Bell and spigot butt joint type large-diameter prestressed steel cylinder concrete pipeline mounting device
By designing a device that includes an external baffle assembly, a built-in baffle assembly, a connecting tie rod assembly, an electric inverting chain and an internal traveling trolley, the difficulty in installing large-diameter prestressed steel cylinder concrete pipes is solved and the convenience is achieved. Fast docking operation improves installation efficiency and saves labor.
Patent Information
- Application Number
- CN202420169731.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-24
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-01-24
AI Technical Summary
Due to their large size and heavy mass during installation of large-diameter prestressed steel cylinder concrete pipes, the socket and docking operation is very difficult and difficult to complete efficiently.
Installation devices including external baffle components, built-in baffle components, connecting rod components, electric reverse chains and internal traveling trolleys are used. Through the cooperation of these components, the convenient and quick docking of pipelines is achieved.
It improves the efficiency of pipeline installation, saves labor, and simplifies the socket connection process.
Smart Images

Figure CN221824751U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipe butt installation, in particular to a socket butt type large-diameter prestressed steel cylinder concrete pipe installation device. Background Art
[0002] The socket-butted large-diameter prestressed steel cylinder concrete pipe is a composite pipe material. Since it has multiple layers of different composite materials distributed radially, it has the characteristics of steel pipe and reinforced concrete material. Therefore, it has the advantages of wide application range, long economic life, good seismic performance and low operating cost.
[0003] However, due to the large diameter and heavy weight of large-diameter prestressed steel tube concrete pipes, the socket and spigot connection operation during installation is very difficult. Utility Model Content
[0004] The utility model aims to solve the deficiencies of the prior art and provides a socket-jointed large-diameter prestressed steel cylinder concrete pipeline installation device.
[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical solutions:
[0006] A socket-jointed large-diameter prestressed steel cylinder concrete pipe installation device comprises an external baffle assembly, an internal baffle assembly, a connecting rod assembly, an electric fall chain and an internal walking trolley;
[0007] The external baffle assembly includes an external baffle, which is arranged outside the end surface of the pipeline, the length of the external baffle is greater than the inner diameter of the pipeline, and two first connecting ear plates are symmetrically arranged on the side of the external baffle facing the inner cavity of the pipeline, and the first connecting ear plates are penetrated by a first connecting hole;
[0008] The built-in baffle assembly includes a built-in baffle, which is arranged inside the pipeline, the length of the built-in baffle is smaller than the inner diameter of the pipeline, two second connecting ear plates are symmetrically arranged on one side surface of the built-in baffle, and the second connecting ear plates are penetrated by second connecting holes, and plug-in baffles are symmetrically arranged on both end surfaces of the built-in baffle, and the plug-in baffles are inserted into the gaps at the butt sockets of the two pipelines;
[0009] The connecting rod assembly comprises a rod, and pull rings are provided at both ends of the rod;
[0010] The inner traveling trolley is arranged inside the pipeline, and the electric fall chain is arranged on the inner traveling trolley;
[0011] The external baffle assembly is connected to another external baffle assembly or to the internal baffle assembly through two connecting rod assemblies and an electric fall chain, and the electric fall chain is connected between the two connecting rod assemblies.
[0012] Contact plates are fixedly arranged at two ends of the side surface of the external baffle plate facing the inner cavity of the pipeline.
[0013] The beneficial effects of the utility model are as follows: the utility model can conveniently and quickly connect the pipe sockets, improve the efficiency of pipe installation, and save labor. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 A state diagram of the utility model when two pipelines are butt-jointed;
[0015] Figure 2 A state diagram of the utility model used when multiple pipelines are connected;
[0016] Figure 3 It is a front view of the external baffle assembly;
[0017] Figure 4 is a top view of the external baffle assembly;
[0018] Figure 5 It is a front view of the built-in baffle assembly;
[0019] Figure 6 is a top view of the built-in baffle assembly;
[0020] Figure 7 It is a structural schematic diagram of the connecting rod assembly;
[0021] Figure 8 This is a schematic diagram of the inner walking trolley being arranged in the pipeline;
[0022] Fig. 9 This is the main view of the inner walking trolley;
[0023] Fig.10 It is a side view of the inner walking trolley;
[0024] In the figure: 1-external baffle assembly; 2-internal baffle assembly; 3-connecting pull rod assembly; 4-electric fall chain; 5-internal walking trolley; 6-pipeline;
[0025] 11-external baffle; 12-first connecting ear plate; 13-first connecting hole; 14-contact plate;
[0026] 21-built-in baffle; 22-second connecting ear plate; 23-second connecting hole; 24-plug-in baffle;
[0027] 31-pull rod; 32-pull ring;
[0028] 51-walking pole; 52-end cross bar; 53-connecting cross bar; 54-n-shaped seat; 55-walking wheel; 56-supporting diagonal brace;
[0029] The following is a detailed description of the embodiments of the present invention with reference to the accompanying drawings. DETAILED DESCRIPTION
[0030] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention. The present invention is described in more detail in the following paragraphs by way of example with reference to the accompanying drawings. The advantages and features of the present invention will become clearer according to the following description. It should be noted that the drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.
