Flat-top tower crane structure convenient for integral transportation of rotary structure
By canceling the transition section between the tower head and the upper rotary support and setting up a transition section below the lower rotary support, the problems of too high transportation height of the tower crane and large bending moment of the rotary structure are solved, achieving lower transportation costs. The height and smaller stress and bending moment simplify the dismantling process of the tower head and ensure the normal operation of the tower crane lifting operation.
Patent Information
- Application Number
- CN202420485927.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-03-13
AI Technical Summary
During transportation of existing medium-sized tower cranes, the transition joint between the tower head and the upper slewing support causes the overall height to be too high and needs to be dismantled, and the slewing structure is subject to a large bending moment, which increases the difficulty of transportation and the structural strength requirements.
The transition section between the tower head and the upper rotary support is canceled and connected directly through the pin shaft. A transition section is set up under the lower rotary support. A frame structure and jacking connection plate are used to reduce the overall height and stress bending moment. At the same time, Allows the set to be transported as a whole.
It reduces the overall transportation height, reduces the stress bending moment of the rotating structure, simplifies the dismantling process of the tower head, reduces the manufacturing difficulty and strength requirements, and ensures the normal progress of the tower crane lifting operation.
Smart Images

Figure CN221876422U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a flat-top tower crane, in particular to a flat-top tower crane structure which is convenient for overall transportation of a rotary structure. Background Art
[0002] Tower cranes are widely used as construction equipment for vertical and horizontal transportation in civil and industrial construction sites, highway and railway bridge projects, and power facility construction sites. This equipment is mainly composed of foundation, tower body, upper and lower slewing supports, transition section, tower head, balance arm, counterweight, lifting arm, mechanism, trolley and hook. A slewing gear ring is installed between the upper and lower slewing supports to enable the upper boom to rotate and reach the specified position. In existing medium-sized tower cranes, a transition section is set between the tower head and the upper slewing support. The transition section and the tower head are integrally welded. Usually, the upper slewing support and the transition section are connected by a pin. (1) The transition section and the tower head are relatively large in size. After being connected to the slewing support, the overall transportation is too high and needs to be disassembled. (2) The sleeve and slewing connection need to be disassembled during transportation. (3) The slewing structure is subjected to a large bending moment. Utility Model Content
[0003] The utility model aims to provide a flat-top tower crane structure which is convenient for the overall transportation of the rotary structure, so as to solve the shortcomings of the prior art such as too high transportation height and large bending moment of the rotary structure.
[0004] The utility model is realized by adopting the following technical scheme: a flat-top tower crane structure which is convenient for the overall transportation of the rotating structure, characterized in that it comprises a rotating upper support, a rotating lower support, a transition section, a balance arm, a boom, and a tower head, wherein the balance arm and the boom are connected to the tower head, the tower head is connected to the pin shaft of the rotating upper support, the rotating lower support is connected to the rotating upper support through a rotating gear ring, the transition section is arranged below the rotating lower support, and the bottom of the transition section can be connected to a lifting sleeve.
[0005] Furthermore, the tower head is mainly composed of a main structural beam and a tower head bottom plate, the tower head bottom plate is integrally connected to the main structural beam, and the tower head bottom plate is arranged on both sides of the bottom end of the main structural beam.
[0006] Furthermore, an upper support connection hole is provided on the tower head, and the upper support connection hole is arranged on the axis of the main structure beam.
[0007] Furthermore, the rotary upper support includes an upper support body, and an upper support connecting ear plate is provided on the upper support body, and the upper support connecting ear plate is connected to the upper support connecting hole pin shaft.
[0008] Furthermore, a connection pin hole is provided on the upper support connection ear plate, the upper support connection ear plate is arranged between the tower head bottom plates on both sides of the main structure beam, and the connection pin hole is arranged coaxially with the upper support connection hole.
[0009] Furthermore, the slewing lower support includes a lower support body, and a connecting sleeve is provided on the side of the lower support body.
