A method for self-synchronization grid connection control of N+X miniaturized diesel generator set grid connection device
By using the self-synchronization grid connection control method of the N+X miniaturized diesel generator set grid connection device, rapid and reliable emergency power supply of diesel generator sets in places such as nuclear power plants is realized. This solves the problem of system function degradation caused by the failure of a single unit, meets the reliability requirements of Class 1 nuclear safety equipment, and has significant engineering application value.
Patent Information
- Application Number
- CN202611331608.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-31
- Publication Date
- 2026-11-17
AI Technical Summary
The existing emergency power supply system for diesel generator sets is prone to degradation or failure of the entire system function when a single unit fails. It cannot reliably supply power within 10 seconds in places such as nuclear power plants, and cannot meet the stringent requirements of Class 1 nuclear safety equipment.
The N+X miniaturized diesel generator set grid connection device adopts a self-synchronizing grid connection control method. It utilizes a system consisting of N main generator sets and X standby generator sets to monitor the status of each generator set in real time, automatically switch to quasi-synchronous mode, and use CAN bus for distributed fault-tolerant communication to achieve parallel start-up and dynamic reconfiguration of load distribution, ensuring fast and reliable emergency power supply.
It improves the system's reliability and resilience, enabling it to power up within 10 seconds in the event of a nuclear power plant LOOP accident. It tolerates hardware and software failures, ensures that the system's core functions are not affected, meets the requirements of Class 1 nuclear safety equipment, and has engineering application value.
Smart Images

Figure CN123121809A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of diesel generator sets, specifically a self-synchronizing grid connection control method for an N+X miniaturized diesel generator set grid connection device. Background Technology
[0002] For locations with high emergency power supply requirements, such as nuclear power plants, hospitals, and data centers, current solutions generally employ "self-synchronization" grid connection technology to ensure the entire process from command to power supply is completed within 10 seconds. While self-synchronization is fast, its success depends on the absolute reliability of a series of stages, including unit startup, speed-up, voltage build-up, and circuit breaker execution. In practice, a momentary failure in any stage (such as circuit breaker jamming or momentary malfunction of the speed sensor) can cause a single unit to fail to self-synchronize. The traditional approach is to manually remove the faulty unit from the sequence for maintenance, but this directly leads to grid connection timeouts. Consequently, a partial failure of a single unit can cause the entire emergency power supply system to degrade or even fail, which is unacceptable for equipment performing Class 1 safety functions. Summary of the Invention
[0003] To overcome the shortcomings of the prior art, this invention provides an N+X miniaturized diesel generator set grid connection device self-synchronization grid connection control method. The aim is to replace one large emergency diesel generator set with N+X miniaturized generator sets; N units are for primary use, and X units are for backup; reducing costs and avoiding the risk of backup power failure due to single-point failures. Through this N+X miniaturized diesel generator set grid connection device self-synchronization grid connection control method, the diesel generator set can be started quickly and reliably, achieving diesel-to-electricity switching to mains power in a short time, improving response speed and success rate.
[0004] To achieve the above objectives, the present invention provides the following technical solution: a self-synchronizing grid connection control method for an N+X miniaturized diesel generator set grid connection device, comprising the following steps.
[0005] S1: Construct an N+X unit structure; N small units are the main units, and X small units are the backup units; the N+X units together provide emergency power supply.
[0006] S2: In response to an accident signal, control N+X generating units to start simultaneously and enter the self-synchronous grid connection process in parallel.
[0007] S3: Monitor the status of each unit in the self-synchronization process in real time to see if it is ready. If it is ready, connect it to the grid. If any unit is found to have a fault in the self-synchronization process and cannot complete the self-synchronization preparation, immediately perform the following steps S4-S6 for the faulty unit.
[0008] S4: For the faulty unit, switch from the self-synchronization process to the quasi-synchronization process; control the faulty unit to automatically exit the self-synchronization mode and seamlessly switch to the quasi-synchronization grid connection mode to continue grid connection attempts.
[0009] S5: State Reconfiguration; Generates a system event containing the identifier of the faulty unit and broadcasts it to all other units via real-time CAN bus communication.
