Composite floor slab and building structure

By setting grooves and convex ribs on the prefabricated layer of the composite floor slab, and using the cast-in-place layer to provide anchoring, the problem of insufficient anchor length of the stressed steel bars at the bottom of the slab is solved, the seismic performance of the floor slab is improved, and the transportation and installation costs are reduced. .

CN221855920UActive Publication Date: 2024-10-18SHENZHEN GENERAL INST OF ARCHITECTURAL DESIGN & RES
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323503851.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2024-10-18
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

In laminated floor slabs, the anchorage length of the stress-bearing steel bars at the bottom of the slab is insufficient, which affects the seismic performance of the floor. Especially in structures with few walls, the stress-bearing steel bars at the bottom of the slab cannot achieve tensile yield, affecting the seismic performance of the building.

Method used

By arranging grooves and convex ribs on the prefabricated layer to form a convex part, the buried section of the first stress-bearing bar is buried in the convex part so that its extended section is anchored by the cast-in-place layer to ensure that the anchoring length is not limited. Tension yielding is achieved, and load-bearing steel bars and steel trusses are set within the prefabricated layers to increase load-bearing capacity.

Benefits of technology

It improves the seismic performance of the floor slab, ensures that the first stress-bearing steel bar has sufficient anchorage length and can withstand tensile force, and no stress-bearing steel bars protrude from the prefabricated layer, which does not affect transportation and installation, and reduces transportation and installation costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221855920U_ABST
    Figure CN221855920U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building structures, in particular to a composite floor slab and a building structure.The composite floor slab comprises a prefabricated layer, a cast-in-place layer and a steel bar structure, a plurality of grooves are formed in the prefabricated layer, every two adjacent grooves are arranged in a spaced mode so that a protruding rib can be formed between every two adjacent grooves, and the cast-in-place layer is formed on the prefabricated layer in a pouring mode; a groove is formed in the cast-in-place layer, a convex part is formed in the position, corresponding to the groove, of the cast-in-place layer, the steel bar structure comprises a first stress bar, the first stress bar comprises an embedded section and an extending section, the embedded section is embedded in the convex part, and the extending section extends out of the convex part and is used for achieving anchoring. According to the utility model, the first stress rib has enough anchoring length, so that the first stress rib can realize tensile yield, and the anti-seismic property of the floor slab can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building structures, in particular to a composite floor slab and a building structure. Background Art

[0002] In common composite slabs, the bottom stress-bearing steel bars of the slab are located in the precast concrete layer; because the bottom stress-bearing steel bars at the slab support need to be anchored, the bottom stress-bearing steel bars need to extend a certain length from the precast concrete layer, where the extension length of the bottom stress-bearing steel bars of the slab is the anchorage length of the steel bars in the cast-in-place vertical components. Since the extended bottom stress-bearing steel bars will affect the transportation and installation of the precast composite slab, the extension length is limited, usually controlled at about 5 times the diameter of the steel bar, which leads to insufficient anchorage length. When the composite slab is applied to a structure with few walls, the slab participates in the transmission of horizontal forces as a flat beam in a flat column frame, and the bottom stress-bearing steel bars will bear tensile force. However, insufficient anchorage length will cause the bottom stress-bearing steel bars to fail to achieve tensile yield, thereby affecting the seismic performance of the slab support nodes. Utility Model Content

[0003] The utility model of the embodiment of the present application provides a composite floor and a building structure, which can ensure that the first stress-bearing reinforcement has a sufficient anchorage length, so that the first stress-bearing reinforcement can achieve tensile yielding, which is beneficial to improving the seismic performance of the floor.

[0004] In order to achieve the above object, the utility model provides a composite floor slab, comprising:

[0005] A prefabricated layer, wherein a plurality of grooves are provided on the prefabricated layer, and two adjacent grooves are arranged at intervals to form a convex rib therebetween;

[0006] A cast-in-place layer, wherein the cast-in-place layer is cast on the prefabricated layer, and a convex portion is formed at a position of the cast-in-place layer corresponding to the groove; and

[0007] A steel bar structure, the steel bar structure includes a first stress-bearing bar, the first stress-bearing bar includes an embedded section and a protruding section, the embedded section is embedded in the protrusion, and the protruding section protrudes from the protrusion for achieving anchoring.

