Building engineering hoisting structure

By designing a construction engineering hoisting structure including a fixed beam, a movable beam, a support rod, a limit rod and a movable block, and using the cooperation of the pull rope and the spring, the inconvenience of clamping the hook plate and the trouble of unloading in the existing technology are solved. solve the problem, realize automated hook plate operation and improve construction efficiency.

CN221876300UActive Publication Date: 2024-10-22闫文海
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420198024.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-10-22
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

When the existing hoisting structure of construction projects is used, multiple hooks are needed to fix various positions of the panels, which makes clamping inconvenient and unloading troublesome.

Method used

A lifting structure including a fixed beam, a movable beam, a support rod, a limit rod, a movable block and a fixed tube is designed. Through the cooperation of the pull rope and the spring, the automatic movement of the movable block is realized and the clamping of the hook plate is simplified. and unloading process.

Benefits of technology

The automatic clamping and unloading of the hook plate is realized, which improves the convenience of operation and simplifies the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221876300U_ABST
    Figure CN221876300U_ABST
Patent Text Reader

Abstract

The utility model discloses a constructional engineering hoisting structure which comprises two fixed beams arranged in the front-back direction, two connecting beams arranged in the left-right direction are fixedly connected between the two fixed beams, supporting rods are fixedly connected to the positions, close to the left side and the right side, of the bottoms of the fixed beams, a movable beam is arranged above the two fixed beams, and the movable beam is fixedly connected to the left side and the right side of the fixed beams. Limiting rods are fixedly connected to the positions, close to the front portion and the rear portion, of the bottom of the movable beam, the bottom ends of the limiting rods are sleeved with limiting pipes, and the bottoms of the limiting pipes are fixedly connected with the top of the fixed beam.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a construction engineering hoisting structure. Background Art

[0002] Construction engineering is a part of construction engineering, which refers to the engineering entity formed by the construction of various types of buildings and their ancillary facilities and the installation of supporting lines, pipelines and equipment. During the construction process of construction engineering, it is often necessary to hoist the plates. However, when using the construction engineering hoisting structure in the prior art, multiple hooks are needed to fix the various positions of the plates, which makes it inconvenient to clamp and also makes unloading more troublesome. In this regard, we propose a construction engineering hoisting structure. Utility Model Content

[0003] The technical problem solved by the utility model is to overcome the defects of the prior art and provide a construction engineering hoisting structure.

[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0005] A construction engineering hoisting structure comprises two fixed beams arranged in the front-back direction, two connecting beams arranged in the left-right direction are fixedly connected between the two fixed beams, the bottom of the fixed beams near the left and right sides are fixedly connected with support rods, a movable beam is arranged above the two fixed beams, the bottom of the movable beam near the front and back sides are fixedly connected with limit rods, the bottom end of the limit rod is sleeved with a limit tube, the bottom of the limit tube is fixedly connected to the top of the fixed beam, the top of the fixed beam is provided with a through groove near the left and right sides, and a movable block is movably connected in the through groove A through hole is provided on the side wall of the movable block, a fixed tube is provided in the through hole, the side walls on both sides of the fixed tube are fixedly connected to the inner wall of the through groove, a fixed block is provided in the fixed tube, and the top and bottom of the inner cavity of the fixed tube are provided with movable grooves matching the fixed block, the top and bottom of the fixed block are respectively fixedly connected to the top and bottom of the inner cavity of the through hole, a pull rope is fixedly connected to the side wall of the fixed block, an L-shaped through groove is provided on the inner wall of the through groove, the other end of the pull rope passes through the L-shaped through hole and is fixedly connected to the bottom of the movable beam, and the bottom of the movable block is fixedly connected to a hook plate.

[0006] Preferably, a rubber pad is fixedly connected to the bottom end of the support rod.

[0007] Preferably, the left and right side walls of the limiting rod are fixedly connected to limiting blocks near the bottom, and the left and right inner walls of the limiting tube are provided with limiting grooves matching the limiting blocks.

[0008] Preferably, the front and rear walls of the movable block are movably connected with pulleys near the four corners through rotating shafts and bearings, and the front and rear inner walls of the through slot are provided with sliding grooves matching the pulleys.

[0009] Preferably, a spring is sleeved on the fixing tube.

[0010] Preferably, guide wheels are movably connected to the inner wall of the L-shaped through groove near the top and the bottom via a rotating shaft and a bearing.

[0011] Compared with the prior art, the beneficial effects of the utility model are:

[0012] In the present technical solution, through the cooperation between the pull rope and the fixed block, it can be achieved that when lifting, the pull rope first pulls the two movable blocks to move toward the middle, thereby driving the bottom of the two hook plates to be inserted under the material, thereby realizing automatic and convenient clamping of the device. At the same time, through the action of the spring, when lowering the device, the two movable blocks move back to back, causing the hook plate to open automatically, thereby realizing convenient unloading of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the structure of the utility model;

[0014] Figure 2 It is a three-dimensional diagram of the movable block and the hook plate of the utility model;

[0015] Figure 3 It is a side view of the utility model;

[0016] Figure 4 for Figure 1 Enlarged view of point A in the middle;

[0017] Figure 5 for Figure 1 Enlarged view of point B in the middle.