[0010] Furthermore, the slewing lower support is connected to the transition section bolts via a connecting sleeve.
[0011] Furthermore, the transition section includes a transition section body, the transition section body adopts a frame structure, jacking connection plates are arranged around the transition section body, and the jacking connection plates are provided with pin holes that can be connected to the jacking sleeve.
[0012] The utility model discloses a flat-top tower crane structure that is convenient for the overall transportation of the slewing structure. By eliminating the transition section between the tower head and the slewing upper support, the height is lowered, the overall transportation height is reduced, and the distance between the balance arm and the boom to the slewing upper support is closer, so that the slewing structure is subjected to a smaller bending moment, and the strength requirement of the overall structure is reduced, which is conducive to the optimization of the slewing structure. At the same time, the tower head and the slewing upper support are directly connected by a pin shaft, which is convenient to manufacture and is conducive to the removal of the tower head under different transportation conditions. A transition section is added below the slewing lower support, which not only reduces the difficulty of manufacturing the slewing lower support, but also ensures that the overall height remains unchanged, the tower crane jacking operation can be carried out normally, and it can be transported as a whole with the sleeve. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. The drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0014] Figure 1 It is a schematic diagram of a flat-top tower crane structure that is convenient for the overall transportation of the rotating structure;
[0015] Figure 2 It is a schematic diagram of the rotary upper support structure;
[0016] Figure 3 It is a schematic diagram of the slewing lower support structure;
[0017] Figure 4 It is a schematic diagram of the transition section structure;
[0018] Figure 5 This is a schematic diagram of the tower head structure;
[0019] In the figure: 1-slewing upper support; 2-slewing lower support; 3-transition section; 4-balance arm; 5-jib; 6-tower head; 11-upper support body; 12-upper support connecting ear plate; 13-connecting pin hole; 21-lower support body; 22-connecting sleeve; 31-transition section body; 32-lifting connecting plate; 61-upper support connecting hole; 62-main structure beam; 63-jib connecting hole; 64-balance arm connecting hole; 65-tower head bottom plate. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.
[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] like Figure 1-5 As shown, a flat-top tower crane structure convenient for overall transportation of a slewing structure comprises a slewing upper support 1, a slewing lower support 2, a transition section 3, a balance arm 4, a boom 5 and a tower head 6, wherein the tower head 6 is connected to the balance arm 4 and the boom 5 on both sides, and the tower head 6 is mainly composed of a main structural beam 62 and a tower head bottom plate 65, wherein the main structural beam 62 has two groups, each group of main structural beams 62 is arranged at an angle and welded, and the main structural beam 62 is connected to the tower head top plate at the top and the tower head bottom plate 65 at the bottom, wherein There are four tower head bottom plates 65 divided into two groups, wherein each group of tower head bottom plates 65 is composed of two tower head bottom plates 65, each group of tower head bottom plates 65 is arranged on both sides of the end of the main structure beam 62 and welded to the main structure beam 62, and the tower head bottom plates 65 are also provided with upper support connecting holes 61, boom connecting holes 63 and balance arm connecting holes 64, and the lower part of the tower head 6 is connected to the rotating upper support 1 through the upper support connecting hole 61, and the upper support connecting hole 61 is arranged on the axis of the main structure beam 62.
[0023] The slewing upper support 1 includes an upper support body 11, on which four upper support connecting ear plates 12 are welded. The upper support body 11 is mainly composed of two upper and lower structural plates, which are connected by the upper support connecting ear plate 12. One end of the upper support connecting ear plate 12 extends out from the upper support body 11. The protruding portion of the upper support connecting ear plate 12 is provided with a connecting pin hole 13. The upper support connecting hole 61 is pin-connected to the upper support connecting ear plate 12 through the connecting pin hole 13. The upper support connecting ear plate 12 is inserted between each group of tower head bottom plates 65, and the connecting pin hole 13 is coaxially arranged with the upper support connecting hole 61.