[0010] S6: Logic Reconfiguration; All valid units that receive this event immediately mark the faulty unit as "offline" or "delayed grid connection" in their respective system models, and based on the updated system model, after determining that the conditions for the synchronization stage have been met, output the excitation establishment voltage to supply power to the emergency bus.
[0011] As a further optimization, in step S3, the method for determining whether the preparation is complete is to check whether the unit has started successfully, whether it has reached the rated speed, and whether the circuit breaker has been closed; if the unit has started, the unit has reached the rated speed, and the unit circuit breaker has been closed, then the preparation is determined to be complete; otherwise, it is determined that the self-synchronization preparation cannot be completed.
[0012] As a further optimization, in step S3, the seamless switch to quasi-synchronous grid connection mode means that when the faulty unit switches to quasi-synchronous mode, it continues to operate, its excitation system remains active, and only its grid connection control algorithm switches from a coarse synchronization mode based on speed tracking to a fine synchronization mode based on precise matching of voltage, frequency and phase; and when the precise matching of voltage, frequency and phase is completed, it continues to attempt grid connection.
[0013] As a further optimization, the method for determining whether the self-synchronization stage has met the conditions in step S6 is that when the sum of the number of units that have successfully connected to the grid through the self-synchronization mode and the number of units that have connected to the grid through the quasi-synchronization mode reaches or exceeds the preset minimum number of units N that must be put into operation, the system is considered to have the load-carrying capacity.
[0014] As a further optimization, in step S5, the real-time communication bus adopts a multi-master, broadcast CAN fieldbus system to ensure the reliability and timeliness of system state reconstruction commands.
[0015] As a further optimization, if the faulty unit successfully connects to the grid after switching to quasi-synchronous mode, it will broadcast a "grid connection successful" event to the system, and the system will then reintegrate it into the online unit pool to participate in subsequent load allocation and scheduling.
[0016] As a further optimization, once this emergency power supply operation is completed, the next operation will not affect the new self-synchronization grid connection operation, and all units will still be executed according to S2-S6.
[0017] As a further optimization, the self-synchronization grid connection control method of the N+X miniature diesel generator set grid connection device is based on an N+X miniature generator set mechanism, where the total rated power of the N+X miniature generator sets is 110%-130% of the full load power of the electrical facilities. Each miniature generator set includes a generator set circuit breaker connected to the emergency busbar supplying power to the electrical facilities, and its rated power is less than 20% of the full load power of the electrical facilities. The N+X miniature generator set mechanism includes a mains circuit breaker and a diesel-electric circuit breaker, as well as N+X miniature diesel generator sets. Both the mains circuit breaker and the diesel-electric circuit breaker are connected to the electrical facilities circuit. When the mains power fails, the diesel-electric circuit breaker closes and the mains circuit breaker opens. When the mains power is restored, the mains circuit breaker closes and the diesel-electric circuit breaker opens.
[0018] Compared with the prior art, the beneficial effects of the present invention are as follows.
[0019] First, a leap in reliability: from "system degradation" to "single-machine degradation", the performance of a single machine is degraded, but the core functions of the system are not affected, thus improving the reliability of the system.
[0020] Second, maximizing the use of the time window: In a nuclear power plant LOOP (lost coolant accident) scenario, nuclear safety regulations require the entire process from command to power supply to be completed within 10 seconds. This invention maximizes the use of this time window through the following methods.
[0021] Parallel startup: N+X units start up simultaneously and enter the self-synchronization process in parallel.
[0022] Rapid switching: Faulty units do not need to be shut down and restarted; the control algorithm seamlessly switches modes.
[0023] Overlapping optimization: While some units are rapidly supplying power, the faulty units complete precise grid connection in the background, achieving "overlapping optimization" in terms of time.
[0024] Third, the system's resilience and intelligence have been improved, as detailed below.
[0025] Hardware fault tolerance: It can tolerate momentary hardware failures such as circuit breaker jamming and sensor malfunction.
[0026] Software fault tolerance: It can cope with soft faults such as short-term communication interruptions.
[0027] Adaptability: The system model is dynamically updated, and the load distribution strategy is adjusted in real time.
