Hanging basket crane suitable for construction of steel inclined strut prestressed concrete bridge
By designing a hanging basket crane that integrates the main truss system, bottom basket system, traveling anchoring system, crane system and guide system, the problem of single function of the hanging basket crane in the existing technology is solved, and the hoisting of steel diagonal braces and concrete The integration of box beam pouring improves construction efficiency and safety, and reduces costs and construction schedules.
Patent Information
- Application Number
- CN202420181640.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In the construction of existing steel diagonal braced concrete bridges, the hanging basket crane has a single function, which affects the construction efficiency, resulting in high construction costs and long construction period.
A hanging basket crane suitable for the construction of steel diagonal braced prestressed concrete bridges is designed. It integrates the main truss system, bottom basket system, traveling anchoring system, crane system and guide system to realize the hoisting of steel diagonal braces and concrete boxes. The integration of beam pouring and the use of hoists and fish-belly beams solve the difficulty in lifting caused by the small width of the steel diagonal braces.
By integrating equipment, the construction cost is reduced, the construction period is shortened, the construction efficiency is improved, the safety of the hoisting process is improved, and the construction difficulty is reduced.
Smart Images

Figure CN221837417U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of bridge engineering, in particular to a hanging basket crane suitable for the construction of steel diagonal brace prestressed concrete bridges. Background Art
[0002] A long-span bridge is a bridge that spans a large body of water, a valley or other open area, and has a very long main span. A steel brace prestressed concrete bridge is one of the long-span bridges. This bridge type combines the design of a hollow prestressed concrete bridge. The lower chord brace adopts a steel box girder structure. The steel brace is installed in sections and requires the use of lifting equipment. The upper chord adopts a prestressed concrete box girder structure and is constructed by cantilever casting with a hanging basket.
[0003] Due to geographical limitations, the design of the segmented installation of steel diagonal braces is to use large-scale hoisting machinery, which is costly and has a long construction period. Many factors are uncontrollable. The hanging basket construction method has been widely used in large-span continuous beam bridges in China. This method has the characteristics of convenient construction, fast construction, and economy. For example, the hanging basket construction is applied to steel diagonal brace concrete prestressed rigid frame bridges. The traditional construction process is to use a hanging basket to construct the concrete beams, and the steel diagonal braces are installed by a beam crane. The two are constructed separately, which requires two sets of equipment, which will increase the construction cost and extend the construction period, affecting the efficiency of bridge construction. Therefore, considering that the upper chord concrete construction equipment is a hanging basket, combined with the construction process, whether the hanging basket structure can be optimized and designed, supplemented and improved, so that it can meet the cantilever casting of the upper chord concrete beam and the hoisting function of the lower chord steel diagonal brace, and better adapt to the construction needs of the steel diagonal brace prestressed concrete bridge, is now an urgent problem to be solved. Summary of the invention
[0004] In view of this, the utility model aims to propose a hanging basket crane suitable for the construction of steel diagonal brace prestressed concrete bridges, so as to solve the problem that the hanging basket crane used in the existing steel diagonal brace concrete construction has a single function and affects the construction efficiency.
[0005] In order to achieve the above object, the technical solution of the utility model is implemented as follows:
[0006] A hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge, comprising:
[0007] A main truss system, comprising a main truss, a front crossbeam arranged at one end of the main truss, and a rear anchor crossbeam arranged at the other end of the main truss, wherein at least two main trusses are arranged at intervals, each main truss is provided with a plurality of vertical rods, and the vertical rods of two adjacent main trusses are connected by a cross-link truss;
[0008] A bottom basket system, comprising a bottom basket cross beam and a bottom basket longitudinal beam, wherein the bottom basket cross beam and the bottom basket longitudinal beam are both provided with a plurality of bottom basket hangers, and the bottom basket hangers are connected to the front cross beam or the cross truss through a hanger assembly;
[0009] The walking anchoring system comprises a track, a walking trolley and a walking rowing boat arranged on the track, one end of the main truss is arranged on the walking rowing boat, and the other end is arranged on the walking trolley, and a power component for driving the walking rowing boat to move is arranged on the track;
[0010] The overhead crane system includes a hoisting device arranged on a main truss, wherein the main truss is provided with a driving assembly for driving the hoisting device to move;
[0011] The guide system comprises a guide beam, a guide beam hanger and a guide beam slide arranged on the guide beam, the guide beam slide is slidably installed on the guide beam, and the guide beam hanger and the guide beam slide are both connected to the concrete beam.
