judgment to precise calculation through quantitative evaluation, three-dimensional decision-making, and economic verification.

[0020] Specifically, this method first quantifies and scores the health status and technical performance of each subsystem, including the generator body, excitation system, and lubrication system. Then, it integrates health status, performance satisfaction, and modification cost into a comprehensive decision-making model, simultaneously calculating the combined score for each subsystem across three routes: reuse, modification, and new construction. This score reflects the performance return achievable at a given cost under specific equipment conditions; based on this, the highest-scoring route for each subsystem is automatically selected, and the results are aggregated to form the overall plan. Finally, a full life-cycle economic assessment is conducted to calculate the investment payback period and internal rate of return, performing a final verification of the plan. If the economic performance fails to meet the standards, the decision weights are automatically adjusted, and a new optimization is sought.

[0021] By transforming complex engineering, technical, and economic decisions into standardized processes that are quantifiable, calculable, and verifiable, the renovation plan achieves optimal economic efficiency for the overall investment while meeting technical standards, thus avoiding blind decision-making. Attached Figure Description

[0022] Figure 1 This is a flowchart of the present invention. Detailed Implementation

[0023] The present invention will be further described below with reference to the accompanying drawings: Example 1, please refer to Figure 1 This invention provides a method for planning the conversion route of a decommissioned generator into a camera, comprising: S1. Establish a health assessment index system for each subsystem of the decommissioned unit, conduct quantitative assessment of each subsystem, and obtain the health score of each subsystem. The decommissioned generator unit was disassembled into independent functional units such as the generator body, excitation system, lubrication system, cooling system, and control system. Then, a set of measurable indicators was established for each unit, collecting hard data such as stator winding insulation resistance, dielectric loss factor, partial discharge, and rotor inter-turn short circuit status. Maintenance personnel obtained raw parameters through on-site testing and offline detection, and then mapped each indicator to a score from 0 to 10 based on a preset scoring standard, where 0 represents complete failure and 10 represents brand new condition. Finally, based on the importance of each indicator to the functional safety of the subsystem, different weights were assigned, and the results were weighted and summed to obtain a comprehensive health score H. Instrumental data and quantitative scores replaced subjective judgments of approximate usability, allowing for horizontal comparisons of the status of different equipment and components, providing a unified baseline for subsequent cost calculations and scheme selection.

[0024] S2. Based on the technical specifications of the synchronous condenser operation, determine the performance requirements that each subsystem needs to achieve, and calculate the performance satisfaction score of each subsystem based on the gap between the existing performance and the required performance. The specific technical thresholds imposed on each subsystem by the synchronous condenser were identified. For example, the excitation system required a delay time and a forced excitation rise time of no more than 0.02 seconds, and the control system response time needed to be reduced to within 50 milliseconds. Then, by reviewing the original equipment nameplate parameters, historical operating curves, and conducting supplementary tests, the actual achievable performance level of each subsystem was evaluated. The gap between the actual capability and the technical threshold was converted into a performance satisfaction score P on a scale of 0 to 10, with 10 points for complete compliance. For example, the original DCS control system of a power plant had a response time of approximately 200 milliseconds, far from meeting the rapid response requirements of the synchronous condenser, resulting in a score of only 3 points. This approach transforms engineering specifications into calculable indicators, accurately identifying which subsystems can be used adequately and which are critical bottlenecks, avoiding wasting funds on areas where performance is already excessive.

[0025] S3. Construct a decision model that includes three elements: equipment health, technical performance, and transformation cost, based on the performance satisfaction scores of each subsystem, and calculate the comprehensive evaluation value for each subsystem. The decision-making model uses a three-dimensional evaluation formula: F = αH + βP + γC. H comes from the health score of S1, P from the performance satisfaction score of S2, and C is the normalized cost score. Lower investment results in a higher cost score. α, β, and γ are adjustable weighting coefficients. Three plans—reuse, modification, and new construction—are designed for each subsystem, and their respective H, P, and C values ​​are estimated and then entered into the formula for calculation. For example, for a lubricating oil system with acceptable health but slightly deficient performance, the reuse plan might have a high cost score but a low performance score. The modification plan, which requires more investment to improve the performance score, might actually result in a higher overall score than either reuse or new construction. This model-based approach transforms qualitative trade-offs based on experience into quantitative comparisons. Decision-makers can adjust the weighting coefficients and recalculate based on whether cost-saving or performance is prioritized, with the calculated score directly pointing to the option with the highest overall benefit.

[0026] S4. Determine the optimal transformation route for each subsystem based on the comprehensive evaluation value to form a transformation plan.

