Splicing type concrete pipe pile

Through the combined design of the I-shaped structure and slot insert blocks, the problem that the existing precast concrete pipe piles cannot be adjusted in height is solved, the flexible adjustment of the height of the pipe piles and the support stability are achieved, ensuring that the support requirements of the building are met.

CN221878058UActive Publication Date: 2024-10-22LUAN HENGJI BUILDING MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323431293.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-15
Publication Date
2024-10-22
Estimated Expiration
2033-12-15

AI Technical Summary

Technical Problem

Existing precast concrete pipe piles lack the function of splicing and lengthening, and cannot meet the support needs of different building heights.

Method used

A spliced ​​concrete pipe pile is designed. The combination of the I-shaped structure and the slot insert allows the height of the pipe pile to be adjusted. The tapered structure of the bottom plate and the insertion rod ensures that it is fixed to the ground. The L plate and the reinforcing plate strengthen the connection. degree, fixed rails and fixed sleeves improve connection stability.

Benefits of technology

It realizes the flexible adjustment of the height of the pipe pile, ensures the stability of the building support, prevents tilting, and improves the connection strength between the pipe pile and the bottom plate to meet different building support needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878058U_ABST
    Figure CN221878058U_ABST
Patent Text Reader

Abstract

The utility model provides a spliced concrete pipe pile. The spliced concrete pipe pile comprises a bottom plate, an inserting rod is installed at the bottom of the bottom plate, a first pipe pile is installed at the top of the bottom plate, and the first pipe pile is of an I-shaped structure; the second pipe pile is arranged to be of an I-shaped structure, and the second pipe pile is installed at the top of the first pipe pile in an inserted mode; and the third pipe pile is arranged to be of an I-shaped structure, and the third pipe pile is installed at the top of the second pipe pile in an inserted mode. The first pipe piles are installed at the top of the bottom plate, the second pipe piles are inserted into the tops of the first pipe piles, the third pipe piles are inserted into the tops of the second pipe piles, the top plate is installed at the tops of the third pipe piles, and the top plate can be used for supporting a building; and the overall height of the device can be adjusted, so that the building supporting requirements under different conditions are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of concrete pipe piles, in particular to a spliced ​​concrete pipe pile. Background Art

[0002] Concrete pipe piles are a common form of foundation structure, widely used in engineering fields such as buildings, bridges, docks, and flood control projects. It is a circular tubular element made of concrete. The pipe piles are usually embedded in the ground by drilling or hitting, and are used to support and transfer the load of buildings or structures to the underground soil layer. Concrete pipe piles have high strength and rigidity and can withstand large loads. Because they are designed as a circular cross-section structure with good bending and shear resistance, the construction of concrete pipe piles usually adopts methods such as drilling, hitting or extrusion. The drilling method is to put the prefabricated pipe piles into the hole after digging a hole underground, and then pour concrete to solidify. The hitting method is to use a pile driver to drive the pipe piles directly into the soil layer. The extrusion method is usually suitable for soft soil layers. The pile body is formed by pressing the pipe piles and discharging soil to the edge. Concrete pipe piles are widely used in various projects, including foundation support of buildings, bridge pile foundations, marine docks and dam structures. In flood control projects such as rivers, estuaries and coasts, concrete pipe piles are also used as fixed protective structures and wave energy dissipation devices. The length and diameter of concrete pipe piles depend on the project requirements and underground soil conditions. Usually, the pile length is generally several meters to tens of meters, and the diameter can range from tens of centimeters to several meters. Concrete pipe piles are usually used in conjunction with other basic engineering structures, such as pile foundations, caps, underground continuous walls, etc. By combining with other structures, concrete pipe piles can provide a stable and reliable load transfer path.

