Balance-weight-free hanging basket for staggered cantilever structure building

By designing the structure of the hanging basket without counterweight and using the combination of beams, brackets and U-shaped clips, the problem of difficulty in installing conventional hanging baskets in staggered cantilever structures has been solved, and safe and reliable hanging basket connections and simple construction have been achieved. Improved construction efficiency and safety.

CN221856148UActive Publication Date: 2024-10-18中国水利水电第七工程局有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420225480.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-10-18
Estimated Expiration
2034-01-30

AI Technical Summary

Technical Problem

In the construction of staggered cantilevered structures, conventional lever-type hanging baskets have many counterweights and connecting parts and are cumbersome to construct, which poses many safety hazards. Moreover, traditional counterweighted hanging baskets are not suitable for the installation conditions of staggered structural plate beams. Reliable installation is difficult to achieve.

Method used

A weightless hanging basket is designed, which adopts a structure including beams, brackets, hanging ropes and U-shaped clamps. The bracket is composed of uprights, diagonal braces and bases. It is anchored to the structural plate beams through U-shaped clamps, and the hanging ropes pass through PVC The casing is connected to the limiter, and the cross beam is fixed with buckles to ensure structural force balance and safety.

Benefits of technology

It achieves a safe and reliable connection of the hanging basket, simplifies the installation process, reduces the number of connecting parts, improves construction efficiency and safety, has a simple structure and low cost, and is suitable for exterior wall construction of split-level buildings. It can be quickly installed and disassembled, and can be repeatedly use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221856148U_ABST
    Figure CN221856148U_ABST
Patent Text Reader

Abstract

The utility model relates to a counterweight-free hanging basket for a staggered cantilever structure building, which comprises a lifting rope, a hanging basket, a cross beam and two supports fixedly connected to a structural plate beam, the cross beam is horizontally connected between the two supports, and the hanging basket is connected to the cross beam through the lifting rope; the hanging basket has the beneficial effects that the U-shaped steel plate on the base of the bracket of the hanging basket is anchored with the structural plate girder through the rear anchor bolt, so that the base can be stably and reliably connected with the structural plate girder, and the hanging basket is safer and more reliable to use. Installation and construction are simple, cost is low, connecting parts are few, and operation is safe and reliable. Compared with an existing clamping type suspension mechanism and a wall-straddling type suspension mechanism which are free of balance weights, the hanging basket suspension mechanism is free of balance weights, solves the problem that a hanging basket cannot be erected on a staggered overhanging floor slab, is simple in overall structure, convenient and flexible to install and use and high in construction efficiency, and has good practical value and application prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction devices, in particular to a non-counterweight hanging basket used for staggered cantilever structure buildings. Background Art

[0002] High-altitude working hanging baskets are widely used in the construction, decoration, cleaning and maintenance of exterior walls. They are one of the indispensable mechanical equipment for exterior wall construction. The upper part is fixed to the building by a roof suspension mechanism. At present, the roof suspension mechanism is commonly used to adopt the lever principle. It is composed of square tubes of different specifications and welded reinforcements, supplemented by steel wire ropes, inclined rods, counterweights, etc. Its front arm extends a certain distance outside the structure, and the rear arm is fixed to the suspension mechanism; however, in the construction of inter-layer staggered cantilever structures, the conventional lever-type hanging basket has many counterweights and connecting parts, and the construction is cumbersome, resulting in many potential safety hazards. The traditional counterweight hanging basket does not have ideal installation conditions on the staggered structure slab beam, and it is difficult to install it reliably. Utility Model Content

[0003] The utility model aims to solve the above deficiencies in the prior art and provides a non-counterweight hanging basket for staggered cantilever structure buildings.

[0004] The technical solution adopted by the utility model is: a weightless hanging basket for staggered cantilever structure buildings, comprising a hanging rope and a hanging basket, and also comprising a crossbeam and two brackets fixedly connected to the structural plate beam, the crossbeam is horizontally connected between the two brackets, and the hanging basket is connected to the crossbeam through the hanging rope; the bracket comprises a column, a diagonal brace and a base fixedly installed on the structural plate beam, the column is vertically connected to the base, and two diagonal braces symmetrically connect the column and the base on both sides of the column.

