Construction protection structure for existing ancient trees in basement

By setting cement-poured slope protection piles and reinforcement structures around the ancient trees, a sealed concrete protective cage is formed, which solves the problem of soil loss around the ancient trees during the construction process and ensures the survival of the ancient trees and the smooth progress of the construction.

CN221855569UActive Publication Date: 2024-10-18TAIXING FIRST CONSTR INSTALLATION
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420635489.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-10-18
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

During the construction process, the soil around the ancient trees was lost due to settlement and rainwater erosion, which affected the survival of the ancient trees, especially the unavoidable soil erosion problem during basement construction.

Method used

Multiple cement-poured slope protection piles are used to form a cylindrical cage, which is reinforced by structures such as crown beams, ring beams, prestressed anchor cables and steel wire mesh. Combined with the concrete shell and drainage system, a sealed protective structure is formed to support the soil and prevent collapse. .

Benefits of technology

It effectively supports the soil around the ancient trees, prevents collapse and settlement, improves the strength and aesthetics of the protective structure, protects the survival of the ancient trees, and facilitates the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855569U_ABST
    Figure CN221855569U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of building construction, and provides a construction protection structure for existing ancient trees in a basement. Comprising a plurality of slope protection piles, the slope protection piles are distributed along the circumference of the outer side of an ancient tree to form a cylindrical cage body, a top beam is installed at the top ends of the slope protection piles, a plurality of ring beams are installed on the outer sides of the slope protection piles, pre-stressed anchor cables are installed on the outer sides of the slope protection piles, a steel wire mesh is installed on the outer side wall of the cylindrical cage body, and a concrete layer is sprayed on the outer side of the steel wire mesh. According to the technical scheme, soil, below the ground, of the ancient tree can be effectively supported, collapse of the soil can be prevented in the subsequent basement digging process, and the influence on survival of the ancient tree is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a construction protection structure for existing ancient trees in a basement. Background Art

[0002] In the process of promoting urban village renovation and other construction, there are usually century-old trees or ancient trees on the national protection list at the construction site. Due to the particularity of the ancient trees and local customs and habits, they cannot be easily moved and can only coexist with buildings.

[0003] During the construction process, it is inevitable to dig around the ancient tree, especially when the ancient tree is located in the basement of the building to be built. Since the construction of the basement requires digging from the ground to a depth of more than ten meters or even dozens of meters, even if the area around the ancient tree is left empty during the excavation process, after the basement is excavated, the ancient tree is located in an isolated island position in the basement, and the surrounding soil will be eroded due to sedimentation, rain erosion, etc., which will eventually affect the survival of the ancient tree. Summary of the invention

[0004] In order to solve the protection problem of existing ancient trees during the construction process, the utility model provides a construction protection structure for existing ancient trees in the basement.

[0005] The technical solution adopted by the utility model is:

[0006] The construction protection structure of the existing ancient trees in the basement includes a plurality of slope protection piles, which are cement cast-in-place piles. The plurality of slope protection piles are distributed along the outer circumference of the ancient trees to form a cylindrical cage. Each slope protection pile is inserted from the ground below the floor of the basement. A crown beam is installed on the top of the slope protection pile. The crown beam is an annular beam. The steel bars in the crown beam are connected to the steel bars on the top of each slope protection pile; a plurality of ring beams are installed on the outer side of the slope protection pile. The ring beams are distributed at equal intervals along the height direction of the slope protection pile, and the ring beams are fixedly connected to the outer side of each slope protection pile; a prestressed anchor cable is installed on the outer side of the slope protection pile, and the prestressed anchor cable spirally surrounds from top to bottom on the upper part of the columnar cage formed by the slope protection pile or forms a plurality of closed anchor cable circles evenly distributed up and down on the outer side of the columnar cage; the anchor cable circle forms a prestress toward the inner side of the columnar cage for the slope protection pile; a wire mesh is installed on the outer side wall of the columnar cage, and a concrete layer is sprayed on the outer side of the wire mesh.

[0007] Furthermore, the ring beam is connected to the slope protection piles through channel steels, the outer sides of the slope protection piles are fixedly installed with channel steels, the channel steels are horizontally arranged and open to the outside, and the steel cage of the ring beam is fixedly welded to the channel steels.

[0008] Furthermore, a channel steel is arranged on the outer side of each slope protection pile, and the channel steel is welded to the steel cage inside the slope protection pile or fixed to the slope protection pile by expansion screws.

[0009] Furthermore, a channel steel is provided at the contact point between the prestressed anchor cable and the slope protection pile, the channel steel is fixed to the outer side of the slope protection pile by means of expansion screws, and the prestressed anchor cable cooperates with the channel steel.

[0010] Furthermore, the prestressed anchor cable is fixed by an anchor cable clamp, and the anchor cable clamp includes a pair of I-beams, the pair of I-beams are perpendicular to the slope protection piles and fixedly connected to the slope protection piles, and pressure plates are respectively installed on both sides of the pair of I-beams, and anchor cable holes are provided on the pressure bearing plates. The prestressed anchor cable passes through the anchor cable holes and the gap between the pair of I-beams. Anchors are installed on the prestressed anchor cables, and the pressure plates limit the anchors.

