Super-high building truss reinforcing layer steel beam and steel reinforced concrete column combined structure

By using a combination of straight beams and curved reinforcing beams with steel-concrete composite columns in super high-rise buildings, the problem of complex formwork erection in traditional construction has been solved, thereby improving structural strength and construction efficiency.

CN221878388UInactive Publication Date: 2024-10-22CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420358623.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In traditional steel structure construction, the number of connection nodes between horizontal steel beams and vertical steel support columns increases, and the formwork erection becomes more complex, resulting in low construction efficiency and high costs.

Method used

The structure adopts a combination of straight beams and curved reinforcing beams with steel-concrete columns, connected by the first and second beam-column joints, combined with diagonal braces and reinforcing connecting plates, which simplifies the formwork erection and welding operations.

Benefits of technology

It improved structural strength, simplified the formwork erection process, reduced labor costs and construction difficulty, and improved construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878388U_ABST
    Figure CN221878388U_ABST
Patent Text Reader

Abstract

The utility model discloses an ultrahigh building truss reinforcing layer steel beam and steel reinforced concrete column combined structure which comprises a steel beam, section steel columns and a concrete layer arranged on the outer sides of the section steel columns, the steel beam comprises a cross beam and an arc-shaped reinforcing beam, and the two ends of the cross beam are fixedly installed on the two adjacent section steel columns through first beam column connectors. The two ends of the arc-shaped reinforcing beams are fixedly installed on the two adjacent section steel columns through second beam column connectors. Reinforcing plates are fixedly arranged on the two sides of the first beam column connector, and inclined supporting rods are fixedly arranged between the reinforcing plates and the cross beam. The second beam column connector is located below the first beam column connector. According to the structure, a group of straight cross beams and a group of arc-shaped reinforcing beams are adopted, so that the structural strength of the whole structure is improved, beam-column connecting joints are compact, a template is convenient to erect, the construction efficiency is improved, and the application prospect is wide.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of super-high building steel structure construction, in particular to a super-high building truss reinforcement layer steel beam and steel concrete column combined structure. Background Art

[0002] At present, super-high buildings occupy part of the construction market, and their structural forms are becoming increasingly diversified. Due to construction cost reasons, the structural form of full reinforced concrete structure + intermediate steel structure truss reinforcement layer is still favored. The reinforced concrete floor has a simple structural form, uses an aluminum formwork system, and adopts a construction deployment of simultaneous casting of vertical and horizontal structures. In order to keep the construction pace the same as other floors and improve quality and efficiency, a new steel structure truss reinforcement layer is added in the middle. It is necessary to focus on solving the construction difficulties caused by differences in structural forms. A super-high building has 61 floors above ground, a total building height of 268m, and a single-story area of ​​about 3,000 ㎡. The whole is a full reinforced concrete structure, with the 29th floor being a steel truss reinforcement layer. The horizontal structure of the truss layer adds exposed steel beams instead of concrete beams, which are combined with reinforced concrete floor slabs to form steel-concrete composite floor slabs. In traditional building steel structure construction, horizontal steel beams and vertical steel support columns are usually fixedly connected to form a building support body. For the structural requirements of the reinforced layer, two sets of horizontal steel beams are usually set in parallel, and supports are set between the two sets of horizontal steel beams to improve the strength of the structure. This construction method increases the number of beam-column nodes, and it is difficult to set up formwork between two adjacent horizontal steel beams. The formwork needs to be cut and spliced ​​on site, which reduces construction efficiency and increases construction costs. Utility Model Content

