Boiler dust removal system with fork joint elbow
By designing an inclined air inlet pipe section and an air outlet pipe section in the boiler dust removal system to form a buffer angle, and embedding a filter in the air inlet pipe section, the problem of short service life of the cross-joint elbow is solved and the wear resistance is improved. and gas flow efficiency to ensure the normal operation of the boiler dust removal system.
Patent Information
- Application Number
- CN202420428451.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-05
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-05
AI Technical Summary
The service life of the cross-joint elbow in the existing boiler dust removal system is short, which causes the dust gas to easily collide and wear at the intersection, affecting the normal operation of the boiler.
Design a boiler dust removal system with cross-connected elbows. By adding inclined air inlet pipe sections and air outlet pipe sections between the delivery pipe and the ash hopper, a buffer angle is formed to reduce the impact of dust gas on the pipe wall. A filter is embedded in the air inlet pipe section for preliminary filtration to improve gas flow efficiency and filtration effect.
It extends the service life of the forked elbow, reduces pipe wall wear, ensures the normal operation of the boiler dust removal system, and improves the smoothness of gas flow and filtration efficiency.
Smart Images

Figure CN221867749U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of boiler dust removal systems and relates to a boiler dust removal system with a forked elbow. Background Art
[0002] The exhaust system of the boiler exhaust gas in a power plant is usually equipped with a dust removal system to eliminate the environmental pollution caused by the dust in the exhaust gas. In the current power plants, the dust-containing airflow enters the pressure bin pump from the ash hopper and enters the ash storage through the pipeline. A balance pipe is also provided between the ash hopper and the pressure bin pump, and the corners of the balance pipe and the connection with the ash hopper are connected through elbows.
[0003] Normally, in order to ensure that the airflow containing dust in the ash hopper can quickly flow into the pressure bin pump, a straight pipe setting is currently adopted. For example, the Chinese patent application [Authorization Announcement No.: CN219179003U] discloses a sampling system for a boiler, including a sampling steel pipeline, a purge pipeline, an ash hopper, a storage tank and an air source, wherein one end of the sampling pipeline is connected to the ash hopper, and the other end of the sampling pipeline is connected to the storage tank, a first valve body and a second valve body are arranged at intervals on the passage of the sampling pipeline, one end of the purge pipeline is connected to the sampling pipeline and the connection point is located between the first valve body and the second valve body, the other end of the purge pipeline is connected to the air source, and the extension direction of the purge pipeline and the extension direction of the sampling pipeline are arranged perpendicular to each other.
[0004] Although the above structure diverts the dust-containing gas through the first valve body and the second valve body, when the dust-containing gas enters the storage tank from the ash hopper, the purge pipeline and the sampling pipeline are arranged perpendicular to each other, which makes it easy for the dust-containing gas to collide at the intersection of the purge pipeline and the sampling pipeline. During the boiler production process, the gas flow rate is relatively high, which may lead to serious wear and even ash leakage at the intersection, thereby affecting the normal operation of the boiler. Utility Model Content
[0005] The purpose of the utility model is to solve the above problems in the existing technology and propose a boiler dust removal system with a forked elbow. The technical problem to be solved by the utility model is: how to solve the problem of short service life of the forked elbow in the existing boiler dust removal system.
[0006] The purpose of the utility model can be achieved through the following technical solutions:
[0007] A boiler dust removal system with a forked elbow comprises an ash hopper and a conveying tank located below the ash hopper, the upper end of the conveying tank is connected to a conveying pipe located on one side of the ash hopper, the conveying pipe is vertically arranged, and is characterized in that the upper end of the conveying pipe has a corner end bent in a direction away from the ash hopper, the corner end is connected to the forked elbow, the forked elbow comprises an air inlet pipe section which is inclined from bottom to top and the lower end of which is connected to the corner end, and an air outlet pipe section which is inclined from top to bottom and the lower end of which is connected to the ash hopper, the upper end of the air outlet pipe section is connected to the upper end of the air inlet pipe section, and a buffer angle is formed between the upper side of the air outlet pipe section and the upper side of the air inlet pipe section, and the buffer angle is an obtuse angle.