[0012] Furthermore, the bottom basket hanger is a T-shaped structural member.
[0013] Furthermore, the boom assembly includes a boom, one end of which is connected to the bottom basket hanger, and the other end of which is connected to the front crossbeam or the cross-link truss.
[0014] Furthermore, the power assembly includes a traveling oil cylinder or a hand chain hoist, one end of which is detachably mounted on the track, and the other end is connected to the traveling rowing boat.
[0015] Furthermore, the running anchoring system also includes a steel support arranged on the concrete beam, the track is laid on the steel support, a track anchor beam is arranged above the track, and the track anchor beam is connected to the concrete beam through a connecting piece.
[0016] Furthermore, the hoisting equipment includes a walking truss slidably arranged on the main truss, and a fish-belly crossbeam arranged below the walking truss, and the hoisting equipment is provided with a lifting component for driving the fish-belly crossbeam to rise and fall.
[0017] Furthermore, the lifting assembly includes a winch arranged on the walking truss, and at least two winches are arranged on the left and right sides corresponding to the walking truss. The winches are arranged in a staggered manner. The left and right ends of the fishbelly crossbeam are connected to the winch through a hook pulley block. Fixed pulley blocks that cooperate with the hook pulley blocks are provided at the positions corresponding to the winches on the left and right sides of the walking truss.
[0018] Furthermore, a sling assembly is provided on the fish-belly cross beam, and the sling assembly includes hook ears correspondingly arranged at the left and right ends of the fish-belly cross beam, and lifting ears arranged at intervals in the middle of the fish-belly cross beam, and the hook ears are connected to the hook of the hook pulley block through a hook wire rope.
[0019] Furthermore, the main truss is provided with an I-shaped slide rail, the walking truss is provided with a moving trolley that cooperates with the slide rail, and the moving trolley is provided with a slide groove that cooperates with the slide rail; a support wheel that cooperates with the slide rail is provided at a position corresponding to the middle of the slide groove below the moving trolley, and a limiting wheel that cooperates with the slide rail is provided at positions corresponding to the left and right sides of the slide groove; the supporting wheel and the limiting wheel are both rotatably installed on the moving trolley, and a plurality of the supporting wheels and the limiting wheels are arranged at intervals along the length direction of the slide rail.
[0020] Furthermore, a reinforcing rod is provided at a position of the traveling truss corresponding to the moving trolley. The reinforcing rod is vertically arranged on the traveling truss, and a protrusion for reinforcing the structural strength is provided at one end of the reinforcing rod facing the moving trolley.
