Connector for quenching heat exchange
By designing connection reinforcement components and docking installation components in the quenching heat exchanger, the problem of insufficient connector stability is solved, achieving higher stability and lower maintenance difficulty, and simplifying the operation process.
Patent Information
- Application Number
- CN202323581319.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-27
AI Technical Summary
The connector structure of the existing quenching heat exchanger is insufficient in structural stability, resulting in poor connection stability, affecting the long-term use of the equipment and making maintenance and disassembly difficult.
A connector is designed that includes connecting reinforcement components and docking installation components. Through components such as electric hydraulic cylinders, slides, push rod groups, reinforced extrusion plates, and sealing ring blocks, docking fixation and liquid transmission are achieved, reducing installation and Difficulty of repair.
It improves the stability and use stability of the connector, reduces the difficulty of repair and disassembly, and simplifies the operation process.
Smart Images

Figure CN221802630U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of rapid cooling and heat exchange connection, in particular to a connector for rapid cooling and heat exchange. Background Art
[0002] A quenching heat exchanger is a device that transfers part of the heat of a hot fluid to a cold fluid. It is also called a heat exchanger. Heat exchangers play an important role in chemical, petroleum, power, food and many other industrial productions. In chemical production, heat exchangers can be used as heaters, coolers, condensers, evaporators and reboilers, etc., and are widely used.
[0003] At present, the C5 fraction, C9 fraction and cracking fuel oil produced as by-products of ethylene cracking units are mainly used as raw materials, which are comprehensively utilized through distillation separation, polymerization, hydrogenation, crystallization and other chemical process treatments. For some connector components in the heat exchanger, the requirement for heat exchanger connector accessories and heaters is that the connection is firm when they cooperate with each other, but the current connector connection structure is mostly fixed by simple bolts, and the connection stability is poor, so a connector with high connection stability for rapid cooling and heat exchange is very important.
[0004] Therefore, those skilled in the art provide a connector for rapid cooling and heat exchange to solve the problems raised in the above background technology. Utility Model Content
[0005] The purpose of the utility model is to provide a connector for rapid cooling and heat exchange to solve the problems raised in the above background technology.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] A connector for rapid cooling and heat exchange comprises a base, a rapid cooling heat exchanger body is mounted on the upper end of the base, a connection and fixing auxiliary device is mounted on the front end of the rapid cooling heat exchanger body, and the connection and fixing auxiliary device comprises: a connection reinforcement component and a docking installation component.
[0008] As a further scheme of the utility model, the connection and reinforcement assembly includes: an electric hydraulic cylinder, a slide groove, a receiving frame, a first electric push rod group, a second electric push rod group, a first reinforcement extrusion plate and a second reinforcement extrusion plate, the output end of the first electric push rod group is equipped with a first pushing clamping plate, the output end of the second electric push rod group is equipped with a second pushing clamping plate, the lower end of the receiving frame is fixedly installed with a sliding block, the sliding block is movably installed in the slide groove, the lower end of the electric hydraulic cylinder is fixedly installed with a welding plate, the front end of the welding plate is fixedly installed at the rear end of the base, and the slide groove is opened at the upper end of the base.
[0009] As a further solution of the utility model, the docking installation assembly includes: an input pipe, a second sealing ring block, a first sealing ring block, an output docking pipe and a sealing extension sleeve, the rear end of the sealing extension sleeve is installed inside the front end of the output docking pipe, the front end outer wall of the sealing extension sleeve is installed on the inner wall of the input pipe, the inner wall of the second sealing ring block is fixedly installed on the front end outer wall of the input pipe, a sealing docking groove is opened at the front end of the second sealing ring block, a sealing gasket block is fixedly installed at the front end of the first sealing ring block, and the front end of the sealing gasket block is detachably installed inside the sealing docking groove.
[0010] As a further solution of the utility model, the first reinforcement extrusion plate is installed on the front end outer wall of the first sealing ring block, the second reinforcement extrusion plate is installed on the front end outer wall of the second sealing ring block, and the inner side of the first reinforcement extrusion plate is fitted and docked with the inner side of the second reinforcement extrusion plate.
[0011] As a further solution of the present invention, the second pushing plate and the first pushing plate are of the same size and model, the first pushing plate and the second pushing plate are both C-shaped, and the supporting frame is provided with two groups, and the upper ends of the two groups of supporting frames are respectively installed on the lower ends of the second electric push rod group and the first electric push rod group.
