Settlement displacement observation device for water transfer project

By using the sealing design of the linkage rod and the protective cover in the settlement displacement observation device of the water diversion project, the problem of observation accuracy under the influence of external wind and water flow is solved, and accurate measurement of the settlement and displacement of the dam is achieved.

CN221859548UInactive Publication Date: 2024-10-18山东省调水工程运行维护中心
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420540249.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing settlement displacement observation device of the water diversion project is affected by external wind and water flow, and the observation accuracy is affected, affecting the safety and stable operation of the dam.

Method used

A device including a linkage rod, a benchmark pole, a linkage sleeve, a protective cover and a sealing gasket is designed. The protective cover is closely attached to the dam through the sealing gasket to reduce external interference, and the settlement displacement is measured through the observation piece and the contact piece.

Benefits of technology

It effectively reduces external interference, improves the accuracy of observation, and ensures accurate measurement of dam settlement and displacement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221859548U_ABST
    Figure CN221859548U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of dam settlement monitoring, and particularly relates to a water transfer project settlement displacement observation device which comprises a linkage rod, the linkage rod is installed at a dam, a fixing sleeve is installed on the surface of the linkage rod, a marker post is arranged on one side of the linkage rod, and the marker post penetrates through the dam to be inserted into the ground. A slidable linkage sleeve is installed on the surface of the marker post, a connecting rod is installed between the linkage sleeve and the fixing sleeve, a protective cover is arranged at the top of the linkage rod and used for covering the linkage rod and the marker post, and the bottom of the surface of the protective cover is sleeved with a mounting base. According to the utility model, the protective cover covers the original structure, and then the protective cover is sealed through the arrangement of the mounting seat and the sealing gasket, so that the stability of the structure in the protective cover during use is effectively ensured, and when the settlement is observed, the observation is not influenced by external water, wind and the like; and therefore, the observation accuracy is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of dam settlement monitoring, in particular to a settlement displacement observation device for a water diversion project. Background Art

[0002] The water diversion project settlement and displacement observation device is mainly used to observe the settlement and displacement of the water diversion project dam. Specifically, the device sets a vertically distributed benchmark structure between the water diversion project dam and the ground, and the linkage rod is installed on the water diversion project dam, which follows the synchronous settlement and displacement of the water diversion project dam. When the linkage rod settles, the linkage slider is driven to slide downward synchronously through the connecting piece. The distance the linkage slider moves downward is the settlement depth of the water diversion project dam. In this way, the settlement and displacement of the dam can be observed and recorded conveniently and intuitively, thereby ensuring the safety and stable operation of the water diversion project. When observing, since each structure is exposed to the air, it is easy to be affected by external wind and water flow, which affects the accuracy of observation, and thus affects the observation effect of the dam. Utility Model Content

[0003] In order to solve the above problems, the utility model proposes a water diversion project settlement displacement observation device to more accurately solve the problems raised in the above background technology.

[0004] The utility model is realized by the following technical solutions:

[0005] The utility model proposes a settlement and displacement observation device for a water diversion project, comprising a linkage rod, wherein the linkage rod is installed at the dam, a fixed sleeve is installed on the surface of the linkage rod, a benchmark is arranged on one side of the linkage rod, the benchmark penetrates the dam and is inserted into the ground, a slidable linkage sleeve is installed on the surface of the benchmark, a connecting rod is installed between the linkage sleeve and the fixed sleeve, a protective cover is arranged on the top of the linkage rod, the protective cover is used to cover the linkage rod and the benchmark, a mounting seat is sleeved on the bottom of the surface of the protective cover, the mounting seat is detachably connected to the dam, a sealing pad is installed on the bottom of the protective cover, and the sealing pad is tightly fitted to the dam.

[0006] Preferably, a locking piece is installed on the top of the mounting seat, a sleeve plate is installed on the surface of the protective cover, and the locking piece is used to push the sleeve plate.

[0007] Preferably, a circular plate is installed on the surface of the mounting seat, and the circular plate is tightly fitted to the dam and fixed to the dam by screws.

[0008] Preferably, a contact piece is installed on the surface of the linkage sleeve, and an observation piece is installed on the inner wall of the protective cover, and the observation piece is used to measure the displacement change of the contact piece when the position of the contact piece changes.

[0009] Preferably, a mounting rod is installed on the back of the observation piece, the mounting rod is connected to the protective cover, and a touch rod is installed on the bottom of the observation piece, and the touch rod is in contact with the linkage sleeve.

[0010] Preferably, the locking member comprises a threaded ring mounted on the top of the mounting seat, a threaded rod is threadedly connected to the inner wall of the threaded ring, the threaded rod passes through the mounting seat and is inserted into the top of the sleeve plate and is rotatably connected to the sleeve plate via a bearing.

