High-rail infiltration line main body support
By designing the main bracket of the high-rail impregnation line and using the combination of gantry components and I-beam rails, the problem of difficulty in adjusting the number of tanks on the existing equipment rack is solved, and the separation and installation of the robotic arms and tanks and the adjustment of the number of tanks are realized. Flexible adaptation improves equipment flexibility and production efficiency.
Patent Information
- Application Number
- CN202322844656.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-23
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2033-10-23
AI Technical Summary
Due to the low track design of the existing fully automatic impregnation equipment frame, it is difficult to quickly adjust the number of tanks to adapt to process changes, resulting in large welding deformations and difficulty in achieving track assembly connections.
Design a high-rail impregnation line main support, which uses a combination of gantry components and I-beam tracks. The support is separated from the tank. Through the adjustment of the gantry components and I-beam tracks, the installation of the mechanical arm and the flexible adaptation of the number of tanks can be achieved. , using H-shaped rails to install beams and reinforcements to ensure the stability and solidity of the structure.
The separate installation of the robotic arm and the tank body is realized, and the tank body is supported independently, which facilitates quick adjustment of the number of tanks when the process changes, simplifies the production process, and improves the flexibility and disassembly of the equipment.
Smart Images

Figure CN221869096U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of infiltration line brackets, in particular to a high rail infiltration line main body bracket. Background Art
[0002] The impregnation equipment is a special equipment for impregnating machined parts made of aluminum, magnesium alloy die castings, gray cast iron and other related materials. The workpiece is impregnated with an organic impregnant, which is impregnated by a combination of vacuum extraction and pressurization. The impregnant is infiltrated into the holes of the workpiece, and then the impregnant in the pores is heated to induce a polymerization reaction to form a stable solid substance to fill the pores, thereby achieving a sealing effect. The impregnated product not only has sealing properties but also improves corrosion resistance and cutting performance, and enhances the physical strength of thin walls. This equipment is suitable for mass production of products with complex part shapes and high precision requirements, especially the processing of boxes and complex structural parts. It is widely used in the precision and efficient processing of complex parts in industries such as automobile manufacturing, aerospace, shipbuilding, and new energy industries. Aluminum alloy casting parts on aircraft have invisible pinholes, pores, shrinkage holes and other micropores during casting. These are formed when the aluminum alloy generates gas during casting and the original gas in the mold moves around inside the material, or when it shrinks during the molding process. Depending on the different characteristics of the pinholes, it may cause leakage from the inside of the part to the outside, such as lubricating oil, grease, cooling water, gasoline, air, air conditioning refrigerant gas and other liquids and gases inside the part housing. In addition, water will penetrate from the outside, which will affect or even damage the function of the part, so it is necessary to perform an impregnation treatment. The impregnation treatment refers to the process of making the liquid impregnant penetrate into the micropores of the casting to solidify it, thereby preventing the parts from leaking gas, oil or water.
[0003] The existing fully automatic impregnation equipment robot arm is installed on a frame used to support the tank body. The tank body needs to be installed in the frame, and a track is laid on the frame. A total of four rollers in the front and rear of the robot arm run on the track. The track is in a low-track state compared to the tank body. When the process changes and the tank body needs to be increased or decreased, it can only be adjusted by increasing the welding frame length or cutting the frame to shorten it. In this process, the welding deformation is large, and it is difficult to achieve track assembly connection at the low track. Utility Model Content
[0004] The technical problem to be solved by the utility model is: by setting a bracket separated from the tank body for installing the robot arm, the bracket is located above the tank body and has no connection with the tank body. The tank body is independent of the bracket and is located below the bracket. Since the bracket is separated from the tank body, the tank body can be added or reduced quickly as the process changes, and the bracket can be adjusted separately to adapt to the increase or decrease in the number of tank bodies, thereby changing the production process.
[0005] The technical solution adopted by the utility model to solve the technical problem is: a high rail infiltration line main body bracket, including: a plurality of gantry components and a plurality of I-beam rails;
[0006] The gantry assembly includes a vertical frame, a horizontal beam and a track mounting beam, wherein the horizontal beam is mounted on the upper end of the vertical frame, the vertical frame and the horizontal beam form a door-shaped structure, and the track mounting beam is mounted on the vertical frame near the horizontal beam;
[0007] The two ends of the I-beam track are respectively connected to the track mounting beams on two adjacent gantry assemblies;
[0008] Reinforcing ribs are installed between two adjacent gantry assemblies.
