Floor slab construction reserved hole anti-seepage plugging structure
By forming enlarged grooves in the floor holes and pouring micro-expanded fine stone concrete of a higher grade in stages, combined with the use of waterproof coatings, the problem of poor waterproofing effect in the existing technology is solved and a more efficient anti-seepage effect is achieved. Reduced processing costs.
Patent Information
- Application Number
- CN202323362142.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-12-11
AI Technical Summary
The existing hole sealing technology for reserved floor construction has the problem of poor waterproofing effect. Especially during the subsequent decoration process, water seepage is prone to occur, resulting in property losses.
The anti-seepage sealing structure of reserved holes is adopted in graded construction, including forming enlarged grooves in the floor holes, pouring a higher grade micro-expanded fine stone concrete filling body in two times, and coating the gaps and surfaces with JS-II type waterproofing Paint to form a ladder structure to improve anti-seepage capabilities.
It significantly improves the anti-seepage capability of the reserved holes in the floor slab, reduces the cost of dealing with anti-seepage problems, and enhances the waterproofing effect through enlarged grooves and multi-layer waterproof coatings to avoid water seepage problems.
Smart Images

Figure CN221856294U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of floor slab construction, in particular to an anti-seepage plugging structure for reserved holes in floor slab construction. Background Art
[0002] At present, the reserved holes in the construction of building slabs are usually sealed with a one-time sealing method using a higher grade micro-expansive concrete without any anti-seepage measures. When the owner subsequently renovates and lays the floor tiles, the reserved holes are prone to water seepage, which will further cause property losses to the residents downstairs.
[0003] Currently, there is a utility model patent with application number 202020001667.4 and invention name: A device for sealing reserved holes. It discloses a solution for sealing holes using a device similar to an umbrella rib structure in combination with a steel sleeve and a support plate. It can improve the sealing effect and thus enhance the waterproof performance. However, this sealing solution relies on operator proficiency and is prone to poor waterproofing due to improper construction.
[0004] For example, the application number is CN202121110287.5, and the name of the invention is: A new type of anti-leakage hole sealing structure sealing tool and house building, which uses an anti-leakage cover to fill the holes, but if this additional device is not well protected during the subsequent construction process, it is easy to be damaged or collided, causing displacement, affecting the sealing effect.
[0005] How to improve the traditional concrete sealing solution to solve the leakage problem is a new problem that needs to be solved urgently. Utility Model Content
[0006] The utility model aims to address the deficiencies of the prior art and thus provide a floor slab construction reserved hole anti-seepage plugging structure with graded construction and improved anti-seepage effect.
[0007] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: an anti-seepage plugging structure for reserved holes in floor construction, including floor holes, floor expansion grooves, a first concrete filling body, a second concrete filling body, a waterproof coating interlayer, and a waterproof coating surface layer;
[0008] The floor holes are through holes that penetrate the floor;
[0009] The floor expansion groove is a groove arranged above the floor hole and having a diameter larger than the floor hole, and the upper end opening of the floor hole is located in the floor expansion groove;
[0010] The first concrete filling body is filled in the holes of the floor slab;
[0011] The second concrete filling body is filled in the floor slab expansion groove;
[0012] A waterproof coating interlayer is arranged between the floor slab enlarged groove and the second concrete filling body, a waterproof coating surface layer is arranged on the surface of the second concrete filling body, and the waterproof coating surface layer extends in all directions to cover the transition joint between the floor slab and the floor slab enlarged groove.
[0013] Based on the above, the first concrete filling body is a slightly expanded fine stone concrete with a grade one level higher than that of the floor slab concrete.
[0014] Based on the above, the second concrete filling body is a slightly expanded fine stone concrete with a grade one level higher than that of the floor slab concrete.
[0015] Based on the above, the depth of the floor slab enlarged groove is ≥20 mm, and the thickness of the second concrete filling body is equal to the groove depth of the floor slab enlarged groove.
[0016] Based on the above, the diameter of the floor expansion groove is at least twice the diameter of the floor hole.
[0017] Based on the above, the thickness of the waterproof coating interlayer and the waterproof coating surface layer are both ≥1.5mm.
[0018] Based on the above, the model of the waterproof coating interlayer and the waterproof coating surface layer is JS-II waterproof coating.
[0019] Based on the above, the dimension of the waterproof coating surface layer extending outward from the transition joint is ≥5cm.
[0020] Compared with the prior art, the utility model has substantial characteristics and progress. Specifically, on the basis of traditional floor holes, the utility model excavates the upper part of the hole to form an enlarged groove around it, and the sealing concrete is poured in two times, and waterproof coating is applied after each concrete pouring. The stepped structure formed by the two pourings and the increased waterproof coating interlayer and surface layer are utilized to improve the anti-seepage ability of the reserved holes in the floor, and especially save the cost invested in dealing with the anti-seepage problem. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural principle diagram of the anti-seepage plugging structure of the reserved holes in the floor construction of the utility model.
[0022] In the figure: 1. Floor holes; 2. Floor expansion grooves; 3. First concrete filling body; 4. Second concrete filling body; 5. Waterproof coating interlayer; 6. Waterproof coating surface layer; 7. Transition joint. DETAILED DESCRIPTION
[0023] The technical solution of the utility model is further described in detail below through specific implementation methods.
[0024] like Figure 1 As shown, a structure for anti-seepage plugging of reserved holes in floor construction includes a floor hole 1, a floor expansion groove 2, a first concrete filling body 3, a second concrete filling body 4, a waterproof coating interlayer 5, and a waterproof coating surface layer 6.