[0021] Compared with the prior art, the basket crane suitable for the construction of steel braced prestressed concrete bridges described in the utility model has the following advantages:
[0022] The utility model discloses a hanging basket crane suitable for the construction of a prestressed concrete bridge with steel diagonal braces. By setting a main truss system, a bottom basket system, a traveling anchoring system, a crane system and a guide system, the lifting of the steel diagonal braces and the pouring of the concrete box beam are integrated into a set of equipment, which reduces the cost at the economic level, facilitates the on-site construction and helps shorten the construction period. Among them, by setting the winch of the crane system on a movable traveling truss, and staggering the height of the winch on the left and right sides of the traveling truss, not only the movement of the winch is achieved, but also the crossing of the cables on the winch can be prevented, which helps to improve the safety during the lifting process. In addition, by using the winch to connect the fish-belly crossbeam and installing a hoist under the fish-belly crossbeam to lift the steel diagonal brace, the problem that the steel diagonal brace cannot be directly lifted due to its small width is solved, which helps to reduce the construction difficulty and further improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the accompanying drawings:
[0024] Figure 1 This is a structural schematic diagram of a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0025] Figure 2 for Figure 1 The structural diagram of the 1-1 direction;
[0026] Figure 3It is a structural schematic diagram of a hanging basket crane suitable for the construction of a steel diagonal brace prestressed concrete bridge according to an embodiment of the utility model when performing suspended pouring of a steel-concrete combined section;
[0027] Figure 4 It is a structural schematic diagram of a hanging basket crane suitable for the construction of a steel diagonal brace prestressed concrete bridge according to an embodiment of the utility model when performing suspended pouring of an upper chord concrete prestressed beam;
[0028] Figure 5 This is a structural schematic diagram of a main truss system in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0029] Figure 6 This is a structural schematic diagram of a bottom basket system in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0030] Figure 7 for Figure 6 The structural diagram of the 2-2 direction;
[0031] Figure 8 This is a structural schematic diagram of a guide system in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0032] Fig. 9 This is a structural schematic diagram of a traveling anchoring system in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0033] Fig.10 This is a structural schematic diagram of a crane system in a basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0034] Fig.11 This is a structural schematic diagram of a mobile trolley in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the utility model;
[0035] Fig.12 The present invention is a schematic structural diagram of a sling assembly in a hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to an embodiment of the present invention.
[0036] Description of reference numerals:
[0037] 1. Main truss system; 10. Formwork; 11. Main truss; 12. Rear anchor beam; 13. Front beam; 14. Cross truss; 15. Slide rail; 2. Bottom basket system; 21. Bottom basket beam; 22. Bottom basket longitudinal beam; 23. Bottom basket hanger; 3. Guide system; 31. Guide beam; 32. Guide beam hanger; 33. Guide beam slide; 34. Guide beam hanger; 4. Walking anchor system; 41. Track; 42. Steel support; 43. Track anchor beam; 44. Walking rowing; 45. Walking small Car; 46, power assembly; 5, boom assembly; 6, overhead crane system; 61, fixed pulley block; 62, walking truss; 63, mobile trolley; 631, supporting wheel; 632, limiting wheel; 64, winch; 65, hook pulley block; 66, fish-belly crossbeam; 661, hook lifting eye; 662, hook wire rope; 663, lifting lifting eye; 664, lifting wire rope; 67, reinforcement rod; 68, raised part; 7, operating platform; 8, steel diagonal braced box beam; 9, concrete beam. DETAILED DESCRIPTION
[0038] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0039] A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges, such as Figures 1 to 12 As shown, it includes a main truss system 1, a bottom basket system 2, a traveling anchor system 4, a crown crane system 6 and a guide system 3.
[0040] The main truss system 1 includes a main truss 11, a front crossbeam 13 provided at one end of the main truss 11, and a rear anchor crossbeam 12 provided at the other end of the main truss 11. At least two main trusses 11 are provided at intervals, and each main truss 11 is provided with a plurality of vertical bars, and the vertical bars of two adjacent main trusses 11 are connected by a cross-link truss 14. Exemplarily, the cross section of the main truss 11 is box-shaped, and pins can be used between the vertical bars and the main truss 11, and between each vertical bar to achieve detachable connection. Among them, the cross-link truss 14 is made of circular steel pipe, and a connecting sleeve for installing the cross-link truss 14 can be fixed on the main truss 11. The rear anchor crossbeam 12 and the front crossbeam 13 are made of steel sections. The cross-link truss 14, the rear anchor crossbeam 12 and the front crossbeam 13 can be fixed on the main truss 11 by bolts to achieve detachable installation.
[0041] In actual application, the rear anchor beam 12 is located at the rear end of the main truss 11 and can be used in conjunction with the traveling anchor system 4 to prevent the basket from tipping forward. The front beam 13 is used to bear and transfer the load from the bottom basket system 2. By setting the cross-link truss 14 on the vertical rod of the main truss 11, the left and right main trusses 11 can be connected as a whole, increasing the transverse stiffness of the basket crane. At the same time, the cross-link truss 14 can also bear and transfer the load from the bottom basket system 2 together with the front beam 13, which is conducive to dispersing the stress of the main truss system 1, thereby improving the stability of the basket crane during construction.