[0012] As a further solution of the utility model, the outer wall diameter of the sealing extension sleeve is the same as the inner diameter of the output butt pipe, and the rear ends of the output butt pipe and the sealing extension sleeve are both equipped with delivery pipes, and the outer wall diameter of the sealing extension sleeve is the same as the inner diameter of the input pipe.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] By setting up a connection and fixing auxiliary device, after the second sealing ring block and the first sealing ring block are connected, the subsequent liquid input and transmission work can be carried out through the delivery pipe, and the front end of the rapid cooling heat exchanger body is connected and fixed by the connection reinforcement component and the docking installation component, which further reduces the problem of reduced connection stability during long-term use of the equipment while achieving stable installation. The equipment is installed by pushing and squeezing the connection reinforcement component and the docking installation component, which reduces the difficulty of maintenance and disassembly while also reducing the difficulty of using and operating the entire device. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the overall structure of a connector used for rapid cooling and heat exchange;
[0016] Figure 2 It is a schematic diagram of the structure of a connection and fixing auxiliary device for a connector used for rapid cooling and heat exchange;
[0017] Figure 3It is a schematic diagram of the structure of a connection reinforcement component of a connector used for rapid cooling and heat exchange;
[0018] Figure 4 The present invention is a schematic diagram of the structure of a docking installation assembly of a connector used for rapid cooling and heat exchange.
[0019] In the figure: 1. base; 2. connecting and fixing auxiliary device; 21. connection and reinforcement component; 211. welding plate; 212. slide groove; 213. receiving frame; 214. first electric push rod group; 215. first push splint; 216. first reinforcement extrusion plate; 217. second electric push rod group; 218. second push splint; 219. second reinforcement extrusion plate; 210. sliding block; 2101. electric hydraulic cylinder; 22. docking installation component; 221. input pipeline; 222. second sealing ring block; 223. sealing docking groove; 224. delivery pipe; 225. output docking pipe; 226. sealing extension sleeve; 227. first sealing ring block; 228. sealing gasket block; 3. rapid cooling heat exchanger body. DETAILED DESCRIPTION
[0020] See also Figures 1-2 In an embodiment of the utility model, a connector for rapid cooling and heat exchange includes a base 1, a rapid cooling heat exchanger body 3 is installed on the upper end of the base 1, a connection and fixing auxiliary device 2 is installed at the front end of the rapid cooling heat exchanger body 3, and the connection and fixing auxiliary device 2 includes: a connection reinforcement component 21 and a docking installation component 22.
[0021] like Figure 3 As shown, the connection reinforcement component 21 includes: an electric hydraulic cylinder 2101, a slide 212, a receiving frame 213, a first electric push rod group 214, a second electric push rod group 217, a first reinforcement extrusion plate 216 and a second reinforcement extrusion plate 219. The output end of the first electric push rod group 214 is equipped with a first push clamping plate 215, and the output end of the second electric push rod group 217 is equipped with a second push clamping plate 218. The lower end of the receiving frame 213 is fixedly installed with a sliding block 210, and the sliding block 210 can be movably installed on In the slide groove 212, a welding plate 211 is fixedly installed at the lower end of the electric hydraulic cylinder 2101, and the front end of the welding plate 211 is fixedly installed at the rear end of the base 1. The slide groove 212 is opened at the upper end of the base 1. The second pushing clamp 218 and the first pushing clamp 215 are of the same size. The first pushing clamp 215 and the second pushing clamp 218 are both C-shaped. There are two groups of receiving frames 213, and the upper ends of the two groups of receiving frames 213 are respectively installed at the lower ends of the second electric push rod group 217 and the first electric push rod group 214.
[0022] like Figure 4As shown, the docking installation assembly 22 includes: an input pipe 221, a second sealing ring block 222, a first sealing ring block 227, an output docking pipe 225 and a sealing extension sleeve 226. The rear end of the sealing extension sleeve 226 is installed inside the front end of the output docking pipe 225, and the front end outer wall of the sealing extension sleeve 226 is installed on the inner wall of the input pipe 221. The inner wall of the second sealing ring block 222 is fixedly installed on the front end outer wall of the input pipe 221. A sealing docking groove 223 is opened at the front end of the second sealing ring block 222. A sealing pad 228 is fixedly installed at the front end of the first sealing ring block 227. The front end of the sealing pad 228 is detachably installed inside the sealing docking groove 223. The first reinforcement extrusion plate 216 is installed on the front end outer wall of the first sealing ring block 227, the second reinforcement extrusion plate 219 is installed on the front end outer wall of the second sealing ring block 222, the inner side of the first reinforcement extrusion plate 216 is fitted and docked on the inner side of the second reinforcement extrusion plate 219, the outer wall diameter of the sealing extension sleeve 226 is the same as the inner diameter of the output butt joint 225, the output butt joint 225 and the sealing extension sleeve 226 are both installed with a delivery pipe 224 at the rear end, and the outer wall diameter of the sealing extension sleeve 226 is the same as the inner diameter of the input pipe 221; when the device is in use, the electric hydraulic cylinder 2101 can be started, and the electric hydraulic cylinder 2101 can be started to bring The sliding block 210 at the output end moves forward and backward in the slide groove 212. After the sliding block 210 completes the movement, it drives the first electric push rod group 214 installed at the upper end to move forward and backward. When the first electric push rod group 214 at the upper end is driven to move to a fixed position, the input pipe 221 and the output butt joint pipe 225 can be docked. When the output butt joint pipe 225 and the input pipe 221 are docked, the first electric push rod group 214 and the second electric push rod group 217 are started. When the first electric push rod group 214 is started, it drives the first push clamping plate 215 at the output end to move forward. When the first push clamping plate 215 moves forward, it can drive the first seal installed inside. The sealing ring block 227 and the second sealing ring block 222 perform a further docking operation. After the second sealing ring block 222 and the first sealing ring block 227 complete the docking, the subsequent liquid input and transmission operation can be performed through the delivery pipe 224. The front end of the quench heat exchanger body 3 is docked and fixed by the connection reinforcement component 21 and the docking installation component 22. While achieving stable installation, the problem of reduced connection stability during long-term use of the equipment is further reduced. The equipment is installed by pushing and squeezing the connection reinforcement component 21 and the docking installation component 22, which reduces the difficulty of maintenance and disassembly while also reducing the difficulty of using and operating the entire device.