[0027] After calculating the three sets of F-values ​​(reuse, modification, and new construction) for each subsystem in S3, the route with the highest F-value is selected. For example, for the generator body required by the synchronous condenser, the F-value for the reuse option is 6.63, the F-value for the modification option is 8.75, and the F-value for the new construction option is 7.86. Therefore, the modification route is chosen for this subsystem. After all the routes for all subsystems are determined, they are combined to form a complete overall modification plan, at which point an overall investment estimate can be obtained. Because the decision for each subsystem is made independently after calculation and selection of the best option, the final overall plan naturally possesses the characteristic of minimizing total investment, ensuring optimal economic efficiency across the entire system.

[0028] Example 2: This invention provides a method for planning the conversion route of a decommissioned generator into a camera, comprising: S1. Establish a health assessment index system for each subsystem of the decommissioned unit and conduct quantitative assessment of each subsystem; S2. Determine the performance requirements of each subsystem based on the technical specifications of the synchronous condenser operation. S3. Construct a decision-making model that includes three elements: equipment health, technical performance, and modification cost; S4. Calculate the comprehensive evaluation value of the reuse plan, renovation plan, and new construction plan for each subsystem; S5. Determine the optimal transformation route for each subsystem based on the comprehensive evaluation value, and form an overall transformation plan; S6. Conduct a full life-cycle economic assessment of the overall renovation plan to verify its feasibility.

[0029] The decommissioned generating units are divided into subsystems, including the generator body, excitation system, lubrication system, cooling system, and control system. Health assessment indicators are established for each subsystem, including: Generator body: stator winding insulation resistance (MΩ), dielectric loss factor tanδ (%), partial discharge (pC), rotor inter-turn short circuit condition, core insulation resistance (MΩ), bearing wear (mm). Excitation system: aging degree of rectifier components, wear of demagnetizing switch contacts, insulation resistance of excitation transformer, and service life of control board components; Lubricating oil system: oil pump motor insulation, oil pump efficiency, pipeline corrosion, oil cooler heat exchange efficiency, oil tank cleanliness; Cooling system: water pump efficiency, cooling tower packing aging, heat sink corrosion, fan vibration value; Control system: DCS controller load rate, I / O module channel integrity rate, communication bus bit error rate, operator station response time; Each indicator is scored from 0 to 10, with 0 being completely ineffective and 10 being a brand new state. The health score H of each subsystem is calculated by weighting.

[0030] S2. Based on the technical specifications of the synchronous condenser, determine the performance requirements that each subsystem needs to achieve.

[0031] The technical requirements that the operation of the synchronous condenser imposes on the subsystem include: Generator body: reactive power regulation capacity ≥118Mvar, stator overload capacity 3.5 times / 15s, rotor overload capacity 2.5 times / 15s; Excitation system: delay time ≤ 0.02s, strong excitation rise time ≤ 0.02s, strong deceleration fall time ≤ 0.025s; Lubricating oil system: oil supply pressure 0.1-0.25MPa, oil supply temperature 40-45℃, oil pump standby rate 100%; Cooling system: Cooling water flow rate, inlet and outlet temperature rise, and heat exchange efficiency meet the rated loss heat dissipation requirements of the synchronous condenser; Control system: Response time, control accuracy, and human-machine interaction functions meet the operating requirements of the synchronous condenser; Based on the gap between the existing performance and the required performance of each subsystem, calculate the performance satisfaction score P (0-10 points, 10 points is fully satisfied).

[0032] S3. Construct a decision-making model that includes three elements: equipment health, technical performance, and modification cost.

[0033] Establish a three-dimensional decision space and define the comprehensive evaluation value F: F = αH + βP + γC Where H is the health score (0-10), P is the performance satisfaction score (0-10), C is the cost score (normalized according to the renovation cost, the lower the cost, the higher the score), and α, β, γ are weighting coefficients, α+β+γ=1.

[0034] The values ​​of α, β, and γ are determined based on the project objectives: if the goal is to maximize the reuse of existing equipment, a higher value for α is used; if the goal is to achieve technical performance targets, a higher value for β is used; if the goal is to minimize investment, a higher value for γ is used. Generally, a value of α=0.3, β=0.4, and γ=0.3 is recommended.

[0035] S4. Calculate the comprehensive evaluation value of the reuse plan, renovation plan, and new construction plan for each subsystem.

[0036] For each subsystem, three alternative routes are designed: Reuse option: Retain and use the existing stock without any modification. Calculate F_reuse.

[0037] Modification plan: This includes overhauling, replacing components, and upgrading performance. Calculate modification F.

[0038] New Plan: Completely replace all equipment with new equipment. Calculate F for the new plan.