[0028] Recoverability: The fault will not affect the next self-synchronization grid connection operation after it is cleared.
[0029] Fourth, it offers enhanced safety; meeting the stringent requirements of Class 1 nuclear safety equipment. Class 1 nuclear power equipment demands extremely high reliability, and the failure of the entire emergency power supply system due to the malfunction of a single unit is unacceptable in traditional solutions. This invention, through triple protection of mode redundancy, distributed fault tolerance, and dynamic reconfiguration, ensures that even if individual units fail, the entire emergency power supply system can still meet the stringent time limit of reliable power supply within 10 seconds, demonstrating significant engineering application value and socio-economic benefits.
[0030] In summary, this invention achieves the effect of "ensuring a balance between response speed and success rate at the system level" by trading pattern redundancy for system reliability, distributed architecture for fault tolerance and resilience, and dynamic reconfiguration for time utilization. Attached Figure Description
[0031] Figure 1 This is a schematic diagram of the structure of the N+X small generator sets in the embodiment.
[0032] Figure 2 This is a flowchart illustrating an example.
[0033] In the diagram: 1. Emergency busbar; 2. Electrical facilities; 3. Mains circuit breaker; 4. Diesel-electric circuit breaker; 5. Small generator set; 6. Generator set circuit breaker. Detailed Implementation
[0034] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some preferred embodiments of the present invention, and not all embodiments. Those skilled in the art should understand that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the scope of protection of the present invention.
[0035] Example: Please refer to Figure 1-2 .
[0036] This invention provides a self-synchronization grid connection control method for an N+X miniaturized diesel generator set grid connection device, which is applied to emergency power supply in nuclear power plants. The method includes the following steps.
[0037] Step S1: In response to the nuclear power plant LOOP accident signal, control N+X units to start up simultaneously and enter the self-synchronous grid connection process in parallel.
[0038] Step S2: Monitor the status of each unit in the self-synchronization process in real time. The status includes whether the start-up is successful, whether the rated speed is reached, and whether the circuit breaker is ready to close.
[0039] Step S3: When a fault is detected in any unit during the self-synchronization process, immediately perform the following steps S4-S6:
[0040] Step S4, self-synchronization to quasi-synchronization switching: Control the faulty unit to automatically exit the self-synchronization mode and seamlessly switch to the quasi-synchronization grid connection mode to continue grid connection attempts;
[0041] Step S5, State Reconstruction: Generate a system event containing the identifier of the faulty unit and broadcast it to all other units in the system via the real-time communication bus;
[0042] Step S6, Logic Reconfiguration: All valid generating units that receive this event immediately mark the faulty unit as "offline" or "delayed grid connection" in their respective system models. Based on the updated system model (N'+X', where N'+X'=N+XA), they determine that the conditions have been met since the synchronization phase and then output the excitation establishment voltage to supply power to emergency bus 1. Here, N' should be the number of normally operating units in the primary generating units, X' should be the number of normally operating units in the standby generating units, and A represents the faulty unit.
[0043] The N+X miniature diesel generator set grid connection device self-synchronization grid connection control method is based on an N+X miniature generator set mechanism. The total rated power of the N+X miniature generator sets 5 is 110%-130% of the full load power of the power-consuming facility 2. Each miniature generator set 5 includes a generator set circuit breaker 6 connected to the emergency busbar 1 supplying power to the power-consuming facility 2, and its rated power is less than 20% of the full load power of the power-consuming facility 2. Therefore, the number of N+X miniature generator sets 5 is at least 6. The N+X miniature generator set mechanism 5 includes a mains circuit breaker 3 and a diesel-electric circuit breaker 4, as well as N+X miniature diesel generator sets. Both the mains circuit breaker 3 and the diesel-electric circuit breaker 4 are connected to the load (power-consuming facility 2) circuit. When the mains power fails, the diesel-electric circuit breaker 4 closes and the mains circuit breaker 3 opens. When the mains power is restored, the mains circuit breaker 3 closes and the diesel-electric circuit breaker 4 opens.
