A three-phase input soft-charging circuit

By replacing the precharge contactor and high-power resistor in the traditional scheme with a precharge relay and a wire-wound resistor group, the soft charging circuit is integrated and miniaturized, solving the problems of large circuit size, high cost and complex assembly in the existing technology.

CN123121952APending Publication Date: 2026-11-17NINGBO EASTONE MEDICAL INSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611470905.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-21
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In existing soft-charging circuit solutions, the pre-charging resistor needs to be a high-power aluminum-cased resistor or a thick-film high-voltage resistor, which is bulky and expensive. The pre-charging contactor and the main contactor occupy a lot of installation space, have a low degree of integration, and are not conducive to the miniaturization of the equipment.

Method used

Precharge relays are used instead of precharge contactors, and wire-wound resistor groups are used instead of high-power aluminum-cased resistors. Soft-charge control, detection, and contactor control circuits are integrated on the same PCB, reducing the number of contactors and simplifying wiring.

Benefits of technology

It reduces circuit size and cost, increases integration, simplifies assembly, and reduces system complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123121952A_ABST
    Figure CN123121952A_ABST
Patent Text Reader

Abstract

This invention discloses a three-phase input soft-charging circuit, including a soft-charging control circuit, a main circuit charging circuit, a soft-charging detection circuit, and a contactor control circuit. The soft-charging control circuit includes a pre-charge relay and a current-limiting resistor group composed of multiple wire-wound resistors connected in series and parallel. The main circuit charging circuit includes a main contactor and a rectifier bridge. The soft-charging detection circuit detects the charging current. The contactor control circuit controls the main contactor. The soft-charging control circuit, soft-charging detection circuit, contactor control circuit, and rectifier bridge are all integrated on the same PCB. This invention uses only one contactor and replaces aluminum-cased resistors with wire-wound resistors, improving integration and reducing size and cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to soft-charging circuits, and more particularly to a three-phase input soft-charging circuit. Background Technology

[0002] High-voltage, high-power equipment such as frequency converters, UPS, DC charging piles, and power storage converters (PCS) typically use rectifier and filter circuits to rectify and filter the AC power output from the grid to obtain the required operating voltage. This rectifier and filter circuit generally includes a rectifier bridge and an energy storage module. The rectifier bridge converts AC power into pulsating DC power. The energy storage module uses a series-parallel structure of multiple capacitors (electrolytic capacitors or supercapacitors) to smooth and filter the pulsating DC power, outputting a stable DC voltage to supply power to the downstream load. It also stores excess electrical energy as charge in the capacitors.

[0003] When the mains AC power is three-phase, the rectifier bridge has three AC input terminals, a positive output terminal, and a negative output terminal. The three AC input terminals are connected to the three live wires of the mains to supply three-phase AC power. The positive and negative output terminals are connected to the two ends (positive and negative) of the energy storage module to load pulsating DC power onto the module. In practical applications, the rectifier bridge is connected to the mains via a power connector and cable, and a fuse is connected in series.

[0004] When the rectifier and filter circuit is not connected to three-phase AC power, the capacitor in the energy storage module does not store any charge, and its voltage is zero. When the rectifier and filter circuit is connected to three-phase AC power, that is, at the moment when the high-voltage, high-power equipment is powered on, the voltage across the capacitor in the energy storage module cannot change abruptly and remains zero. Therefore, its resistance to current is minimal, equivalent to a short circuit. At this time, a huge surge current will be generated across the capacitor, the peak value of which may be tens or even hundreds of times the normal current, reaching hundreds or thousands of amperes. Such a huge current may blow fuses, damage cables and power grid connectors, cause severe impact on the power grid, and affect the operation of other equipment in the power grid.

[0005] To suppress the surge current generated at the moment of power-on, existing technology adds a soft-charging circuit before the rectifier bridge, so that the power supply path of high-voltage, high-power equipment is: three-phase AC power → soft-charging circuit → rectifier bridge → energy storage module.

[0006] The most widely used and classic soft-charging circuit scheme in the engineering field is the "pre-charging resistor + pre-charging contactor + main contactor" topology. This is a hardware scheme with sequential logic control. Its core idea is: first limit the current, then shoot through.

