Hot air supply system based on cooperation of heat pump and electric heating of drying equipment
By combining a heat pump and an electric heating system in the drying equipment, the fresh air is preheated and the flue gas is recovered, which solves the problems of high heating power consumption of the drying equipment and insufficient temperature of the heat pump, and realizes an efficient and energy-saving heating air system, which reduces costs. Electric heating equipment consumes more power and increases the temperature of hot air.
Patent Information
- Application Number
- CN202323211372.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-28
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2033-11-28
AI Technical Summary
Existing drying equipment consumes a lot of power during the heating process, and the heat supplied by the heat pump is not sufficient to meet high temperature requirements. Furthermore, the improvement of the combination of electric heating and heat pumps requires high costs and long production shutdowns for modification, which is difficult for enterprises to accept.
On the basis of the original electric heating system, a heat pump is added to preheat the fresh air, and then electric heating is used to bring the hot air to the required temperature. Combined with the flue gas recovery heat exchanger and heat pump heating system, a dual energy-saving effect is achieved, and the hot air temperature and temperature rise are increased. rate.
Through preheating and flue gas recovery, the power consumption of electric heating equipment is significantly reduced, the heating rate of hot air temperature is increased, higher temperature requirements and energy saving effects are achieved, and changes to the original process control method are avoided.
Smart Images

Figure CN221859165U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of heat pumps, and in particular to a hot air supply system based on a heat pump and electric heating of drying equipment. Background Art
[0002] Drying equipment refers to a combination of a series of mechanical equipment that uses certain technical means to dry the moisture or other liquids on the surface of objects, such as ovens, dryers, clothes dryers, etc. At present, drying equipment mainly uses electric heating to heat the fresh air to a set temperature threshold to form high-temperature hot air, which is then transported to the drying equipment to heat or dry the materials. Since the use of electric heating alone to heat the fresh air consumes a lot of electricity, a high-power electric heating device is required to meet the requirement of heating such a large air volume.
[0003] Heat pump is a highly efficient energy-saving device that fully utilizes low-grade thermal energy. Heat can be transferred spontaneously from a high-temperature object to a low-temperature object, but not spontaneously in the opposite direction. The working principle of a heat pump is a mechanical device that forces heat to flow from a low-temperature object to a high-temperature object in a reverse cycle. It consumes only a small amount of reverse cycle net work to obtain a large amount of heat supply, and can effectively utilize the low-grade thermal energy that is difficult to use to achieve energy saving.
[0004] At present, drying equipment either uses electric heating or heat pumps for heating. Electric heating consumes a lot of electricity, and the temperature of the hot air obtained by the heat pump is 60℃-80℃. Moreover, if the heat pump is used alone to provide hot air for the drying equipment, the temperature of the hot air cannot meet higher temperature requirements, such as 100℃-150℃, which greatly hinders the research and development and application of heat pumps in more drying industries. In the prior art, drying equipment also uses electric heating + heat pumps. The electric heating is set at the hot water outlet of the heat pump, and the hot water is heated to a high temperature again, and then heat exchanged with the fresh air to increase its temperature. However, for some old drying equipment using electric heating, if this structural improvement is adopted, it is often necessary to comprehensively improve the entire process and control system before the technology can be used. However, this modification cost is high, and it also needs to be shut down for a long time before the modification can be completed, which will affect the production of the entire enterprise. Therefore, many enterprises are unwilling to adopt this modification method. Utility Model Content
[0005] In order to overcome the shortcomings of the prior art, the utility model provides a hot air supply system based on a heat pump and electric heating of a drying equipment to solve the above-mentioned traditional problems. On the basis of the original electric heating hot air system, a heat pump is added in front of the electric heating equipment, and the heat pump is used to preheat the fresh air, and then the hot air is heated by electricity to reach the required temperature, and finally sent into the drying equipment to heat the material.
