Soil nail and anchor rod composite supporting structure

By introducing a composite support structure of soil nails and anchor rods into the double-row pile support structure, using connecting beams and soil nails to strengthen the relationship between piles, and anchoring prestressed anchor rods to the rock mass, deep foundation pits and poor foundations are solved. The problem of insufficient stability of the supporting structure and inconvenient construction under geological conditions has been achieved to achieve higher overall stiffness and ease of construction.

CN221895787UActive Publication Date: 2024-10-25HUAINAN ZHONGTONG CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323006419.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-07
Publication Date
2024-10-25
Estimated Expiration
2033-11-07

AI Technical Summary

Technical Problem

When the excavation depth of the foundation pit is large or the geological conditions are poor, the double-row pile foundation pit support structure cannot meet the design requirements and lacks space, resulting in insufficient stability of the support structure and inconvenient construction.

Method used

A composite support structure of soil nails and anchor rods is used, and the stability and overall stiffness of the support structure are enhanced by setting up a fixing effect between connecting beams and soil nail-reinforced piles, and using prestressed anchor rods to anchor the rock mass.

Benefits of technology

It improves the stability and overall stiffness of the supporting structure, simplifies the construction process, and enhances the supporting effect. It is suitable for engineering applications in deep foundation pits and poor geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221895787U_ABST
    Figure CN221895787U_ABST
Patent Text Reader

Abstract

The utility model discloses a soil nail and anchor rod composite supporting structure, and relates to the technical field of supporting devices, the soil nail and anchor rod composite supporting structure comprises a first row of piles, a second row of piles, a first ring beam and a second ring beam, the first ring beam is connected with the first row of piles, the second ring beam is connected with the second row of piles, and a first connecting beam is connected between the first ring beam and the second ring beam; a first waist beam, a second waist beam and a third waist beam are respectively arranged on the first row of piles, soil nails are connected between the second ring beam and the first waist beam, a first anchor rod is fixedly mounted on the second waist beam, and one end of the first anchor rod is anchored in a stable rock mass within a sliding surface. By arranging the first anchor rods and the second anchor rods, the first row of piles and the second row of piles can be fixed to stable rock masses at different positions, so that the advantages of the anchor rods and soil nails can be played, the stable effect of supporting can be further enhanced, construction is easy and convenient in engineering, and the self-stability, the overall rigidity and the supporting effect are enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of support devices, and in particular to a composite support structure of soil nails and anchor rods. Background Art

[0002] Composite support structure refers to a composite support system formed by soil nails, anchor rods and reinforced cement soil pile walls. It can replace support systems such as excavation and bored piles, and also saves the surface layer of sprayed anchor support. When vertical cement soil piles have quality problems such as bifurcation, remedial measures such as manual plastering and mesh sprayed concrete can be taken. The composite support structure is an assembly of a single-row pile support structure and a double-row pile support structure. The double-row pile support structure is a form of enclosure structure that has emerged in recent years and has been increasingly widely used in engineering. It is a spatial portal structure system formed by two rows of parallel reinforced concrete piles and connecting beams on the top of the piles.

[0003] Since the ordinary double-row pile support structure has the advantages of large overall rigidity, simple and fast construction, it is only suitable for use when the excavation depth of the foundation pit is not large. When the excavation depth of the foundation pit is large or the geological conditions are poor, if the ordinary double-row pile foundation pit support structure cannot meet the design requirements and there is not enough space for construction, how to maintain the stability of the support structure and facilitate construction is the biggest problem encountered by the ordinary double-row pile support structure. Utility Model Content

[0004] The purpose of the utility model is to solve or at least alleviate the problem existing in the prior art that, when a general double-row pile foundation pit support structure is required and cannot meet the design requirements and there is not enough space for construction, how to maintain the stability of the support structure while facilitating construction is the biggest problem encountered by the general double-row pile support structure.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a composite support structure of soil nails and anchor rods, comprising a first row of piles, a second row of piles, a first ring beam and a second ring beam, the first ring beam is connected to the first row of piles, the second ring beam is connected to the second row of piles, a first connecting beam is connected between the first ring beam and the second ring beam, a first waist beam, a second waist beam and a third waist beam are respectively arranged on the first row of piles, soil nails are connected between the second ring beam and the first waist beam, a first anchor rod is fixedly installed on the second waist beam, and one end of the first anchor rod is anchored in a stable rock mass within the sliding surface.

[0006] By adopting the above technical solution, the fixing effect between the first row of piles and the second row of piles can be strengthened by providing the first connecting beam and the second connecting beam, and the fixing effect between the first row of piles and the second ring beam can also be strengthened by providing soil nails.