[0042] The bottom basket system 2 includes a bottom basket cross beam 21 and a bottom basket longitudinal beam 22, and a plurality of bottom basket hangers 23 are provided on the bottom basket cross beam 21 and the bottom basket longitudinal beam 22, and the bottom basket hangers 23 are connected to the front cross beam 13 or the cross truss 14 through the hanger assembly 5. Exemplarily, the bottom basket longitudinal beam 22 is made of steel, the bottom basket cross beam 21 is a double-piece steel, the bottom basket hanger 23 is a T-shaped structural member, and the hanger assembly 5 includes a hanger, one end of which is connected to the bottom basket hanger 23, and the other end is connected to the front cross beam 13 or the cross truss 14.
[0043] Through the cooperation of the bottom basket cross beam 21 and the bottom basket longitudinal beam 22, when the template 10 is set for pouring construction, the concrete load is transferred to the template 10 and the bottom basket system 2 through the template 10. Among them, the bottom basket longitudinal beam 22 directly bears the pouring load, and then transfers the load to the bottom basket cross beam 21, and the hanger is responsible for transferring the load on the bottom basket cross beam 21 to the main truss 11, and the front cross beam 13 and the cross truss 14 on the main truss 11 are used to achieve uniform distribution of force, thereby ensuring the stability of the bottom basket system 2.
[0044] In actual application, the operating platform 7 can be installed on both the bottom basket cross beam 21 and the bottom basket longitudinal beam 22, and the suspension rod and the bottom basket hanger 23 can be connected in a detachable manner. The bottom basket cross beam 21 is located below the bottom basket longitudinal beam 22. A plurality of bottom basket longitudinal beams 22 can be provided according to actual construction needs. Two bottom basket cross beams 21 can be provided at intervals along the length direction of the bottom basket longitudinal beam 22, wherein the front bottom basket cross beam 21 can be connected to the front cross beam 13 through the bottom basket hanger 23 and the suspension rod, and the rear bottom basket cross beam 21 can be connected to the cross-link truss 14 through the bottom basket hanger 23 and the suspension rod, so as to achieve a stable setting of the bottom basket system 2. In addition, those skilled in the art can also set a suitable number of bottom basket cross beams 21 according to actual needs, and set the bottom basket hanger 23 and the suspension rod on the bottom basket cross beam 21, so as to further improve the stability of the bottom basket system 2 on the concrete bridge.
[0045] The above-mentioned formwork 10 generally includes an outer formwork and an inner formwork, and forms a complete formwork system with the bottom basket system 2. Those skilled in the art can also choose other suitable formworks 10 according to actual needs, which will not be described in detail here. In addition, it should be noted that the design of the formwork 10 is based on the one-time pouring of box girder concrete in the entire section. The entire formwork 10 system must be in place once with the main truss 11, which can make the operation easier, effectively shorten the movement and installation cycle of the formwork 10, and ensure the appearance quality of the concrete. Among them, the outer formwork can be designed in sections, and the side formwork can be extended after the upper chord is poured to the steel-concrete joint section. The segmented design of the outer formwork is also a common technical means used by those skilled in the art, which will not be described in detail here.
[0046] The above-mentioned traveling anchoring system 4 includes a track 41, and a traveling trolley 45 and a traveling rowing boat 44 arranged on the track 41. One end of the main truss 11 is arranged on the traveling rowing boat 44, and the other end is arranged on the traveling trolley 45. The track 41 is provided with a power assembly 46 for driving the traveling rowing boat 44 to move. Exemplarily, the power assembly 46 includes a traveling oil cylinder or a hand chain hoist, and one end of the traveling oil cylinder or the hand chain hoist is detachably mounted on the track 41, and the other end is connected to the traveling rowing boat 44.