[0005] Furthermore, the base is provided with a U-shaped clip which is connected and fixed with the structural plate beam. The U-shaped clip includes a U-shaped steel plate and a post-anchor bolt. The U-shaped steel plate fastened on the base is anchored to the structural plate beam by the post-anchor bolt. There are no less than six U-shaped clips arranged on the base, which can stabilize the base and anchor it with the structural plate beam, making the hanging basket safer and more reliable to use.

[0006] Furthermore, the lifting rope is connected to the hanging basket through a PVC sleeve provided on the structural plate beam. The lifting rope is also provided with a limit piece for limiting the upward and downward movement of the hanging basket, which reliably limits the operation of the hanging basket and ensures safe operation.

[0007] Furthermore, the suspension rope is provided with a buckle and is fixed to the middle position of the crossbeam by the buckle, so as to maintain the structural force balance of the supporting hanging basket.

[0008] Furthermore, the crossbeam adopts Q235B steel rectangular tube with specifications of 80mm*80mm*4mm and a length of 2.3m; the column adopts Q235B steel rectangular tube with specifications of 80mm*80mm*4mm and a length of 1.0m; the diagonal brace adopts steel rectangular tube with specifications of 40mm*40mm*4mm and a length of 0.85m, so as to ensure that the device has high structural strength.

[0009] Furthermore, the U-shaped steel plate is made of 50*350*2mm Q235B steel plate, and the post-anchor bolt is a M10*80mm stainless steel anchor bolt, which can maintain a reliable anchoring strength between the base and the structural plate beam.

[0010] The utility model has the beneficial effect that the U-shaped steel plate on the base of the bracket of the hanging basket is anchored to the structural plate beam through the rear anchor bolt, so that the base can be stably connected with the structural plate beam, and the use of the hanging basket is safer and more reliable. The installation and construction is simple, the cost is low, the number of connecting parts is small, and the operation is safe and reliable.

[0011] Compared with the existing clamp-type suspension mechanism and wall-riding suspension mechanism without counterweight, the hanging basket suspension mechanism has no counterweight and solves the technical problem that the traditional hanging basket cannot be set up on the staggered cantilevered floor. The hanging basket has a simple structure, low cost, fast installation, flexible use, safety and reliability, which can greatly improve the construction efficiency. After the construction is completed, it can be disassembled as a whole and reused. Its installation and disassembly has no effect on the building structure itself, especially in the exterior wall construction of staggered buildings, it has good practical value and application prospects. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the structure of the utility model;

[0013] Figure 2 It is a schematic diagram of the anchor connection between the base and the structural beam plate of the utility model;

[0014] Figure 3 It is a side view of the bracket of the utility model;

[0015] Figure 4 It is a schematic diagram of the implementation of the utility model.

[0016] Parts in the figure: 1-crossbeam; 2-clip; 3-bracket; 31-column; 32-diagonal brace; 33-base; 5-structural plate beam; 6-limiting piece; 7-hanging basket; 9-hanging rope; 10-U-shaped clip; 11-rear anchor bolt; 12-U-shaped steel plate; 19-PVC casing. DETAILED DESCRIPTION

[0017] Reference Figures 1 to 4As shown, a weightless hanging basket for a staggered cantilever structure building includes a hanging rope 9 and a hanging basket 7, and also includes a crossbeam 1 and two brackets 3 fixedly connected to the structural plate beam 5, the crossbeam 1 is horizontally connected between the two brackets 3, and the hanging basket 7 is connected to the crossbeam 1 through the hanging rope 9; the bracket 3 includes a column 31, a diagonal brace 32 and a base 33 fixedly installed on the structural plate beam 5, the column 31 is vertically connected to the base 33, and two diagonal braces 32 symmetrically connect the column 31 and the base 33 on both sides of the column 31.

[0018] Among them, a U-shaped card 10 is provided on the base 33 and is connected and fixed to the structural plate beam 5. The U-shaped card 10 includes a U-shaped steel plate 12 and a post-anchor bolt 11. The U-shaped steel plate 12 fastened on the base 33 is anchored to the structural plate beam 5 through the post-anchor bolt 11. There are no less than six U-shaped cards 10 arranged on the base 33, which can make the base 33 firmly anchored to the structural plate beam 5, and the hanging basket 7 is safe and reliable to use.

