Coal mine chamber supporting device and system
Through the synergistic effect of connecting beams, anchor components and anchor cables, combined with the buffering effect of elastic parts, the problem of stress concentration in the chamber under complex geological conditions is solved, the support effect is improved, the risk of anchor cable breakage is reduced, and the safety of the coal mine is improved production level.
Patent Information
- Application Number
- CN202420650522.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-10-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Under complex geological conditions, the stress concentration between adjacent working surfaces causes the cave to be in a high-stress environment. The combined anchor cable support method is unable to withstand the huge pressure, causing the anchor cables to break, affecting the normal use of the cave.
The synergistic effect of connecting beams, anchor components and anchor cables is used to improve the overall performance of the support device through the partial pressure of the connecting beams, the fitting and fixation of the anchor components and the strong tightening of the anchor cables, combined with the buffering effect of the elastic parts. Prevent chamber collapse and anchor cable breakage.
It effectively prevents chamber collapse, reduces the risk of anchor cable breakage, improves the safety production level of coal mines, and provides a strong safety guarantee for coal mines.
Smart Images

Figure CN221879441U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of mine equipment, in particular to a coal mine chamber supporting device and system. Background Art
[0002] In the process of coal mining, especially in areas with complex geological conditions such as Xiaojiawa Coal Mine, chamber support is an important link to ensure safe production and efficient operation. In order to meet the support needs under complex geological conditions, combined anchor cable technology is widely used in chamber support.
[0003] In related technologies, due to the influence of geological structure, mining methods and other factors, stress concentration often occurs between adjacent working faces, which puts the chamber in a stress-increasing zone, causing the mine pressure to be abnormally severe, and exerting huge pressure on the support structure of the chamber. In this high-stress environment, the combined anchor cable support method is often unable to withstand the huge pressure, causing the anchor cable to be broken, making the chamber unable to be used normally. Utility Model Content
[0004] The utility model aims to solve one of the technical problems in the related art to at least a certain extent. To this end, a coal mine chamber support device is proposed in the embodiment of the utility model, which can improve the chamber support effect and provide a strong guarantee for the safe production of coal mines.
[0005] In addition, an embodiment of the utility model also provides a coal mine chamber support system.
[0006] The coal mine chamber support device provided by the embodiment of the utility model comprises:
[0007] Connecting beams;
[0008] A plurality of anchoring assemblies, wherein the plurality of anchoring assemblies are arranged at intervals on the connecting beam, the anchoring assemblies include a fixing seat and an anchoring seat which are arranged opposite to each other, the fixing seat and the anchoring seat are correspondingly arranged on both sides of the connecting beam, and the fixing seat is arranged in contact with the inner wall of the chamber;
[0009] A plurality of anchor cables are provided in one-to-one correspondence with the anchoring assemblies, and the anchor cables are used to fix the anchoring assemblies and the connecting beams to the inner wall of the chamber.
[0010] The coal mine chamber support device provided by the embodiment of the utility model realizes effective support of the chamber wall through the synergistic effect of the connecting beam, the anchoring assembly and the anchor cable. Among them, the pressure-dividing effect of the connecting beam, the fitting fixation of the anchoring assembly and the strong tensioning of the anchor cable jointly improve the overall performance of the support device, which can not only effectively prevent the collapse of the chamber, but also reduce the risk of anchor cable breakage, improve the safety production level of the coal mine, and provide a strong guarantee for the safety production of the coal mine.
[0011] In some embodiments, the anchoring assembly further includes an elastic member, and two ends of the elastic member are correspondingly abutted against the fixing seat and the anchoring seat.
[0012] In some embodiments, the elastic member includes a spring and a plurality of elastic pads, the spring is sleeved on the anchor cable, and the plurality of elastic pads are correspondingly arranged on both sides of the connecting beam.