[0003] The utility model aims to provide a super-high building truss reinforcement layer steel beam and steel concrete column combined structure, the structure adopts a group of straight beams and a group of arc-shaped reinforcement beams, which not only improves the structural strength of the overall structure, but also makes the beam-column connection nodes compact, facilitates the support of the formwork, improves the construction efficiency, and has broad application prospects.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] A combined structure of reinforced layer steel beams and steel-concrete columns of a super-high building truss, comprising a steel beam, a steel column and a concrete layer arranged on the outside of the steel column, the steel beam comprising a cross beam and an arc-shaped reinforcing beam, the two ends of the cross beam being fixedly mounted on two adjacent steel columns via a first beam-column joint, and the two ends of the arc-shaped reinforcing beam being fixedly mounted on two adjacent steel columns via a second beam-column joint; reinforcing plates are fixedly mounted on both sides of the first beam-column joint, and diagonal braces are fixedly mounted between the reinforcing plates and the cross beam; the second beam-column joint is located below the first beam-column joint.

[0006] Preferably, a first reinforcing connecting plate is fixedly provided at a connection position between the first beam-column joint and the cross beam; and a second reinforcing connecting plate is fixedly provided at a connection position between the second beam-column joint and the arc-shaped reinforcing beam.

[0007] Preferably, the cross beam and the arc-shaped reinforcement beam are both H-shaped steel.

[0008] Preferably, the first beam-column joint includes a first main connecting portion corresponding to the crossbeam and a first diagonal bracing portion fixedly arranged on both sides of the first main connecting portion, and one end of the first main connecting portion and the first diagonal bracing portion are both fixedly mounted on the steel column.

[0009] Preferably, the second beam-column joint comprises a mounting plate, a second main connecting portion fixedly mounted on the mounting plate, and a second diagonal bracing portion fixedly arranged between the second main connecting portion and the steel column.

[0010] In the utility model, a group of arc-shaped reinforcement beams are arranged at the bottom of the straight cross beam, which improves the overall structural strength, and the connection nodes of the cross beam and the arc-shaped reinforcement and the steel column are close. When setting up the formwork, the two adjacent connection nodes are cast in the concrete layer, which simplifies the complexity of setting up the formwork, improves the construction efficiency, reduces the labor required for setting up the formwork, and reduces the labor cost. The first beam-column joint and the second beam-column joint are arranged to facilitate the on-site welding of the beam and column, improve the construction efficiency, and reduce the difficulty of welding. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the structure of the utility model;

[0012] Figure 2 This is a schematic diagram of the floor structure of the utility model;

[0013] In the figure: 1. steel beam; 2. steel column; 3. concrete layer; 4. floor slab; 5. first beam-column joint; 6. second beam-column joint; 7. reinforcing plate; 8. diagonal brace; 10. cross beam; 11. arc-shaped reinforcing beam; 12. first reinforcing connecting plate; 13. second reinforcing connecting plate; 50. first main connection; 51. first diagonal brace; 60. mounting plate; 61. second main connection; 62. first diagonal brace. DETAILED DESCRIPTION

[0014] The utility model is further described below in conjunction with the accompanying drawings:

[0015] like Figure 1 and Figure 2The illustrated structure of a super-high building truss reinforcement layer steel beam and steel concrete column combination includes a steel beam 1, a steel column 2, and a concrete layer 3 cast outside the steel column 2, a steel bar structure is arranged in the concrete layer 3, the concrete layer 3 is cast at the same time as the floor slab 4, and the top of the steel beam 1 is flush with the bottom of the floor slab 4. That is, the top surface of the template of the built floor slab 4 is flush with the top surface of the steel beam 1. The template of the floor slab 4 is built at the same time as the template of the steel column 2, and then cast uniformly after the construction is completed.

[0016] The steel beam 1 includes a cross beam 10 and an arc-shaped reinforcement beam 11. Both the cross beam 10 and the arc-shaped reinforcement beam 11 are made of H-shaped steel, and the steel column 2 is also made of H-shaped steel. The two ends of the cross beam 10 are fixedly mounted on two adjacent steel columns 2 through a first beam-column joint 5, and the two ends of the arc-shaped reinforcement beam 11 are fixedly mounted on two adjacent steel columns 2 through a second beam-column joint 6. The second beam-column joint 6 is located below the first beam-column joint 5 and close to the first beam-column joint 5.