[0025] The floor hole 1 is a through hole penetrated on the floor, and the floor expansion groove 2 is a groove arranged above the floor hole 1 and having a diameter larger than the floor hole 1. The upper end opening of the floor hole 1 is located in the floor expansion groove 2. In this embodiment, the floor expansion groove 2 is concentric with the floor hole 1, and the diameter of the floor expansion groove 2 is at least twice that of the floor hole 1 to form a step-type hole with a stable structure. When water seepage occurs, the seepage water flow must first pass through the steps before entering the floor hole 1 below, which greatly improves the water seepage problem.
[0026] The first concrete filling body 3 is filled in the floor slab hole 1, and the first concrete filling body 3 is a slightly expanded fine stone concrete with a grade one level higher than that of the floor slab concrete.
[0027] The second concrete filling body 4 is filled in the floor expansion groove. The second concrete filling body is a slightly expanded fine stone concrete with a grade one level higher than the floor concrete. The depth of the floor expansion groove is ≥20mm, and the thickness of the second concrete filling body is equal to the groove depth of the floor expansion groove.
[0028] A waterproof coating interlayer is arranged between the floor expansion groove 2 and the second concrete filling body 4, and a waterproof coating surface layer is arranged on the surface of the second concrete filling body. The waterproof coating surface layer extends in all directions to cover the transition joint 7 between the floor and the floor expansion groove, and the dimension of the waterproof coating surface layer 6 extending outward from the transition joint is ≥5cm.
[0029] The thickness of the waterproof coating interlayer 5 and the waterproof coating surface layer 6 are both ≥1.5 mm, and the model of the waterproof coating interlayer 5 and the waterproof coating surface layer 6 is JS-II waterproof coating.
[0030] This scheme was experimentally verified in the main project of the shantytown renovation project on Jinghua West Road (Zhaizi Village) in Lushi County. This project is a traditional house construction project. During the construction process, it is necessary to reserve holes for cantilever scaffolding channel steel rings, concrete pouring pump pipe holes, and wire holes on the floor slab. Some holes will be reserved in the bathroom. It is very important to do a good job of anti-seepage plugging of the above reserved holes. Brief description of the anti-seepage plugging method for reserved holes: chisel down around the reserved holes to form an enlarged groove, pour the plugging concrete in two times, and apply waterproof paint on the top of the concrete each time.
[0031] The main construction steps are:
[0032] (1) Expand the area around the reserved hole by 10 cm and chisel 2 cm downwards, making sure that the steel bars of the floor slab are not exposed during the chiseling process;
[0033] (2) Roughen the inner wall of area A;
[0034] (3) Rinse areas A and B with clean water;
[0035] (4) Use formwork to seal the bottom of area A and pour concrete in area A;
[0036] (5) Apply 1.5 mm thick JS-II waterproof coating evenly on the bottom and sides of area B;
[0037] (6) Pouring concrete in area B;
[0038] (7) Apply 1.5mm thick JS-II waterproof coating evenly on the top of the concrete in area B, and the coating range needs to be extended by 5cm. The concrete in areas A and B are both micro-expansive fine stone concrete of a higher grade.
[0039] Finally, it should be noted that: The above describes in detail the preferred implementation of this patent, but this patent is not limited to the above implementation. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of this patent.
Claims
1. An anti-seepage plugging structure for reserved holes in floor construction, characterized in that: It includes floor holes, floor expansion grooves, a first concrete filling body, a second concrete filling body, a waterproof coating interlayer, and a waterproof coating surface layer; The floor holes are through holes that penetrate the floor; The floor expansion groove is a groove arranged above the floor hole and having a diameter larger than the floor hole, and the upper end opening of the floor hole is located in the floor expansion groove; The first concrete filling body is filled in the holes of the floor slab; The second concrete filling body is filled in the floor slab expansion groove; A waterproof coating interlayer is arranged between the floor slab enlarged groove and the second concrete filling body, a waterproof coating surface layer is arranged on the surface of the second concrete filling body, and the waterproof coating surface layer extends in all directions to cover the transition joint between the floor slab and the floor slab enlarged groove.
2. The anti-seepage plugging structure for reserved holes in floor construction according to claim 1 is characterized by: The first concrete filling body is slightly expanded fine stone concrete with a grade one level higher than that of the floor slab concrete.
3. The anti-seepage plugging structure for reserved holes in floor construction according to claim 1 or 2, characterized in that: The second concrete filling body is slightly expanded fine stone concrete with a grade one level higher than that of the floor slab concrete.
4. The anti-seepage plugging structure for reserved holes in floor construction according to claim 3 is characterized by: The depth of the floor slab enlarged groove is ≥20 mm, and the thickness of the second concrete filling body is equal to the groove depth of the floor slab enlarged groove.
5. The anti-seepage plugging structure for reserved holes in floor construction according to claim 4 is characterized by: The diameter of the floor slab enlarged groove is at least twice the diameter of the floor slab hole.
6. The anti-seepage plugging structure for reserved holes in floor construction according to claim 5, characterized in that: The thickness of the waterproof coating interlayer and the waterproof coating surface layer are both ≥1.5mm.
7. The anti-seepage plugging structure for reserved holes in floor construction according to claim 6 is characterized by: The model of the waterproof coating interlayer and the waterproof coating surface layer is JS-II waterproof coating.
8. The anti-seepage plugging structure for reserved holes in floor construction according to claim 7 is characterized by: The dimension of the waterproof coating surface layer extending outward from the transition joint is ≥5cm.