[0009] As a preferred technical solution of the present utility model, the cross-section of the track mounting beam is H-shaped, and the I-beam track is mounted on the track mounting beam by mounting bolts.
[0010] By adopting the above technical solution, since the cross section of the track mounting beam is H-shaped, it is convenient to drill holes on the track mounting beam to fix the mounting bolts.
[0011] As a preferred technical solution of the utility model, an oblique square gasket is arranged between the mounting bolt and the track mounting beam.
[0012] By adopting the above technical solution and providing an oblique square gasket, the firmness of the installation between the mounting bolts and the track mounting beam is ensured.
[0013] As a preferred technical solution of the utility model, the number of I-beam rails between two adjacent gantry assemblies is two, and the two I-beam rails are parallel to each other.
[0014] By adopting the above technical solution and setting two parallel I-beam rails, it is convenient to install the robot arm needed in the subsequent installation.
[0015] As a preferred technical solution of the utility model, a reinforcement column is arranged between the cross beam and the track installation beam.
[0016] By adopting the above technical solution and arranging reinforcing columns, the firmness of fixing the track mounting beam can be ensured.
[0017] As a preferred technical solution of the utility model, the reinforcing ribs between two adjacent gantry assemblies are installed on the upright frames of the corresponding gantry assemblies.
[0018] By adopting the above technical solution, the reinforcement ribs are provided, thereby ensuring the stability of the combination of several gantry components.
[0019] The beneficial effects of the utility model are embodied in:
[0020] 1. A gantry assembly is provided in conjunction with an I-beam track to install a robot arm that is required, so that the robot arm is separated from the tank body, and the tank body is fixed with a separate support leg. When the number of tank bodies needs to be increased or decreased according to process requirements, the number of gantry assemblies and the number of I-beam tracks are adjusted accordingly for adaptation. Since the I-beam track and the track mounting beam in the gantry assembly are installed through perforated mounting bolts, it is convenient to increase or decrease the gantry assembly and the I-beam track. At the same time, it is also convenient to directly disassemble and package the tank body for transportation and transfer. In the above manner, a bracket separated from the tank body is provided for installing the robot arm. The bracket is located above the tank body and has no connection with the tank body. The tank body is independent of the bracket and is located below the bracket. Since the bracket is separated from the tank body, the tank body can be easily and quickly increased or decreased as the process changes, and the bracket can be adjusted separately to adapt to the increase or decrease in the number of tank bodies, thereby changing the production process. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is a schematic diagram of a bracket after the gantry assembly and the I-shaped cylinder track of the utility model are combined;
[0022] Figure 2 It is a schematic diagram of the gantry assembly of the utility model;
[0023] Figure 3 It is a schematic diagram of part A of the utility model;
[0024] Figure 4 It is a schematic diagram of part B of the utility model.
[0025] In the figure: 1. gantry assembly; 101. vertical frame; 102. cross beam; 103. track mounting beam; 104. reinforcing column; 2. I-beam track; 3. reinforcing ribs; 4. mounting bolts; 5. oblique square gasket. DETAILED DESCRIPTION
[0026] Now the utility model will be described in further detail with reference to the accompanying drawings.
[0027] Combined with Figure 1-4 As shown, a main support of a high rail infiltration line includes a gantry assembly 1, a vertical frame 101, a crossbeam 102, a track mounting beam 103, a reinforcing column 104, an I-beam track 2, a reinforcing rib 3, a mounting bolt 4 and a rhombus gasket 5.