[0008] As an optional implementation, in the present invention, at least one inner wall surface of the groove is inclined from the bottom of the groove toward the top of the groove, so that the opening area of ​​the top of the groove is larger than the opening area of ​​the bottom of the groove.

[0009] As an optional implementation, in the present utility model, the first force-bearing rib is located at one end of the convex portion adjacent to the bottom of the groove.

[0010] As an optional implementation, in the present invention, the steel bar structure further includes load-bearing steel bars, which are arranged in the prefabricated layer, and the load-bearing steel bars are located on a side of the prefabricated layer away from the convex rib.

[0011] As an optional embodiment, in the utility model, the steel bar structure also includes a steel bar truss, which is arranged in the prefabricated layer and partially passes through the convex ribs and extends into the cast-in-place layer. Along the thickness direction of the composite floor slab, the part of the steel bar truss located in the prefabricated layer is staggered with the load-bearing steel bars.

[0012] As an optional embodiment, in the utility model, the steel structure also includes a second stress-bearing reinforcement, which is arranged in the cast-in-place layer, and the second stress-bearing reinforcement is located on the side of the cast-in-place layer away from the convex portion. Along the thickness direction of the composite floor slab, the part of the steel truss located in the cast-in-place layer is staggered with the second stress-bearing reinforcement.

[0013] As an optional implementation, in the present utility model, the extended section includes one or more of straight-line steel bars, curved steel bars, and broken-line steel bars.

[0014] As an optional embodiment, in the present invention, the thickness of the prefabricated layer at the groove is 25 mm to 45 mm, and the thickness of the prefabricated layer at the rib is 60 mm to 100 mm; and / or

[0015] The distance between two adjacent convex ribs is 60 mm to 120 mm, and the width of the convex rib is 60 mm to 120 mm.

[0016] The utility model also provides a building structure, comprising a cast-in-place wall and a plurality of composite floor slabs as described above, wherein the plurality of composite floor slabs are connected to the cast-in-place wall, and the extended section of the first stress-bearing reinforcement is anchored in the cast-in-place wall.

[0017] As an optional embodiment, in the utility model, in the two composite floor slabs located on both sides of the cast-in-place wall, the first stress-bearing reinforcements of the two composite floor slabs are integrally arranged, or the extending sections of the first stress-bearing reinforcements of the two composite floor slabs are interconnected in the cast-in-place wall.

[0018] Beneficial effects:

[0019] The utility model provides a composite floor and building structure, including a prefabricated layer, a cast-in-place layer and a first stress-bearing reinforcement. By arranging a groove on the prefabricated layer, a convex portion can be arranged on the cast-in-place layer corresponding to the position of the groove, and by burying the embedded section of the first stress-bearing reinforcement in the convex portion, the first stress-bearing reinforcement can be arranged in the cast-in-place layer outside the prefabricated layer without affecting the first stress-bearing reinforcement as the stress-bearing reinforcement of the prefabricated layer. At this time, the first stress-bearing reinforcement is anchored by the cast-in-place layer, and the anchoring method and anchoring length can be unrestricted, so that the first stress-bearing reinforcement has a sufficient anchoring length, so that the first stress-bearing reinforcement can withstand the tensile force to achieve tensile yield, thereby improving the seismic performance of the floor.

[0020] In addition, since there are no stress-bearing steel bars protruding from the prefabricated layer, the transportation and installation of the prefabricated panels will not be affected. At the same time, the setting of the grooves makes the weight of the prefabricated layer lighter than that of conventional prefabricated panels, which is conducive to saving transportation costs and installation costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0022] Figure 1 It is a structural schematic diagram of a composite floor disclosed in an embodiment of the utility model;

[0023] Figure 2 It is a structural schematic diagram of a building structure disclosed in an embodiment of the utility model;

[0024] Figure 3 yes Figure 2 Cross-sectional view along AA direction;

[0025] Figure 4 It is a structural schematic diagram of another building structure disclosed in an embodiment of the utility model.