[0044] Based on the above, in step S3, the seamless switch to quasi-synchronous grid connection mode means that when the faulty unit switches to quasi-synchronous mode, it continues to operate and its excitation system remains active. Only its grid connection control algorithm switches from a coarse synchronization mode based on speed tracking to a fine synchronization mode based on precise matching of voltage, frequency and phase.
[0045] Based on the above, in step S3, the logic for determining that the conditions for the self-synchronization stage have been met is as follows: when the sum of the number of units that have successfully connected to the grid through the self-synchronization mode and the number of units that have connected to the grid through the quasi-synchronization mode reaches or exceeds the preset minimum number of units N that must be put into operation, the system is considered to have load-carrying capacity.
[0046] Based on the above, the real-time communication bus adopts a multi-master, broadcast CAN fieldbus system to ensure the reliability and timeliness of system state reconstruction commands.
[0047] Based on the above, if a faulty unit successfully reconnects to the grid after switching to quasi-synchronous mode, it will broadcast a "grid connection successful" event to the system. The system will then reintegrate the unit into the online unit pool to participate in subsequent load allocation and scheduling.
[0048] Based on the above, once this power supply operation is completed, the next operation will not affect the new self-synchronous grid connection operation.
[0049] Based on this, the main differences between this embodiment and the prior art are as follows.
[0050] First, an intelligent and seamless switching mechanism between synchronous and quasi-synchronous modes.
[0051] Existing technical shortcomings: Current solutions generally adopt "self-synchronization" grid connection technology to pursue speed, but the success of self-synchronization is highly dependent on the absolute reliability of each link, such as unit startup, speed increase, voltage build-up, and circuit breaker operation. A momentary failure in any link (such as circuit breaker jamming or speed sensor failure) will cause the self-synchronization of a single unit to fail. The traditional approach is to manually shut down the unit, which directly causes the entire emergency power supply system to degrade or even fail.
[0052] The difference between this invention and existing technologies lies in its proposed dynamic mode switching mechanism from self-synchronization to quasi-synchronization. When a fault is detected in any unit during the self-synchronization process, instead of simply shutting it down, the system automatically and seamlessly switches to a more precise quasi-synchronization mode to continue grid connection attempts. The key features are: the faulty unit continues to operate, and the excitation system remains active; the grid connection control algorithm seamlessly switches from a "coarse synchronization mode based on speed tracking" to a "fine synchronization mode based on precise voltage, frequency, and phase matching"; and the switching process requires no shutdown and restart, avoiding the lengthy restart wait after the faulty unit exits in traditional solutions.
[0053] This dual-mode collaborative strategy, which prioritizes speed and guarantees accuracy, has not been reported in existing technologies and embodies a non-obvious technical concept.
[0054] Second, a distributed system-level collaborative fault-tolerant architecture based on the CAN bus.
[0055] Existing technical defects: Traditional diesel generator set grid connection systems are mostly centralized or master-slave control architectures. Fault information of a single unit needs to be reported to the central controller for unified processing, which poses the risk of single point of failure and communication delay.
[0056] The difference between this invention and existing technologies is that it employs a multi-master, broadcast CAN fieldbus, broadcasting fault events as a system-level status message to all networked units, with each unit independently performing the following operations:
[0057] In the local system model, the faulty unit is marked as "offline" or "delayed grid connection";
[0058] Based on the updated system model (N'+X'=N+XA), the conditions of the contemporaneous stage are reassessed;
[0059] It autonomously outputs excitation voltage to supply power to emergency bus 1.
[0060] This decentralized, distributed, fault-tolerant architecture eliminates the risk of single-point failure in the central controller, while utilizing a broadcast mechanism to ensure real-time state reconstruction, demonstrating significant innovation in the field of diesel generator set grid connection.
[0061] Third, dynamic capacity reconstruction and "time window overlap optimization" strategies.
[0062] Existing technical shortcomings: In traditional solutions, the successful grid connection of generating units and fault recovery are sequential relationships—first ensure that the minimum number of generating units are connected to the grid for power supply, and then deal with the faulty generating units, resulting in low utilization of the time window.