[0006] The utility model is implemented by the following technical solutions:
[0007] A heating air supply system based on a heat pump and electric heating of a drying device, the drying device comprising at least one hot air inlet, at least one hot air exhaust outlet and a main exhaust duct connected to the hot air exhaust outlet, the heating air supply system being provided with a primary filter, a fan, a flue gas recovery heat exchanger, a heat pump heating system and an electric heating heat exchanger in sequence along the flow direction of fresh air, the flue gas recovery heat exchanger being used to be installed on the main exhaust duct, the heat pump heating system comprising a compressor, a condenser, a throttling expansion valve, an evaporator and a separator connected end to end, the heat exchange ends of the condenser being respectively connected to the flue gas recovery heat exchanger and the electric heating heat exchanger, and the hot air outlet of the electric heating heat exchanger being used to be connected to the hot air inlet.
[0008] Preferably, a mixer is provided between the heat exchange end of the condenser and the electric heating heat exchanger, and the mixer is connected to a circulating air duct, one end of which is used to be connected between the hot air exhaust port and the flue gas recovery heat exchanger.
[0009] Preferably, the mixer is a mixing tank or an ejector.
[0010] Preferably, when the mixer is an ejector, the ejector includes an ejector flow inlet, an ejected flow inlet and an ejection outlet, the ejector flow inlet is connected to the heat exchange end outlet of the condenser, the ejected flow inlet is connected to the air outlet of the circulating air duct, and the ejection outlet is connected to the air inlet of the electric heating heat exchanger.
[0011] Preferably, a high temperature resistant medium efficiency filter / high temperature resistant high efficiency filter is also provided at the rear end of the electric heating heat exchanger.
[0012] Preferably, the fan is a blower.
[0013] The utility model is also implemented by the following technical solutions:
[0014] A heat pump-assisted heating air supply system based on a drying device, the drying device comprising at least one hot air inlet, at least one hot air exhaust outlet and an exhaust main duct connected to the hot air exhaust outlet, the hot air supply system being provided with a primary filter, a fan, a flue gas recovery heat exchanger, a heat pump heating system and an electric heating heat exchanger in sequence along the flow direction of fresh air, the flue gas recovery heat exchanger being used to be installed on the exhaust main duct, the heat pump heating system comprising a compressor, a condenser, a throttling expansion valve, an evaporator, a separator, a water storage tank, a water pump and a preheating heat exchanger, the compressor, the condenser, the throttling expansion valve, the evaporator and the separator being connected end to end to form a preheating circulation system, the water inlet of the water storage tank and the water outlet of the preheating heat exchanger being respectively connected to the heat exchange end of the condenser, the water pump being arranged on the water outlet pipe of the water storage tank, the preheating heat exchanger being arranged between the flue gas recovery heat exchanger and the electric heating heat exchanger, and the hot air outlet of the electric heating heat exchanger being used to be connected to the hot air inlet.
[0015] Preferably, the heat pump heating system further comprises a circulating water pipeline, and both ends of the circulating water pipeline are respectively connected to the outlet of the water pump and the water inlet of the heat exchange end of the condenser.
[0016] Compared with the prior art, the beneficial effects of the present invention are:
[0017] 1. The heating air system of the utility model uses the functions of flue gas recovery heat exchanger, heat pump heating system, electric heating heat exchanger and other equipment. The flue gas recovery heat exchanger is used to recover the waste heat of the exhaust air, and the heat pump heating system is used to preheat the fresh air in a further step. Finally, the electric heating heat exchanger is used to heat the fresh air to the required temperature requirement. The system combines the flue gas recovery heat exchanger, heat pump heating system and other structures to achieve a dual energy-saving effect, realize preheating of the fresh air, and save the heating power when the fresh air is raised from low temperature to high temperature, which can greatly reduce the power consumption of the electric heating equipment and also increase the heating rate of the hot air temperature.
[0018] 2. The hot air supply system of the utility model adds a heat pump before the air inlet of the electric heating heat exchanger on the basis of the original electric heating hot air system to preheat the fresh air, that is, a condenser installation position is opened in front of the electric heating heat exchanger. There is no need to change the control method of the original process. The final hot air temperature requirement is controlled by the electric heating equipment, so that the temperature of the hot air can reach a higher temperature requirement, thereby achieving the effect of saving electricity.