[0026] Description of reference numerals:

[0027] 100, prefabricated layer; 110, groove; 120, convex rib; 200, cast-in-place layer; 210, convex part; 300, steel structure; 310, first stress-bearing reinforcement; 311, embedded section; 312, extended section; 320, second stress-bearing reinforcement; 330, load-bearing reinforcement; 340, steel truss; 400, cast-in-place wall; 410, lower wall; 420, upper wall. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0029] In the present invention, the terms "upper", "lower", "top", "bottom", "inner", "outer", "middle", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings. These terms are mainly used to better describe the present invention and its embodiments, and are not used to limit the indicated structures, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0030] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those skilled in the art, the specific meanings of these terms in this utility model can be understood according to specific circumstances.

[0031] In addition, the terms "disposed", "provided with", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two structures, elements, or components. For ordinary technicians in this field, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.

[0032] In addition, the terms "first", "second", etc. are mainly used to distinguish different structures, elements or components (the specific types and structures may be the same or different), and are not used to indicate or imply the relative importance and quantity of the indicated structures, elements or components. Unless otherwise specified, "plurality" means two or more.

[0033] The following is a detailed description with reference to the accompanying drawings.

[0034] See also Figure 1 This embodiment provides a composite floor slab, which can be used in building structures (refer to the building structure). Figure 2-Figure 4 ), the building structure also includes a cast-in-place wall 400, and the composite floor is connected to the cast-in-place wall 400.

[0035] The structure of the composite floor slab will be described in detail below with reference to the accompanying drawings. Specifically, the composite floor slab includes a prefabricated layer 100, a cast-in-place layer 200, and a steel structure 300. The prefabricated layer 100 is provided with a plurality of grooves 110, and two adjacent grooves 110 are arranged at intervals to form a convex rib 120 therebetween. The cast-in-place layer 200 is cast on the prefabricated layer 100, and a convex portion 210 is formed at a position of the cast-in-place layer 200 corresponding to the groove 110. The steel structure 300 includes a first force-bearing rib 310, and the first force-bearing rib 310 includes an embedded section 311 (see Figure 2 ) and the extension section 312 (see Figure 2 ), the embedded section 311 is embedded in the convex part 210, and the extended section 312 extends from the convex part 210 for anchoring. That is, when the composite floor is connected to the cast-in-place wall 400, the extended section 312 is partially or completely arranged in the cast-in-place wall 400.

[0036] It should be noted that the grooves 110 and the ribs 120 can extend along the length direction or width direction of the prefabricated board formed by the prefabricated layer 100, and are preferably arranged along the length direction of the prefabricated board. The number of grooves 110 and ribs 120 can be designed according to actual needs. For example, when the spacing arrangement direction of the grooves 110 and the ribs 120 is the two side directions of the prefabricated layer 100, the two side edges of the prefabricated layer 100 are preferably provided with grooves 110. The provision of the grooves 110 can increase the contact area between the cast-in-place layer 200 and the prefabricated layer 100 at the edge, thereby facilitating the joint treatment of the cast-in-place layer 200 and the prefabricated layer 100, and at the same time can appropriately reduce the weight of the prefabricated layer 100, which is conducive to saving transportation costs. In addition, when the composite floor is used in a building structure and is connected to another composite floor, the grooves 110 at the edges of the two composite floor can jointly form a joint groove for facilitating the joint treatment of the two composite floor, and joint connecting longitudinal reinforcement can be arranged in the joint groove. The joint connecting longitudinal reinforcement combined with the cast-in-place concrete in the joint groove can realize the fixed connection between the two composite floor.