[0024] A slewing gear ring is arranged between the slewing upper support 1 and the slewing lower support 2, and a transition section 3 is connected to the bottom of the slewing lower support 2 by bolts. The slewing lower support 2 includes a lower support body 21, and a connecting sleeve 22 for connecting with the transition section 3 is arranged on the side of the lower support body 21. The transition section 3 includes a transition section body 31, and the transition section body 31 adopts a frame structure, and its height is determined according to actual needs. A jacking connecting plate 32 is arranged around the transition section body 31, and the jacking connecting plate 32 is used to connect with the pin shaft of the jacking sleeve frame.
[0025] A flat-top tower crane structure that is convenient for the overall transportation of a rotating structure eliminates the transition section between the tower head 6 and the rotating upper support 1, and directly connects the tower head 6 and the rotating upper support 1 through a pin shaft. The height is lower, which reduces the overall transportation height. The balance arm 4 and the boom 5 are closer to the rotating upper support 1, so that the rotating structure is subjected to a smaller bending moment, and the strength requirement of the overall structure is reduced, which is beneficial to the optimization of the rotating structure. A transition section 3 is added below the rotating lower support 2 to ensure that the overall height remains unchanged, and the tower crane jacking operation can be carried out normally.
[0026] The above embodiments describe the basic principle and main features of the utility model and the advantages of the utility model. The technicians in this industry should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the changes and modifications made by the technicians in this field shall be within the scope of protection of the claims attached to the utility model.
Claims
1. A flat-top tower crane structure that facilitates the overall transportation of the rotating structure, characterized in that: The utility model comprises a slewing upper support (1), a slewing lower support (2), a transition section (3), a balancing arm (4), a boom (5), and a tower head (6), wherein the balancing arm (4) and the boom (5) are connected to the tower head (6), the tower head (6) is connected to the slewing upper support (1) by a pin shaft, the slewing lower support (2) is connected to the slewing upper support (1) via a slewing gear ring, the transition section (3) is arranged below the slewing lower support (2), and the bottom of the transition section (3) can be connected to a lifting frame.
2. A flat-top tower crane structure that facilitates the overall transportation of the rotating structure according to claim 1, characterized in that: The tower head (6) is mainly composed of a main structural beam (62) and a tower head bottom plate (65); the tower head bottom plate (65) is integrally connected to the main structural beam (62); and the tower head bottom plate (65) is arranged on both sides of the bottom end of the main structural beam (62).
3. The flat-top tower crane structure that is convenient for overall transportation of the rotating structure according to claim 1 is characterized in that: An upper support connection hole (61) is provided on the tower head (6), and the upper support connection hole (61) is arranged on the axis of the main structure beam (62).
4. A flat-top tower crane structure that facilitates the overall transportation of the rotating structure according to claim 3, characterized in that: The rotary upper support (1) comprises an upper support body (11), an upper support connecting ear plate (12) is provided on the upper support body (11), and the upper support connecting ear plate (12) is pin-connected to the upper support connecting hole (61).
5. A flat-top tower crane structure that facilitates the overall transportation of the rotating structure according to claim 4, characterized in that: The upper support connection ear plate (12) is provided with a connection pin hole (13), the upper support connection ear plate (12) is arranged between the tower head bottom plates (65) on both sides of the main structure beam (62), and the connection pin hole (13) is coaxially arranged with the upper support connection hole (61).
6. The flat-top tower crane structure that is convenient for overall transportation of the rotating structure according to claim 1, characterized in that: The slewing lower support (2) comprises a lower support body (21), a connecting sleeve (22) is provided on the side of the lower support body (21), and the slewing lower support (2) is bolted to the transition section (3) via the connecting sleeve (22).
7. The flat-top tower crane structure that is convenient for overall transportation of the rotating structure according to claim 1 is characterized in that: The transition section (3) comprises a transition section body (31), the transition section body (31) is provided with lifting connection plates (32) around its periphery, the lifting connection plates (32) are provided with pin holes that can be connected to a lifting sleeve, and the transition section body (31) adopts a frame structure.