Modularized prefabricated cable duct bank

Through the modular design and specific installation structure, the problem of inconvenient replacement and connection operations of cable ducts is solved, the convenient replacement of cable ducts and the convenient connection of prefabricated cable ducts are realized, and the operating space and replacement efficiency are improved.

CN221885946UActive Publication Date: 2024-10-22ZHEJIANG YISHI CONCRETE STRUCTURAL COMPONENTS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420414703.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2024-10-22
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

The existing cable ducts are fixedly connected to the concrete and cannot be separated and replaced, and the connection operation space of the prefabricated cable ducts is small and inconvenient.

Method used

Design modular prefabricated cable ducts, using installation structures and connection structures, including slidable installation tubes, plug-in slots, placement slots, fixing blocks and fixing bolts. The cable ducts can be replaced by turning the fixing bolts and using connecting rods. Connect the outside of the prefabricated cable duct with a threaded sleeve to expand the operating space.

Benefits of technology

It realizes the convenient replacement of cable ducts and the convenient connection of prefabricated cable ducts, improving the operating space and replacement efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221885946U_ABST
    Figure CN221885946U_ABST
Patent Text Reader

Abstract

The utility model provides a modularized prefabricated cable duct bank which comprises a prefabricated cable duct bank body and further comprises an installation structure, the installation structure is arranged in the side wall of the prefabricated cable duct bank body, and a cable duct bank pipeline and a communication duct bank pipeline are arranged in the installation structure. The connection of the first fixing bolts is always located on the outer sides of the prefabricated cable duct bank bodies, the operation space is large, operation is convenient, and the two prefabricated cable duct bank bodies can be conveniently connected, and the second fixing bolts are taken down from the first mounting pipe or the second mounting pipe by rotating the second fixing bolts, so that the prefabricated cable duct bank bodies can be conveniently connected. The fixing blocks are arranged in the containing grooves and the fixing grooves, so that the fixing blocks are separated from the containing grooves and the fixing grooves, the cable duct bank pipeline or the communication duct bank pipeline is not limited any more, the cable duct bank pipeline or the communication duct bank pipeline can be pulled to be taken out from the first installation pipe or the second installation pipe to be replaced, and the cable duct bank pipeline or the communication duct bank pipeline can be conveniently and well replaced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a modular prefabricated cable conduit. Background Art

[0002] Cable duct is a kind of cable duct that meets the requirements of substation cable access channels and overhead line underground, and provides a power channel for power supply supporting plots along the line.

[0003] Underground cable conduits are mainly cast-in-place, that is, a single-hole pipe is placed after the trench is excavated, and finally concrete is cast into a whole. However, the cast cable conduit is fixedly connected to the concrete and cannot be separated. When the internal cable conduit is damaged, it cannot be replaced, which is very inconvenient. In addition, when connecting two prefabricated cable conduits, the nut needs to be threaded onto the connecting bolt through the bolt connection port, and the operating space is small, which is not convenient to operate. Therefore, how to facilitate the replacement of cable conduits and make the connection operation of two prefabricated cable conduits more convenient are important issues that need to be solved in the design of modular prefabricated cable conduits. Utility Model Content

[0004] In order to solve the problem of facilitating the replacement of cable conduits and making the connection operation of two prefabricated cable conduits more convenient, the utility model provides a modular prefabricated cable conduit.

[0005] The utility model solves the above technical problems through the following technical solutions:

[0006] The utility model provides a modular prefabricated cable conduit, comprising a prefabricated cable conduit main body, and further comprising:

[0007] An installation structure, wherein the installation structure is arranged in the side wall of the prefabricated cable conduit body, and a cable conduit pipe and a communication conduit pipe are arranged in the installation structure;

[0008] A connection structure 1, wherein the connection structure 1 is arranged on the prefabricated cable arrangement pipe body;

[0009] The second connection structure is arranged on the connection structure, and the first connection structure and the connection structure connect the two prefabricated cable duct bodies together.

[0010] Preferably, a lifting nut is fixedly provided on the top side wall of the prefabricated cable drain pipe body, and a lifting ring is fixedly connected to the lifting nut.

[0011] Preferably, the mounting structure includes a mounting tube 1, a plug-in slot, a placement slot, a fixing block, a fixing bolt 2 and a mounting tube 2. The mounting tube 1 and the mounting tube 2 are fixedly connected to the side wall of the prefabricated cable drainage pipe body. The side walls of the mounting tube 1 and the mounting tube 2 are provided with plug-in slots and placement slots at equal distances. The fixing bolt 2 is rotatably connected to the side wall of the fixing block. The fixing bolt 2 is threadedly connected to the side wall of the placement slot. The fixing block and the placement slot cooperate with each other.