[0011] Preferably, a mounting plate is installed at the bottom of the linkage rod, and a limit seat is connected to the surface of the mounting plate by screws, and the limit seat is installed at the dam.

[0012] Preferably, an observation window is provided on the surface of the protective cover for observing the measurement result after the observation piece is measured.

[0013] Compared with the prior art, the utility model provides a water diversion project settlement displacement observation device, which has the following beneficial effects:

[0014] The water diversion project settlement displacement observation device, by covering the protective cover on the original structure and then sealing the protective cover through the arrangement of a mounting seat and a sealing gasket, effectively ensures the stability of the structure inside the protective cover during use, so that when observing the settlement, it will not be affected by external water and wind, thereby ensuring the accuracy of the observation.

[0015] The water diversion project settlement displacement observation device is installed on the upper side of the linkage sleeve through the observation piece, so that when the dam settles, it can effectively measure the settlement value at the first time, thereby effectively ensuring the accuracy of the measurement. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a structural schematic diagram of a water diversion project settlement displacement observation device proposed by the utility model;

[0017] Figure 2 This is a schematic diagram of the structure of a water diversion project settlement displacement observation device before improvement proposed by the utility model;

[0018] Figure 3 The utility model is a structural cross-sectional view of a water diversion project settlement displacement observation device.

[0019] In the figure: 1. linkage rod; 11. mounting plate; 12. limit seat; 2. fixing sleeve; 3. benchmark; 4. linkage sleeve; 41. contact piece; 5. connecting rod; 6. protective cover; 61. sleeve plate; 7. mounting seat; 71. circular plate; 72. locking piece; 8. sealing gasket; 9. observation piece; 91. mounting rod; 92. touch rod. DETAILED DESCRIPTION

[0020] In order to more clearly and completely illustrate the technical solution of the present invention, the present invention is further described below in conjunction with the accompanying drawings.

[0021] Example

[0022] like Figure 1-Figure 3 As shown, a device for observing the settlement and displacement of a water diversion project proposed in an embodiment of the utility model comprises a linkage rod 1, which is installed at the dam. A fixed sleeve 2 is installed on the surface of the linkage rod 1. A benchmark rod 3 is arranged on one side of the linkage rod 1. The benchmark rod 3 penetrates the dam and is inserted into the ground. A slidable linkage sleeve 4 is installed on the surface of the benchmark rod 3. A connecting rod 5 is installed between the linkage sleeve 4 and the fixed sleeve 2. A protective cover 6 is arranged on the top of the linkage rod 1. The protective cover 6 is used to cover the linkage rod 1 and the benchmark rod 3. A mounting seat 7 is sleeved on the bottom of the surface of the protective cover 6. The mounting seat 7 is detachably connected to the dam. A sealing gasket 8 is installed at the bottom of the protective cover 6. The sealing gasket 8 fits tightly to the dam.

[0023] In the utility model, when the protective cover 6 is covered on the surfaces of the linkage rod 1, the fixed sleeve 2, the benchmark 3, the linkage sleeve 4 and the connecting rod 5 for protection, the protective cover 6 can better extrude the sealing pad 8 and then connect with the dam through the setting of the mounting seat 7, which effectively ensures the fitting effect between the protective cover 6 and the dam, and further ensures the sealing effect, so that when observing the change of the position of the linkage sleeve 4 in the protective cover 6, the observation effect is more accurate.

[0024] Among them, a locking piece 72 is installed on the top of the mounting seat 7, a sleeve plate 61 is installed on the surface of the protective cover 6, the locking piece 72 is used to push the sleeve plate 61, and a circular plate 71 is installed on the surface of the mounting seat 7. The circular plate 71 is tightly fitted with the dam and fixed to the dam by screws. The locking piece 72 includes a threaded ring installed on the top of the mounting seat 7, and a threaded rod is threadedly connected to the inner wall of the threaded ring. The threaded rod passes through the mounting seat 7 and is inserted into the top of the sleeve plate 61 and is rotatably connected to it through a bearing.

[0025] In the utility model, when the mounting seat 7 is used, the installation of the mounting seat 7 is facilitated by the provided circular plate 71, and the provided locking member 72 plays a role in pushing the sleeve plate 61, so that the sleeve plate 61 can drive 62 to squeeze the sealing pad 8 more tightly downward, thereby ensuring the sealing effect between the bottom of the protective cover 6 and the dam.

[0026] Among them, a contact piece 41 is installed on the surface of the linkage sleeve 4, and an observation piece 9 is installed on the inner wall of the protective cover 6. The observation piece 9 is used to measure the displacement change of the contact piece 41 when its position changes. A mounting rod 91 is installed on the back of the observation piece 9, and the mounting rod 91 is connected to the protective cover 6. A touch rod 92 is installed on the bottom of the observation piece 9, and the touch rod 92 is in contact with the linkage sleeve 4. An observation window is set on the surface of the protective cover 6 for observing the measurement results after the observation piece 9 measures.