[0037] During operation, the prefabricated layer 100 and the cast-in-place layer 200 are mainly made of concrete, wherein the prefabricated layer 100 is made in the factory, and the prefabricated layer 100 forms a prefabricated board after solidification, and the prefabricated board is transported and installed to the construction site. After the prefabricated board is installed in place, the first stress reinforcement 310 is placed in the groove 110, and the diameter and spacing arrangement of the first stress reinforcement 310 can be flexibly changed and unrestricted, and then the first stress reinforcement 310 can be fixed in the required position by binding or other means according to the anchoring requirements, and finally the prefabricated board is used as the template foundation to complete the cast-in-place layer 200 at the construction site. After the pouring is completed, at the end support position, the first stress reinforcement 310 is anchored by the concrete of the cast-in-place layer 200, and can be extended into the vertical member (such as the cast-in-place wall 400) as a straight anchor, or can be extended into the vertical member as a bent anchor, and the anchoring method and anchoring length are not restricted.

[0038] It can be seen that the composite floor of the utility model is provided with a groove 110 on the prefabricated layer 100, so that the cast-in-place layer can be provided with a convex portion corresponding to the position of the groove, and by burying the embedded section of the first stress-bearing reinforcement in the convex portion, the first stress-bearing reinforcement 310 can be provided in the cast-in-place layer 200 outside the prefabricated layer 100 without affecting the first stress-bearing reinforcement 310 as the stress-bearing reinforcement of the prefabricated layer 100. At this time, the first stress-bearing reinforcement 310 is provided with anchoring by the cast-in-place layer 200, and the anchoring method and anchoring length can be unrestricted, so that the first stress-bearing reinforcement 310 has a sufficient anchoring length, so that the first stress-bearing reinforcement 310 can withstand the tensile force to achieve tensile yielding, thereby improving the seismic performance of the floor. In addition, the prefabricated layer 100 of the composite floor of the utility model has no stress-bearing reinforcement protruding, which will not affect the transportation and installation of the prefabricated board. At the same time, the setting of the groove 110 makes the weight of the prefabricated layer 100 smaller than that of the conventional prefabricated board, which is conducive to saving transportation costs and installation costs.

[0039] Please refer again Figure 1 At least one inner wall surface of the groove 110 is inclined from the bottom of the groove 110 to the top of the groove 110, so that the opening area of ​​the top of the groove 110 is larger than the opening area of ​​the bottom of the groove 110. This arrangement not only facilitates the casting and molding of the cast-in-place layer 200 from top to bottom, but also increases the contact area between the protrusion 210 and the convex rib 120, which is beneficial to improve the bonding strength between the protrusion 210 and the convex rib 120 after the cast-in-place layer 200 is cast and molded.

[0040] Optionally, the cross-sectional shape of the groove 110 may be an inverted trapezoid or other shapes that meet the requirements, and the groove 110 may be designed with one side wall inclined or both side walls inclined, so as to well increase the contact area between the protrusion 210 and the rib 120. Exemplarily, the cross-sectional shape of the groove 110 is an inverted isosceles trapezoid, which not only allows the protrusion 210 and the rib 120 to have a better contact area, but also allows the composite floor formed by the prefabricated layer 100 and the cast-in-place layer 200 to better bear force in the horizontal direction.

[0041] In this embodiment, the first stress-bearing rib 310 is located at one end of the convex portion 210 adjacent to the bottom of the groove 110. This arrangement allows the first stress-bearing rib 310 to be closer to the prefabricated layer 100 so that the first stress-bearing rib 310 can better help the prefabricated layer 100 to withstand the tensile force from the horizontal direction, that is, it can improve the stress condition of the prefabricated layer 100 of the composite floor slab, which is beneficial to improving the seismic performance of the composite floor slab.

[0042] In actual settings, the first stress-bearing rib 310 can be placed at the bottom of the groove 110, so that during the formation of the cast-in-place layer 200, the first stress-bearing rib 310 can be located at the end where the convex portion 210 is connected to the bottom of the groove 110. Of course, in other embodiments, the first stress-bearing rib 310 can also be suspended relative to the bottom of the groove 110.