[0019] The suspension rope 9 is connected to the hanging basket 7 through the PVC sleeve 19 provided on the structural plate beam 5. The suspension rope 9 is also provided with a limiter 6 for limiting the upward and downward movement of the hanging basket 7, which can reliably limit the operation of the hanging basket 7 and ensure safe operation.

[0020] The hanging rope 9 is provided with a buckle 2 and is fixed to the middle position of the crossbeam 1 by the buckle 2 to keep the structural force balance of the supporting hanging basket 7.

[0021] The crossbeam 1 is made of Q235B steel rectangular tube with a specification of 80mm*80mm*4mm and a length of 2.3m; the column 31 is made of Q235B steel rectangular tube with a specification of 80mm*80mm*4mm and a length of 1.0m; the diagonal brace 32 is made of steel rectangular tube with a specification of 40mm*40mm*4mm and a length of 0.85m, so as to ensure that the device has a high structural strength.

[0022] The U-shaped steel plate 12 is made of 50*350*2mm Q235B steel plate, and the rear anchor bolt 11 is a M10*80mm stainless steel anchor bolt, which can maintain a reliable anchoring strength between the base 33 and the structural plate beam 5.

[0023] Implementation process: During the construction of the inter-layer staggered cantilever structure, after the structural plate beam 5 of the cantilever structure reaches the structural strength, the installation of the non-counterweight hanging basket can be carried out. First, after measuring and laying out, holes are drilled in the structural plate beam 5; the PVC sleeve 19 and the U-shaped card 10 are installed, wherein the post-anchor bolt 11 has a drilling diameter of 13mm and a hole depth of 96mm, and the U-shaped steel plate 12 is fastened to the base 33 and anchored with the structural plate beam 5 by the post-anchor bolt 11; six U-shaped cards 10 are arranged on the base 33 of the present embodiment, and then the bracket 3 and the fixed beam 1 are installed; the lifting rope 9 passes through the PVC sleeve 19 on the structural plate beam 5 and is fixed in the middle position of the beam 1 by the buckle 2; after the lifting rope 9 is installed with the limit piece 6, it is installed with the hanging basket 7, and it can be put into use after the pre-weight test. After the construction is completed, the non-counterweight hanging basket can be disassembled and reused.

Claims

1. A non-counterweight hanging basket for a staggered cantilever structure building, comprising a hanging rope (9) and a hanging basket (7), characterized in that: It also comprises a crossbeam (1) and two brackets (3) fixedly connected to the structural plate beam, the crossbeam (1) being horizontally connected between the two brackets (3), and the hanging basket (7) being connected to the crossbeam (1) via a hanging rope (9); The support (3) comprises a column (31), a diagonal brace (32) and a base (33) fixedly mounted on a structural plate beam, wherein the column (31) is vertically connected to the base (33), and two diagonal braces (32) are symmetrically connected to the column (31) and the base (33) on both sides of the column (31).

2. The weightless hanging basket for staggered cantilevered structure buildings according to claim 1, characterized in that: The base (33) is provided with a U-shaped clip (10) connected and fixed to the structural plate beam, and the U-shaped clip (10) includes a U-shaped steel plate (12) and a post-anchor bolt (11). The U-shaped steel plate (12) fastened on the base (33) is anchored to the structural plate beam through the post-anchor bolt (11).

3. The weightless hanging basket for staggered cantilevered structure buildings according to claim 1, characterized in that: The suspension rope (9) is connected to the suspension basket (7) through a PVC sleeve (19) provided on the structural plate beam, and the suspension rope (9) is also provided with a limiting member (6) for limiting the upward and downward movement of the suspension basket (7).

4. The weightless hanging basket for staggered cantilevered structure buildings according to claim 1, characterized in that: The suspension rope (9) is provided with a buckle (2) and is fixed to the middle position of the crossbeam (1) via the buckle (2).

5. The weightless hanging basket for staggered cantilevered structure buildings according to claim 1, characterized in that: The cross beam (1) is made of Q235B steel rectangular tube with a specification of 80mm*80mm*4mm and a length of 2.3m; the upright column (31) is made of Q235B steel rectangular tube with a specification of 80mm*80mm*4mm and a length of 1.0m; the diagonal brace (32) is made of steel rectangular tube with a specification of 40mm*40mm*4mm and a length of 0.85m.