[0047] Specifically, a plurality of mounting holes can be arranged at intervals on the track 41, and the traveling oil cylinder or the hand chain hoist can be fixed on the track 41 through a pin shaft, and the other end is rotatably connected to the traveling rowing boat 44 through the pin shaft, and a connecting ring that cooperates with the pin shaft is fixed on the traveling rowing boat 44. In addition, those skilled in the art can also select other suitable power components 46 and their installation methods according to actual needs to realize driving the traveling rowing boat 44 to move, and then enable the traveling rowing boat 44 to drive the main truss 11 to move, which will not be repeated here.
[0048] In actual application, the main truss 11 can be fixed on the walking rowing boat 44 and the walking trolley 45 by bolts, and the walking rowing boat 44 and the walking trolley 45 are both rotatably installed with walking wheels that cooperate with the track 41. At the same time, the walking anchoring system 4 also includes a steel support 42 set on the concrete beam 9, the track 41 is laid on the steel support 42, and a track anchor beam 43 is provided above the track 41, and the track anchor beam 43 is connected to the concrete beam 9 through a connector.
[0049] For example, the track 41 can be laid on the steel support 42 (if there is a gap between the steel support 42 and the bridge deck, a steel plate needs to be used to fill it). The track anchor beam 43 can fix the track 41 to the concrete beam 9 bridge deck through the fine-rolled threaded steel (i.e., the connecting piece), and the root of the fine-rolled threaded steel is connected to the vertical prestressed embedded reinforcement of the concrete beam 9 through the threaded steel connector to ensure the stability of the track 41.
[0050] In addition, when the hanging basket is being cast, the walking rowing boat 44 at the front fulcrum of the main truss 11 can also rely on the bearing seat and the mechanical lock hydraulic top as support, so that the contact surface between the walking rowing boat 44 and the track 41 is in a separated state. When the hanging basket needs to move, the bearing seat and the mechanical lock hydraulic top at the front fulcrum can be unloaded to make the walking rowing boat 44 fall onto the track 41. The walking of the hanging basket can be driven by a walking cylinder or a hand winch, and by pulling the front fulcrum of the hanging basket, the walking rowing boat 44 moves forward on the track 41 to realize the walking of the main truss system 1.
[0051] Optionally, the track 41 can be designed as a multi-section structure, which is convenient for assembly and disassembly, and quick and convenient to move. By designing a walking trolley 45 at the rear fulcrum of the hanging basket, the walking trolley 45 can roll forward on the bottom surface of the flange on the track 41, reducing the difficulty of moving the main truss 11. At the same time, the track 41 is anchored by connecting the track anchor beam 43 pressed on it with the embedded reinforcement of the concrete beam 9, so that the hanging basket can move more smoothly and reliably.
[0052] The overhead crane system 6 includes a hoisting device arranged on the main truss 11, and a driving assembly for driving the hoisting device to move is arranged on the main truss 11. Exemplarily, the hoisting device includes a traveling truss 62 slidably arranged on the main truss 11, and a fish-bellied crossbeam 66 arranged below the traveling truss 62, and a lifting assembly for driving the fish-bellied crossbeam 66 to rise and fall is arranged on the hoisting device. Among them, the driving assembly can also be a traveling cylinder, one end of which is connected to the main truss 11, and the other end is connected to the traveling truss 62. Those skilled in the art can also select other suitable driving assemblies according to actual needs to realize driving the traveling truss 62 to move, which will not be described in detail here.
[0053] Optionally, the lifting assembly includes a winch 64 disposed on the traveling truss 62, and at least two winches 64 are disposed on the left and right sides of the traveling truss 62, and each of the winches 64 is arranged at a high and low position. The left and right ends of the fish-belly type cross beam 66 are connected to the winch 64 through a hook pulley block 65, and a fixed pulley block 61 cooperating with the hook pulley block 65 is disposed at the positions corresponding to the winches 64 on the left and right sides of the traveling truss 62. Among them, the hook pulley block 65 includes a wheel frame, a hook fixed below the wheel frame, and a movable pulley rotatably mounted above the wheel frame, and the fixed pulley block 61 includes a fixed pulley rotatably mounted on the traveling truss 62. The fixed pulley block 61 and the hook pulley block 65 form a pulley block to drive the lifting and lowering of the fish-belly type cross beam 66, which is a common technical means for those skilled in the art, and therefore will not be described in detail here.