[0018] Numbers in the figure: 1. Fixed beam; 2. Support rod; 3. Fixed block; 4. Pull rope; 5. Movable beam; 6. Limit block; 7. Fixed pipe; 8. Pulley; 9. Movable block; 10. Hook plate; 11. Connecting beam; 12. Guide wheel; 13. Limit pipe; 14. Limit rod. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] See also Figure 1-5The utility model provides a technical solution: a construction engineering hoisting structure, including two fixed beams 1 arranged along the front and rear directions, two connecting beams 11 arranged in the left and right directions are fixedly connected between the two fixed beams 1, the bottom of the fixed beams 1 near the left and right sides are fixedly connected with support rods 2, the bottom of the support rods 2 are fixedly connected with rubber pads, a movable beam 5 is arranged above the two fixed beams 1, the bottom of the movable beam 5 near the front and rear is fixedly connected with a limit rod 14, the bottom of the limit rod 14 is sleeved with a limit tube 13, the limit rod The left and right side walls 14 are fixedly connected to the limit blocks 6 near the bottom, and the inner walls on the left and right sides of the limit tube 13 are provided with limit grooves matching the limit blocks 6, the bottom of the limit tube 13 is fixedly connected to the top of the fixed beam 1, and the top of the fixed beam 1 is provided with through grooves near the left and right sides, and the movable blocks 9 are movably connected in the through grooves, and the front and rear walls of the movable blocks 9 are movably connected to the pulleys 8 through the rotating shafts and bearings near the four corners, and the inner walls of the front and rear sides of the through grooves are provided with sliding grooves matching the pulleys 8, and the side walls of the movable blocks 9 are provided with through holes, and the through holes are provided. A fixing tube 7 is arranged in the hole, and the side walls on both sides of the fixing tube 7 are fixedly connected to the inner wall of the through slot, a spring is sleeved on the fixing tube 7, a fixing block 3 is arranged in the fixing tube 7, and the top and bottom of the inner cavity of the fixing tube 7 are provided with movable grooves matching the fixing block 3, the top and bottom of the fixing block 3 are respectively fixedly connected to the top and bottom of the inner cavity of the through hole, a pull rope 4 is fixedly connected to the side wall of the fixing block 3, an L-shaped through slot is arranged on the inner wall of the through slot, and the other end of the pull rope 4 passes through the L-shaped through hole and is fixedly connected to the bottom of the movable beam 5, and the inner wall of the L-shaped through slot is close to the top and bottom of the movable beam 5. The guide wheels 12 are movably connected to the bottom through the rotating shaft and the bearing, and the bottom of the movable block 9 is fixedly connected with a hook plate 10. Through the cooperation between the pull rope 4 and the fixed block 3, it can be achieved that when lifting, the pull rope 4 first pulls the two movable blocks 9 to move to the middle, thereby driving the bottoms of the two hook plates 10 to be inserted under the material, thereby realizing automatic and convenient clamping of the device. At the same time, through the action of the spring, when lowering the device, the two movable blocks 9 move back to back, so that the hook plate 10 automatically opens, realizing convenient unloading of the device.

[0021] Working principle: When in use, place the device above the material. When the movable beam 5 is lifted and moves upward, the movable beam 5 pulls the four pull ropes 4 and drives the movable block 9 in the same fixed beam 1 to move toward each other, thereby driving the two hook plates 10 to be inserted under the material. The setting of the pulley 8 makes the movement of the movable block 9 smoother and more stable. When the side wall of the movable block 9 contacts the inner wall of the through groove or the hook plate 10 contacts the side wall of the material, the material can be lifted at this time, realizing its automatic and convenient clamping. When unloading, when the device is lifted and placed on the ground, under the action of the spring, the movable block 9 moves to the initial position, and the material can be taken out at this time.

[0022] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction engineering hoisting structure, comprising two fixed beams (1) arranged in a front-to-rear direction, characterized in that: Two connecting beams (11) arranged in left and right directions are fixedly connected between the two fixed beams (1); the bottom of the fixed beam (1) near the left and right sides is fixedly connected to a support rod (2); a movable beam (5) is arranged above the two fixed beams (1); the bottom of the movable beam (5) near the front and rear sides is fixedly connected to a limit rod (14); the bottom end of the limit rod (14) is sleeved with a limit tube (13); the bottom of the limit tube (13) is fixedly connected to the top of the fixed beam (1); the top of the fixed beam (1) near the left and right sides is provided with a through groove; a movable block (9) is movably connected in the through groove; and the side wall of the movable block (9) is provided with a through groove. A through hole is provided, wherein a fixed tube (7) is provided in the through hole, and the side walls on both sides of the fixed tube (7) are fixedly connected to the inner wall of the through groove, a fixed block (3) is provided in the fixed tube (7), and the top and bottom of the inner cavity of the fixed tube (7) are provided with movable grooves matching the fixed block (3), and the top and bottom of the fixed block (3) are respectively fixedly connected to the top and bottom of the inner cavity of the through hole, a draw rope (4) is fixedly connected to the side wall of the fixed block (3), and an L-shaped through groove is provided on the inner wall of the through groove, and the other end of the draw rope (4) passes through the L-shaped through hole and is fixedly connected to the bottom of the movable beam (5), and the bottom of the movable block (9) is fixedly connected to a hook plate (10).

2. A construction engineering hoisting structure according to claim 1, characterized in that: A rubber pad is fixedly connected to the bottom end of the support rod (2).

3. A construction engineering hoisting structure according to claim 1, characterized in that: The left and right side walls of the limiting rod (14) are fixedly connected to the limiting blocks (6) near the bottom, and the left and right inner walls of the limiting tube (13) are provided with limiting grooves matching the limiting blocks (6).

4. A construction engineering hoisting structure according to claim 1, characterized in that: The front and rear walls of the movable block (9) are movably connected to pulleys (8) near the four corners via rotating shafts and bearings, and the front and rear inner walls of the through slot are provided with sliding grooves matching the pulleys (8).

5. A construction engineering hoisting structure according to claim 1, characterized in that: The fixing tube (7) is sleeved with a spring.