[0013] In some embodiments, the connecting beam includes a first connecting rod and a second connecting rod, the first connecting rod and the second connecting rod are arranged side by side, a first clamping cavity and a second clamping cavity are formed between the fixed seat and the anchor seat, the first connecting rod is arranged in the first clamping cavity, and the second connecting rod is correspondingly arranged in the second clamping cavity.
[0014] In some embodiments, the connecting beam further includes a plurality of third connecting rods, two ends of the third connecting rods are correspondingly connected to the first connecting rod and the second connecting rod, and the plurality of third connecting rods are spaced apart along the length direction of the first connecting rod.
[0015] In some embodiments, the first connecting rod and the second connecting rod are both configured to be cylindrical, and the diameters of the first connecting rod and the second connecting rod are configured to be 15 mm to 25 mm.
[0016] In some embodiments, a first anchor hole is provided on the fixing seat, a second anchor hole is provided on the anchoring seat, the anchor cable has a locking end, the locking end passes through the first anchor hole and the second anchor hole in sequence, and a lock is provided on the locking end.
[0017] In some embodiments, the lock includes a sleeve and a locking tube, wherein the locking tube is disposed between the anchor cable and the sleeve, and a plurality of clamping arms are disposed at the end of the locking tube. The clamping arms are disposed at circumferential intervals along the anchor cable, and the clamping arms are inclined from the outer periphery of the sleeve toward the center of the sleeve.
[0018] In some embodiments, the spacing between two adjacent anchoring assemblies ranges from 1500 mm to 2000 mm;
[0019] And / or, the length of the fixing seat is set to 250 mm to 350 mm, the width of the fixing seat is set to 250 mm to 350 mm, and the thickness of the fixing seat is set to 15 mm to 25 mm;
[0020] And / or, the diameter of the anchor cable is 25 mm to 30 mm, and the length of the anchor cable is 7000 mm to 7600 mm.
[0021] The coal mine chamber support system provided by the embodiment of the utility model comprises the above-mentioned coal mine chamber support device, wherein the coal mine chamber support device is provided in plurality, and the plurality of coal mine chamber support devices are arranged at intervals along the inner wall of the chamber. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a structural schematic diagram of a coal mine chamber supporting device provided by an embodiment of the utility model.
[0023] Figure 2 It is a schematic diagram of the internal structure of a coal mine chamber support device provided by an embodiment of the utility model.
[0024] Figure 3 It is a stereoscopic diagram of a lock in a coal mine chamber supporting device provided by an embodiment of the utility model.
[0025] Figure 4 It is a structural schematic diagram of a lock in a coal mine chamber supporting device provided by an embodiment of the utility model.
[0026] Figure 5 It is a structural schematic diagram of a coal mine chamber support system provided by an embodiment of the utility model.
[0027] Reference numerals:
[0028] 100. Coal mine chamber support device; 200. Chamber inner wall;
[0029] 10. Connecting beam; 11. First connecting rod; 12. Second connecting rod; 13. Third connecting rod;
[0030] 20. Anchor assembly; 21. Fixing seat; 211. First groove; 212. Second groove; 22. Anchor seat; 221. Third groove; 222. Fourth groove; 23. Elastic member; 231. Spring; 232. Elastic pad; 24. First clamping cavity; 25. Second clamping cavity; 26. Arched portion;
[0031] 30. Anchor cable; 31. Locking end;
[0032] 40. Lock; 41. Bushing; 42. Locking tube; 43. Clamping arm. DETAILED DESCRIPTION
[0033] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but cannot be understood as limiting the present invention.
[0034] like Figures 1 to 4As shown, an embodiment of the utility model provides a coal mine chamber support device 100, which includes a connecting beam 10, a plurality of anchoring assemblies 20 and a plurality of anchor cables 30. The plurality of anchoring assemblies 20 are arranged at intervals on the connecting beam 10, and the anchoring assembly 20 includes a fixing seat 21 and an anchoring seat 22 which are arranged opposite to each other. The fixing seat 21 and the anchoring seat 22 are correspondingly arranged on both sides of the connecting beam 10, and the fixing seat 21 is arranged in contact with the inner wall 200 of the chamber; the anchor cables 30 and the anchoring assemblies 20 are arranged in a one-to-one correspondence, and the anchor cables 30 are used to fix the anchoring assemblies 20 and the connecting beam 10 to the inner wall 200 of the chamber.