[0023] The working principle of the utility model is as follows: when the device is in use, the electric hydraulic cylinder 2101 can be started, and after the electric hydraulic cylinder 2101 is started, the sliding block 210 at the output end is driven to move forward and backward in the slide groove 212. After the sliding block 210 completes the movement, it drives the first electric push rod group 214 installed on the upper end to move forward and backward. When the first electric push rod group 214 at the upper end is driven to move to a fixed position, the input pipe 221 and the output butt pipe 225 can be docked. When the output butt pipe 225 and the input pipe 221 are docked, the first electric push rod group 214 is started and the output butt pipe 225 is docked. The second electric push rod group 217 drives the first pushing clamp 215 at the output end to move forward after the first electric push rod group 214 is started. When the first pushing clamp 215 moves forward, it can drive the first sealing ring block 227 and the second sealing ring block 222 installed inside to perform a further docking work. After the second sealing ring block 222 and the first sealing ring block 227 are docked, subsequent liquid input and transmission work can be carried out through the delivery pipe 224. The front end of the rapid cooling heat exchanger body 3 is docked and fixed by the connection reinforcement component 21 and the docking installation component 22.
[0024] What is described above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A connector for rapid cooling and heat exchange, comprising a base (1), characterized in that: A quench heat exchanger body (3) is mounted on the upper end of the base (1), and a connection and fixing auxiliary device (2) is mounted on the front end of the quench heat exchanger body (3). The connection and fixing auxiliary device (2) comprises: a connection reinforcement component (21) and a docking installation component (22).
2. A connector for rapid cooling and heat exchange according to claim 1, characterized in that: The connection reinforcement component (21) comprises: an electric hydraulic cylinder (2101), a slide groove (212), a receiving frame (213), a first electric push rod group (214), a second electric push rod group (217), a first reinforcement extrusion plate (216) and a second reinforcement extrusion plate (219); a first push clamping plate (215) is installed at the output end of the first electric push rod group (214); a second push clamping plate (218) is installed at the output end of the second electric push rod group (217); a sliding block (210) is fixedly installed at the lower end of the receiving frame (213); the sliding block (210) is movably installed in the slide groove (212); a welding plate (211) is fixedly installed at the lower end of the electric hydraulic cylinder (2101); a front end of the welding plate (211) is fixedly installed at the rear end of the base (1); and the slide groove (212) is opened at the upper end of the base (1).
3. A connector for rapid cooling and heat exchange according to claim 2, characterized in that: The docking installation assembly (22) comprises: an input pipe (221), a second sealing ring block (222), a first sealing ring block (227), an output docking pipe (225) and a sealing extension sleeve (226); the rear end of the sealing extension sleeve (226) is installed inside the front end of the output docking pipe (225); the front end outer wall of the sealing extension sleeve (226) is installed on the inner wall of the input pipe (221); the inner wall of the second sealing ring block (222) is fixedly installed on the front end outer wall of the input pipe (221); the front end of the second sealing ring block (222) is provided with a sealing docking groove (223); the front end of the first sealing ring block (227) is fixedly installed with a sealing pad block (228); the front end of the sealing pad block (228) is detachably installed inside the sealing docking groove (223).
4. A connector for rapid cooling and heat exchange according to claim 3, characterized in that: The first reinforcing extrusion plate (216) is mounted on the front end outer wall of the first sealing ring block (227), the second reinforcing extrusion plate (219) is mounted on the front end outer wall of the second sealing ring block (222), and the inner side of the first reinforcing extrusion plate (216) is fitted and docked with the inner side of the second reinforcing extrusion plate (219).
5. A connector for rapid cooling and heat exchange according to claim 2, characterized in that: The second pushing clamp plate (218) and the first pushing clamp plate (215) are of the same size and model; the first pushing clamp plate (215) and the second pushing clamp plate (218) are both C-shaped; the receiving frame (213) is provided with two groups, and the upper ends of the two groups of receiving frames (213) are respectively mounted on the lower ends of the second electric push rod group (217) and the first electric push rod group (214).
6. A connector for rapid cooling and heat exchange according to claim 3, characterized in that: The outer wall diameter of the sealing extension sleeve (226) is the same as the inner diameter of the output butt joint pipe (225); a delivery pipe (224) is installed at the rear ends of the output butt joint pipe (225) and the sealing extension sleeve (226); the outer wall diameter of the sealing extension sleeve (226) is the same as the inner diameter of the input pipe (221).