[0063] The difference between this invention and existing technologies is that it proposes the concept of "time window overlap optimization"—a portion of the generating units quickly connect to the grid and supply power through self-synchronization mode (pursuing the speed limit).
[0064] Meanwhile, the malfunctioning unit seamlessly switches to quasi-synchronous mode in the background to continue grid connection attempts (in pursuit of a higher success rate).
[0065] When the number of units successfully operating in sync plus the number of units already in sync operation is greater than or equal to the preset minimum number of units N, the system is deemed to have load-carrying capacity.
[0066] This parallel processing and dynamic decision-making strategy maximizes the use of the 10-second time window required by nuclear safety regulations, achieving a balance between speed and reliability, and represents a significant technological advancement.
[0067] Fourth, a mechanism for dynamic re-inclusion after a failure.
[0068] If a faulty generating unit successfully reconnects to the grid after switching to quasi-synchronous mode, it broadcasts a "grid connection successful" event to the system. The system then reintegrates the unit into the online generating unit pool for subsequent load allocation and scheduling. This mechanism ensures maximum utilization of system resources and avoids the resource waste associated with "one-time judgment, permanent exclusion."
[0069] The advantages of this embodiment compared to the prior art are as follows.
[0070] First, a leap in reliability: from "system degradation" to "single-machine degradation", the performance of a single machine is degraded, but the core functions of the system are not affected, thus improving the reliability of the system.
[0071] Second, maximizing the use of the time window: In a nuclear power plant LOOP (lost coolant accident) scenario, nuclear safety regulations require the entire process from command to power supply to be completed within 10 seconds. This invention maximizes the use of this time window through the following methods.
[0072] Parallel startup: N+X units start up simultaneously and enter the self-synchronization process in parallel.
[0073] Rapid switching: Faulty units do not need to be shut down and restarted; the control algorithm seamlessly switches modes.
[0074] Overlapping optimization: While some units are rapidly supplying power, the faulty units complete precise grid connection in the background, achieving "overlapping optimization" in terms of time.
[0075] Third, the system's resilience and intelligence have been improved, as detailed below.
[0076] Hardware fault tolerance: It can tolerate momentary hardware failures such as circuit breaker jamming and sensor malfunction.
[0077] Software fault tolerance: It can cope with soft faults such as short-term communication interruptions.
[0078] Adaptability: The system model is dynamically updated, and the load distribution strategy is adjusted in real time.
[0079] Recoverability: The fault will not affect the next self-synchronization grid connection operation after it is cleared.
[0080] Fourth, it offers enhanced safety; meeting the stringent requirements of Class 1 nuclear safety equipment. Class 1 nuclear power equipment demands extremely high reliability, and the failure of the entire emergency power supply system due to the malfunction of a single unit is unacceptable in traditional solutions. This invention, through triple protection of mode redundancy, distributed fault tolerance, and dynamic reconfiguration, ensures that even if individual units fail, the entire emergency power supply system can still meet the stringent time limit of reliable power supply within 10 seconds, demonstrating significant engineering application value and socio-economic benefits.
[0081] In summary, this embodiment employs intelligent and seamless switching between self-synchronization and quasi-synchronization at the control strategy layer, balancing speed and accuracy. The system architecture layer utilizes distributed collaborative fault tolerance based on the CAN bus to eliminate single points of failure. The scheduling optimization layer employs dynamic capacity reconfiguration and time window overlap optimization to maximize the utilization of the 10-second time limit. In general, this embodiment trades mode redundancy for system reliability, distributed architecture for fault tolerance and resilience, and dynamic reconfiguration for time utilization; these three elements work together to achieve the core technical effect of "ensuring a balance between response speed and success rate at the system level."
[0082] All parts of this invention not described in detail are prior art. This is not because these parts are unnecessary, but because they do not involve the inventive points of this invention, and since they are all prior art, they are not elaborated upon. For those skilled in the art, the technical features of the above embodiments can be combined arbitrarily. For the sake of brevity, not all possible combinations of the technical features in the above embodiments have been described. However, as long as the combination of these technical features does not contradict each other, it should be considered within the scope of this specification. The scope of this invention is defined by the appended claims and their equivalents.