[0039] The cost of the renovation plan (Crenovation) is estimated based on the actual amount of renovation work, while the cost of the new construction plan (Cnew construction) is estimated based on the equipment purchase price.

[0040] S5. Determine the optimal transformation route for each subsystem based on the comprehensive evaluation value, and form an overall transformation plan.

[0041] For each subsystem, compare the options Freuse, Fmodify, and Fbuild, and take the route corresponding to the maximum value as the optimal modification route for that subsystem. Summarize the modification routes of all subsystems to form an overall modification plan.

[0042] S6. Conduct a full life-cycle economic assessment of the overall renovation plan to verify its feasibility.

[0043] Calculate the initial total investment for the overall renovation plan. Based on the predicted revenue from synchronous condenser operation (reactive power compensation revenue, ancillary service revenue), calculate economic indicators such as the payback period and internal rate of return. If the payback period exceeds the set threshold (e.g., 6 years), or the internal rate of return is lower than the benchmark value (e.g., 8%), return to S3 to adjust the weighting coefficients and re-optimize until the economic requirements are met.

[0044] Example 3: Taking a 150MW decommissioned unit of Huaneng Zhongtai Power Plant as an example, the method of the present invention is implemented.

[0045] S1 evaluation results: Generator body: Stator winding insulation resistance value 500MΩ (the full score is ≥1000MΩ), score is 5 points; dielectric loss factor tanδ=2.5% (the full score is ≤1.5%), score is 4 points; weighted health H=4.5 points.

[0046] Lubrication system: The oil pump has good insulation and an efficiency of 85%, scoring 8 points; the pipeline has slight corrosion, scoring 7 points; the weighted average score is 7.8 points.

[0047] Control system: DCS controller load rate 85%, I / O module channel integrity rate 90%, both are 2015 products, score 5 points; weighted H=5 points.

[0048] S2 performance satisfaction assessment: Generator body: The reactive power regulation capability is assessed to reach 120Mvar, which meets the requirement of ≥118Mvar, P=9 points; the overload capacity needs to be verified, and is tentatively estimated to be P=7 points.

[0049] Lubrication system: The existing oil pump flow rate can meet the lubrication requirements of the synchronous condenser, P=9 points; however, the pressure stability needs to be optimized, P=7 points.

[0050] Control system: The existing DCS response time is about 200ms, the synchronous condenser requires ≤50ms, P=3 minutes.

[0051] S3 has weights of α=0.3, β=0.4, and γ=0.3.

[0052] Calculation of evaluation values ​​for each subsystem of S4: Generator body: Reuse Plan: H=4.5, P=7, C cost score is estimated at 7 points based on 0.1 billion yuan, F reuse = 0.3×4.5+0.4×7+0.3×7=6.15 Renovation Plan: H is assessed at 8, P at 9, C's cost score is estimated at 8 points (based on 0.05 billion yuan), F (renovation cost) = 0.3 × 8 + 0.4 × 9 + 0.3 × 8 = 8.4 New Construction Plan: H=10, P=10, C (cost score estimated at 0.3 billion yuan, 3 points), F (new construction) = 0.3 × 10 + 0.4 × 10 + 0.3 × 3 = 7.9 Take the maximum value F and modify it, then select the modification scheme.

[0053] Lubrication system: Reuse option: H=7.8, P=7, C cost score is 9 points, F reuse = 0.3×7.8+0.4×7+0.3×9=7.84 Modification plan: H=9, P=9, C (cost score) is 7 points, F (modification cost) = 0.3×9 + 0.4×9 + 0.3×7 = 8.4 New Scheme: H=10, P=10, C (cost score) is 4 points, F (new construction) = 0.3×10 + 0.4×10 + 0.3×4 = 8.2 Take the maximum value F for modification and select the modification plan (adding a frequency converter).

[0054] Control system: Reuse Plan: H=5, P=3, C (cost score) is 9 points, F (reuse) = 0.3×5 + 0.4×3 + 0.3×9 = 5.4 Modification plan: H=7, P=7, C (cost score) is 6 points, F (modification cost) = 0.3×7 + 0.4×7 + 0.3×6 = 6.7 New Scheme: H=10, P=10, C (cost score) is 3 points, F (new construction) = 0.3×10 + 0.4×10 + 0.3×3 = 7.9 Create a new scheme by taking the maximum value F.

[0055] The S5 solution comprises: generator body modification, lubrication system modification and frequency converter addition, and new control system construction, with a total estimated investment of approximately 21 million yuan.

[0056] S6 Economic Assessment: Based on an annual income of 6.56 million yuan, the investment payback period is 3.2 years, and the internal rate of return is 25%, which meets the feasibility requirements.