[0054] In actual application, the two winches 64 are respectively responsible for controlling the hooks on the left and right sides to lift the fish-belly beam 66, thereby realizing the lifting operation of the steel diagonal brace box beam 8 assembled on the fish-belly beam 66. By arranging the winches 64 in a high and low staggered manner, the cables on the winches 64 can be prevented from crossing, which is beneficial to improving the safety during the lifting process. Specifically, when lifting, the operator can first lower the fish-belly beam 66, use the fish-belly beam 66 to connect with the steel diagonal brace box beam 8 through the front and rear steel wire ropes, and set the angle before lifting. Afterwards, the winch 64 is used to lift the fish-belly beam 66. After the steel diagonal brace box beam 8 is lifted to the installation elevation, the overhead crane uses the drive assembly to drive the overall longitudinal movement of the lifting equipment, and the fish-belly beam 66 fine-adjusts the angle to align the steel diagonal brace box beam 8. In addition, during the lifting condition, each system of the hanging basket crane is required to be in an anchored state.
[0055] Optionally, a sling assembly is provided on the fish-belly cross beam 66, and the sling assembly includes hook ears 661 correspondingly arranged at the left and right ends of the fish-belly cross beam 66, and lifting ears 663 arranged at intervals in the middle of the fish-belly cross beam 66, and the hook ears 661 are connected to the hook of the hook pulley block 65 through a hook wire rope 662. Exemplarily, four hook ears 661 can be arranged corresponding to the left and right ends of the fish-belly cross beam 66, and each hook ear 661 is fixed on the fish-belly cross beam 66, so as to form a stable triangular lifting structure at the end of the fish-belly cross beam 66, which is conducive to improving the stability of the fish-belly cross beam 66 during the lifting process. Similarly, the lifting ears 663 can also be arranged in groups of two, and two groups are arranged at intervals, and each lifting ear 663 is fixed on the fish-belly cross beam 66, so as to facilitate the lifting of the rigid diagonal brace through the lifting wire rope 664.
[0056] In actual application, the fish-belly cross beam 66 can be used to connect the steel diagonal brace box beam 8 to be hoisted through the hoisting lugs 663 and the hoisting wire ropes 664, and the hoisting angle of the hoisted steel diagonal brace can be controlled by the length of the hoisting wire ropes 664. Afterwards, the hook pulley block 65 in the hoisting equipment can be connected through the hook lugs 661 and the hook wire ropes 662, and the hook pulley block 65 can be controlled up and down by the hoisting machine 64 in the hoisting equipment to realize the lifting and lowering of the sling assembly and the steel diagonal brace box beam 8, which is easy to operate.
[0057] Optionally, an I-shaped slide rail 15 is provided on the main truss 11, a moving trolley 63 cooperating with the slide rail 15 is provided on the walking truss 62, and a slide groove cooperating with the slide rail 15 is provided on the moving trolley 63; a support wheel 631 cooperating with the slide rail 15 is provided at a position corresponding to the middle of the slide groove below the moving trolley 63, and a limiting wheel 632 cooperating with the slide rail 15 is provided at positions corresponding to the left and right sides of the slide groove, and the support wheel 631 and the limiting wheel 632 are both rotatably mounted on the moving trolley 63, and a plurality of the support wheels 631 and the limiting wheels 632 are arranged at intervals along the length direction of the slide rail 15. For example, two support wheels 631 can be arranged at intervals, and two limiting wheels 632 can be arranged at intervals on each side of the moving trolley 63. Those skilled in the art can also adjust the number of the support wheels 631 and the limiting wheels 632 according to actual needs, which will not be repeated here.