[0043] Please continue reading Figure 1 or Figure 3 The steel structure 300 also includes a second stress-bearing reinforcement 320, which is arranged in the cast-in-place layer 200, and the second stress-bearing reinforcement 320 is located on the side of the cast-in-place layer 200 away from the protrusion 210. By adding the second stress-bearing reinforcement 320, it can serve as the load-bearing support reinforcement of the composite floor slab, which can further improve the load-bearing capacity of the composite floor slab itself and meet the load-bearing requirements of the composite floor slab in the building structure.

[0044] It can be understood that by arranging the second stress-bearing reinforcement 320 and the first stress-bearing reinforcement 310 distributed up and down along the thickness direction of the composite floor in the composite floor, and the first stress-bearing reinforcement 310 is located at the end of the protrusion 210 adjacent to the bottom of the groove 110, the first stress-bearing reinforcement 310 can be used as the bottom stress-bearing reinforcement of the composite floor, while the second stress-bearing reinforcement 320 is located on the side of the cast-in-place layer 200 away from the protrusion 210, and the second stress-bearing reinforcement 320 can be used as the top stress-bearing reinforcement of the composite floor. The cooperation between the two enables the composite floor to be relatively balanced in the upper and lower forces, thereby more reasonably optimizing the load-bearing performance of the composite floor.

[0045] In this example, see Figure 1The steel structure 300 also includes load-bearing steel bars 330, which are arranged in the prefabricated layer 100, and the load-bearing steel bars 330 are located on the side of the prefabricated layer 100 away from the convex rib 120. By arranging the load-bearing steel bars 330 in the prefabricated layer 100, the self-weight of the prefabricated panels and the load during construction can be borne, so as to facilitate the transportation and installation of the prefabricated panels formed by the prefabricated layer 100.

[0046] In this embodiment, the steel structure 300 also includes a steel truss 340, which is arranged in the prefabricated layer 100 and partially extends into the cast-in-place layer 200 through the convex ribs 120, wherein most of the steel truss 340 is located in the prefabricated layer 100. By setting up the steel truss 340, on the one hand, it can be used to bear the dead weight of the prefabricated board and the load during construction, and on the other hand, it can be used as a connecting component between the prefabricated layer 100 and the cast-in-place layer 200, which is beneficial to strengthen the connection strength between the prefabricated layer 100 and the cast-in-place layer 200.

[0047] It can be understood that when the load-bearing steel bars 330 and the steel trusses 340 are arranged in the prefabricated layer 100, the portion of the steel trusses 340 located in the prefabricated layer 100 is staggered with the load-bearing steel bars 330 along the thickness direction of the composite floor slab. The staggered arrangement of the load-bearing steel bars 330 and the steel trusses 340 can avoid mutual interference. Similarly, when the steel trusses 340 and the second force-bearing bars 320 are arranged in the cast-in-place layer 200, the portion of the steel trusses 340 located in the cast-in-place layer 200 is staggered with the second force-bearing bars 320 along the thickness direction of the composite floor slab. The staggered arrangement of the steel trusses 340 and the second force-bearing bars 320 can avoid mutual interference.

[0048] Also, see Figure 1 The load-bearing reinforcement 330 may be a reinforcement mesh disposed in the prefabricated layer 100, that is, the load-bearing reinforcement 330 may be composed of transverse reinforcements and longitudinal reinforcements. Similarly, the second force-bearing reinforcement 320 may be a reinforcement mesh disposed in the cast-in-place layer 200, and the second force-bearing reinforcement 320 may also be composed of transverse reinforcements and longitudinal reinforcements.

[0049] In this embodiment, since the length and shape of the extended section 312 directly affect the anchorage length of the first force-bearing reinforcement 310, and the first force-bearing reinforcement 310 is separated from the prefabricated layer 100 and its shape and length are not restricted, the extended section 312 can be one or more of straight-line reinforcement, curved reinforcement, and broken-line reinforcement. Specifically, the first force-bearing reinforcement 310 of a suitable shape can be selected according to the actual construction situation, so as to meet the installation requirements of different building structures, which is conducive to expanding the scope of application of the composite floor.