[0019] 3. The heating air system of the utility model is provided with a circulating air duct, which recycles part of the exhaust air and mixes it with the fresh air, and then reuses it after increasing its dryness through electric heating equipment, so that the energy-saving effect of the system is better. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1It is a schematic diagram of the connection structure of the hot air supply system of the first embodiment on the drying equipment;
[0021] Figure 2 It is a schematic diagram of the connection structure of the hot air supply system of the second embodiment on the drying equipment;
[0022] Figure 3 It is a first structural schematic diagram of the heat pump heating system of the utility model;
[0023] Figure 4 It is a second structural schematic diagram of the heat pump heating system of the utility model;
[0024] Figure 5 It is a schematic diagram of the connection structure of the hot air supply system of the third embodiment on the drying equipment;
[0025] Figure 6 It is a schematic diagram of the connection structure of the hot air supply system of the fourth embodiment on the drying equipment.
[0026] In the figure: 10, drying equipment; 11, exhaust main duct; 20, heating air system; 21, primary filter; 22, fan; 23, flue gas recovery heat exchanger; 24, heat pump heating system; 240, compressor; 241, condenser; 242, throttling expansion valve; 243, evaporator; 244, separator; 245, water storage tank; 246, water pump; 25, electric heating heat exchanger; 26, mixer; 260, circulating air duct. DETAILED DESCRIPTION
[0027] In order to make the above-mentioned purposes, features and advantages of the utility model more obvious and easy to understand, the specific implementation methods of the utility model are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the utility model. However, the utility model can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the utility model, so the utility model is not limited by the specific embodiments disclosed below.
[0028] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, "plurality" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0029] In the description of the present utility model, it is necessary to understand that when an element is considered to be "connected" to another element, it may be directly connected to another element or there may be intermediate elements at the same time. On the contrary, when an element is said to be "directly" connected to another element, there are no intermediate elements.
[0030] See also Figure 1 , is a heating air supply system 20 of the first embodiment, which is a heating air supply structure based on the heat pump of the drying equipment 10 and electric heating, and is used to supply hot air for the drying equipment 10. Specifically, the drying equipment 10 includes at least one hot air inlet, at least one hot air exhaust port and an exhaust main duct 11 connected to the hot air exhaust port. The heating air supply system 20 is sequentially arranged along the fresh air flow direction with a primary filter 21, a fan 22, a flue gas recovery heat exchanger 23, a heat pump heating system 24 and an electric heating heat exchanger 25. The flue gas recovery heat exchanger 23 is used to be installed on the exhaust main duct 11. The heat pump heating system 24 includes a compressor 240, a condenser 241, a throttling expansion valve 242, an evaporator 243 and a separator 244 (such as Figure 3 ), the heat exchange ends of the condenser 241 are respectively connected to the flue gas recovery heat exchanger 23 and the electric heating heat exchanger 25, and the hot air outlet of the electric heating heat exchanger 25 is used to be connected to the hot air inlet.
[0031] The above-mentioned heating air system 20 is achieved through the functions of equipment such as the flue gas recovery heat exchanger 23, the heat pump heating system 24, and the electric heating heat exchanger 25. The flue gas recovery heat exchanger 23 is used to recover the waste heat of the exhaust air, and the heat pump heating system 24 is used to preheat the fresh air in a further step. Finally, the fresh air is heated by the electric heating heat exchanger 25 to reach the required temperature requirement. The system combines structures such as the flue gas recovery heat exchanger 23 and the heat pump heating system 24 to achieve a dual energy-saving effect, realize preheating of the fresh air, and save the heating power when the fresh air is raised from low temperature to high temperature, which can greatly reduce the power consumption of the electric heating equipment and also increase the heating rate of the hot air temperature.
[0032] In this embodiment, a mixer 26 is further provided between the heat exchange end of the condenser 241 and the electric heating heat exchanger 25. The mixer 26 is connected to a circulating air duct 260. One end of the circulating air duct 260 is used to connect between the hot air exhaust port and the flue gas recovery heat exchanger 23. This structure recovers part of the exhaust air and mixes it with the fresh air, and then reuses it after increasing its dryness through the electric heating device, so that the energy saving effect of the system is better. In one embodiment, the mixer 26 is a mixing tank or an ejector. When the mixer 26 is an ejector, such as Figure 2In the heating air supply system 20 of the second embodiment shown, the ejector includes an ejection flow inlet, an ejected flow inlet and an ejection outlet, the ejection flow inlet is connected to the heat exchange end outlet of the condenser 241, the ejected flow inlet is connected to the air outlet of the circulating air duct 260, and the ejection outlet is connected to the air inlet of the electric heating heat exchanger 25. By taking advantage of the fact that the wind force of the fresh air is greater than the wind force of the return air, part of the return air is sucked in to achieve uniform mixing of the mixed air.