[0011] Furthermore, the closed anchor cable ring is provided with a plurality of anchor cable hoops which are distributed at equal intervals.

[0012] Furthermore, a drainage trough is provided at the bottom of the cylindrical cage body, and the drainage trough is connected to the drainage system of the basement.

[0013] Furthermore, a plurality of circles of transverse tensioning bars are provided on the outer side of the steel wire mesh.

[0014] After adopting the above technical scheme, the beneficial effects of the utility model are:

[0015] A circle of slope protection piles is used to form a cage-like protective structure on the outside of the ancient tree, which can effectively support the soil below the ground of the ancient tree. In the subsequent excavation of the basement, it can prevent the collapse of the soil and avoid affecting the survival of the ancient tree; the slope protection piles are reinforced by crown beams, ring beams, etc. to increase the strength of the cage-like protective structure, and further reinforced with prestressed anchor cables to improve the protective effect of the protective structure; on the outside of the cage-like structure, a steel mesh is installed and concrete is sprayed to make the outside of the cage-like structure a sealed concrete layer, which prevents the soil inside from partial collapse due to its own gravity settlement and rain erosion. At the same time, it can also improve the appearance of the protection system and facilitate subsequent construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural schematic diagram of the utility model.

[0017] Figure 2 This is a schematic diagram of AA.

[0018] Figure 3 This is a schematic diagram of the structure of the anchor cable clamp.

[0019] In the figure: slope protection piles 1, crown beam 2, ring beam 3, prestressed anchor cable 4, concrete shell 5, channel steel 6, anchor cable clamp 7, I-beam 71, a pair of pressure plates 72, anchor 73, wire mesh 8, transverse tension bars 9, and drainage holes 10. DETAILED DESCRIPTION

[0020] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings:

[0021] like Figure 1-2 As shown, the basement has a construction protection structure for ancient trees, which is composed of slope protection piles 1, crown beams 2, ring beams 3, prestressed anchor cables 4, and concrete shells 5. It is used to protect the underground part of the ancient trees located in the basement of the building during the construction process and after the construction is completed.

[0022] The slope protection piles 1 are cement cast-in-place piles. Before the construction of the basement, a circle of slope protection piles surrounding the ancient tree is formed on the outside of the ancient tree by drilling holes, injecting mud, hanging steel cages, and pouring concrete. The slope protection piles are densely arranged, and a small gap is left between adjacent slope protection piles to prevent the soil on the inside of the slope protection piles from collapsing in the gap during the subsequent excavation of the basement. In this technical solution, 40 slope protection piles are provided, that is, one is provided every 9°. The top of the slope protection pile 1 is slightly higher than the ground, and the bottom of the slope protection pile 1 is below the ground of the basement. A circle of slope protection piles 1 forms a cylindrical cage-shaped protective structure around the ancient tree.

[0023] During the construction of the basement, it is necessary to dig down to a depth of more than ten meters. During the digging process, since there is no soil support on the outside of the cylindrical cage-shaped protection structure, the soil inside it will exert pressure on the slope protection piles 1 to the outside. In order to ensure the strength of the slope protection piles and prevent deformation, a cap beam 2 is cast at the upper end of the slope protection piles. The cap beam 2 is an annular beam. The steel bars in the cap beam 2 are connected to the steel bars at the top of each slope protection pile 1, and the top of each slope protection pile 1 is fixed by the cap beam 2.

[0024] During the excavation process, the slope protection piles 1 are continuously exposed above the soil surface. After each excavation to a certain depth, the ring beam 3 and the prestressed anchor cable 4 are respectively installed on the outside of the slope protection pile 1 to reinforce the part exposed above the soil surface. The ring beam 3 is connected to the slope protection pile 1 through the channel steel 6. The concrete is excavated at the same height on the outside of each slope protection pile 1 to expose the internal steel bars, and the channel steel 6 is welded. The channel steel 6 is horizontally arranged and opened to the outside. The channel steel serves as the fulcrum for the casting of the ring beam 3. The steel cage of the ring beam 3 is fixedly welded to the channel steel 6, and then the ring beam 3 is cast. After the excavation is completed, the cage formed by the slope protection pile 1 is provided with a plurality of equally spaced ring beams 3 from top to bottom in addition to the top crown beam 2 for its reinforcement.

[0025] In addition to the ring beam 3 , the technical solution is also reinforced by means of prestressed anchor cables 4 .

[0026] The prestressed anchor cable 4 spirally wraps around the upper part of the columnar cage formed by the slope protection pile from top to bottom or forms multiple closed anchor cable loops evenly distributed up and down on the outside of the columnar cage. The anchor cable loop forms prestress toward the inner side of the columnar cage on the slope protection pile. The prestressed anchor cable 4 is fixed by an anchor cable clamp 7. Each circle of prestressed anchor cable is fixed by multiple circumferentially evenly distributed anchor cable clamps 7 to prevent the prestressed anchor cable 4 from being reduced due to tensile deformation or loosening. In this technical solution, an anchor cable clamp 7 is set every 120°.