[0007] like Figure 1As shown, existing soft-charging circuit schemes typically include five parts: a soft-charging control circuit (containing a pre-charging contactor and a pre-charging resistor), a main circuit charging circuit (containing a main contactor and a rectifier bridge), a soft-charging detection circuit (bus voltage detection), a pre-charging contactor control circuit, and a main contactor control circuit. Specifically, the soft-charging control circuit includes a pre-charging contactor and a pre-charging resistor; the main circuit charging circuit includes a main contactor and a rectifier bridge; the soft-charging detection circuit detects the bus voltage; the pre-charging contactor control circuit controls the pre-charging contactor to engage or disengage; and the main contactor control circuit controls the main contactor to engage or disengage.

[0008] Upon power-up, the pre-charge contactor control circuit engages the pre-charge contactor, while the main contactor control circuit disengages it. The pre-charge contactor, pre-charge resistor, and rectifier bridge form a charging circuit to charge the energy storage module. The pre-charge resistor limits the charging current, and the soft-charge detection circuit monitors the bus voltage in real time. Once the bus voltage reaches a level close to the AC voltage amplitude, the main contactor control circuit engages the main contactor, and the pre-charge contactor control circuit disengages it. At this point, the main contactor and rectifier bridge form the charging circuit to charge the energy storage module, bringing the equipment into normal operation.

[0009] However, existing soft-charging circuit solutions have the following shortcomings: (1) The pre-charge resistor needs to be a high-power aluminum shell resistor or a thick film high-voltage resistor, which is large in size and high in cost. (2) The pre-charge contactor and the main contactor occupy a lot of installation space, and additional wiring is required between them and the pre-charge resistor, which increases the system cost and assembly complexity; (3) The pre-charge contactor, pre-charge resistor and main contactor are all independent devices, which are placed separately from the rectifier bridge and energy storage module and wired separately. The integration level is low, which is not conducive to the miniaturization of the equipment. Summary of the Invention

[0010] The technical problem to be solved by this invention is that, although existing soft-charging circuit solutions can effectively suppress surge current, they have problems such as complex circuit structure, high assembly complexity, high cost, low integration, and large overall size, which are not conducive to the miniaturization of equipment. This invention provides a three-phase input soft-charging circuit.

[0011] The technical solution adopted by this invention to solve the above-mentioned technical problems is as follows: a three-phase input soft-charging circuit, comprising: a soft-charging control circuit, including a pre-charge relay and a current-limiting resistor group, wherein the pre-charge relay is used to control the on / off state of the current-limiting resistor group; a main circuit charging circuit, including a main contactor and a rectifier bridge, wherein the main contactor is used to connect the three-phase power supply to the rectifier bridge, wherein the three-phase power supply includes a first live wire, a second live wire, and a third live wire; a soft-charging detection circuit, used to detect the charging current; and a contactor control circuit, used to control the on / off state of the main contactor; wherein the soft-charging detection circuit outputs a signal when the charging current drops to a preset value, so that the pre-charge relay is disconnected and the main contactor is engaged; the current-limiting resistor group is composed of multiple wire-wound resistors connected in series and / or in parallel; the soft-charging control circuit, the soft-charging detection circuit, the contactor control circuit, and the rectifier bridge are all integrated on the same PCB.

[0012] Furthermore, the soft-charge control circuit also includes a fourth resistor and a fifth resistor. The rectifier bridge has a first AC input terminal, a second AC input terminal, and a third AC input terminal. The first AC input terminal, the second AC input terminal, and the third AC input terminal are all used to connect to a three-phase power supply. The contacts of the pre-charge relay are connected between the first live wire and the third live wire and the current-limiting resistor group. The current-limiting resistor group is connected to the first AC input terminal and the third AC input terminal. The fourth resistor and the fifth resistor are connected in parallel to form a sampling resistor. The sampling resistor is connected between the contacts of the pre-charge relay and the current-limiting resistor group.

[0013] Furthermore, the current-limiting resistor group includes a first current-limiting resistor group and a second current-limiting resistor group. The first current-limiting resistor group is composed of multiple wire-wound resistors connected in parallel and then in series, and the second current-limiting resistor group is composed of multiple wire-wound resistors connected in parallel and then in series. The first current-limiting resistor group is connected to the first AC input terminal, and the second current-limiting resistor group is connected to the third AC input terminal.