[0003] The existing authorized public number is CN211735362U, which discloses a precast concrete pipe pile, belonging to the field of construction technology. It solves the technical problems of poor bearing capacity of existing precast concrete pipe piles. The precast concrete pipe pile includes a hollow cylindrical pile body, and the outer wall of the pile body is provided with a plurality of bosses arranged at intervals along the circumference of the pile body, characterized in that the boss is in the shape of an elongated strip and arranged parallel to the axis of the pile body, the upper end face of the boss is flush with the upper end face of the pile body, the lower end face of the boss is flush with the lower end face of the pile body, and the boss gradually retracts toward the pile body along its table surface. The utility model improves the bearing capacity of the precast concrete pipe pile while ensuring the convenience of piling. However, the above-mentioned precast concrete pipe pile does not have the function of splicing and lengthening. In the actual use of concrete pipe piles, since the heights of the buildings to be supported are different, it is necessary to adjust the height of the concrete pipe pile to meet the support needs of different buildings. Therefore, it is necessary to provide a splicing type concrete pipe pile to solve the above problems. Utility Model Content

[0004] The technical content of the utility model is to provide a spliced ​​concrete pipe pile.

[0005] In order to solve the above problems, the utility model provides a spliced ​​concrete pipe pile, including: a base plate, a plug rod is installed at the bottom of the base plate, a first pipe pile is installed on the top of the base plate, and the first pipe pile is arranged as an I-shaped structure; a second pipe pile, the second pipe pile is arranged as an I-shaped structure, and the second pipe pile is inserted and installed on the top of the first pipe pile; a third pipe pile, the third pipe pile is arranged as an I-shaped structure, and the third pipe pile is inserted and installed on the top of the second pipe pile.

[0006] As a further solution of the present invention, four groups of fixing blocks are evenly installed on the side of the base plate, the top and bottom of the fixing blocks are flush with the top and bottom of the base plate respectively, the insertion rod is fixedly installed at the bottom of the fixing block, and the bottom of the insertion rod is set to a conical structure, which is convenient for inserting the insertion rod into the ground, thereby fixing the base plate to the ground.

[0007] As a further solution of the present invention, an L-plate is installed on the bottom side of the first pipe pile, and the side of the L-plate is fixedly connected to the side of the first pipe pile by a fixing bolt, the bottom of the L-plate is fixedly connected to the top of the bottom plate by a fixing bolt, and a reinforcing plate is installed on the top of the L-plate, and the reinforcing plate and the L-plate are perpendicular to each other. A total of four groups of L-plates are arranged on both sides of the first pipe pile, which can improve the connection firmness between the first pipe pile and the bottom plate.

[0008] As a further solution of the present invention, a first plug block is installed at the bottom of the second pipe pile, and the first plug block is inserted into a slot opened at the top of the first pipe pile. The first plug block is arranged as an I-shaped structure, and has a large contact area with the slot, thereby providing a stable connection between the first pipe pile and the second pipe pile.

[0009] As a further solution of the present invention, fixed rails are installed on both sides of the top of the first pipe pile and both sides of the bottom of the second pipe pile. The fixed rails are fixedly connected to the first pipe pile and the second pipe pile through fixed plates. Fixing bolts are inserted into the two sets of fixed rails on the same side, so that the two sets of fixed rails are assembled together.

[0010] As a further solution of the present invention, a fixing sleeve is installed on the outer side of the fixing rail, the inner top surface and the bottom surface of the fixing sleeve are both arranged with protruding structures, the fixing rail is provided with corresponding grooves, and three groups of fixing bolts are inserted in the fixing sleeve, and the fixing bolts pass through the fixing sleeve and the two groups of fixing rails, so that the fixing sleeve and the two groups of fixing rails are assembled together.

[0011] As a further solution of the present invention, a second plug block is installed at the bottom of the third pipe pile, and the second plug block is inserted into a slot opened at the top of the second pipe pile. The second plug block is arranged in an I-shaped structure, and assembly plates are installed on both sides of the top of the second pipe pile and both sides of the bottom of the third pipe pile. The two sets of assembly plates on the same side are assembled together by fixing bolts, so that the third pipe pile is installed on the top of the second pipe pile.

[0012] As a further solution of the present invention, a top plate is installed on the top of the third pipe pile, a third plug block is installed on the bottom of the top plate, the third plug block is inserted into a slot opened on the top of the third pipe pile, a fixing bolt is inserted on the left side of the third pipe pile, the fixing bolt penetrates the third pipe pile and the third plug block in turn, and then the third plug block is firmly installed in the slot opened on the top of the third pipe pile.