[0031] It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0032] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art in the technical field of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0033] The utility model is further described below in conjunction with the accompanying drawings and embodiments:
[0034] A socket-jointed large-diameter prestressed steel cylinder concrete pipe installation device, such as Figures 1 to 10 As shown, it includes an external baffle assembly 1, a built-in baffle assembly 2, a connecting rod assembly 3, an electric fall chain 4 and an internal walking trolley 5.
[0035] like Figure 3 to Figure 4 As shown, the external baffle assembly 1 includes an external baffle 11, which is arranged on the outer side of the end surface of the pipe 6, and the length of the external baffle 11 is greater than the inner diameter of the pipe 6. Two first connecting ear plates 12 are symmetrically provided on the side of the external baffle 11 facing the inner cavity of the pipe 6, and the first connecting ear plates 12 are penetrated by first connecting holes 13. Contact plates 14 are fixedly provided at both ends of the side of the external baffle 11 facing the inner cavity of the pipe 6.
[0036] like Figures 5 and 6As shown, the built-in baffle assembly 2 includes a built-in baffle 21, which is arranged inside the pipe 6. The length of the built-in baffle 21 is smaller than the inner diameter of the pipe 6. Two second connecting ear plates 22 are symmetrically provided on one side surface of the built-in baffle 21. The second connecting ear plates 22 are penetrated by second connecting holes 23. Plug-in baffles 24 are symmetrically provided on both end surfaces of the built-in baffle 21. The plug-in baffles 24 are inserted into the gap at the socket joints of the two pipes 6.
[0037] The external baffle 11 and the internal baffle 21 are both made by cutting and processing a Q235B steel plate with a thickness of 16 mm. The thickness of the plug-in baffle 24 is 3 mm.
[0038] like Figure 7 As shown, the connecting rod assembly 3 includes a rod 31 , and pull rings 32 are provided at both ends of the rod 31 .
[0039] The pull rod 31 is made of HPB300 round steel with a diameter of 16 mm.
[0040] By retracting the electric fall chain 4, the socket of the pipe 6 to be installed at the rear can be pulled into the socket of the pipe 6 installed at the front.
[0041] like Figure 8 , Fig. 9 , Fig.10 As shown, the inner walking trolley 5 includes four walking uprights 51, two of the four walking uprights 51 are located at the front side and the other two are located at the rear side, two end cross bars 52 are provided up and down between the two walking uprights 51 located at the front side, two connecting cross bars 53 are provided up and down between the two walking uprights 51 corresponding to the front and rear sides, and walking wheels 55 are installed at the bottom of the walking uprights 51 through n-shaped seats 54, and a supporting diagonal brace 56 is provided between the two connecting cross bars 53 on the same side.
[0042] The function of the inner walking trolley 5 is to place the connecting rod assembly 3 and the electric fall chain 4 on the trolley for transportation, which is convenient and labor-saving.
[0043] The inner walking trolley 5 is spliced by a scaffold steel pipe with a diameter of 48mm and a scaffold buckle, with steel wheels welded underneath, and can be pushed and walked directly in the pipeline 6.
[0044] The external baffle assembly 1 is connected to another external baffle assembly 1 or to the internal baffle assembly 2 via two connecting rod assemblies 3 and an electric fall chain 4 , and the electric fall chain 4 is connected between the two connecting rod assemblies 3 .
[0045] When installing pipeline 6, the inner pull method is used for installation, and the process is as follows:
[0046] According to the pipeline layout diagram, place the first section of the pipeline 6 on the foundation and fix it by piling sandbags on both sides of the pipeline 6 to increase the side friction of the pipeline 6 under stress and ensure that there is no horizontal and lateral movement when pulling the second section of the pipeline 6. After the first section of the pipeline 6 is placed and fixed, install the second section of the pipeline 6. First, hoist the second section of the pipeline 6 into place and check whether the center line of the second section of the pipeline 6 meets the requirements. Then place the external baffle assembly 1 at the front end of the first section of the pipeline 6 and the end end of the second section of the pipeline 6, and connect the two external baffle assemblies 1 with two 20-ton electric fall chains 4 and the connecting rod assembly 3, as shown in the figure. Figure 1 As shown. At this time, the 180-ton crawler crane wire rope for hoisting the second section of the pipeline 6 is in a taut hoisting working state, in order to reduce the friction between the second section of the pipeline 6 and the foundation and facilitate installation. Finally, the electric fall chain 4 inside the pipeline 6 is tightened, and the first section of the pipeline 6 and the second section of the pipeline 6 are slowly and tightly connected together. The maximum axial clearance between the pipe openings should be greater than 5mm and not greater than 25mm. During the installation construction, a 25mm thick wooden block can be processed and placed on the socket connection end face. During the installation process of the pipeline 6, the 25mm wooden block can be squeezed tight, and the pressure test of the socket joint of the pipeline 6 is carried out at the same time. The installation method of the third section of the pipeline 6 is the same as above.