[0014] Furthermore, the soft-charge detection circuit includes a sixth resistor, a seventh resistor, and an optocoupler. The voltage signals across the fourth and fifth resistors are input to the optocoupler via the sixth and seventh resistors. The output of the optocoupler is used to output a signal characterizing the charging current.

[0015] Furthermore, the contactor control circuit includes a control relay, a second diode, and an RC snubber circuit. The main contactor has a first control pin and a second control pin, which are the terminals of the control coil of the main contactor. The contacts of the control relay are connected between the first control pin of the main contactor and the second live wire. The second control pin of the main contactor is used to connect to the neutral wire. The second diode is connected in parallel with the coil of the control relay. The RC snubber circuit is connected between the first control pin and the second control pin of the main contactor.

[0016] Furthermore, the main circuit charging circuit also includes an energy storage capacitor bank, a first resistor, a second resistor, and a third resistor. The energy storage capacitor bank includes a first capacitor and a second capacitor connected in series. The first resistor and the second resistor are connected in parallel with the first capacitor and the second capacitor, respectively, for voltage equalization. The third resistor is connected in parallel with the energy storage capacitor bank.

[0017] Furthermore, the soft-charging control circuit is configured to connect the first live wire and the third live wire to the first AC input terminal and the third AC input terminal via the current-limiting resistor group during the soft-charging phase, while the second live wire is not connected during the soft-charging phase; the main circuit charging circuit is configured to charge the first live wire, the second live wire, and the third live wire via the first AC input terminal, the second AC input terminal, and the third AC input terminal respectively after the main contactor is engaged.

[0018] Compared with the prior art, the advantages of the present invention are as follows: (1) Reduce the number of contactors and simplify assembly. This invention uses a pre-charge relay instead of a traditional pre-charge contactor. The pre-charge relay is responsible for the switching function during the soft charging stage, and the main contactor only engages after soft charging is completed. The traditional solution requires two contactors, a pre-charge contactor and a main contactor, which occupy installation space and require additional wiring. In contrast, the entire circuit in this invention uses only one main contactor, thereby reducing the number of contactors and simplifying assembly.

[0019] (2) The current-limiting resistor is small in size and low in cost. The current-limiting resistor group of the present invention is composed of multiple wire-wound resistors, eliminating the need for high-power aluminum shell resistors or thick-film high-voltage resistors used in traditional solutions. The wire-wound resistors are small in size and low in cost, and multiple wire-wound resistors connected in series and / or in parallel can flexibly achieve the required current-limiting capability and power capacity, thereby reducing the size and cost of the current-limiting resistor while meeting the current-limiting requirements.

[0020] (3) High integration and reduced overall size. In this invention, the current-limiting resistor is a small wire-wound resistor instead of the high-power aluminum-cased resistor of the traditional solution, which reduces the size of the soft-charging control circuit. This allows the soft-charging control circuit, soft-charging detection circuit, contactor control circuit, and rectifier bridge to be integrated on the same PCB, and the rectifier bridge does not need to be external. The above integration method reduces the wiring between independent components, eliminates the need for an external rectifier bridge and additional cables, thereby improving the integration and reducing the overall size.

[0021] (4) Simplified detection circuit. The soft charging detection circuit of the present invention directly detects the charging current, while the traditional solution detects the bus voltage. The charging current directly reflects the charging state of the capacitor. When the charging current drops to a preset value, it indicates that the capacitor is close to being fully charged. Therefore, it is not necessary to detect the bus voltage to determine that soft charging is complete, which simplifies the detection circuit.

[0022] (5) Simplified wiring during soft charging. In this invention, the soft charging control circuit connects only the first and third live wires to the rectifier bridge via a current-limiting resistor group during the soft charging phase, while the second live wire is not connected. Therefore, the number of cables connecting the soft charging control circuit to the main circuit charging circuit is reduced from three to two, eliminating the need for current-limiting resistors on all three phases and further simplifying the wiring. Attached Figure Description