[0007] Optionally, a second anchor rod is fixedly mounted on the third waist beam, and one end of the second anchor rod is anchored in the rock mass.

[0008] By adopting the above technical solution, the second anchor rod is provided so as to achieve the function of fixed installation.

[0009] Optionally, the first anchor rod and the second anchor rod are both prestressed anchor rods.

[0010] By adopting the above technical solution, by setting the first anchor rod and the second anchor rod as prestressed anchor rods, a certain pre-compression stress can be applied to the surrounding rock through the anchoring force generated by the anchor head, thereby actively reinforcing the surrounding rock.

[0011] Optionally, a second connecting beam is connected between the first row of piles and the second row of piles.

[0012] By adopting the above technical solution, the second connecting beam is provided to assist in installation and fixing.

[0013] Optionally, the first connecting beam and the second connecting beam are both reinforced concrete beams.

[0014] By adopting the above technical solution, the first connecting beam and the second connecting beam are both reinforced concrete beams, so that they are more durable.

[0015] Optionally, the anchoring end of the soil nail is fixed to the top end of the second ring beam.

[0016] By adopting the above technical solution, soil nails can be set to reinforce the installation.

[0017] Optionally, the first row of piles and the second row of piles are cast-in-place concrete piles.

[0018] By adopting the above technical solution, the first row of piles and the second row of piles are set as concrete cast-in-place piles. The concrete cast-in-place piles can bear the load of the building and transfer the load to the foundation.

[0019] In summary, the beneficial effects of this application are as follows:

[0020] 1. The new type of the present application adopts the cooperation of the first anchor rod, etc., and by setting the first anchor rod and the second anchor rod, the first row of piles and the second row of piles can be fixed to the stable rock mass at different positions, so as to give play to the advantages of the anchor rod and the soil nail, and further enhance the stabilizing effect of the support, simplify the construction in the project, and enhance its own stability, overall rigidity and support effect.

[0021] 2. The new type of the present application adopts the cooperation of soil nails, etc., and by setting the first connecting beam and the second connecting beam, the fixing effect between the first row of piles and the second row of piles can be strengthened, and by setting the soil nails, the fixing effect between the first row of piles and the second ring beam can also be strengthened. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the entire application;

[0023] Figure 2 It is a schematic diagram of the second connecting beam of the present application;

[0024] Figure 3 This is a schematic diagram of the first anchor rod of this application.

[0025] Explanation of the accompanying drawings: In the figure: 1, first row of piles; 2, second row of piles; 3, first ring beam; 4, second ring beam; 5, first connecting beam; 6, first waist beam; 7, second waist beam; 8, third waist beam; 9, soil nails; 10, first anchor rod; 11, second anchor rod; 12, second connecting beam. DETAILED DESCRIPTION

[0026] The following is combined with Figure 1-3 This application is described in further detail.

[0027] See also Figure 1-3 A composite support structure of soil nails and anchor rods, comprising a first row of piles 1, a second row of piles 2, a first ring beam 3 and a second ring beam 4, the first row of piles 1 and the second row of piles 2 are both located on one side of a foundation pit, and the foundation pit can be supported by the first row of piles 1 and the second row of piles 2, the first ring beam 3 is connected to the first row of piles 1, and the first ring beam 3 and the second ring beam 4 are provided to enhance the spatial rigidity and integrity of the house, prevent wall cracking caused by uneven foundation settlement or vibration load, and enhance the integrity and integrity of the house, resist wall cracking caused by uneven foundation settlement or vibration load, the second ring beam 4 is connected to the second row of piles 2, and the first ring beam 3 and the second ring beam 4 are connected. The first connecting beam 5, the first ring beam 3 and the second ring beam 4 are respectively located at the place where the first row of piles 1 and the second row of piles 2 are connected to the first connecting beam 5, and the first connecting beam 5 is located above the first ring beam 3 and the second ring beam 4, and there are two first connecting beams 5, which are arranged in parallel. The first row of piles 1 are respectively provided with a first waist beam 6, a second waist beam 7 and a third waist beam 8, and soil nails 9 are connected between the second ring beam 4 and the first waist beam 6. The placement angle of the soil nails 9 is 30 degrees. By setting the soil nails 9, the role of reinforcement and stability can be achieved. The second waist beam 7 is fixedly installed with a first anchor rod 10, and the angle of the first anchor rod 10 is 15 degrees. One end of the first anchor rod 10 is anchored in the stable rock mass within the sliding surface.

