Tower crane verticality detection device

By designing the connecting components and reset components, and using the locking rod to cooperate with the connecting groove, the tower crane verticality detection device is quickly installed and disassembled, and the problem of long disassembly and assembly time caused by bolt installation in the existing technology is solved. Improved work efficiency.

CN221897482UActive Publication Date: 2024-10-25CHONGQING JINGYUN TESTING TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420619660.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-28
Publication Date
2024-10-25
Estimated Expiration
2034-03-28

AI Technical Summary

Technical Problem

When the existing tower crane verticality detection device needs to adjust the position of the detection device when the tower crane continues to increase in height, the detection device is installed on the tower body through bolts, which results in a long disassembly and assembly time and reduces work efficiency.

Method used

A tower crane verticality detection device is designed, which uses connecting components including connecting plates, movable plates, connecting rods, connecting blocks, locking rods and reset components. The locking rod cooperates with the connecting groove and uses springs and power components to achieve Quick connection and disassembly, reducing disassembly and assembly time.

Benefits of technology

The rapid installation and disassembly of the tower crane verticality detection device is realized, which improves work efficiency and reduces time waste caused by bolt installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221897482U_ABST
    Figure CN221897482U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of detection devices, in particular to a verticality detection device for a tower crane, which comprises a connecting plate, a movable plate, a connecting rod, a connecting block, a locking rod and a reset component. The connecting block makes contact with the locking rod so as to drive the locking rod to move on the movable plate, the connecting rod continues to be moved so that when the connecting block does not make contact with the locking rod, the locking rod is driven to reset through the reset component, the locking rod is inserted into the connecting groove while resetting, and the locking rod is inserted into the locking groove. The problems that in the using process of an existing device, when it is found that the position of a detection device needs to be adjusted along with continuous height increasing of a tower crane, due to the fact that the detection device is installed on a tower body through bolts, a large amount of time needs to be spent on disassembly and assembly and reinstallation, and the detection device is inconvenient to adjust are solved. And the working efficiency is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of detection devices, in particular to a verticality detection device for a tower crane. Background Art

[0002] Tower crane is also called tower crane. It is a rotating crane with the boom installed on the top of a tall tower. It has a large working space and is mainly used for vertical and horizontal transportation of materials and installation of building components in house construction. It consists of three parts: metal structure, working mechanism and electrical system. The metal structure includes tower body, boom and base, etc. The working mechanism has four parts: lifting, luffing, rotation and travel. The electrical system includes motors, controllers, distribution cabinets, connecting lines, signals and lighting devices, etc.

[0003] The existing Chinese patent number CN212747823U discloses a tower body verticality detection device for a tower crane, including a tower body, and the outer wall of the tower body support column is provided with a detection device, the detection device includes a fixing seat, the rear side of the fixing seat is movably connected with a U-shaped bolt, the front side of the fixing seat is provided with a rectangular fixing plate, the front side of the rectangular fixing plate is provided with symmetrically distributed fixing convex plates, a rectangular connecting block is movably connected between the two fixing convex plates, the front end of the rectangular connecting block is provided with a circular solid block, the top of the circular solid block is provided with a plurality of equally spaced annular patterns, and the bottom of the circular solid block is provided with a fixing sleeve. The tower body verticality detection device of the tower crane can fix the detection device to the support column of the tower body through the U-shaped bolt, the first fastening nut and the fixing seat, and the verticality of the tower body can be detected in real time through the cooperation of the laser emitter and the annular pattern.

[0004] Using the above method, it was found during use that as the tower crane continued to increase in height, when the position of the detection device needed to be adjusted, since the detection device was installed on the tower body by bolts, it took a lot of time to disassemble and reinstall it, thereby reducing work efficiency. Utility Model Content

[0005] The utility model aims to provide a tower crane verticality detection device, which solves the problem that the existing device needs to spend a lot of time to disassemble and reinstall the detection device when the position of the detection device needs to be adjusted as the tower crane continues to increase in height, because the detection device is installed on the tower body by bolts, thereby reducing the work efficiency.

[0006] To achieve the above-mentioned purpose, the utility model provides a tower crane verticality detection device, comprising a tower body, a fixing plate and a detection mechanism, wherein the detection mechanism is mounted on the fixing plate.

[0007] Wherein, it also includes a connecting component, which includes a connecting plate, a movable plate, a connecting rod, a connecting block, a locking rod and a reset component, the connecting plate is located on the outside of the tower body, the connecting rod is fixedly mounted on the connecting plate, the connecting block is fixedly mounted on the side of the connecting rod away from the connecting plate, the movable plate is connected to the connecting plate through the connecting block, the locking rod is slidably mounted on the connecting block, the connecting block has a connecting groove, the locking rod cooperates with the connecting groove, the movable plate has a locking groove, the locking groove cooperates with the connecting block, and the reset component is arranged on the movable plate.

[0008] Wherein, the reset component includes a disc, a spring and a power component, the disc is slidably mounted on the movable plate, two ends of the spring are respectively connected to the disc and the movable plate, and the power component is arranged on the locking rod.

[0009] Wherein, the power component includes a power plate, a handle and a protective element, the power plate is fixedly mounted on the side of the locking rod away from the movable plate, the handle is fixedly mounted on the power plate, and the protective element is arranged on the connecting plate.

[0010] Wherein, the protective element comprises an insulating layer and a protective pad, the insulating layer is fixedly mounted on the connecting plate, and the protective pad is fixedly mounted on a side of the insulating layer away from the connecting plate.

[0011] Wherein, the connecting component also includes an auxiliary component, and the auxiliary component includes magnet 1 and magnet 2. Magnet 1 is fixedly mounted on the movable plate, and magnet 2 is fixedly mounted on the connecting plate.