[0023] Figure 1 Functional block diagram of existing soft-charging circuits; Figure 2 This is a functional block diagram of the soft charging circuit of the present invention; Figure 3 This is the overall circuit diagram of the soft charging circuit of the present invention; In the diagram above: K1 - Precharge relay, model HF175F-24-2ZTF; K1A - Coil of precharge relay K1; K1B, K1C - Two sets of changeover switches for precharge relay K1; R1 - First resistor; R2 - Second resistor; R3 - Third resistor; R4 - Fourth resistor; R5 - Fifth resistor; R6 - Sixth resistor; R7 - Seventh resistor; R8 to R23 - Eighth to Twenty-third resistors, forming a current-limiting resistor group; R24 - Twenty-fourth resistor; R25 - Twenty-fifth resistor; R26 - Twenty-sixth resistor; U1 - Optocoupler; D1 - First diode; D2 - Second diode; D3 - Rectifier bridge; KL1 - Main contactor; CX1 - First capacitor; CX2 - Second capacitor; K2 - Control relay; LD2 - Light-emitting diode; C8 - Absorption capacitor; L1 - First live wire; L2 - Second live wire; L3 - Third live wire; N - Neutral wire. Detailed Implementation

[0024] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are merely intended to explain the invention and not to limit it. Those skilled in the art will recognize that the invention can be practiced without some of these specific details. The following description of the embodiments is merely to provide a better understanding of the invention by illustrating examples of it.

[0025] It should be noted that, in this document, relational terms such as "first" and "second" are used merely to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes said element.

[0026] Example: This example provides a three-phase input soft-charging circuit.

[0027] Figure 2 The functional block diagram of the three-phase input soft-charge circuit is shown. Figure 3 The overall circuit diagram of the three-phase input soft-charge circuit is shown.

[0028] like Figure 2 and Figure 3 As shown, the three-phase input soft-charging circuit of this embodiment includes a soft-charging control circuit, a main circuit charging circuit, a soft-charging detection circuit, and a contactor control circuit. The soft-charging control circuit is used to limit the charging current during the soft-charging phase; the main circuit charging circuit is used for the charging connection of the main circuit; the soft-charging detection circuit is used to detect the charging current; and the contactor control circuit is used to control the on / off state of the main contactor. The soft-charging control circuit, soft-charging detection circuit, contactor control circuit, and rectifier bridge D3 are all integrated on the same PCB.

[0029] The three-phase power supply includes the first live wire L1, the second live wire L2, and the third live wire L3.

[0030] The soft-charge control circuit includes a pre-charge relay K1 and its drive circuit, a current-limiting resistor group R8-R23, a fourth resistor R4, and a fifth resistor R5. The pre-charge relay K1 is a Hongfa HF175F-24-2ZTF type relay, which can be directly soldered onto the PCB without additional installation space or wiring, thereby reducing size and assembly complexity. Figure 3 K1A, K1B, and K1C are the three components of the precharge relay K1. K1 is a relay with two sets of changeover switches. K1A is the coil of relay K1, K1B is one set of changeover switches of relay K1, and K1C is the other set of changeover switches of relay K1. K1A, K1B, and K1C are collectively referred to as the precharge relay K1.

[0031] Pin 5 of K1B is connected to the first live wire L1, pin 4 is connected to the fourth resistor R4 and the fifth resistor R5, and pin 3 is not connected. Pin 6 of K1C is connected to the third live wire L3, pin 7 is connected to the current-limiting resistor group, and pin 8 is not connected. By default, pins 3 and 4 of K1B are connected, and pins 7 and 8 of K1C are connected. After the coil is energized, pins 4 and 5 of K1B are connected, and pins 7 and 6 of K1C are connected.