[0035] Specifically, the connecting beam 10 can be arranged in close contact with the inner wall 200 of the chamber, which can effectively disperse the pressure of the chamber top and the surrounding rock formations, and disperse the pressure to multiple anchoring components 20, thereby reducing the risk of anchor cable breakage caused by stress concentration, making the tension borne by the anchor cable 30 more uniform, helping to improve the tensile performance of the anchor cable 30, and enhancing the overall strength and stability of the coal mine chamber support device 100. Furthermore, the fixing seat 21 is closely fitted to the inner wall 200 of the chamber, ensuring the close combination of the coal mine chamber support device 100 and the chamber wall, which can effectively prevent the collapse of the chamber. In addition, the anchoring seat 22 works in conjunction with the fixing seat 21, which can effectively enhance the overall stability of the coal mine chamber support device 100.
[0036] In summary, the coal mine chamber support device 100 realizes effective support of the chamber wall through the synergistic effect of the connecting beam 10, the anchor assembly 20 and the anchor cable 30. The pressure-dividing effect of the connecting beam 10, the fitting fixation of the anchor assembly 20 and the strong tension of the anchor cable 30 jointly improve the overall performance of the coal mine chamber support device 100, which can not only effectively prevent the collapse of the chamber, but also reduce the risk of anchor cable breakage, improve the safety production level of the coal mine, and provide a strong guarantee for the safety production of the coal mine.
[0037] Furthermore, the spacing between two adjacent anchoring assemblies 20 ranges from 1500mm to 2000mm, for example, 1500mm, 1600mm, 1800mm, 2000mm. It should be noted that appropriate spacing can ensure that when the coal mine chamber support device 100 is subjected to external force, each anchoring assembly 20 can work together to share the external force. If the spacing is too small, the coal mine chamber support device 100 may be too dense as a whole, increasing the difficulty and cost of construction; and if the spacing is too large, the stability of the coal mine chamber support device 100 may be reduced, and it may not be able to effectively resist external forces.
[0038] In some embodiments, the anchor assembly 20 further includes an elastic member 23, and the two ends of the elastic member 23 are correspondingly abutted against the fixing seat 21 and the anchor seat 22. When the chamber is subjected to external forces, such as rock movement or earthquake, the elastic member 23 can effectively absorb and disperse the impact forces to reduce the direct impact on the anchor cable 30, thereby reducing the risk of the anchor cable 30 breaking due to instantaneous overload.
[0039] Secondly, the elastic member 23 can balance the unevenness of the rock formation inside the chamber and the change of stress to a certain extent, making the force on the anchor cable 30 more uniform, reducing the risk of fracture due to local stress concentration, thereby extending the service life of the coal mine chamber support device 100.
[0040] In this embodiment, the elastic member 23 includes a spring 231 and a plurality of elastic pads 232, wherein the spring 231 is sleeved on the anchor cable 30, and the plurality of elastic pads 232 are correspondingly arranged on both sides of the connecting beam 10. The spring 231 is sleeved on the anchor cable 30, so that the spring 231 can directly adjust the stress of the anchor cable 30. That is, when the chamber is subjected to external forces, such as rock movement or earthquake, the spring 231 can absorb and disperse these impact forces through its elastic deformation, thereby reducing the direct impact on the anchor cable 30. In this way, when the anchor cable 30 is subjected to instantaneous overload, the spring 231 can provide additional support and buffering, thereby reducing the risk of the anchor cable breaking.