Claims
1. A self-synchronizing grid connection control method for an N+X miniaturized diesel generator set grid connection device, characterized in that, Includes the following steps: S1: Construct an N+X unit structure; N small units (5) are used as the main units, and X small units (5) are used as backup units; N+X units provide emergency power supply as a whole; S2: In response to an accident signal, control N+X units to start up simultaneously and enter the self-synchronous grid connection process in parallel. S3: Monitor the status of each unit in the self-synchronization process in real time to see if it is ready. If it is ready, connect it to the grid. If any unit is found to have a fault in the self-synchronization process and cannot complete the self-synchronization preparation, immediately perform the following steps S4-S6 for the faulty unit. S4: For the faulty unit, switch from the self-synchronization process to the quasi-synchronization process; control the faulty unit to automatically exit the self-synchronization mode and seamlessly switch to the quasi-synchronization grid connection mode to continue grid connection attempts; S5: State Restructuring; Generate a system event containing the identifier of the faulty unit and broadcast it to all other units via real-time bus communication; S6: Logic Reconfiguration; All valid units that receive this event immediately mark the faulty unit as "offline" or "delayed grid connection" in their respective system models, and based on the updated system model, after determining that the conditions have been met since the synchronization stage, output excitation establishment voltage to supply power to the emergency bus (1).
2. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 1, characterized in that: In step S3, the method for determining whether the preparation is complete is to check whether the unit has started successfully, whether the rated speed has been reached, and whether the circuit breaker has been closed. If the unit has started, the unit has reached the rated speed, and the unit circuit breaker (6) has been closed, then the preparation is complete; otherwise, the self-synchronization preparation cannot be completed.
3. According to the N+X miniaturized diesel generator set grid connection device self-synchronization grid connection control method as described in claim 1, in step S3, the seamless switch to quasi-synchronization grid connection mode means that when the faulty generator set switches to quasi-synchronization mode, it continues to operate, its excitation system remains active, and only its grid connection control algorithm switches from the coarse synchronization mode based on speed tracking to the fine synchronization mode based on precise matching of voltage, frequency and phase; and when the precise matching of voltage, frequency and phase is completed, it continues to attempt grid connection.
4. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 1, characterized in that: The method for determining whether the self-synchronization stage has met the conditions in step S6 is that when the sum of the number of units that have successfully connected to the grid through the self-synchronization mode and the number of units that have connected to the grid through the quasi-synchronization mode reaches or exceeds the preset minimum number of units N that must be put into operation, the system is considered to have the load-carrying capacity.
5. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 1, characterized in that: In step S5, the real-time communication bus adopts a multi-master, broadcast CAN fieldbus system to ensure the reliability and timeliness of system state reconstruction commands.
6. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 3, characterized in that: If the faulty unit successfully reconnects to the grid after switching to quasi-synchronous mode, it will broadcast a "grid connection successful" event to the system. The system will then reintegrate the unit into the online unit pool to participate in subsequent load allocation and scheduling.
7. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 1, characterized in that: Once this emergency power supply operation is completed, the next operation will not affect the new self-synchronization grid connection operation, and all units will still be executed according to S2-S6.
8. The self-synchronization grid connection control method for the N+X miniaturized diesel generator set grid connection device according to claim 1, characterized in that: The N+X miniature diesel generator set grid connection device self-synchronization grid connection control method is based on an N+X miniature generator set mechanism. The rated power of the N+X miniature generator sets (5) is 110%-130% of the full load power of the power supply facility (2). Each miniature generator set (5) includes a generator set circuit breaker (6) connected to the emergency busbar (1) supplying power to the power supply facility (2), and its rated power is less than 20% of the full load power of the power supply facility (2). The N+X miniature generator set mechanism includes a mains circuit breaker (3) and a diesel-electric circuit breaker (4). The mains circuit breaker (3) and the diesel-electric circuit breaker (4) are both connected to the circuit of the power supply facility (2). When the mains power fails, the diesel-electric circuit breaker (4) closes and the mains circuit breaker (3) opens. When the mains power is restored, the mains circuit breaker (3) closes and the diesel-electric circuit breaker (4) opens.