[0027] like Figure 3 As shown, the anchor cable clamp 7 is composed of a pair of I-beams 71, a pair of pressure plates 72 and an anchor 73. The pair of I-beams 71 are perpendicular to the slope protection piles 1 and are distributed up and down. One end of the I-beam 71 is fixedly connected to the slope protection piles 1 by excavating the slope protection piles and welding them to the internal steel bars or by expansion screws. Pressure plates 72 are welded and installed on both sides of the fixed structure composed of a pair of I-beams 71. Each pressure plate 72 is provided with an anchor hole. The connecting line of the anchor holes corresponding to the pair of pressure plates 72 passes through the gap between the pair of I-beams 71. The prestressed anchor cable 4 passes through the anchor hole and the gap between the pair of I-beams 71. Anchor 73 is installed on the prestressed anchor cable 4. The anchor 73 is fixedly installed on the prestressed anchor cable 4. The pressure plate 72 is used to limit the anchor 73 to prevent the prestressed anchor cable 4 from loosening.

[0028] After the cage-like structure formed by the slope protection piles 1, the crown beam 2, the ring beam 3, and the prestressed anchor cable 4 is constructed, a steel mesh 8 is installed on the outside of the cage-like structure. The steel mesh 8 is fixed by steel nails or the like, and the steel mesh is fixed on the outside of the steel mesh 8 by means of transverse reinforcement 9 or by winding a steel wire ring. Finally, a 50 mm fine stone concrete layer is sprayed on the outside of the steel mesh 8 to form a concrete shell 4. After the construction of the concrete shell 4 is completed, the part of the ancient tree located in the basement is a cylindrical sealed protection structure.

[0029] In order to avoid water accumulation inside, a drainage hole 10 is provided at the bottom of the sealing protection structure near the basement floor, and the drainage hole 10 is connected to the drainage system of the basement.

Claims

1. The construction protection structure of the existing ancient trees in the basement includes a plurality of slope protection piles, which are cement cast-in-place piles. The plurality of slope protection piles are distributed along the outer circumference of the ancient trees to form a cylindrical cage. Each slope protection pile is inserted from the ground to below the floor of the basement. It is characterized in that A crown beam is installed at the top of the slope protection pile, and the crown beam is an annular beam. The steel bars in the crown beam are connected to the steel bars at the top of each slope protection pile; a plurality of ring beams are installed on the outside of the slope protection pile, and the ring beams are evenly spaced along the height direction of the slope protection pile, and the ring beams are fixedly connected to the outer side of each slope protection pile; a prestressed anchor cable is installed on the outside of the slope protection pile, and the prestressed anchor cable spirally surrounds from top to bottom on the upper part of the columnar cage formed by the slope protection pile or forms a plurality of closed anchor cable circles evenly distributed up and down on the outside of the columnar cage; the anchor cable circle forms prestress on the slope protection pile toward the inside of the columnar cage; a wire mesh is installed on the outer side wall of the columnar cage, and a concrete layer is sprayed on the outer side of the wire mesh.

2. The construction protection structure for the existing ancient trees in the basement according to claim 1, It is characterized in that The ring beam is connected to the slope protection piles through channel steels, the outer sides of the slope protection piles are fixedly installed with channel steels, the channel steels are horizontally arranged and open to the outside, and the steel cage of the ring beam is fixedly welded to the channel steels.

3. The construction protection structure for the old trees in the basement according to claim 2, It is characterized in that Channel steel is arranged on the outer side of each slope protection pile, and the channel steel is welded to the steel cage inside the slope protection pile or fixed to the slope protection pile by expansion screws.

4. The construction protection structure for the existing ancient trees in the basement according to claim 1, It is characterized in that A channel steel is provided at the contact point between the prestressed anchor cable and the slope protection pile. The channel steel is fixed to the outer side of the slope protection pile by expansion screws, and the prestressed anchor cable cooperates with the channel steel.

5. The construction protection structure for the existing ancient trees in the basement according to claim 4, It is characterized in that The prestressed anchor cable is fixed by an anchor cable clamp, which includes a pair of I-beams, which are perpendicular to the slope protection piles and fixedly connected to the slope protection piles. Pressure plates are installed on both sides of the pair of I-beams, and anchor cable holes are provided on the pressure plates. The prestressed anchor cable passes through the anchor cable holes and the gap between the pair of I-beams. Anchors are installed on the prestressed anchor cable, and the pressure plates limit the anchors.

6. The construction protection structure for the existing ancient trees in the basement according to claim 5, It is characterized in that The closed anchor rope ring is provided with a plurality of anchor rope hoops which are distributed at equal intervals.

7. The construction protection structure for the existing ancient trees in the basement according to claim 1, It is characterized in that A drainage trough is provided at the bottom of the cylindrical cage body, and the drainage trough is connected to the drainage system of the basement.

8. The construction protection structure for the existing ancient trees in the basement according to claim 1, It is characterized in that The outer side of the steel wire mesh is provided with a plurality of circles of transverse tensioning bars.