[0050] In this embodiment, the thickness of the precast layer 100 at the groove 110 is 25mm-45mm, and the thickness of the precast layer 100 at the rib 120 is 60mm-100mm; and / or, the spacing between two adjacent ribs 120 is 60mm-120mm, and the width of the rib 120 is 60mm-120mm. By selecting a precast layer 100 of appropriate thickness and a rib 120 of appropriate size, the precast layer 100 has sufficient rigidity to avoid excessive deformation of the precast panel during transportation and installation, so that the precast panel can bear the deadweight of the composite panel before the concrete of the cast-in-place layer 200 reaches the design strength.

[0051] It is understandable that the above values ​​can be adjusted according to different floor spans and stress requirements. For example, when the floor span is large, a composite floor with thicker plate thickness at the groove, thicker plate thickness at the rib, narrower rib spacing, and wider rib width can be selected. For example, when the floor span is in the range of 1.5m to 2.4m, the dimensions of the composite floor are: 25mm plate thickness at the groove, 60mm plate thickness at the rib, 120mm rib spacing, and 100mm rib width. When the floor span is in the range of 2.4m to 3.6m, the dimensions of the composite floor are: 30mm plate thickness at the groove, 70mm plate thickness at the rib, 90mm rib spacing, and 110mm rib width. When the floor span is in the range of 3.6m to 4.8m, the dimensions of the composite floor are: 35mm plate thickness at the groove, 100mm plate thickness at the rib, 60mm rib spacing, and 120mm rib width.

[0052] See also Figure 2-Figure 4 As mentioned above, this embodiment provides a building structure, including a cast-in-place wall 400 and a plurality of the above-mentioned composite floor slabs, wherein the plurality of composite floor slabs are connected to the cast-in-place wall 400, and the extended section 312 of the first stress reinforcement 310 is anchored in the cast-in-place wall 400. The cast-in-place wall 400 and the cast-in-place layer 200 of the composite floor slab are both cast-in-place, so that the first stress reinforcement 310 can be more easily anchored in the cast-in-place wall 400 (that is, the vertical component), and at the same time, the anchoring length of the first stress reinforcement 310 can be sufficient and unrestricted.

[0053] It can be understood that the cast-in-place wall 400 includes a lower wall 410 and an upper wall 420. During operation, the lower wall 410 is first formed by casting at the construction site, and then the prefabricated board formed by the prefabricated layer 100 is placed between the lower wall 410 and another lower wall 410 or other vertical components. Then, the first stress-bearing reinforcement 310 of appropriate length and shape can be selected according to the anchoring requirements, and then the required first stress-bearing reinforcement 310 is placed in the groove 110 of the prefabricated layer 100 and fixed by binding or other means. Finally, the cast-in-place layer 200 and the upper wall 420 are formed together by pouring concrete, so as to realize the anchoring of the protruding section 312 of the first stress-bearing reinforcement 310 in the cast-in-place wall 400, and complete the installation of the composite floor slab and the cast-in-place wall 400.

[0054] In one example, in two composite floor slabs located on both sides of the cast-in-place wall 400, the first stress-bearing reinforcement 310 of the two composite floor slabs are integrally arranged.

[0055] In another example, in the two composite floor slabs located on both sides of the cast-in-place wall 400, the extended sections 312 of the first stress reinforcement 310 of the two composite floor slabs are connected to each other. Whether the two composite floor slabs are designed to be connected to each other by the first stress reinforcement 310 or to share the same stress reinforcement, the first stress reinforcement 310 can have a sufficient anchoring length, so that the first stress reinforcement 310 can withstand the tensile force to achieve tensile yielding, thereby improving the seismic performance of the building, and can also form a certain restraining force between the two composite floor slabs, which is conducive to optimizing the force at various locations of the building, thereby further improving the seismic resistance of the building.