[0028] Combined with Figure 1-4As shown, a main support of a high rail infiltration line includes: a plurality of gantry components 1 and a plurality of I-beam rails 2, the gantry component 1 includes a stand 101, a crossbeam 102 and a rail mounting beam 103, the crossbeam 102 is installed at the upper end of the stand 101, the stand 101 and the crossbeam 102 form a door-shaped structure, the rail mounting beam 103 is installed at the stand 101 near the crossbeam 102, the two ends of the I-beam rail 2 are respectively connected to the rail mounting beams 103 on two adjacent gantry components 1, and a reinforcing rib 3 is installed between two adjacent gantry components 1. The gantry component 1 is provided in conjunction with the I-beam rail 2 to install a mechanical arm that needs to be used, so that the mechanical arm is separated from the tank body, and the tank body is fixed with a separate support leg. When it is necessary to perform according to the process requirements When the number of tank bodies is increased or decreased, the number of gantry assemblies 1 and the number of I-beam rails 2 are adjusted accordingly to adapt. Since the I-beam rail 2 and the rail mounting beam 103 in the gantry assembly 1 are installed through perforated mounting bolts 4, it is convenient to increase or decrease the gantry assembly 1 and the I-beam rail 2. At the same time, it is also convenient to directly disassemble and package the tank bodies for transportation. In the above manner, a bracket separated from the tank body is set to install the robot arm. The bracket is located above the tank body and has no connection with the tank body. The tank body is independent of the bracket and is located below the bracket. Since the bracket is separated from the tank body, the tank body can be easily and quickly increased or decreased as the process changes, and the bracket can be adjusted separately to adapt to the increase or decrease in the number of tank bodies, thereby changing the production process.
[0029] Combined with Figure 1-4 As shown, the track mounting beam 103 has an H-shaped cross section, the I-beam track 2 is mounted on the track mounting beam 103 by means of mounting bolts 4, an oblique square gasket 5 is arranged between the mounting bolts 4 and the track mounting beam 103, the number of I-beam tracks 2 between two adjacent gantry assemblies 1 is two, and the two I-beam tracks 2 are parallel to each other, a reinforcing column 104 is arranged between the cross beam 102 and the track mounting beam 103, and the reinforcing ribs 3 between the two adjacent gantry assemblies 1 are installed on the stand 1 of the corresponding gantry assembly 1 01, since the cross-section of the track mounting beam 103 is H-shaped, it is convenient to drill holes on the track mounting beam 103 to fix the mounting bolts 4. By setting the oblique square gasket 5, the firmness of the installation between the mounting bolts 4 and the track mounting beam 103 is ensured. By setting two parallel I-beam rails 2, it is convenient to install the robot arm required for subsequent installation. By setting the reinforcement column 104, the firmness of the track mounting beam 103 is ensured. Since the reinforcement ribs 3 are set, the stability of the combination of several gantry components 1 is ensured.
[0030] Working principle: When in use, select the corresponding number of gantry assemblies 1 and I-beam rails 2 according to the number of tank bodies used in the process, and then install the I-beam rails 2 on the rail mounting beam 103 through the mounting bolts 4, so that several gantry assemblies 1 and I-beam rails 2 form a bracket for installing a robotic arm. The extent of the I-beam rails 2 is determined according to specific process requirements. The bracket is located above the tank body, and the robotic arm installed on the bracket is separated from the tank body. The tank body is fixed by a separate support leg. The robotic arm is installed by setting a bracket separated from the tank body. The bracket is located above the tank body and has no connection with the tank body. The tank body is independent of the bracket and is located below the bracket. Since the bracket is separated from the tank body, the tank body can be easily and quickly increased or decreased as the process changes, and the bracket can be adjusted separately to adapt to the increase or decrease in the number of tank bodies, thereby changing the production process.
[0031] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and the description in the specification are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A main support for a high rail infiltration line, include: A plurality of gantry assemblies (1) and a plurality of I-beam rails (2), characterized in that: The gantry assembly (1) comprises a stand (101), a crossbeam (102) and a track mounting beam (103); the crossbeam (102) is mounted on the upper end of the stand (101); the stand (101) and the crossbeam (102) form a door-shaped structure; and the track mounting beam (103) is mounted on the stand (101) at a position close to the crossbeam (102); The two ends of the I-beam track (2) are respectively connected to the track mounting beams (103) on two adjacent gantry assemblies (1); A reinforcing rib (3) is installed between two adjacent gantry assemblies (1).
2. A high rail infiltration line main body support according to claim 1, Features: The track installation beam (103) has an H-shaped cross section, and the I-beam track (2) is installed on the track installation beam (103) by means of installation bolts (4).
3. A high rail infiltration line main body support according to claim 2, Features: An oblique square gasket (5) is provided between the mounting bolt (4) and the track mounting beam (103).
4. A high rail infiltration line main body support according to claim 1, Features: There are two I-beam rails (2) between two adjacent gantry assemblies (1), and the two I-beam rails (2) are parallel to each other.
5. The high rail infiltration line main body support according to claim 1, Features: A reinforcement column (104) is provided between the cross beam (102) and the track installation beam (103).