[0033] In other embodiments, the rear end of the electric heating heat exchanger 25 is also provided with a high temperature resistant medium efficiency filter / high temperature resistant high efficiency filter. In this embodiment, the primary filter 21, the high temperature resistant medium efficiency filter, the high temperature resistant high efficiency filter and other filters are bag filters to filter impurities and moisture in the fresh air to prevent these substances from causing other effects on the heated materials. The filtering accuracy, temperature requirements and models are existing technologies, which are specifically selected according to needs and will not be repeated here. The electric heating heat exchanger 25 is provided with an electric heating coil.
[0034] In this embodiment, the fan 22 is a blower 22 .
[0035] like Figure 1 , Figure 2 Combination Figure 4 , another heat pump heating system 24 is provided. Specifically, the drying equipment 10 includes at least one hot air inlet, at least one hot air exhaust port and an exhaust main duct 11 connected to the hot air exhaust port. The hot air supply system 20 is sequentially provided with a primary filter 21, a fan 22, a flue gas recovery heat exchanger 23, a heat pump heating system 24 and an electric heating heat exchanger 25 along the fresh air flow direction. The flue gas recovery heat exchanger 23 is used to be installed on the exhaust main duct 11. The heat pump heating system 24 includes a compressor 240, a condenser 241, a throttling expansion valve 242, and an evaporator 243. , separator 244, water storage tank 245, water pump 246 and preheating heat exchanger, the compressor 240, condenser 241, throttling expansion valve 242, evaporator 243 and separator 244 are connected end to end to form a preheating circulation system, the water inlet of the water storage tank 245 and the water outlet of the preheating heat exchanger are respectively connected to the heat exchange end of the condenser 241, the water pump 246 is arranged on the water outlet pipe of the water storage tank 245, the preheating heat exchanger is arranged between the flue gas recovery heat exchanger 23 and the electric heating heat exchanger 25, and the hot air outlet of the electric heating heat exchanger 25 is used to be connected to the hot air inlet.
[0036] The above-mentioned heating air system 20 can heat water in advance by using the heat pump principle through the use of the water storage tank 245. The obtained hot water is stored in the water storage tank 245. It can also use the off-peak electricity situation to pre-heat the water to improve the stability of the equipment. At the same time, the heat pump heating system 24 can also be moved outside the original drying room, and only the pre-heating heat exchanger is retained to avoid the inconvenience of installing the heat pump heating system 24 due to insufficient floor space in the drying room, or the heating effect is affected by the long refrigerant pipeline (such as the structure of the heat pump heating system 24 in the first embodiment), so as to improve the convenience of installation or modification.
[0037] In this embodiment, the heat pump heating system 24 also includes a circulating water pipe, the two ends of which are respectively connected to the outlet of the water pump 246 and the water inlet of the heat exchange end of the condenser 241 to form circulating heating and store heat in the water storage tank 245 for subsequent use.
[0038] For example Figure 5 , which is a heating air supply system 20 of the third embodiment of the utility model. Different from the first embodiment, the drying equipment 10 includes 5 drying boxes, each of which includes a hot air inlet and a hot air exhaust port, each hot air inlet is connected to a separate heating air supply system 20, each heating air supply system 20 is provided with fresh air by a total hot air supply main pipe, and each hot air exhaust port is collected in the same exhaust main pipe 11 for external discharge, and the heating air supply system 20 is arranged with a flue gas recovery heat exchanger 23, a heat pump heating system 24 and an electric heating heat exchanger 25, and the hot air supply main pipe is arranged with a primary filter 21, a fan 22 and a flue gas recovery heat exchanger 23, and the flue gas recovery heat exchanger 23 is arranged on the exhaust main pipe 11, and the heat pump heating system 24 is as shown in FIG. Figure 3 / Figure 4 The heat pump heating system 24 is the same as the heat pump heating system 24, and the fresh air volume and exhaust air volume are controlled by setting control valves in each device. Other structures are similar to the heating air supply system 20 of the first embodiment. Among them, the mixer 26 is a mixing tank.