[0057] In another embodiment of the present invention, a modification route planning system for converting decommissioned generators into camera converters is provided, which can be used to implement the above-mentioned modification route planning method for converting decommissioned generators into camera converters. Specifically, the system includes: The quantitative assessment module is used to establish a health assessment index system for each subsystem of the decommissioned unit, to conduct quantitative assessment of each subsystem, and to obtain the health score of each subsystem. The satisfaction calculation module is used to determine the performance requirements that each subsystem needs to achieve based on the technical specifications of the synchronous condenser operation, and to calculate the performance satisfaction score of each subsystem based on the gap between the existing performance and the required performance. The comprehensive calculation module is used to construct a decision model that includes three elements: equipment health, technical performance, and transformation cost, based on the performance satisfaction scores of each subsystem, and to calculate the comprehensive evaluation value for each subsystem. The output module is used to determine the optimal transformation route for each subsystem based on the comprehensive evaluation value, and to form a transformation plan.

[0058] The module division in this embodiment of the invention is illustrative and represents only one logical functional division. In actual implementation, other division methods may be used. Furthermore, the functional modules in the various embodiments of the invention can be integrated into a single processor, exist as separate physical entities, or be integrated into a single module. The integrated modules described above can be implemented in hardware or as software functional modules.

[0059] In another embodiment of the present invention, a computer device is provided, comprising a processor and a memory. The memory stores a computer program, which includes program instructions. The processor executes the program instructions stored in the computer storage medium. The processor may be a Central Processing Unit (CPU), or other general-purpose processors, digital signal processors (DSPs), application-specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. It is the computing and control core of the terminal, suitable for implementing one or more instructions, specifically suitable for loading and executing one or more instructions in the computer storage medium to achieve a corresponding method flow or corresponding function. The processor described in this embodiment of the present invention can be used in the operation of a method for planning the conversion route of a decommissioned generator into a camera.

[0060] In another embodiment of the present invention, a storage medium is provided, specifically a computer-readable storage medium (Memory), which is a memory device in a computer device used to store programs and data. It is understood that the computer-readable storage medium here can include both the built-in storage medium in the computer device and extended storage media supported by the computer device. The computer-readable storage medium provides storage space that stores the terminal's operating system. Furthermore, the storage space also stores one or more instructions suitable for loading and execution by a processor. These instructions can be one or more computer programs (including program code). It should be noted that the computer-readable storage medium here can be high-speed RAM or non-volatile memory, such as at least one disk storage device. The processor can load and execute one or more instructions stored in the computer-readable storage medium to implement the corresponding steps of the method for planning the conversion route of a decommissioned generator to a camera in the above embodiments.

[0061] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0062] This invention is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0063] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0064] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.

[0065] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the specific implementation of the present invention. Any modifications or equivalent substitutions that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A method for planning the conversion route of a decommissioned generator into a camera, characterized in that, include: Establish a health assessment index system for each subsystem of the decommissioned unit, conduct quantitative assessments of each subsystem, and obtain a health score for each subsystem; Based on the technical specifications for synchronous condenser operation, the performance requirements of each subsystem are determined, and the performance satisfaction score of each subsystem is calculated based on the gap between the existing performance and the required performance. Based on the performance satisfaction scores of each subsystem, a decision model is constructed that includes three elements: equipment health, technical performance, and transformation cost. A comprehensive evaluation value is then calculated for each of the subsystems. Based on the comprehensive evaluation value, the optimal transformation route for each subsystem is determined, and a transformation plan is formed.

2. The method for planning the conversion route of a decommissioned generator into a camera according to claim 1, characterized in that, The establishment of a health assessment index system for each subsystem of the decommissioned unit, the quantitative assessment of each subsystem, and the resulting health score for each subsystem include: The decommissioned generator unit is divided into subsystems: generator body, excitation system, lubrication system, cooling system and control system. A health assessment index is established for each subsystem. Each index is scored from 0 to 10, with 0 being complete failure and 10 being brand new. The health score H of each subsystem is calculated by weighting.

3. The method for planning the conversion route of a decommissioned generator into a camera according to claim 2, characterized in that, Establish health assessment indicators for each subsystem, including: Generator body: stator winding insulation resistance, dielectric loss factor, partial discharge, rotor inter-turn short circuit condition, core insulation resistance, bearing wear, etc. Excitation system: aging degree of rectifier components, wear of demagnetizing switch contacts, insulation resistance of excitation transformer, service life of control board components, etc. Lubricating oil system: oil pump motor insulation, oil pump efficiency, pipeline corrosion, oil cooler heat exchange efficiency, oil tank cleanliness, etc. Cooling system: water pump efficiency, cooling tower packing aging, heat sink corrosion, fan vibration, etc. Control system: DCS controller load rate, I / O module channel integrity rate, communication bus bit error rate, operator station response time, etc.