[0058] In actual application, the slide rail 15 can be fixed on the main truss 11, and the mobile trolley 63 is provided with an inverted T-shaped slide groove that cooperates with the slide rail 15. The inverted T-shaped slide groove cooperates with the slide rail 15, which is conducive to improving the stability of the mobile trolley 63 moving on the slide rail 15. In addition, the mobile trolley 63 can be fixed on the walking truss 62 by bolts, and by providing a rotatable support wheel 631 and a limit wheel 632 on the mobile trolley 63, it is conducive to reducing the resistance of the mobile trolley 63 to move, and it is convenient for the operator to use the driving assembly to drive the mobile trolley 63 to move, thereby realizing the driving of the walking truss 62.
[0059] Optionally, a reinforcing rod 67 is provided on the traveling truss 62 at a position corresponding to the moving trolley 63, and the reinforcing rod 67 is vertically arranged on the traveling truss 62, and a protrusion 68 for reinforcing the structural strength is provided at one end of the reinforcing rod 67 facing the moving trolley 63. Exemplarily, the reinforcing rod 67 can be fixed on the traveling truss 62 by bolts or pins, or can be directly fixed on the traveling truss 62. By providing the reinforcing rod 67 at a position corresponding to the moving trolley 63 on the traveling truss 62, it is helpful to improve the structural strength of the traveling truss 62 at the moving trolley 63, thereby ensuring that the traveling truss 62 can be stably moved during the hoisting process.
[0060] The guide system 3 includes a guide beam 31, and a guide beam hanger 32 and a guide beam slide 33 provided on the guide beam 31. The guide beam slide 33 is slidably mounted on the guide beam 31, and the guide beam hanger 32 and the guide beam slide 33 are both connected to the concrete beam 9. Exemplarily, the guide beam hanger 32 and the guide beam slide 33 can be mounted and fixed on the concrete beam 9 by a guide beam hanger 34. The guide system 3 can bear the internal mold load during the travel of the hanging basket, which belongs to the technical means commonly used by those skilled in the art and will not be repeated here.
[0061] In actual application, according to the characteristics of the steel braced concrete prestressed rigid frame bridge, the upper chord concrete box girder can be cantilever cast and constructed using a diamond hanging basket (i.e., the main truss 11 uses a diamond structural member), and the lower chord steel box girder is hoisted with the help of the upper chord diamond hanging basket. The overhead crane system 6 is set up, and the lower chord arch rib box girder is hoisted in sections by installing the existing hoisting equipment on the fish belly cross beam 66, thereby integrating two sets of equipment into one set of equipment, which is beneficial to improving construction efficiency.
[0062] The utility model discloses a hanging basket crane suitable for the construction of a prestressed concrete bridge with steel diagonal braces. By setting a main truss system, a bottom basket system, a traveling anchoring system, a crane system and a guide system, the lifting of the steel diagonal braces and the pouring of the concrete box beam are integrated into a set of equipment, which reduces the cost at the economic level, facilitates the on-site construction and helps shorten the construction period. Among them, by setting the winch of the crane system on a movable traveling truss, and staggering the height of the winch on the left and right sides of the traveling truss, not only the movement of the winch is achieved, but also the crossing of the cables on the winch can be prevented, which helps to improve the safety during the lifting process. In addition, by using the winch to connect the fish-belly crossbeam and installing a hoist under the fish-belly crossbeam to lift the steel diagonal brace, the problem that the steel diagonal brace cannot be directly lifted due to its small width is solved, which helps to reduce the construction difficulty and further improve the construction efficiency.