[0039] like Figure 6 , which is a heating air supply system 20 of the fourth embodiment of the utility model, is different from the third embodiment in that the mixer 26 is an ejector, through which the return air is sucked.
[0040] In the above embodiments, each pipeline or equipment is also provided with control valves, temperature gauges, pressure gauges and other instrument valves to achieve the normal operation of each system. Since it is not the focus of the present invention, it will not be described here.
[0041] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0042] The above-mentioned embodiments only express several implementation methods of the utility model, and the description is relatively specific and detailed, but it cannot be understood as limiting the scope of the utility model patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the utility model, which all belong to the protection scope of the utility model. Therefore, the protection scope of the utility model patent shall be based on the attached claims.
Claims
1. A hot air supply system based on a heat pump and electric heating of a drying device, wherein the drying device comprises at least one hot air inlet, at least one hot air outlet and an exhaust main duct connected to the hot air outlet, characterized in that: The heating air system is provided with a primary filter, a fan, a flue gas recovery heat exchanger, a heat pump heating system and an electric heating heat exchanger in sequence along the fresh air flow direction. The flue gas recovery heat exchanger is used to be installed on the exhaust main duct. The heat pump heating system includes a compressor, a condenser, a throttling expansion valve, an evaporator and a separator connected end to end. The heat exchange ends of the condenser are respectively connected to the flue gas recovery heat exchanger and the electric heating heat exchanger. The hot air outlet of the electric heating heat exchanger is used to be connected to the hot air inlet; a mixer is also provided between the heat exchange end of the condenser and the electric heating heat exchanger. The mixer is connected to a circulating air duct. One end of the circulating air duct is used to be connected between the hot air exhaust port and the flue gas recovery heat exchanger; the mixer is a mixing tank or an ejector.
2. The heating air supply system according to claim 1, characterized in that: When the mixer is an ejector, the ejector includes an ejection flow inlet, an ejected flow inlet and an ejection outlet, the ejection flow inlet is connected to the heat exchange end outlet of the condenser, the ejected flow inlet is connected to the air outlet of the circulating air duct, and the ejection outlet is connected to the air inlet of the electric heating heat exchanger.
3. The heating air supply system according to claim 1, characterized in that: The rear end of the electric heating heat exchanger is also provided with a high temperature resistant medium efficiency filter / high temperature resistant high efficiency filter.
4. The heating air supply system according to claim 1, characterized in that: The fan is a blower.
5. A hot air supply system based on a heat pump combined with electric heating of a drying device, wherein the drying device comprises at least one hot air inlet, at least one hot air outlet and a main exhaust duct connected to the hot air outlet, characterized in that: The heating air system is provided with a primary filter, a fan, a flue gas recovery heat exchanger, a heat pump heating system and an electric heating heat exchanger in sequence along the fresh air flow direction. The flue gas recovery heat exchanger is used to be installed on the exhaust main pipeline. The heat pump heating system includes a compressor, a condenser, a throttling expansion valve, an evaporator, a separator, a water storage tank, a water pump and a preheating heat exchanger. The compressor, condenser, throttling expansion valve, evaporator and separator are connected end to end to form a preheating circulation system. The water inlet of the water storage tank and the outlet of the preheating heat exchanger are connected end to end. The water inlets are respectively connected to the heat exchange ends of the condensers, the water pump is arranged on the water outlet pipe of the water storage tank, the preheating heat exchanger is arranged between the flue gas recovery heat exchanger and the electric heating heat exchanger, and the hot air outlet of the electric heating heat exchanger is used to be connected to the hot air inlet; a mixer is also provided between the preheating heat exchanger and the electric heating heat exchanger, and the mixer is connected to a circulating air duct, and one end of the circulating air duct is used to be connected between the hot air exhaust port and the flue gas recovery heat exchanger; the mixer is a mixing tank or an ejector.
6. The heating air supply system according to claim 5, characterized in that: The heat pump heating system also includes a circulating water pipeline, and both ends of the circulating water pipeline are respectively connected to the outlet of the water pump and the water inlet of the heat exchange end of the condenser.
Citation Information
Cited By
Centralized control energy-saving control system, computer equipment and computer readable storage medium
CN117469959A
A centralized energy-saving control system, computer equipment, and computer-readable storage medium
CN117469959B