[0012] Preferably, the first installation tube is slidably connected to the cable drainage pipe, and the second installation tube is slidably connected to the communication drainage pipe.

[0013] In the present technical solution, the fixing bolt 2 is rotated to remove it from the mounting tube 1 or the mounting tube 2, so that the fixing block is disengaged from the placement groove and the fixing groove, and the cable drainage pipe or the communication drainage pipe is no longer restricted. The cable drainage pipe or the communication drainage pipe can be pulled out of the mounting tube 1 or the mounting tube 2 for replacement.

[0014] Preferably, connecting blocks are fixedly connected at equal distances on the outer side walls of the cable drainage pipe and the communication drainage pipe, and the connecting blocks and the plug-in slots cooperate with each other.

[0015] In the technical solution, the connection block is inserted into the insertion groove, which can restrict the cable drainage pipe and the communication drainage pipe to prevent the cable drainage pipe and the communication drainage pipe from rotating.

[0016] Preferably, fixing grooves are provided at equal distances on the side walls of the cable drainage pipe and the communication drainage pipe, and the fixing grooves and fixing blocks cooperate with each other.

[0017] In the technical solution, the fixing block is fixed into the placement groove and the fixing groove to restrict and fix the cable drainage pipe or the communication drainage pipe.

[0018] Preferably, the connection structure includes a fixing bolt, a fixing threaded sleeve and a connecting hole, the fixing threaded sleeve is fixedly connected to the side wall of the prefabricated cable duct body, the fixing bolt is threadedly connected to the fixing threaded sleeve, and the connecting hole is opened on the side wall of the prefabricated cable duct body.

[0019] Preferably, the connecting hole and the fixing threaded sleeve are perpendicular to each other and communicated with each other.

[0020] Preferably, the second connection structure comprises a connecting rod and a threaded groove, the connecting rod is slidably connected in the connecting hole, and two threaded grooves are provided on the side wall of the connecting rod.

[0021] In this technical solution, a connecting rod is inserted into a connecting hole of another prefabricated cable conduit body, the remaining threaded hole on the connecting rod is aligned with a fixed threaded sleeve on another prefabricated cable conduit body, a fixing bolt is threadedly connected in the fixed threaded sleeve and the threaded hole, and the two prefabricated cable conduit bodies are connected together through the connecting rod.

[0022] Preferably, the thread groove and the fixing bolt cooperate with each other.

[0023] On the basis of being in accordance with the common sense in the art, the above-mentioned preferred conditions can be arbitrarily combined to obtain the preferred embodiments of the present utility model.

[0024] The positive and progressive effects of the utility model are:

[0025] 1. Two prefabricated cable conduit bodies are connected together through a connecting rod. When connecting, the connection to the fixing bolt is always located on the outside of the prefabricated cable conduit body. The operating space is large and the operation is convenient, which makes it easier to connect the two prefabricated cable conduit bodies.

[0026] 2. Remove the fixing bolt 2 from the mounting tube 1 or the mounting tube 2 by rotating the fixing bolt 2, so that the fixing block is disengaged from the placement groove and the fixing groove, and the cable drainage pipe or the communication drainage pipe is no longer restricted. The cable drainage pipe or the communication drainage pipe can be pulled out from the mounting tube 1 or the mounting tube 2 for replacement. After replacement, fix the fixing block to the placement groove and the fixing groove to restrict and fix the cable drainage pipe or the communication drainage pipe, so as to facilitate better replacement of the cable drainage pipe or the communication drainage pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the utility model.

[0028] Figure 2 It is a schematic diagram of the overall internal structure of the utility model.

[0029] Figure 3 It is a schematic diagram of the overall side structure of the utility model.

[0030] Figure 4 For this utility model Figure 2 A local enlarged structural diagram

[0031] Description of Reference Numerals

[0032] 1. Prefabricated cable drainage pipe body; 2. Lifting nut; 3. Lifting ring; 4. Connection structure one; 401. Fixing bolt one; 402. Fixing threaded sleeve; 403. Connection hole; 5. Connection structure two; 501. Connecting rod; 502. Threaded groove; 6. Cable drainage pipe; 7. Communication drainage pipe; 8. Fixing groove; 9. Installation structure; 901. Installation pipe one; 902. Plug-in groove; 903. Placement groove; 904. Fixing block; 905. Fixing bolt two; 906. Installation pipe two; 10. Connection block. DETAILED DESCRIPTION

[0033] The present invention is further described below by way of embodiments, but the present invention is not limited to the scope of the embodiments.