[0032] The current-limiting resistor group R8-R23 is composed of multiple wire-wound resistors connected in series and / or in parallel. Specifically, as shown... Figure 3As shown, the first current-limiting resistor group is formed by connecting the eighth resistor R8, the tenth resistor R10, the twelfth resistor R12, and the fourteenth resistor R14 in parallel, and then connecting them in parallel with the ninth resistor R9, the eleventh resistor R11, the thirteenth resistor R13, and the fifteenth resistor R15, forming a series resistor group. The second current-limiting resistor group is formed by connecting the sixteenth resistor R16, the eighteenth resistor R18, the twentieth resistor R20, and the twenty-second resistor R22 in parallel, and then connecting them in parallel with the seventeenth resistor R17, the nineteenth resistor R19, the twenty-first resistor R21, and the twenty-third resistor R23, forming a series resistor group. The first live wire L1 and the third live wire L3 are two phases of the three-phase power supply, connected to the input terminals L1 and L3 of the main contactor KL1, and then connected to pins 5 and 6 of the pre-charge relay K1, respectively. Pins 3 and 8 of K1 are not connected; by default, pins 7 and 8 of K1 are connected, and pins 3 and 4 are connected. Pin 4 of K1 is connected to one end of the parallel connection of the fourth resistor R4 and the fifth resistor R5. The other end of the parallel connection of the fourth resistor R4 and the fifth resistor R5 is connected to one end of the first current-limiting resistor group. The other end of the first current-limiting resistor group is connected to the first AC input terminal of the rectifier bridge D3. Pin 7 of K1 is connected to one end of the second current-limiting resistor group. The other end of the second current-limiting resistor group is connected to the third AC input terminal of the rectifier bridge D3. The cathode of the first diode D1 is connected to pin 1 of the relay K1 and is also connected to the E24V power supply; the anode of D1 is connected to pin 2 of K1 and is also connected to the relay control signal SOFT_RLY. One end of the twenty-fifth resistor R25 is connected to the E24V power supply, and the other end is connected to the anode of the light-emitting diode LD1; the cathode of LD1 is connected to the anode of D1 and is also connected to the relay control signal SOFT_RLY. The current-limiting resistor group is composed of multiple wire-wound resistors connected in parallel and then in series. Parallel connection can increase power capacity, and series connection can increase resistance value, thereby achieving the required current-limiting capability and power capacity within a limited volume, replacing the high-power aluminum shell resistors or thick film high-voltage resistors in traditional solutions. The soft-charging control circuit connects the first live wire L1 and the third live wire L3 to the current-limiting resistor group. Only two phases of the three-phase input are needed to form the soft-charging path, eliminating the need for additional current-limiting resistors on all three phases. This simplifies the circuit and reduces the number of current-limiting resistors. Since the soft-charging control circuit only connects the first live wire L1 and the third live wire L3 to the current-limiting resistor group, the number of cables connecting the soft-charging control circuit to the main circuit charging circuit is reduced from three to two, further simplifying the wiring.

[0033] The main circuit charging circuit includes a main contactor KL1, a rectifier bridge D3, energy storage capacitor banks CX1 and CX2, a first resistor R1, a second resistor R2, and a third resistor R3. Specifically, as follows... Figure 3As shown, rectifier bridge D3 has a first AC input terminal, a second AC input terminal, and a third AC input terminal. The first AC input terminal is pin 3, used to connect to the first live wire L1; the second AC input terminal is pin 2, used to connect to the second live wire L2; and the third AC input terminal is pin 1, used to connect to the third live wire L3. L1, L2, and L3 are respectively connected to the input terminals L1, L2, and L3 of the main contactor KL1, and its output terminals T1, T2, and T3 are respectively connected to pins 3, 2, and 1 of rectifier bridge D3. The positive output terminal 5 of rectifier bridge D3 is connected to the positive terminal of the first capacitor CX1 and one end of the first resistor R1 and the third resistor R3. The negative terminal of the first capacitor CX1 and the other end of the first resistor R1 are connected in parallel to one end of the parallel connection of the second capacitor CX2 and the second resistor R2. The other end of the parallel connection of the second capacitor CX2 and the second resistor R2 is connected to the negative output terminal 4 of rectifier bridge D3 and the other end of the third resistor R3. The negative terminal of the second capacitor CX2 is defined as DC-, and the positive terminal of the first capacitor CX1 is defined as DC+. The first resistor R1 and the second resistor R2 have the same resistance value and are connected in parallel with the first capacitor CX1 and the second capacitor CX2, which are connected in series, to equalize the voltage and ensure that the first capacitor CX1 and the second capacitor CX2 maintain the same voltage, preventing damage to the capacitors due to uneven voltage distribution caused by differences in leakage current. The third resistor R3 is connected in parallel with the energy storage capacitor bank to release residual charge in the energy storage capacitors after the equipment is powered off, ensuring maintenance safety. The main circuit charging circuit uses only one main contactor KL1. During the soft charging phase, the pre-charge relay K1 handles the switching function. The main contactor KL1 only engages after soft charging is completed, thus replacing the two contactors (pre-charge contactor and main contactor) in the traditional solution, solving the problems of needing two contactors, occupying space, and requiring wiring.