[0041] Furthermore, a plurality of elastic pads 232 are correspondingly arranged on both sides of the connecting beam 10, and the elastic pads 232 are located between the fixing seat 21 and the anchoring seat 22, so that an effective buffer layer can be formed between the fixing seat 21 and the anchoring seat 22. When the chamber is subjected to external forces, such as rock movement or earthquake, the elastic pads 232 can absorb and disperse these impact forces, reducing the direct impact on the fixing seat 21 and the anchoring seat 22. This buffering effect not only protects the fixing seat 21 and the anchoring seat 22, but more importantly, reduces the additional tension on the anchor cable 30 due to the impact, thereby reducing the risk of the anchor cable 30 breaking.
[0042] Secondly, due to the elastic properties of the elastic pad 232, the elastic pad 232 can compensate for the slight deformation caused by factors such as rock layer movement or temperature change to a certain extent. This allows the fixing seat 21 and the anchor seat 22 to maintain a tight fit, ensuring the overall stability of the coal mine chamber support device 100.
[0043] In some embodiments, the connecting beam 10 includes a first connecting rod 11 and a second connecting rod 12, which are arranged side by side, and a first supporting cavity and a second clamping cavity 25 are formed between the fixed seat 21 and the anchor seat 22. The first connecting rod 11 is arranged in the first clamping cavity 24, and the second connecting rod 12 is correspondingly arranged in the second clamping cavity 25, thereby improving the structural strength of the connecting beam 10 and improving the stress dispersion performance of the connecting beam 10.
[0044] Specifically, the first connecting rod 11 and the second connecting rod 12 are arranged side by side, so that the connecting beam 10 can distribute stress more evenly when subjected to external force, reduce stress concentration, and thus improve the bearing capacity of the connecting beam 10. At the same time, the first supporting cavity and the second clamping cavity 25 can provide a stable support for the first connecting rod 11 and the second connecting rod 12, so that the connection between the connecting beam 10 and the fixing seat 21 and the anchoring seat 22 is tighter, and can jointly resist the action of external forces. The first connecting rod 11 and the second connecting rod 12 are respectively arranged in the corresponding clamping cavities, ensuring that the connecting beam 10 can maintain a stable position when subjected to force and is not easily displaced or deformed.
[0045] Furthermore, the connecting beam 10 also includes a plurality of third connecting rods 13, the two ends of the third connecting rods 13 are correspondingly connected to the first connecting rod 11 and the second connecting rod 12, and the plurality of third connecting rods 13 are spaced apart along the length direction of the first connecting rod 11, thereby forming a more stable frame structure, which not only enhances the overall structural strength of the connecting beam 10, but also improves the stress dispersion performance of the connecting beam 10.
[0046] Among them, when the coal mine chamber support device 100 is subjected to external force, the third connecting rod 13 can effectively disperse the stress to the first connecting rod 11 and the second connecting rod 12, reduce the stress concentration phenomenon, and thus improve the bearing capacity and stability of the coal mine chamber support device 100. A plurality of third connecting rods 13 are arranged at intervals along the length direction of the first connecting rod 11, so that the connecting beam 10 can form multiple support points when subjected to force, thereby enhancing its overall stability and anti-deformation ability. It should be noted that the number and position of the third connecting rods 13 can be adjusted according to actual needs to adapt to different support conditions and stress distribution requirements.
[0047] In this embodiment, the first connecting rod 11 and the second connecting rod 12 are both cylindrical, and the diameters of the first connecting rod 11 and the second connecting rod 12 are set to 15 mm to 25 mm, for example, 15 mm, 18 mm, 20 mm, 25 mm, etc. The cylindrical design enables the first connecting rod 11 and the second connecting rod 12 to better disperse stress when subjected to external force, avoid stress concentration, and thus improve their bearing capacity and stability.