[0028] When in use, the first connecting beam 5 is provided so as to strengthen the fixing effect between the first row of piles 1 and the second row of piles 2 , and the soil nails 9 are provided so as to strengthen the fixing effect between the first row of piles 1 and the second ring beam 4 .

[0029] Reference Figure 1 A second anchor rod 11 is fixedly mounted on the third waist beam 8, and one end of the second anchor rod 11 is anchored in the rock mass. The second anchor rod 11 can be provided to achieve a fixed installation effect.

[0030] Reference Figure 1 and Figure 3 The first anchor rod 10 and the second anchor rod 11 are both prestressed anchor rods. By setting the first anchor rod 10 and the second anchor rod 11 as prestressed anchor rods, a certain pre-compression stress can be applied to the surrounding rock through the anchoring force generated by the anchor head, so as to actively reinforce the surrounding rock.

[0031] Reference Figure 1 and Figure 2 A second connecting beam 12 is connected between the first row of piles 1 and the second row of piles 2. The second connecting beams 12 are two and arranged in parallel, and the second connecting beams 12 can be arranged to assist in installation and fixing.

[0032] Reference Figure 1 and Figure 2 The first connecting beam 5 and the second connecting beam 12 are both reinforced concrete beams. By setting the first connecting beam 5 and the second connecting beam 12 to be both reinforced concrete beams, they are more durable.

[0033] Reference Figure 1 First, corresponding through holes are preset on the first connecting beam 5 and the second ring beam 4. At this time, the anchoring end of the soil nail 9 can be fixed in the through hole on the top of the second ring beam 4, and the other end of the soil nail 9 is fixedly connected to the first waist beam 6. The soil nail 9 can be provided to reinforce the installation.

[0034] Reference Figure 1 The first row of piles 1 and the second row of piles 2 are concrete cast-in-place piles. By setting the first row of piles 1 and the second row of piles 2 as concrete cast-in-place piles, the concrete cast-in-place piles can bear the load of the building and transfer the load to the foundation.

[0035] The implementation principle of the present application is as follows: when in use, first, corresponding through holes are preset on the first connecting beam 5 and the second ring beam 4. At this time, the anchoring end of the soil nail 9 can be fixed in the through hole on the top of the second ring beam 4, and the other end of the soil nail 9 is fixedly connected to the first waist beam 6. By setting the first connecting beam 5 and the second connecting beam 12, the fixing effect between the first row of piles 1 and the second row of piles 2 can be reinforced. By setting the soil nail 9, the fixing effect between the first row of piles 1 and the second ring beam 4 can also be reinforced. By using the first anchor rod 10 and the second anchor rod 11, it can be installed and fixed to the stable rock mass at different positions, playing a role of stable installation, thereby also giving play to the advantages of anchor rods and soil nails, which is simple to construct in the project and enhances the self-stability, overall stiffness and support effect of the support structure.

[0036] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A composite support structure of soil nails and anchor rods, comprising a first row of piles (1), a second row of piles (2), a first ring beam (3) and a second ring beam (4), characterized in that: The first ring beam (3) is connected to the first row of piles (1), the second ring beam (4) is connected to the second row of piles (2), a first connecting beam (5) is connected between the first ring beam (3) and the second ring beam (4), a first waist beam (6), a second waist beam (7) and a third waist beam (8) are respectively arranged on the first row of piles (1), soil nails (9) are connected between the second ring beam (4) and the first waist beam (6), a first anchor rod (10) is fixedly mounted on the second waist beam (7), and one end of the first anchor rod (10) is anchored in a stable rock mass within the sliding surface.

2. A composite support structure of soil nails and anchor rods according to claim 1, characterized in that: A second anchor rod (11) is fixedly mounted on the third waist beam (8), and one end of the second anchor rod (11) is anchored in the rock mass.

3. The composite support structure of soil nails and anchor rods according to claim 1 is characterized in that: The first anchor rod (10) and the second anchor rod (11) are both prestressed anchor rods.

4. The composite support structure of soil nails and anchor rods according to claim 1 is characterized in that: A second connecting beam (12) is connected between the first row of piles (1) and the second row of piles (2).

5. The composite support structure of soil nails and anchor rods according to claim 4 is characterized in that: The first connecting beam (5) and the second connecting beam (12) are both reinforced concrete beams.

6. The composite support structure of soil nails and anchor rods according to claim 1 is characterized in that: The anchoring end of the soil nail (9) is fixed to the top end of the second ring beam (4).