[0017] Reinforcement plates 7 are fixedly provided on both sides of the first beam-column joint 5, and diagonal braces 8 are fixedly provided between the reinforcement plates 7 and the cross beam 10 by welding. The diagonal braces 8 are used for reverse bracing and fixing, which avoids the problem that the traditional tension reinforcement requires on-site cutting and adjustment due to the mismatch of the positions of the tension reinforcement holes, simplifies the construction process and improves the construction efficiency while ensuring the structural strength. A first reinforcing connecting plate 12 is fixedly provided by welding at the connection position of the first beam-column joint 5 and the cross beam 10, and a second reinforcing connecting plate 13 is fixedly provided by welding at the connection position of the second beam-column joint 6 and the arc-shaped reinforcing beam 11. The first reinforcing connecting plate 12 and the second reinforcing connecting plate 13 improve the connection strength between the first beam-column joint 5 and the cross beam 10 and the second beam-column joint 6 and the arc-shaped reinforcing beam 11, thereby increasing the stability of the structure.

[0018] The first beam-column joint 5 includes a first main connection part 50 corresponding to the size of the cross beam 10 and a first diagonal brace part 51 fixedly arranged on both sides of the first main connection part 50 by welding, and one end of the first main connection part 50 and the first diagonal brace part 51 are both fixedly installed on the steel column 2 by welding. The second beam-column joint 6 includes a mounting plate 60 fixedly installed on the steel column 2 by welding at one end, a second main connection part 61 fixedly installed on the mounting plate 60 by welding, and a second diagonal brace part 62 fixedly arranged between the second main connection part 61 and the steel column 2 by welding. The mounting plate 60 is located in the middle of the second main connection part 61, and the second main connection part 61 and the first main connection part 50 are made of H-shaped steel.

[0019] The above embodiments are only some descriptions of the concept and implementation of the utility model, and are not intended to limit the concept and implementation of the utility model. Under the concept of the utility model, technical solutions that have not been substantially changed are still within the scope of protection.

Claims

1. A super-high building truss reinforced layer steel beam and steel concrete column combined structure, comprising a steel beam, a steel column and a concrete layer arranged outside the steel column, characterized in that: The steel beam includes a cross beam and an arc-shaped reinforcement beam, the two ends of the cross beam are fixedly installed on two adjacent steel columns through a first beam-column joint, and the two ends of the arc-shaped reinforcement beam are fixedly installed on two adjacent steel columns through a second beam-column joint; reinforcement plates are fixedly arranged on both sides of the first beam-column joint, and diagonal braces are fixedly arranged between the reinforcement plates and the cross beam; the second beam-column joint is located below the first beam-column joint.

2. The super-high building truss reinforcement layer steel beam and steel concrete column combined structure according to claim 1 is characterized in that: A first reinforcing connecting plate is fixedly arranged at the connecting position between the first beam-column joint and the cross beam; and a second reinforcing connecting plate is fixedly arranged at the connecting position between the second beam-column joint and the arc-shaped reinforcing beam.

3. The super-high building truss reinforcement layer steel beam and steel concrete column combined structure according to claim 1 or 2, characterized in that: The cross beam and the arc-shaped reinforcement beam are both H-shaped steels.

4. The super-high building truss reinforcement layer steel beam and steel concrete column combined structure according to claim 1 is characterized in that: The first beam-column joint includes a first main connection portion corresponding to the crossbeam and first diagonal bracing portions fixedly arranged on both sides of the first main connection portion, and one end of the first main connection portion and the first diagonal bracing portion are both fixedly mounted on the steel column.

5. The super-high building truss reinforced layer steel beam and steel concrete column combined structure according to claim 1 is characterized in that: The second beam-column joint includes a mounting plate, a second main connecting portion fixedly mounted on the mounting plate, and a second diagonal bracing portion fixedly disposed between the second main connecting portion and the steel column.