[0034] The soft-charge detection circuit includes a sixth resistor R6, a seventh resistor R7, and an optocoupler U1. Specifically, as follows... Figure 3As shown, the fourth resistor R4 and the fifth resistor R5 are connected in parallel. One end of the parallel connection is connected to one end of the sixth resistor R6, and the other end is connected to one end of the seventh resistor R7. The other end of the sixth resistor R6 is connected to pin 1 of optocoupler U1, and the other end of the seventh resistor R7 is connected to pin 2 of optocoupler U1. Pin 3 of optocoupler U1 is connected to SGND, and pin 4 is connected to SOFT_SIG, which is connected to the external control unit. Pin 1 of optocoupler U1 is the anode (A), pin 2 is the cathode (N), pin 3 is the emitter (E), and pin 4 is the collector (C). The parallel connection of the fourth resistor R4 and the fifth resistor R5 reduces the resistance and power consumption of the sampling resistor, while improving the current sampling accuracy. Optocoupler U1 achieves signal isolation transmission. There is a potential difference between the soft charging path and the external control unit, and the optocoupler provides electrical isolation, improving safety. The soft charging detection circuit has been changed from the traditional bus voltage detection to charging current detection. The charging current directly reflects the capacitor charging state. When the charging current drops to a preset value, it indicates that the capacitor is nearly fully charged. Soft charging can be determined to be complete without detecting the bus voltage, thus simplifying the detection circuit. The external control unit is used to receive the signal output by the optocoupler U1, determine whether the charging current has dropped to the preset value, and control the precharge relay K1 to disconnect and the main contactor KL1 to engage accordingly.

[0035] The contactor control circuit includes a control relay K2, a second diode D2, a twenty-fourth resistor R24, a light-emitting diode LD2, an absorption capacitor C8, and a twenty-sixth resistor R26. The main contactor KL1 has a first control pin A1 and a second control pin A2. The first control pin A1 and the second control pin A2 are the terminals for the control coil of the main contactor KL1. When the first control pin A1 is connected to the live wire and the second control pin A2 is connected to the neutral wire, the control coil of the main contactor KL1 is energized, and the main contactor KL1 is engaged. When the first control pin A1 is disconnected from the live wire, the control coil of the main contactor KL1 is de-energized, and the main contactor KL1 is disengaged. Specifically, as shown... Figure 3As shown, the cathode of the second diode D2 is connected to pin 3 of relay K2 and one end of the 24th resistor R24, and is also connected to the E24V power supply; the anode of D2 is connected to pin 4 of K2 and the cathode of LD2, and is also connected to the relay control signal MAIN_RLY. The other end of the 24th resistor R24 ​​is connected to the anode of the LED LD2. One end of the absorption capacitor C8 is connected to the neutral line N, and is also connected to the second control pin A2 of the main contactor KL1; the other end of the absorption capacitor C8 is connected to one end of the 26th resistor R26, and the other end of the 26th resistor R26 is connected to the first control pin A1 of the main contactor KL1 and pin 1 of relay K2. Pin 2 of K2 is connected to network G220, i.e., the second live wire L2. The second diode D2 provides a freewheeling circuit for the coil when relay K2 is de-energized, preventing the back electromotive force generated by the coil from damaging the drive circuit. The 24th resistor R24 ​​and the LED LD2 are used to indicate the operating status of relay K2. The absorption capacitor C8 and the twenty-sixth resistor R26 form an RC absorption circuit, which is connected between the first control pin A1 and the second control pin A2 of the main contactor KL1. It absorbs the reverse electromotive force generated when the contactor coil is de-energized, protects the contacts of the relay K2, and extends its service life.

[0036] The operation process of the three-phase input soft-charging circuit in this embodiment is as follows: After power-on, the pre-charge relay K1 engages, and the LED LD1 indicates the relay status. The first and third live wires L1 and L3 of the three-phase live wires are rectified by the rectifier bridge D3 through the current-limiting resistor group R8-R23. At this time, the main contactor KL1 is open, and the second live wire L2 is not connected. Simultaneously, the fourth resistor R4 and the fifth resistor R5 monitor the charging current in real time. When the charging current drops to a certain value, the pre-charge relay K1 opens, the main contactor KL1 engages, and the first, second, and third live wires L1, L2, and L3 are input to the rectifier bridge D3, activating the rectification and filtering of the main circuit.