4. The method for planning the conversion route of a decommissioned generator into a camera according to claim 1, characterized in that, Based on the technical specifications for synchronous condenser operation, the performance requirements of each subsystem are determined, and the performance satisfaction score of each subsystem is calculated based on the gap between its current performance and the required performance. This includes: The technical requirements for the operation of the synchronous condenser on the subsystem include: Generator body: reactive power regulation capacity ≥118Mvar, stator overload capacity 3.5 times / 15s, rotor overload capacity 2.5 times / 15s; Excitation system: delay time ≤ 0.02s, strong excitation rise time ≤ 0.02s, strong deceleration fall time ≤ 0.025s; Lubricating oil system: oil supply pressure 0.1-0.25MPa, oil supply temperature 40-45℃, oil pump standby rate 100%; Cooling system: Cooling water flow rate, inlet and outlet temperature rise, and heat exchange efficiency meet the rated loss heat dissipation requirements of the synchronous condenser; Control system: Response time, control accuracy, and human-machine interaction functions meet the operating requirements of the synchronous condenser; Based on the gap between the existing performance and the required performance of each subsystem, calculate the performance satisfaction score P, ranging from 0 to 10, with 10 indicating complete satisfaction.

5. The method for planning the conversion route of a decommissioned generator into a camera according to claim 1, characterized in that, The decision model, which incorporates three elements—equipment health, technical performance, and modification cost—is constructed based on the performance satisfaction scores of each subsystem. A comprehensive evaluation value is then calculated for each subsystem, including: Calculate the comprehensive evaluation value corresponding to the reuse plan, renovation plan, and new construction plan for each of the subsystems. Establish a three-dimensional decision space and define the comprehensive evaluation value F: F = αH + βP + γC Wherein, H is the health score (0-10), P is the performance satisfaction score (0-10), C is the cost score, and the cost score is normalized based on the renovation cost, with lower costs resulting in higher scores. α, β, and γ are weighting coefficients, and α+β+γ=1.

6. The method for planning the conversion route of a decommissioned generator into a camera according to claim 5, characterized in that, The values ​​of α, β, and γ are determined based on the project objectives: if the goal is to maximize the reuse of existing materials, α should be a high value; if the goal is to achieve technical performance standards, β should be a high value; if the goal is to minimize investment, γ should be a high value.

7. The method for planning the conversion route of a decommissioned generator into a camera according to claim 5, characterized in that, The step of determining the optimal modification route for each subsystem based on the comprehensive evaluation value, and forming a modification plan, includes: The aforementioned reuse scheme refers to the direct retention and use of the subsystem without any processing. The aforementioned modification plan refers to the overhaul, component replacement, or performance upgrade of the subsystem. The proposed new solution refers to completely replacing the atomic system with new equipment. For each subsystem, compare the values ​​of Freuse, Fmodify, and Fnew, and take the route corresponding to the maximum value as the optimal modification route for that subsystem; Calculate the total initial investment for the overall renovation plan; Calculate the payback period and internal rate of return based on the projected revenue from synchronous condenser operation. If the investment payback period exceeds the set threshold or the internal rate of return is lower than the benchmark value, the weighting coefficients are adjusted and the optimization is repeated until the economic requirements are met.

8. A route planning system for converting decommissioned generators into camera converters, characterized in that, include: The quantitative assessment module is used to establish a health assessment index system for each subsystem of the decommissioned unit, to conduct quantitative assessment of each subsystem, and to obtain the health score of each subsystem. The satisfaction calculation module is used to determine the performance requirements that each subsystem needs to achieve based on the technical specifications of the synchronous condenser operation, and to calculate the performance satisfaction score of each subsystem based on the gap between the existing performance and the required performance. The comprehensive calculation module is used to construct a decision model that includes three elements: equipment health, technical performance, and transformation cost, based on the performance satisfaction scores of each subsystem, and to calculate the comprehensive evaluation value for each subsystem. The output module is used to determine the optimal transformation route for each subsystem based on the comprehensive evaluation value, and to form a transformation plan.

9. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the processor executes the computer program, it implements the steps of the method for planning the conversion route of a decommissioned generator to a camera as described in any one of claims 1 to 7.

10. A computer-readable storage medium storing a computer program, characterized in that, When the computer program is executed by the processor, it implements the steps of the method for planning the conversion route of a decommissioned generator to a camera as described in any one of claims 1 to 7.