[0048] Furthermore, the diameters of the first connecting rod 11 and the second connecting rod 12 are set to 15 mm to 25 mm based on comprehensive consideration of the structural strength, stress dispersion performance, and material utilization efficiency of the coal mine chamber support device 100. This diameter range can ensure that the connecting rod has sufficient strength to withstand the external force, and can also avoid excessive diameters that lead to material waste and increase in device weight. Optionally, the third connecting rod can be set to the same specifications as the first connecting rod.
[0049] like Figure 2 As shown, in some embodiments, the fixing seat 21 and the locking seat may be provided with an arched portion 26, and a groove is formed in the arched portion 26, and the first connecting rod 11 and the second connecting rod 12 may be correspondingly arranged in the groove. The arrangement of the arched portion 26 and the groove inside it can not only accurately position the first connecting rod 11 and the second connecting rod 12, ensuring that they can be accurately placed in the clamping cavity to achieve a stable connection, but also can better disperse stress when the fixing seat 21 and the anchoring seat 22 are subjected to external force, thereby reducing the damage to the coal mine chamber support device 100 caused by stress concentration.
[0050] In this embodiment, a first groove 211 and a second groove 212 are provided on the fixing seat 21, and a third groove 221 and a fourth groove 222 are provided on the anchoring seat 22. The first groove 211 and the third groove 221 can cooperate to form a first clamping cavity 24, and the second groove 212 and the fourth groove 222 can cooperate to form a second clamping cavity 25.
[0051] In some embodiments, a first anchor hole is provided on the fixing seat 21, a second anchor hole is provided on the anchor seat 22, the anchor cable 30 has a locking end 31, the locking end 31 passes through the first anchor hole and the second anchor hole in sequence, and a lock 40 is provided on the locking end 31.
[0052] When the locking end 31 of the anchor cable 30 passes through the two anchor holes, the fixing seat 21 and the anchor seat 22 are effectively connected together to form a stable support structure, so that the anchor cable 30 can withstand greater tension, thereby improving the support effect. In addition, the lock 40 on the locking end 31 can be tightly locked on the anchor cable 30 to prevent it from slipping or loosening, and can maintain a stable tension when subjected to external force, which can effectively prevent support failure caused by loosening of the anchor cable 30.
[0053] like Figure 3 and Figure 4 As shown, in some embodiments, the lock 40 includes a sleeve 41 and a locking tube 42. The locking tube 42 is arranged between the anchor cable 30 and the sleeve 41. A plurality of clamping arms 43 are provided at the end of the locking tube 42. The clamping arms 43 are arranged at intervals along the circumference of the anchor cable 30. The clamping arms 43 are inclined from the outer circumference of the sleeve 41 to the center of the sleeve 41.
[0054] Specifically, the lock 40 is located on the side of the anchor seat 22 facing away from the fixing seat 21, and a plurality of clamping arms 43 are evenly arranged along the circumference of the anchor cable 30. When the anchor cable 30 is subjected to an external force, the lock 40 will move toward the anchor seat 22. In this process, the clamping arms 43 on the locking tube 42 will move toward the second anchor hole, and the plurality of clamping arms 43 will be clamped inwardly and tightly inserted into the second anchor hole, thereby enhancing the connection stability between the anchor cable 30 and the anchor seat 22, and improving the locking performance of the lock 40.
[0055] Furthermore, the spring 231 is located between the fixing seat 21 and the anchoring seat 22, and one end of the spring 231 abuts against the first anchor hole of the fixing seat 21, and the other end of the spring 231 abuts against the second anchor hole of the fixing seat 21. When the lock 40 moves toward the anchoring seat 22, the spring 231 can provide a certain restoring force to make the clamping arm 43 more tightly inserted into the second anchor hole, thereby improving the connection stability between the lock 40 and the anchoring seat 22 and preventing the anchor cable 30 from falling off or breaking.
[0056] In this embodiment, a clamping arm 43 may be provided on one end of the locking tube 42, and a threaded section may be provided on one end of the locking tube 42, and a fastener may be provided on the threaded section to fix the anchor cable 30. Optionally, the fastener may be provided as a nut.