[0047] After the third section of pipe 6 is installed, the following pipes 6 are installed, as their lengths become longer and longer. Figure 1 The installation method in is not suitable. Figure 2 The installation method shown, for example, when installing the fourth section of the pipeline 6, first set the built-in baffle assembly 2 at the socket joint between the first section of the pipeline 6 and the second section of the pipeline 6, leaving a 25mm gap at the joint to meet the installation and fixation of the built-in baffle assembly 2, and place the external baffle assembly 1 at the end of the fourth section of the pipeline 6, and use two 20-ton electric fall chains 4 and connecting rod assemblies 3 to connect the two built-in baffle assemblies 2 and the external baffle assembly 1. At this time, the 180-ton crawler crane wire rope for hoisting the fourth section of the pipeline 6 is in a taut hoisting working state, the purpose is to reduce the friction between the fourth section of the pipeline 6 and the foundation, and facilitate installation. Finally, tighten the electric fall chain 4 to complete the installation of the fourth section of the pipeline 6. The installation of the remaining pipelines 6 is similar.
[0048] The utility model can conveniently and quickly connect the sockets and spigots of the pipeline 6, improve the installation efficiency of the pipeline 6, and save labor.
[0049] The utility model is described above by way of example in conjunction with the accompanying drawings. It is obvious that the specific implementation of the utility model is not limited to the above-mentioned method. As long as various improvements are made using the method concept and technical solution of the utility model, or are directly applied to other occasions without improvement, they are all within the protection scope of the utility model.
Claims
1. A socket-jointed large-diameter prestressed concrete cylinder pipe installation device, characterized in that: It comprises an external baffle assembly (1), an internal baffle assembly (2), a connecting rod assembly (3), an electric fall chain (4) and an internal walking trolley (5); The external baffle assembly (1) comprises an external baffle (11), the external baffle (11) being arranged outside the end surface of the pipeline (6), the length of the external baffle (11) being greater than the inner diameter of the pipeline (6), two first connecting ear plates (12) being symmetrically arranged on the side surface of the external baffle (11) facing the inner cavity of the pipeline (6), and the first connecting ear plates (12) being penetrated by a first connecting hole (13); The built-in baffle assembly (2) comprises a built-in baffle (21), the built-in baffle (21) is arranged inside the pipe (6), the length of the built-in baffle (21) is smaller than the inner diameter of the pipe (6), two second connecting ear plates (22) are symmetrically arranged on one side surface of the built-in baffle (21), a second connecting hole (23) penetrates through the second connecting ear plates (22), plug-in baffles (24) are symmetrically arranged on both end surfaces of the built-in baffle (21), and the plug-in baffles (24) are inserted into the gap at the butt sockets of the two pipes (6); The connecting rod assembly (3) comprises a rod (31), and both ends of the rod (31) are provided with pull rings (32); The inner traveling trolley (5) is arranged inside the pipeline (6), and the electric fall chain (4) is arranged on the inner traveling trolley (5); The external baffle assembly (1) is connected to another external baffle assembly (1) or to the internal baffle assembly (2) via two connecting rod assemblies (3) and an electric fall chain (4), and the electric fall chain (4) is connected between the two connecting rod assemblies (3).
2. A socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 1, characterized in that: Contact plates (14) are fixedly provided at both ends of the side surface of the external baffle (11) facing the inner cavity of the pipeline (6).
3. The socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 2 is characterized in that: The thickness of the external baffle (11) is 16 mm.
4. The socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 3 is characterized in that: The diameter of the pull rod (31) is 16 mm.
5. The socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 4 is characterized in that: The thickness of the built-in baffle (21) is 16 mm, and the thickness of the plug-in baffle (24) is 3 mm.
6. The socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 5, characterized in that: The inner walking trolley (5) comprises four walking uprights (51), two of which are located at the front side and the other two are located at the rear side, two end cross bars (52) are arranged above and below between the two walking uprights (51) located at the front side, two connecting cross bars (53) are arranged above and below between the two walking uprights (51) corresponding to the front side and the rear side, and walking wheels (55) are installed at the bottom of the walking uprights (51) through n-shaped seats (54).
7. The socket-jointed large-diameter prestressed concrete cylinder pipe installation device according to claim 6 is characterized in that: A supporting diagonal brace (56) is provided between two connecting cross bars (53) on the same side.