[0034] like Figure 1-4 As shown, a modular prefabricated cable conduit includes a prefabricated cable conduit body 1, and also includes:

[0035] An installation structure 9, wherein the installation structure 9 is arranged in the side wall of the prefabricated cable drainage pipe body 1, and a cable drainage pipe 6 and a communication drainage pipe 7 are arranged in the installation structure 9;

[0036] A connecting structure 4, wherein the connecting structure 4 is arranged on the prefabricated cable arrangement pipe body 1;

[0037] The second connection structure 5 is arranged on the connection structure, and the first connection structure 4 and the connection structure connect the two prefabricated cable duct bodies 1 together.

[0038] A lifting nut 2 is fixedly provided on the top side wall of the prefabricated cable drain pipe body 1 , and a lifting ring 3 is fixedly connected to the lifting nut 2 .

[0039] The mounting structure 9 includes a mounting tube 901, a plug-in slot 902, a placement slot 903, a fixing block 904, a fixing bolt 905 and a mounting tube 906. The mounting tube 901 and the mounting tube 906 are fixedly connected to the side wall of the prefabricated cable drainage pipe body 1. The plug-in slot 902 and the placement slot 903 are equidistantly provided on the side walls of the mounting tube 901 and the mounting tube 906. The fixing bolt 905 is rotatably connected to the side wall of the fixing block 904. The fixing bolt 905 is threadedly connected to the side wall of the placement slot 903. The fixing block 904 and the placement slot 903 cooperate with each other.

[0040] The installation pipe 1 901 is slidably connected to the cable drainage pipe 6, and the installation pipe 2 906 is slidably connected to the communication drainage pipe 7.

[0041] like Figure 4As shown, turn the fixing bolt 2 905 and remove it from the mounting tube 1 901 or the mounting tube 2 906, so that the fixing block 904 is disengaged from the placement groove 903 and the fixing groove 8, and the cable drainage pipe 6 or the communication drainage pipe 7 is no longer restricted. The cable drainage pipe 6 or the communication drainage pipe 7 can be pulled out from the mounting tube 1 901 or the mounting tube 2 906 for replacement.

[0042] The outer walls of the cable conduit 6 and the communication conduit 7 are fixedly connected with connecting blocks 10 at equal distances, and the connecting blocks 10 and the plug-in slots 902 cooperate with each other.

[0043] like Figure 4 As shown, the connection block 10 is inserted into the insertion groove 902, which can restrict the cable drainage pipe 6 and the communication drainage pipe 7 to prevent the cable drainage pipe 6 and the communication drainage pipe 7 from rotating.

[0044] The side walls of the cable drainage pipe 6 and the communication drainage pipe 7 are provided with fixing grooves 8 at equal distances, and the fixing grooves 8 and the fixing blocks 904 cooperate with each other.

[0045] like Figure 4 As shown, the fixing block 904 is fixed into the placement groove 903 and the fixing groove 8 to restrict and fix the cable drainage pipe 6 or the communication drainage pipe 7.

[0046] The connection structure 4 includes a fixing bolt 401, a fixing threaded sleeve 402 and a connecting hole 403. The fixing threaded sleeve 402 is fixedly connected to the side wall of the prefabricated cable duct body 1. The internal thread of the fixing threaded sleeve 402 is connected to the fixing bolt. The connecting hole 403 is opened on the side wall of the prefabricated cable duct body 1.

[0047] The connecting hole 403 and the fixing threaded sleeve 402 are perpendicular to each other and communicated with each other.

[0048] The second connection structure 5 includes a connection rod 501 and a thread groove 502 . The connection rod 501 is slidably connected in the connection hole 403 . Two thread grooves 502 are formed on the side wall of the connection rod 501 .

[0049] like Figure 1 , 3 As shown, the connecting rod 501 is inserted into the connecting hole 403 of another prefabricated cable tube body 1, the remaining threaded hole on the connecting rod 501 is aligned with the fixed threaded sleeve 402 on the other prefabricated cable tube body 1, and the fixing bolt 401 is threadedly connected in the fixed threaded sleeve 402 and the threaded hole, and the two prefabricated cable tube bodies 1 are connected together through the connecting rod 501.

[0050] The thread groove 502 and the fixing bolt 401 cooperate with each other.

[0051] When the utility model is used, when two prefabricated cable tube main bodies 1 are butt-jointed, the connecting rod 501 is slidably connected in the connecting hole 403, the threaded hole on the connecting rod 501 is aligned with the fixed threaded sleeve 402, the fixing bolt 401 is threadedly connected in the fixed threaded sleeve 402 and the threaded hole, the connecting hole 403 on the other prefabricated cable tube main body 1 is butt-jointed with the connecting rod 501, the connecting rod 501 is inserted into the connecting hole 403 of the other prefabricated cable tube main body 1, the remaining threaded hole on the connecting rod 501 is aligned with the fixed threaded sleeve 402 on the other prefabricated cable tube main body 1, the fixing bolt 401 is threadedly connected in the fixed threaded sleeve 402 and the threaded hole, and the two prefabricated cable tube main bodies 1 are connected together through the connecting rod 501. When connecting, the connection of the fixing bolt 401 is always located on the outside of the prefabricated cable tube main body 1, the operation space is large, the operation is relatively convenient, and it is convenient to connect the two prefabricated cable tube main bodies 1.