[0057] In some embodiments, the length of the fixing seat 21 is set to 250mm to 350mm, the width of the fixing seat 21 is set to 250mm to 350mm, and the thickness of the fixing seat 21 is 15mm to 25mm. For example, the length of the fixing seat 21 can be set to 300mm, the width of the fixing seat 21 can be set to 300mm, and the thickness of the fixing seat 21 can be set to 20mm, so as to ensure that the fixing seat 21 has sufficient support area with the wall of the coal mine chamber to form a stable contact, and effectively transmit and disperse the force borne by the coal mine chamber support device 100. In addition, the thickness setting of the fixing seat 21 takes into account both the structural strength of the fixing seat 21 and the efficiency of material use, avoiding the waste of materials caused by excessive thickness and the problem of insufficient strength caused by excessive thinness.
[0058] In some embodiments, the diameter of the anchor cable 30 is 25 mm to 30 mm, and the length of the anchor cable 30 is 7000 mm to 7600 mm. For example, the diameter of the anchor cable 30 can be set to 25 mm, 28.6 mm, 30 mm, etc., which not only has sufficient strength to withstand tension, but also can form a good bond with the rock and soil to ensure the support effect.
[0059] Secondly, the length of the anchor cable 30 is 7000mm to 7600mm, for example, 7000mm, 7300mm, 7600mm, etc., which can avoid the problem that the anchor cable 30 is too short to penetrate the stable rock formation and the anchor cable 30 is too long, resulting in increased construction difficulty and cost, thereby achieving the best support effect.
[0060] like Figure 5 As shown, an embodiment of the utility model further provides a coal mine chamber support system, the coal mine chamber support system includes the above-mentioned coal mine chamber support device 100, the coal mine chamber support device 100 is arranged in plurality, and the plurality of coal mine chamber support devices 100 are arranged at intervals along the inner wall 200 of the chamber.
[0061] In this embodiment, a plurality of coal mine chamber support devices 100 are arranged at intervals along the inner wall 200 of the chamber, so as to effectively cover the entire inner wall 200 of the chamber, forming a complete support system. In addition, each coal mine chamber support device 100 has high structural strength and stability. By reasonably setting the spacing between two adjacent coal mine chamber support devices 100, the stress on the inner wall 200 of the chamber can be effectively borne and dispersed, and the waste of resources caused by too small spacing and the problem of poor support effect caused by too large spacing can be avoided.
[0062] Optionally, the coal mine chamber support device 100 can be set on the roof of the chamber, the spacing between two adjacent coal mine chamber support devices 100 can be set to 1600mm, and the number of coal mine chamber support devices 100 can be set to 3, thereby ensuring that each coal mine chamber support device 100 can fully play its supporting role while avoiding insufficient support due to excessive spacing or waste of resources due to too small spacing.
[0063] During the use of the coal mine chamber support device 100, a hole is drilled on the inner wall of the chamber to place the anchor cable 30 to ensure that the anchor cable 30 can penetrate into the stable rock layer, and an anchor cable anchoring agent is filled in the drill hole to enhance the bonding force between the anchor cable and the rock mass, thereby improving the support effect. Among them, the anchor cable anchoring agent can be selected from three Z2860 to ensure that the anchor cable is firmly supported at multiple locations, thereby further improving the overall performance of the support system.
[0064] Furthermore, the preload force of the anchor cable can be set to be no less than 350 kN, thereby effectively maintaining the optimal working state of the anchor cable in the rock mass, improving the reliability of the anchor cable, and preventing harmful deformation of the surrounding rock.
[0065] In addition, the above-mentioned coal mine chamber support device 100 can be applied to the coal mine chamber support system. Therefore, the beneficial effects that can be achieved by the coal mine chamber support system can refer to the corresponding beneficial effects of the coal mine chamber support device 100 provided above, which will not be repeated here.