[0027] In the utility model, when observing the position change of the linkage sleeve 4, the touch rod 92 at the bottom of the observation piece 9 is affected by the change in the force when the linkage sleeve 4 contacts, so that the reading at the observation piece 9 changes, thereby ensuring the accuracy of the detection. The observation window is provided to facilitate observation at any time when the reading at the observation piece 9 changes. The installation rod 91 is provided to install the observation piece 9, and the contact piece 41 is provided to extend the observation piece 9, so that the observation piece 9 can measure the position change of the linkage sleeve 4 conveniently.

[0028] Among them, a mounting plate 11 is installed at the bottom of the linkage rod 1, and the surface of the mounting plate 11 is connected to a limit seat 12 by screws, and the limit seat 12 is installed at the dam.

[0029] In the utility model, when the linkage rod 1 is used, the mounting plate 11 and the limit seat 12 are detachably connected, so that when necessary, the linkage rod 1 can be disassembled to facilitate the disassembly and installation of the observation structure.

[0030] Finally, it should be noted that the basic concepts have been described above. Obviously, for those skilled in the art, the above detailed disclosure is only an example and does not constitute a limitation of this specification. Although it is not explicitly stated here, those skilled in the art may make various modifications, improvements and corrections to this specification. Such modifications, improvements and corrections are suggested in this specification, so such modifications, improvements and corrections still belong to the spirit and scope of the exemplary embodiments of this specification. At the same time, this specification uses specific words to describe the embodiments of this specification. For example, "one embodiment", "one embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of this specification. Therefore, it should be emphasized and noted that "one embodiment" or "one embodiment" or "an alternative embodiment" mentioned twice or more in different positions in this specification does not necessarily refer to the same embodiment. In addition, certain features, structures or characteristics in one or more embodiments of this specification can be appropriately combined. In addition, unless explicitly stated in the claims, the order of processing elements and sequences described in this specification, the use of alphanumeric characters, or the use of other names are not used to limit the order of the processes and methods of this specification.

[0031] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A water diversion project settlement displacement observation device, comprising a linkage rod (1), characterized in that: The linkage rod (1) is installed at the dam, a fixing sleeve (2) is installed on the surface of the linkage rod (1), a benchmark (3) is arranged on one side of the linkage rod (1), the benchmark (3) penetrates the dam and is inserted into the ground, a slidable linkage sleeve (4) is installed on the surface of the benchmark (3), a connecting rod (5) is installed between the linkage sleeve (4) and the fixing sleeve (2), a protective cover (6) is arranged on the top of the linkage rod (1), the protective cover (6) is used to cover the linkage rod (1) and the benchmark (3), a mounting seat (7) is sleeved at the bottom of the surface of the protective cover (6), the mounting seat (7) is detachably connected to the dam, a sealing gasket (8) is installed at the bottom of the protective cover (6), and the sealing gasket (8) is tightly fitted to the dam.

2. A water diversion project settlement displacement observation device according to claim 1, characterized in that: A locking piece (72) is installed on the top of the mounting seat (7), a sleeve plate (61) is installed on the surface of the protective cover (6), and the locking piece (72) is used to push the sleeve plate (61).

3. A water diversion project settlement displacement observation device according to claim 1, characterized in that: A circular plate (71) is installed on the surface of the mounting seat (7), and the circular plate (71) is tightly attached to the dam and fixed to the dam by screws.

4. The water diversion project settlement displacement observation device according to claim 1, characterized in that: A contact piece (41) is installed on the surface of the linkage sleeve (4), and an observation piece (9) is installed on the inner wall of the protective cover (6). The observation piece (9) is used to measure the displacement change of the contact piece (41) when the position of the contact piece (41) changes.

5. A water diversion project settlement displacement observation device according to claim 4, characterized in that: A mounting rod (91) is installed on the back of the observation piece (9), and the mounting rod (91) is connected to the protective cover (6). A touch rod (92) is installed on the bottom of the observation piece (9), and the touch rod (92) is in contact with the linkage sleeve (4).

6. A water diversion project settlement displacement observation device according to claim 2, characterized in that: The locking member (72) comprises a threaded ring mounted on the top of the mounting seat (7), a threaded rod being threadedly connected to the inner wall of the threaded ring, the threaded rod passing through the mounting seat (7) and inserted into the top of the sleeve plate (61) to be rotatably connected thereto via a bearing.

7. The water diversion project settlement displacement observation device according to claim 1, characterized in that: A mounting plate (11) is installed at the bottom of the linkage rod (1), and a limit seat (12) is connected to the surface of the mounting plate (11) via screws, and the limit seat (12) is installed at the dam.

8. The water diversion project settlement displacement observation device according to claim 4, characterized in that: The surface of the protective cover (6) is provided with an observation window for observing the measurement result after the observation piece (9) measures.