[0013] Compared with the related art, the spliced ​​concrete pipe pile provided by the utility model has the following beneficial effects:

[0014] 1. The utility model installs a first pipe pile on the top of the bottom plate, a second pipe pile is inserted on the top of the first pipe pile, a third pipe pile is inserted on the top of the second pipe pile, and a top plate is installed on the top of the third pipe pile. The top plate can provide support for the building, and the overall height of the device can be adjusted by adjusting the number of the second pipe piles and the third pipe piles, thereby meeting the building support needs in different situations.

[0015] 2. The utility model evenly distributes and installs four sets of fixing blocks on the side of the bottom plate, and the bottom of the fixing blocks is fixed with an insertion rod, and the bottom of the insertion rod is set to a conical structure, which is convenient for inserting the insertion rod into the ground, thereby fixing the bottom plate on the ground, and then fixing the device on the ground, thereby preventing the device from tilting when supporting the building.

[0016] 3. The utility model installs an L-plate between the bottom plate and the first plug column by means of a fixing bolt, and a reinforcing plate is installed on the top of the L-plate. The reinforcing plate and the L-plate are perpendicular to each other, so as to increase the strength of the L-plate 7. The L-plate can be used to increase the firmness of the connection between the first pipe pile and the bottom plate, thereby avoiding the separation of the first pipe pile and the bottom plate due to the excessive weight of the building supported by the top plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to facilitate understanding by those skilled in the art, the present invention is further described below in conjunction with the accompanying drawings.

[0018] Figure 1 It is a top view of a three-dimensional structure of a spliced ​​concrete pipe pile of the utility model;

[0019] Figure 2This is a schematic diagram of the split structure of the second pipe pile and the third pipe pile of a spliced ​​concrete pipe pile of the utility model;

[0020] Figure 3 This is a schematic diagram of the split structure of the first pipe pile and the second pipe pile of a spliced ​​concrete pipe pile of the utility model;

[0021] Figure 4 This is a bottom-up three-dimensional structural schematic diagram of a third pipe pile of a spliced ​​concrete pipe pile of the utility model;

[0022] Figure 5 It is a schematic diagram of the split structure of the top plate and the third pipe pile of a spliced ​​concrete pipe pile of the utility model;

[0023] Figure 6 It is a schematic diagram of the enlarged structure of point A of a spliced ​​concrete pipe pile of the utility model.

[0024] In the figure: 1, bottom plate; 2, plug rod; 3, first pipe pile; 4, second pipe pile; 5, third pipe pile; 6, fixed block; 7, L plate; 8, reinforcement plate; 9, first plug block; 10, fixed rail; 11, fixed sleeve; 12, second plug block; 13, assembly plate; 14, top plate; 15, third plug block. DETAILED DESCRIPTION

[0025] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 A spliced ​​concrete pipe pile, characterized in that it comprises: a bottom plate 1, a plug rod 2 is installed at the bottom of the bottom plate 1, a first pipe pile 3 is installed on the top of the bottom plate 1, and the first pipe pile 3 is arranged in an I-shaped structure; a second pipe pile 4, the second pipe pile 4 is arranged in an I-shaped structure, and the second pipe pile 4 is inserted and installed on the top of the first pipe pile 3; a third pipe pile 5, the third pipe pile 5 is arranged in an I-shaped structure, and the third pipe pile 5 is inserted and installed on the top of the second pipe pile 4.

[0026] Preferably, four groups of fixing blocks 6 are evenly installed on the side of the bottom plate 1, the top and bottom of the fixing blocks 6 are flush with the top and bottom of the bottom plate 1 respectively, the insertion rod 2 is fixedly installed at the bottom of the fixing blocks 6, and the bottom of the insertion rod 2 is set to a conical structure, which is convenient for inserting the insertion rod 2 into the ground, thereby fixing the bottom plate 1 on the ground;

[0027] Preferably, an L-plate 7 is installed on the bottom side of the first pipe pile 3, and the side of the L-plate 7 is fixedly connected to the side of the first pipe pile 3 through a fixing bolt, and the bottom of the L-plate 7 is fixedly connected to the top of the bottom plate 1 through a fixing bolt, and a reinforcing plate 8 is installed on the top of the L-plate 7, and the reinforcing plate 8 and the L-plate 7 are perpendicular to each other, which can increase the strength of the L-plate 7. A total of four groups of L-plates 7 are arranged on both sides of the first pipe pile 3, which can improve the firmness of the connection between the first pipe pile 3 and the bottom plate 1;