[0037] During the soft charging phase, the current passing through the fourth resistor R4 and the fifth resistor R5 is monitored in real time. The current signal is converted into a voltage signal and input to the optocoupler U1. The optocoupler U1 then feeds the signal back to the external control unit. The external control unit determines whether the charging current has dropped to a preset value based on this signal. When the charging current drops to the preset value, the external control unit controls the pre-charge relay K1 to open and controls the main contactor KL1 to close. When the charging current drops to a certain value, the pre-charge relay K1 opens, MAIN_RLY goes low, and the relay K2 closes. G220, i.e., the second live wire L2, is input to the first control pin A1 of the main contactor KL1. The second control pin A2 of the main contactor KL1 is connected to the neutral wire N, so the main contactor KL1 closes. At this time, the soft charging path is disconnected, and the main circuit begins rectification and filtering.

[0038] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A three-phase input soft-charging circuit, comprising a soft-charging control circuit, a main circuit charging circuit, a soft-charging detection circuit, and a contactor control circuit; the soft-charging control circuit is used to limit the charging current during the soft-charging phase; the main circuit charging circuit includes a main contactor and a rectifier bridge, the main contactor being used to connect a three-phase power supply to the rectifier bridge, the three-phase power supply including a first live wire, a second live wire, and a third live wire; the soft-charging detection circuit is used to detect the charging current; the contactor control circuit is used to control the on / off state of the main contactor; characterized in that, The soft-charge control circuit includes a pre-charge relay and a current-limiting resistor group. The pre-charge relay is used to control the on / off state of the current-limiting resistor group. The soft-charge detection circuit outputs a signal when the charging current drops to a preset value, so that the pre-charge relay is disconnected and the main contactor is engaged. The current-limiting resistor group is composed of multiple wire-wound resistors connected in series and / or in parallel.

2. The soft charging circuit according to claim 1, characterized in that, The soft-charge control circuit further includes a fourth resistor and a fifth resistor. The rectifier bridge has a first AC input terminal, a second AC input terminal, and a third AC input terminal. The contacts of the pre-charge relay are connected between the first live wire and the third live wire and the current-limiting resistor group. The current-limiting resistor group is connected to the first AC input terminal and the third AC input terminal. The fourth resistor and the fifth resistor are connected in parallel to form a sampling resistor. The sampling resistor is connected between the contacts of the pre-charge relay and the current-limiting resistor group.

3. The soft charging circuit according to claim 2, characterized in that, The current-limiting resistor group includes a first current-limiting resistor group and a second current-limiting resistor group. The first current-limiting resistor group is composed of multiple wire-wound resistors connected in parallel and then in series. The second current-limiting resistor group is composed of multiple wire-wound resistors connected in parallel and then in series. The first current-limiting resistor group is connected to the first AC input terminal, and the second current-limiting resistor group is connected to the third AC input terminal.

4. The soft charging circuit according to claim 2, characterized in that, The soft-charge detection circuit includes a sixth resistor, a seventh resistor, and an optocoupler. The voltage signals across the fourth and fifth resistors are input to the optocoupler via the sixth and seventh resistors. The output of the optocoupler is used to output a signal characterizing the charging current.

5. The soft-charging circuit according to claim 1, characterized in that, The contactor control circuit includes a control relay, a second diode, and an RC snubber circuit. The main contactor has a first control pin and a second control pin, which are the terminals of the control coil of the main contactor. The contacts of the control relay are connected between the first control pin of the main contactor and the second live wire. The second control pin of the main contactor is used to connect to the neutral wire. The second diode is connected in parallel with the coil of the control relay. The RC snubber circuit is connected between the first control pin and the second control pin of the main contactor.

6. The soft-charging circuit according to claim 1, characterized in that, The main circuit charging circuit also includes an energy storage capacitor bank, a first resistor, a second resistor, and a third resistor. The energy storage capacitor bank includes a first capacitor and a second capacitor connected in series. The first resistor and the second resistor are connected in parallel with the first capacitor and the second capacitor, respectively, for voltage equalization. The third resistor is connected in parallel with the energy storage capacitor bank.

7. The soft charging circuit according to claim 2, characterized in that, The soft-charging control circuit is configured to connect the first live wire and the third live wire to the first AC input terminal and the third AC input terminal via the current-limiting resistor group during the soft-charging phase, and the second live wire is not connected during the soft-charging phase. The main circuit charging circuit is configured to charge the first live wire, the second live wire, and the third live wire through the first AC input terminal, the second AC input terminal, and the third AC input terminal, respectively, after the main contactor is engaged.