[0052] When the cable drainage pipe 6 or the communication drainage pipe 7 is damaged, the fixing bolt 2 905 can be rotated to remove the fixing bolt 2 905 from the mounting pipe 1 901 or the mounting pipe 2 906, so that the fixing block 904 is disengaged from the placement groove 903 and the fixing groove 8, and the cable drainage pipe 6 or the communication drainage pipe 7 is no longer restricted. The cable drainage pipe 6 or the communication drainage pipe 7 can be pulled out from the mounting pipe 1 901 or the mounting pipe 2 906 for replacement. After replacement, the fixing block 904 is fixed to the placement groove 903 and the fixing groove 8 to restrict and fix the cable drainage pipe 6 or the communication drainage pipe 7, so as to facilitate better replacement of the cable drainage pipe 6 or the communication drainage pipe 7.

[0053] The utility model is not limited to the above-mentioned embodiments. Any changes in shape or structure are within the protection scope of the utility model. The protection scope of the utility model is defined by the attached claims. Those skilled in the art can make various changes or modifications to these embodiments without departing from the principle and essence of the utility model, but these changes and modifications are within the protection scope of the utility model.

Claims

1. A modular prefabricated cable duct, comprising a prefabricated cable duct body (1), characterized in that: Also includes: An installation structure (9), the installation structure (9) being arranged in a side wall of the prefabricated cable duct body (1), and the installation structure (9) being provided with a cable duct (6) and a communication duct (7); A connection structure one (4), wherein the connection structure one (4) is arranged on the prefabricated cable duct body (1); The second connection structure (5) is arranged on the connection structure, and the first connection structure (4) and the connection structure connect the two prefabricated cable duct bodies (1) together.

2. The modular prefabricated cable duct according to claim 1, characterized in that: A lifting nut (2) is fixedly arranged on the top side wall of the prefabricated cable drain pipe body (1), and a lifting ring (3) is fixedly connected to the lifting nut (2).

3. The modular prefabricated cable duct according to claim 1, characterized in that: The installation structure (9) comprises an installation tube (901), a plug-in slot (902), a placement slot (903), a fixing block (904), a fixing bolt (905) and an installation tube (906); the installation tube (901) and the installation tube (906) are fixedly connected to the side wall of the prefabricated cable duct body (1); the side walls of the installation tube (901) and the installation tube (906) are provided with plug-in slots (902) and placement slots (903) at equal distances; the fixing bolt (905) is rotatably connected to the side wall of the fixing block (904); the fixing bolt (905) is threadedly connected to the side wall of the placement slot (903); and the fixing block (904) and the placement slot (903) cooperate with each other.

4. The modular prefabricated cable duct according to claim 3, characterized in that: The first installation tube (901) is slidably connected to the cable drainage pipe (6), and the second installation tube (906) is slidably connected to the communication drainage pipe (7).

5. The modular prefabricated cable duct according to claim 4, characterized in that: The outer walls of the cable drainage pipe (6) and the communication drainage pipe (7) are fixedly connected with connection blocks (10) at equal distances, and the connection blocks (10) and the plug-in slots (902) cooperate with each other.

6. The modular prefabricated cable duct according to claim 5, characterized in that: Fixing grooves (8) are provided at equal distances on the side walls of the cable drainage pipe (6) and the communication drainage pipe (7), and the fixing grooves (8) and the fixing blocks (904) cooperate with each other.

7. The modular prefabricated cable duct according to claim 1, characterized in that: The connection structure (4) comprises a fixing bolt (401), a fixing threaded sleeve (402) and a connection hole (403); the fixing threaded sleeve (402) is fixedly connected to the side wall of the prefabricated cable duct body (1); the fixing bolt is connected to the internal thread of the fixing threaded sleeve (402); and the connection hole (403) is provided on the side wall of the prefabricated cable duct body (1).

8. The modular prefabricated cable duct according to claim 7, characterized in that: The connecting hole (403) and the fixing threaded sleeve (402) are perpendicular to each other and communicate with each other.

9. The modular prefabricated cable duct according to claim 1, characterized in that: The second connection structure (5) comprises a connection rod (501) and a thread groove (502). The connection rod (501) is slidably connected in the connection hole (403). Two thread grooves (502) are provided on the side wall of the connection rod (501).

10. The modular prefabricated cable duct according to claim 9, characterized in that: The thread groove (502) and the fixing bolt one (401) cooperate with each other.