[0028] Preferably, a first plug block 9 is installed at the bottom of the second pipe pile 4, and the first plug block 9 is inserted into a slot opened at the top of the first pipe pile 3, so that the second pipe pile 4 is assembled to the top of the first pipe pile 3. The first plug block 9 is set to an I-shaped structure, and has a large contact area with the slot, which can provide a stable connection between the first pipe pile 3 and the second pipe pile 4;

[0029] Preferably, both sides of the top of the first pipe pile 3 and both sides of the bottom of the second pipe pile 4 are installed with fixed rails 10, and the fixed rails 10 are fixedly connected to the first pipe pile 3 and the second pipe pile 4 through a fixing plate. After the first pipe pile 3 and the second pipe pile 4 are assembled together, the two sets of fixed rails 10 installed on the same side of the first pipe pile 3 and the second pipe pile 4 are in contact, and fixing bolts are inserted into the two sets of fixed rails 10 on the same side, so that the two sets of fixed rails 10 are assembled together, and the second pipe pile 4 is firmly installed on the top of the first pipe pile 3;

[0030] Preferably, a fixing sleeve 11 is installed on the outer side of the fixing rail 10, and the inner top surface and bottom surface of the fixing sleeve 11 are both provided with a protruding structure, and a corresponding groove is provided on the fixing rail 10, so that the fixing sleeve 11 cannot be laterally separated from the fixing rail 10 after being installed on the outer sides of the two sets of fixing rails 10, and three sets of fixing bolts are inserted in the fixing sleeve 11, and the fixing bolts pass through the fixing sleeve 11 and the two sets of fixing rails 10, so that the fixing sleeve 11 and the two sets of fixing rails 10 are assembled together, so that the fixing sleeve 11 cannot be longitudinally separated from the fixing rail 10, and the fixing sleeve 11 can be used to stably install the second pipe pile 4 on the top of the first pipe pile 3;

[0031] Preferably, a second plug block 12 is installed at the bottom of the third pipe pile 5, and the second plug block 12 is inserted into the slot opened at the top of the second pipe pile 4, so that the third pipe pile 5 is assembled to the top of the second pipe pile 4. The second plug block 12 is set to an I-shaped structure, and the contact area with the slot is large, which can provide a stable connection between the second pipe pile 4 and the third pipe pile 5. Assembly plates 13 are installed on both sides of the top of the second pipe pile 4 and both sides of the bottom of the third pipe pile 5. The two groups of assembly plates 13 on the same side are assembled together by fixing bolts, so that the third pipe pile 5 is installed on the top of the second pipe pile 4;

[0032] Preferably, a top plate 14 is installed on the top of the third pipe pile 5, and a third plug block 15 is installed on the bottom of the top plate 14. The third plug block 15 is inserted into a slot opened on the top of the third pipe pile 5, so that the top plate 14 is assembled to the top of the third pipe pile 5. A fixing bolt is inserted on the left side of the third pipe pile 5, and the fixing bolt penetrates the third pipe pile 5 and the third plug block 15 in turn, and then the third plug block 15 is firmly installed in the slot opened on the top of the third pipe pile 5. The top plate 14 can provide a supporting effect on the building. By adjusting the number of the second pipe piles 4 and the third pipe piles 5, the overall height of the device can be adjusted to meet the building support needs in different situations.

[0033] It should be noted that the equipment structure and drawings of the utility model mainly describe the principle of the utility model. In terms of the technology of the design principle, the settings of the power mechanism, power supply system and control system of the device are not fully described. On the premise that the technical personnel in this field understand the principle of the above utility model, the details of the power mechanism, power supply system and control system can be clearly known. The control method of the application document is automatic control through a controller, and the control circuit of the controller can be realized by simple programming by the technical personnel in this field;

[0034] The standard parts used therein can all be purchased from the market and can be customized according to the instructions and drawings. The specific connection methods of each part adopt conventional means such as mature bolts, rivets, welding, etc. in the prior art. The machinery, parts and equipment all adopt conventional models in the prior art, and the structures and principles of the components known to technical personnel in this field can be known by these technical personnel through technical manuals or through conventional experimental methods.