[0008] Working principle: a fork elbow is added between the conveying pipe and the ash hopper, the fork elbow has an air inlet pipe section and an air outlet pipe section, both of which are inclined, and the lower end of the air inlet pipe section is connected with the ash hopper, and the dust-containing gas enters the air inlet pipe section from the ash hopper, and then the upper end of the air inlet pipe section is connected with the upper end of the air outlet pipe section, so that the dust-containing gas flows upward from the lower end of the air inlet pipe section to the upper end of the air outlet pipe section, and then flows into the conveying pipe from the lower end of the air outlet pipe section, and flows into the conveying tank through the vertically arranged conveying pipe, thereby realizing the collection of the dust-containing gas. Since a buffer angle is formed between the upper side of the air outlet pipe section and the upper side of the air inlet pipe section, the angle between the dust-containing gas and the pipe wall of the air inlet pipe section and the air outlet pipe section is smaller, which reduces the impact of the dust-containing gas on the pipe wall, reduces the wear of the pipe wall, improves the wear resistance of the fork elbow, thereby extending the service life of the fork elbow, and also ensures the normal operation of the boiler dust removal system.
[0009] In the above-mentioned boiler dust removal system with forked elbows, the upper ends of the air inlet pipe section and the air outlet pipe section are both inclined in a direction away from the ash hopper, and the buffer angle is 135° to 179°.
[0010] By setting the orientation of the upper end of the air inlet pipe section and the upper end of the air outlet pipe section, the flow velocity of the dust-containing gas can be reduced, thereby reducing the impact between the dust-containing gas and the pipe wall. The setting of the buffer angle and the connection of the upper end of the air inlet pipe section with the upper end of the air outlet pipe section can avoid the appearance of an overly horizontally set pipe, which can make it difficult for dust to settle in the pipe, and the gas circulation is smoother, further improving the service life of the fork elbow.
[0011] In the above-mentioned boiler dust removal system with a forked elbow, the lower end of the air inlet pipe section is inserted into the ash hopper, and the pipe opening of the air inlet pipe section is arranged to be inclined downward.
[0012] Through the arrangement of this structure, when pumping air, the air inlet pipe section can introduce gas containing less dust into the forked elbow, and can also guide the gas entering the forked elbow, thereby improving the flow efficiency of the gas.
[0013] In the above-mentioned boiler dust removal system with forked elbows, the air outlet pipe section and the air inlet pipe section are both straight pipes.
[0014] The arrangement of this structure, through the air inlet pipe section and the air outlet pipe section with inclined angles, can reduce the impact between the dust-containing gas and the pipe wall while ensuring smooth gas flow, thereby extending the service life of the fork elbow without affecting the collection of the dust-containing gas.
[0015] In the above-mentioned boiler dust removal system with a forked elbow, the air outlet pipe section and the air inlet pipe section are integrally formed.
[0016] The arrangement of this structure ensures better sealing performance of the air outlet pipe section and the air inlet pipe section, and also makes the installation of the forked elbow more convenient and simple.
[0017] In the above-mentioned boiler dust removal system with forked elbows, a pressure pump chamber capable of pumping dust-containing gas into the delivery tank is arranged in the middle of the delivery pipe.
[0018] By arranging the pressure pump bin in the middle of the conveying pipe, the pressure pump bin can quickly pump the dust-containing gas out of the ash hopper, thereby improving the flow efficiency of the dust-containing gas.
[0019] In the above-mentioned boiler dust removal system with forked elbow, the inner diameter of the air inlet pipe section gradually decreases from one end inserted into the ash hopper to the other end, and the pipe opening of the air inlet pipe section is embedded with a filter net that can filter dust.
[0020] By increasing the air inlet diameter of the air inlet pipe section, the dust-containing gas in the ash hopper can quickly enter the air inlet pipe section from the ash hopper. However, since the flow rate of the dust-containing gas is relatively fast, a filter is embedded in the pipe mouth of the air inlet pipe section to achieve preliminary filtration of the dust-containing gas. The filtered dust adheres to the filter and does not affect the flow of the dust-containing gas, thereby ensuring the flow rate of the dust-containing gas while improving its filtering effect.
[0021] In the above-mentioned boiler dust removal system with a forked elbow, the air inlet pipe section protrudes inwardly on the inner pipe wall at the pipe opening to form an annular abutment shoulder, and the filter screen abuts against the abutment shoulder.
[0022] By setting the abutment shoulder, the filter is pressed against the abutment shoulder under the gas pressure. When the boiler stops using, the fork elbow can be removed and the filter can be removed. At this time, the filter can be quickly removed, making the setting of the filter more stable and replaceable after long-term use, thereby improving the filtering efficiency of dust-containing gas.