[0063] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges. Features: A main truss system (1) comprises a main truss (11), a front crossbeam (13) arranged at one end of the main truss (11), and a rear anchor crossbeam (12) arranged at the other end of the main truss (11), wherein at least two main trusses (11) are arranged at intervals, each main truss (11) is provided with a plurality of vertical rods, and the vertical rods of two adjacent main trusses (11) are connected by a cross-connecting truss (14); A bottom basket system (2) comprises a bottom basket cross beam (21) and a bottom basket longitudinal beam (22), wherein the bottom basket cross beam (21) and the bottom basket longitudinal beam (22) are both provided with a plurality of bottom basket hangers (23), and the bottom basket hangers (23) are connected to a front cross beam (13) or a cross-link truss (14) via a hanger assembly (5); A traveling anchoring system (4) comprises a track (41), a traveling trolley (45) and a traveling rowing boat (44) arranged on the track (41), one end of the main truss (11) being arranged on the traveling rowing boat (44), and the other end being arranged on the traveling trolley (45), and a power assembly (46) for driving the traveling rowing boat (44) to move being arranged on the track (41); The overhead crane system (6) comprises a hoisting device arranged on a main truss (11), wherein the main truss (11) is provided with a driving assembly for driving the hoisting device to move; The guide system (3) comprises a guide beam (31), and a guide beam hanger (32) and a guide beam slide (33) arranged on the guide beam (31); the guide beam slide (33) is slidably mounted on the guide beam (31); and the guide beam hanger (32) and the guide beam slide (33) are both connected to a concrete beam (9).
2. A hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to claim 1, Features: The bottom basket hanger (23) is a T-shaped structural member.
3. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 1 or 2, Features: The suspension rod assembly (5) comprises a suspension rod, one end of which is connected to the bottom basket hanger (23), and the other end of which is connected to the front crossbeam (13) or the cross-linked truss (14).
4. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 1, Features: The power assembly (46) comprises a traveling oil cylinder or a hand chain hoist, one end of which is detachably mounted on the track (41) and the other end is connected to the traveling rowing boat (44).
5. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 1 or 4, Features: The running anchoring system (4) further comprises a steel support (42) arranged on the concrete beam (9), the track (41) being laid on the steel support (42), a track anchor beam (43) being arranged above the track (41), and the track anchor beam (43) being connected to the concrete beam (9) via a connecting piece.
6. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 1, Features: The hoisting device comprises a walking truss (62) slidably arranged on the main truss (11), and a fish-bellied crossbeam (66) arranged below the walking truss (62), and the hoisting device is provided with a lifting component for driving the fish-bellied crossbeam (66) to rise and fall.
7. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 6, Features: The lifting assembly comprises a winch (64) arranged on a walking truss (62), at least two winches (64) are arranged on the left and right sides corresponding to the walking truss (62), and the winches (64) are arranged in a staggered manner. The left and right ends of the fish-belly cross beam (66) are connected to the winches (64) through a hook pulley block (65), and a fixed pulley block (61) cooperating with the hook pulley block (65) is arranged at the positions corresponding to the winches (64) on the left and right sides of the walking truss (62).
8. A hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to claim 7, Features: The fish-bellied cross beam (66) is provided with a sling assembly, which includes hook ears (661) correspondingly arranged at the left and right ends of the fish-bellied cross beam (66), and lifting ears (663) arranged at intervals in the middle of the fish-bellied cross beam (66), and the hook ears (661) are connected to the hook of the hook pulley block (65) through a hook wire rope (662).
9. A hanging basket crane suitable for the construction of a steel braced prestressed concrete bridge according to any one of claims 6 to 8, Features: The main truss (11) is provided with an I-shaped slide rail (15), the walking truss (62) is provided with a moving trolley (63) matched with the slide rail (15), and the moving trolley (63) is provided with a slide groove matched with the slide rail (15); a support wheel (631) matched with the slide rail (15) is provided at a position corresponding to the middle of the slide groove below the moving trolley (63), and a limiting wheel (632) matched with the slide rail (15) is provided at positions corresponding to the left and right sides of the slide groove; the support wheel (631) and the limiting wheel (632) are both rotatably mounted on the moving trolley (63), and a plurality of the support wheels (631) and the limiting wheels (632) are arranged at intervals along the length direction of the slide rail (15).
10. A hanging basket crane suitable for the construction of steel braced prestressed concrete bridges according to claim 9, Features: A reinforcing rod (67) is provided on the traveling truss (62) at a position corresponding to the moving trolley (63). The reinforcing rod (67) is vertically arranged on the traveling truss (62). A protrusion (68) for reinforcing the structural strength is provided at one end of the reinforcing rod (67) facing the moving trolley (63).