[0035] Although the embodiments of the present invention have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and variations or direct or indirect applications may be made to these embodiments without departing from the principles and spirit of the present invention. In other related technical fields, the scope of the present invention is defined by the attached claims and their equivalents, which are equally included in the scope of patent protection of the present invention.

Claims

1. A spliced ​​concrete pipe pile, characterized in that: include: A base plate (1), wherein a plunger (2) is installed at the bottom of the base plate (1), and a first pipe pile (3) is installed at the top of the base plate (1), wherein the first pipe pile (3) is arranged in an I-shaped structure; A second pipe pile (4), wherein the second pipe pile (4) is arranged in an I-shaped structure, and the second pipe pile (4) is inserted and installed on the top of the first pipe pile (3); A third pipe pile (5), wherein the third pipe pile (5) is arranged in an I-shaped structure and is inserted and installed on the top of the second pipe pile (4).

2. The spliced ​​concrete pipe pile according to claim 1, characterized in that: Four groups of fixing blocks (6) are evenly mounted on the side of the base plate (1), the top and bottom of the fixing blocks (6) are respectively flush with the top and bottom of the base plate (1), the insertion rod (2) is fixedly mounted on the bottom of the fixing blocks (6), and the bottom of the insertion rod (2) is arranged to be a conical structure.

3. The spliced ​​concrete pipe pile according to claim 1, characterized in that: An L-plate (7) is installed on the bottom side of the first pipe pile (3), the side of the L-plate (7) is fixedly connected to the side of the first pipe pile (3) via a fixing bolt, the bottom of the L-plate (7) is fixedly connected to the top of the bottom plate (1) via a fixing bolt, and a reinforcing plate (8) is installed on the top of the L-plate (7), the reinforcing plate (8) and the L-plate (7) are perpendicular to each other, and a total of four groups of L-plates (7) are arranged on both sides of the first pipe pile (3).

4. The spliced ​​concrete pipe pile according to claim 1, characterized in that: A first plug block (9) is installed at the bottom of the second pipe pile (4), and the first plug block (9) is inserted into a slot opened at the top of the first pipe pile (3). The first plug block (9) is arranged in an I-shaped structure.

5. The spliced ​​concrete pipe pile according to claim 1, characterized in that: Fixed rails (10) are installed on both sides of the top of the first pipe pile (3) and both sides of the bottom of the second pipe pile (4); the fixed rails (10) are fixedly connected to the first pipe pile (3) and the second pipe pile (4) via fixing plates; fixing bolts are inserted into the two sets of fixed rails (10) on the same side.

6. The spliced ​​concrete pipe pile according to claim 5, characterized in that: A fixing sleeve (11) is installed on the outer side of the fixing rail (10), and the inner top surface and bottom surface of the fixing sleeve (11) are both provided with protruding structures. A corresponding groove is provided on the fixing rail (10), and three groups of fixing bolts are inserted into the fixing sleeve (11), and the fixing bolts pass through the fixing sleeve (11) and the two groups of fixing rails (10).

7. The spliced ​​concrete pipe pile according to claim 1, characterized in that: A second plug block (12) is installed at the bottom of the third pipe pile (5), and the second plug block (12) is inserted into a slot opened at the top of the second pipe pile (4). The second plug block (12) is arranged in an I-shaped structure. Assembly plates (13) are installed on both sides of the top of the second pipe pile (4) and both sides of the bottom of the third pipe pile (5), and the two groups of assembly plates (13) on the same side are assembled together by fixing bolts.

8. The spliced ​​concrete pipe pile according to claim 1, characterized in that: A top plate (14) is installed on the top of the third pipe pile (5), a third plug block (15) is installed on the bottom of the top plate (14), the third plug block (15) is inserted into a slot opened on the top of the third pipe pile (5), a fixing bolt is inserted on the left side of the third pipe pile (5), the fixing bolt penetrates the third pipe pile (5) and the third plug block (15) in sequence, and then the third plug block (15) is firmly installed in the slot opened on the top of the third pipe pile (5).