[0066] In the description of the present invention, it should be understood that the terms "center", "length", "width", "thickness", "up", "down", "left", "right", "top", "bottom", "inside", "outside", "axial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0067] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present utility model, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0068] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0069] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0070] In the present invention, the terms "one embodiment", "some embodiments", etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art can combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples without contradiction.
[0071] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A coal mine chamber support device, It is characterized in that It includes a connecting beam, a plurality of anchoring assemblies and a plurality of anchor cables, wherein the plurality of anchoring assemblies are arranged at intervals on the connecting beam, the anchoring assembly includes a fixing seat and an anchoring seat which are arranged opposite to each other, the fixing seat and the anchoring seat are correspondingly arranged on both sides of the connecting beam, and the fixing seat is arranged in contact with the inner wall of the chamber; the anchor cables and the anchoring assemblies are arranged in a one-to-one correspondence, and the anchor cables are used to fix the anchoring assemblies and the connecting beam to the inner wall of the chamber.
2. The coal mine chamber support device according to claim 1, It is characterized in that The anchoring assembly further comprises an elastic member, two ends of which are correspondingly abutted against the fixing seat and the anchoring seat.
3. The coal mine chamber support device according to claim 2, It is characterized in that The elastic member comprises a spring and a plurality of elastic pads, the spring is sleeved on the anchor cable, and the plurality of elastic pads are correspondingly arranged on both sides of the connecting beam.
4. The coal mine chamber support device according to claim 1, It is characterized in that The connecting beam includes a first connecting rod and a second connecting rod, the first connecting rod and the second connecting rod are arranged side by side, a first clamping cavity and a second clamping cavity are formed between the fixing seat and the anchoring seat, the first connecting rod is arranged in the first clamping cavity, and the second connecting rod is correspondingly arranged in the second clamping cavity.
5. The coal mine chamber support device according to claim 4, It is characterized in that The connecting beam further includes a plurality of third connecting rods, two ends of the third connecting rods are correspondingly connected to the first connecting rod and the second connecting rod, and the plurality of third connecting rods are spaced apart along the length direction of the first connecting rod.
6. The coal mine chamber support device according to claim 4, It is characterized in that The first connecting rod and the second connecting rod are both configured to be cylindrical, and the diameters of the first connecting rod and the second connecting rod are configured to be 15 mm to 25 mm.
7. The coal mine chamber support device according to claim 1, It is characterized in that The fixing seat is provided with a first anchor hole, the anchoring seat is provided with a second anchor hole, the anchor cable has a locking end, the locking end passes through the first anchor hole and the second anchor hole in sequence, and a lock is provided on the locking end.
8. The coal mine chamber support device according to claim 7, It is characterized in that The lock comprises a sleeve and a locking tube, wherein the locking tube is arranged between the anchor cable and the sleeve, and a plurality of clamping arms are arranged at the end of the locking tube, wherein the clamping arms are arranged at intervals along the circumference of the anchor cable, and the clamping arms are arranged obliquely from the outer periphery of the sleeve toward the center of the sleeve.
9. The coal mine chamber support device according to claim 1, It is characterized in that The spacing between two adjacent anchoring assemblies ranges from 1500 mm to 2000 mm; And / or, the length of the fixing seat is set to 250 mm to 350 mm, the width of the fixing seat is set to 250 mm to 350 mm, and the thickness of the fixing seat is set to 15 mm to 25 mm; And / or, the diameter of the anchor cable is 25 mm to 30 mm, and the length of the anchor cable is 7000 mm to 7600 mm.
10. A coal mine chamber support system, It is characterized in that The coal mine chamber support system comprises the coal mine chamber support device according to any one of claims 1 to 9, wherein the coal mine chamber support device is provided in plurality, and the plurality of coal mine chamber support devices are arranged at intervals along the inner wall of the chamber.