[0056] For example, Figure 4 As shown, in the two composite floor slabs located on both sides of the cast-in-place wall 400, the first force-bearing reinforcement 310 of the two composite floor slabs are arranged in one piece. By adopting this anchoring method, on the one hand, the step of connecting and fixing the extended section 312 of the first force-bearing reinforcement 310 at the installation site can be omitted, which is beneficial to improving the construction efficiency of building installation. On the other hand, the axial transmission characteristics can be utilized so that the two composite floor slabs can not only restrain each other to improve the earthquake resistance of the building, but also share the forces from the horizontal direction with each other, thereby improving their respective endurance and extending their service life.

[0057] The composite floor and building structure disclosed in the embodiment of the utility model are introduced in detail above. The principle and implementation mode of the utility model are explained in this article by using specific examples. The description of the above embodiments is only used to help understand the method and core idea of ​​the utility model. At the same time, for the general technicians in this field, according to the idea of ​​the utility model, there will be changes in the specific implementation mode and application scope. In summary, the content of this specification should not be understood as a limitation on the utility model.

Claims

1. A composite floor slab, characterized in that: include: A prefabricated layer, wherein a plurality of grooves are provided on the prefabricated layer, and two adjacent grooves are arranged at intervals to form a convex rib therebetween; A cast-in-place layer, wherein the cast-in-place layer is cast on the prefabricated layer, and a convex portion is formed at a position of the cast-in-place layer corresponding to the groove; as well as A steel bar structure, the steel bar structure includes a first stress-bearing bar, the first stress-bearing bar includes an embedded section and a protruding section, the embedded section is embedded in the protrusion, and the protruding section protrudes from the protrusion for achieving anchoring.

2. The composite floor slab according to claim 1, characterized in that: At least one inner wall surface of the groove is inclined from the bottom of the groove toward the top of the groove, so that the opening area of ​​the top of the groove is larger than the opening area of ​​the bottom of the groove.

3. The composite floor slab according to claim 2, characterized in that: The first stress-bearing rib is located at one end of the convex portion adjacent to the bottom of the groove.

4. The composite floor slab according to claim 1, characterized in that: The steel bar structure also includes load-bearing steel bars, which are arranged in the prefabricated layer and are located on a side of the prefabricated layer away from the convex ribs.

5. The composite floor slab according to claim 4, characterized in that: The steel structure also includes a steel truss, which is arranged in the prefabricated layer and partially passes through the convex ribs and extends into the cast-in-place layer. Along the thickness direction of the composite floor slab, the part of the steel truss located in the prefabricated layer is staggered with the load-bearing steel bars.

6. The composite floor slab according to claim 5, characterized in that: The steel structure also includes second stress-bearing bars, which are arranged in the cast-in-place layer and located on a side of the cast-in-place layer away from the convex portion. Along the thickness direction of the composite floor slab, the part of the steel truss located in the cast-in-place layer is staggered with the second stress-bearing bars.

7. The composite floor slab according to claim 1, characterized in that: The extended section includes one or more of straight-line steel bars, curved steel bars, and broken-line steel bars.

8. The composite floor slab according to any one of claims 1 to 7, characterized in that: The thickness of the prefabricated layer at the groove is 25 mm to 45 mm, and the thickness of the prefabricated layer at the rib is 60 mm to 100 mm; and / or, The distance between two adjacent convex ribs is 60 mm to 120 mm, and the width of the convex rib is 60 mm to 120 mm.

9. A building structure, characterized in that: It comprises a cast-in-place wall and a plurality of composite floor slabs as described in any one of claims 1 to 8, wherein the plurality of composite floor slabs are connected to the cast-in-place wall, and the extended section of the first stress-bearing reinforcement is anchored in the cast-in-place wall.

10. The building structure according to claim 9, characterized in that In the two composite floor slabs located on both sides of the cast-in-place wall, the first stress-bearing reinforcements of the two composite floor slabs are integrally arranged, or the extended sections of the first stress-bearing reinforcements of the two composite floor slabs are interconnected in the cast-in-place wall.