[0023] Compared with the prior art, the utility model has the following advantages: since the upper side of the outlet pipe section and the upper side of the inlet pipe section form a buffer angle, the angle between the dust-containing gas and the pipe walls of the inlet pipe section and the outlet pipe section is smaller. In specific experiments, the buffer angle is 135°~179°, which can not only ensure the flow of the dust-containing gas but also minimize the impact of the dust-containing gas on the fork elbow, reduce the wear of the pipe wall, and improve the wear resistance of the fork elbow, thereby extending the service life of the fork elbow, while also ensuring the normal operation of the boiler dust removal system. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a partial structural diagram of the first embodiment.
[0025] Figure 2 yes Figure 1 A partial enlarged view of point A in the middle.
[0026] Figure 3 It is a partial cross-sectional view of the second embodiment.
[0027] In the figure, 1, ash hopper; 2, conveying tank; 3, conveying pipe; 31, corner end; 4, fork elbow; 41, air inlet pipe section; 41a, pipe mouth; 41b, abutment shoulder; 42, air outlet pipe section; 5, pressure pump chamber; 6, filter screen. DETAILED DESCRIPTION
[0028] The following are specific embodiments of the present invention and the accompanying drawings to further describe the technical solution of the present invention, but the present invention is not limited to these embodiments.
[0029] Embodiment 1
[0030] like Figure 1 As shown, the boiler dust removal system with a forked elbow comprises an ash hopper 1 and a conveying tank 2 located below the ash hopper 1, the upper end of the conveying tank 2 is connected to a conveying pipe 3 located on one side of the ash hopper 1, and the conveying pipe 3 is vertically arranged.
[0031] Specifically, Figure 1 and Figure 2 As shown, the upper end of the conveying pipe 3 has a corner end 31 bent in a direction away from the ash hopper 1, and the corner end 31 is connected to a forked elbow 4, which includes an air inlet pipe section 41 inclined from bottom to top and connected to the corner end 31 at the lower end, and an air outlet pipe section 42 inclined from top to bottom and connected to the ash hopper 1 at the lower end, the upper end of the air outlet pipe section 42 is connected to the upper end of the air inlet pipe section 41, and a buffer angle is formed between the upper side of the air outlet pipe section 42 and the upper side of the air inlet pipe section 41, and the buffer angle is an obtuse angle, which is angle A shown in the figure.
[0032] Working principle: By adding a forked elbow 4 between the conveying pipe 3 and the ash hopper 1, the forked elbow 4 has an air inlet pipe section 41 and an air outlet pipe section 42, and the air inlet pipe section 41 and the air outlet pipe section 42 are both inclined. By connecting the lower end of the air inlet pipe section 41 with the ash hopper 1, the dust-containing gas enters the air inlet pipe section 41 from the ash hopper 1, and then the upper end of the air inlet pipe section 41 is connected with the upper end of the air outlet pipe section 42, so that the dust-containing gas flows upward from the lower end of the air inlet pipe section 41 to the upper end of the air outlet pipe section 42, and then flows out from the lower end of the air outlet pipe section 42. It flows into the conveying pipe 3, and flows into the conveying tank 2 through the vertically arranged conveying pipe 3, thereby realizing the collection of the dust-containing gas. Since the upper side of the outlet pipe section 42 and the upper side of the inlet pipe section 41 form a buffer angle, the angle between the dust-containing gas and the pipe walls of the inlet pipe section 41 and the outlet pipe section 42 is smaller, which reduces the impact of the dust-containing gas on the pipe wall, reduces the wear of the pipe wall, improves the wear resistance of the fork elbow 4, thereby extending the service life of the fork elbow 4, and also ensures the normal operation of the boiler dust removal system.
[0033] like Figure 2 As shown, the upper end of the air inlet pipe section 41 and the upper end of the air outlet pipe section 42 are both inclined in a direction away from the ash hopper 1, and the buffer angle is 135° to 179°.
[0034] like Figure 1 and Figure 2 As shown, the lower end of the air inlet pipe section 41 is inserted into the ash hopper 1, the air inlet pipe section 41 is a straight pipe, the pipe mouth 41a of the air inlet pipe section 41 is tilted downward, the air outlet pipe section 42 and the air inlet pipe section 41 are both straight pipes, and the air outlet pipe section 42 and the air inlet pipe section 41 are integrally formed.
[0035] like Figure 1 As shown, a pressure pump chamber 5 capable of pumping dust-containing gas into the conveying tank 2 is provided in the middle of the conveying pipe 3 .
[0036] Embodiment 2
[0037] The content of this embodiment is basically the same as that of the first embodiment, except that: Figure 3 As shown, the inner diameter of the air inlet pipe section 41 gradually decreases from one end inserted into the ash hopper 1 to the other end, and the pipe mouth 41a of the air inlet pipe section 41 is embedded in the filter screen 6 that can filter dust. The air inlet pipe section 41 protrudes inward on the inner pipe wall at the pipe mouth 41a to form an annular abutment shoulder 41b, and the filter screen 6 abuts against the abutment shoulder 41b.
[0038] By increasing the air inlet diameter of the air inlet pipe section 41, the dust-containing gas in the ash hopper 1 can quickly enter the air inlet pipe section 41 from the ash hopper 1. However, since the flow rate of the dust-containing gas is relatively fast, a filter 6 is embedded in the pipe mouth 41a of the air inlet pipe section 41 to achieve preliminary filtration of the dust-containing gas, and the filtered dust adheres to the filter 6. By setting the abutment shoulder 41b, the filter 6 is pressed against the abutment shoulder 41b under the gas pressure. When the boiler is out of use, the fork elbow can also be disassembled and the filter 6 can be disassembled. At this time, the filter 6 can be quickly disassembled, so that the setting of the filter 6 is more stable and can be replaced after long-term use, thereby improving the filtering efficiency of the dust-containing gas.
[0039] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.
Claims
1. A boiler dust removal system with a forked elbow, comprising an ash hopper (1) and a conveying tank (2) located below the ash hopper (1), wherein the upper end of the conveying tank (2) is connected to a conveying pipe (3) located on one side of the ash hopper (1), and the conveying pipe (3) is arranged vertically. It is characterized in that The upper end of the conveying pipe (3) has a corner end (31) bent in a direction away from the ash hopper (1), and the corner end (31) is connected to a forked elbow (4). The forked elbow (4) comprises an air inlet pipe section (41) inclined from bottom to top and connected to the corner end (31) at the lower end, and an air outlet pipe section (42) inclined from top to bottom and connected to the ash hopper (1) at the lower end. The upper end of the air outlet pipe section (42) is connected to the upper end of the air inlet pipe section (41), and a buffer angle is formed between the upper side of the air outlet pipe section (42) and the upper side of the air inlet pipe section (41), and the buffer angle is an obtuse angle.
2. The boiler dust removal system with a forked elbow according to claim 1, It is characterized in that The upper end of the air inlet pipe section (41) and the upper end of the air outlet pipe section (42) are both inclined in a direction away from the ash hopper (1), and the buffer angle is 135° to 179°.
3. The boiler dust removal system with forked elbow according to claim 1, It is characterized in that The lower end of the air intake pipe section (41) is inserted into the ash hopper (1), and the pipe opening (41a) of the air intake pipe section (41) is arranged to be inclined downward.
4. The boiler dust removal system with a forked elbow according to claim 1, 2 or 3, It is characterized in that The air outlet pipe section (42) and the air inlet pipe section (41) are both straight pipes.
5. The boiler dust removal system with a forked elbow according to claim 1, 2 or 3, It is characterized in that The air outlet pipe section (42) and the air inlet pipe section (41) are integrally formed.
6. The boiler dust removal system with a forked elbow according to claim 1, 2 or 3, It is characterized in that A pressure pump chamber (5) capable of pumping dust-containing gas into the conveying tank (2) is arranged in the middle of the conveying pipe (3).
7. The boiler dust removal system with forked elbow according to claim 3, It is characterized in that The inner diameter of the air intake pipe section (41) gradually decreases from one end inserted into the ash hopper (1) to the other end, and a filter screen (6) capable of filtering dust is embedded in the pipe opening (41a) of the air intake pipe section (41).
8. The boiler dust removal system with forked elbow according to claim 7, It is characterized in that The air inlet pipe section (41) protrudes inwards on the inner pipe wall at the pipe opening (41a) to form an annular abutment shoulder (41b), and the filter screen (6) abuts against the abutment shoulder (41b).