[0012] The utility model discloses a tower crane verticality detection device. When it needs to be installed, the connecting block is slowly placed into the locking groove. The connecting block contacts the locking rod and drives the locking rod to move in the movable plate. The locking rod moves and drives the disc to move, and drives the disc to move and compress the spring. After the connecting block is no longer in contact with the locking, the spring is deformed and resets, driving the disc to reset and the locking rod to reset, thereby driving the locking rod to insert into the connecting groove, so that the connecting plate and the movable plate are connected on one side. When it needs to be disassembled, the power plate is driven to move by the handle, and the power plate moves and drives the locking rod to move, so that after the locking rod is moved out of the connecting groove, the connecting block is removed. The utility model solves the problem found in the existing device during use that when the position of the detection device needs to be adjusted as the tower crane continues to increase in height, since the detection device is installed on the tower body by bolts, it takes a lot of time to disassemble and reinstall, thereby reducing the work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0014] Figure 1 It is a structural schematic diagram of a tower crane verticality detection device according to the first embodiment of the utility model.

[0015] Figure 2 It is a structural schematic diagram of a connecting assembly of a tower crane verticality detection device according to the first embodiment of the utility model.

[0016] Figure 3 It is a structural schematic diagram of a reset component of a tower crane verticality detection device according to the first embodiment of the utility model.

[0017] Figure 4 It is a structural schematic diagram of a tower crane verticality detection device according to a second embodiment of the utility model.

[0018] In the figure: 101-tower body, 102-fixed plate, 103-detection mechanism, 104-connecting plate, 105-movable plate, 106-connecting rod, 107-connecting block, 108-connecting groove, 109-locking rod, 110-locking groove, 111-disc, 112-through, 113-power plate, 114-handle, 115-insulating layer, 116-protective pad, 201-magnet one, 202-magnet two. DETAILED DESCRIPTION

[0019] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0020] The first embodiment of the present application is:

[0021] See also Figure 1-3 , Figure 1 It is a structural schematic diagram of a tower crane verticality detection device according to the first embodiment of the utility model. Figure 2 It is a structural schematic diagram of the connection assembly of the tower crane verticality detection device of the first embodiment of the utility model, Figure 3 It is a structural schematic diagram of a reset component of a tower crane verticality detection device according to the first embodiment of the utility model.

[0022] The present embodiment provides a tower crane verticality detection device, including a tower body 101, a fixed plate 102, a detection mechanism 103 and a connecting assembly, wherein the connecting assembly includes a connecting plate 104, a movable plate 105, a connecting rod 106, a connecting block 107, a locking rod 109 and a reset member, wherein the reset member includes a disc 111, a spring 112 and a power component, wherein the power component includes a power plate 113, a handle 114 and a protective element, wherein the protective element includes an insulating layer 115 and a protective pad 116. The above-mentioned scheme solves the problem that the existing device is found in use that when the position of the detection device needs to be adjusted as the tower crane continues to increase in height, since the detection device is installed on the tower body 101 by bolts, it takes a lot of time to disassemble and reinstall, thereby reducing work efficiency. It can be understood that the above-mentioned scheme can be used in the prospect of the tower crane verticality detection device, and can also be used to solve the adsorption problem.

[0023] In this embodiment, the detection mechanism 103 is installed on the fixed plate 102 , and the locking rod 109 cooperates with the locking groove 110 , so that the connecting plate 104 and the movable plate 105 are quickly connected to the tower body 101 .

[0024] Wherein, the connecting plate 104 is located at the outside of the tower body 101, the connecting rod 106 is fixedly installed on the connecting plate 104, the connecting block 107 is fixedly installed on the side of the connecting rod 106 away from the connecting plate 104, the movable plate 105 is connected to the connecting plate 104 through the connecting block 107, the locking rod 109 is slidably installed on the connecting block 107, the connecting block 107 has a connecting groove 108, the locking rod 109 cooperates with the connecting groove 108, the movable plate 105 has a locking groove 110, the locking groove 110 cooperates with the connecting block 107, the reset member is arranged on the movable plate 105, the movable plate 105 is fixedly installed on the side of the fixed plate 102 away from the detection mechanism 103, the connecting rod 106, the connecting block 107 and the locking rod 109 are made of metal material The locking block is triangular in shape. When in use, the connecting rod 106 and the connecting block 107 are inserted into the locking groove 110, the connecting block 107 contacts the locking rod 109, thereby driving the locking rod 109 to move on the movable plate 105, and continuing to move the connecting rod 106 so that the connecting block 107 is no longer in contact with the locking rod 109, the locking rod 109 is reset by the resetting member, and the locking rod 109 is inserted into the connecting groove 108 while being reset, so that the connecting plate 104 and the movable plate 105 are connected on one side, which solves the problem found in the existing device during use that when the position of the detection device needs to be adjusted as the tower crane continues to increase in height, since the detection device is installed on the tower body 101 by bolts, it takes a lot of time to disassemble and reinstall, thereby reducing work efficiency.

[0025] Secondly, the disc 111 is slidably mounted on the movable plate 105, and both ends of the spring 112 are respectively connected to the disc 111 and the movable plate 105, and the power component is arranged on the locking rod 109. The movable plate 105 has a reset groove matching the disc 111 and the through-hole, and the reset groove is connected to the locking groove 110. The movement of the locking rod 109 drives the disc 111 to move, and the movement of the disc 111 compresses the spring 112. When the connecting block 107 is not in contact with the locking rod 109, the spring 112 resets and drives the disc 111 to reset while driving the locking rod 109 to reset, so that the locking rod 109 is inserted into the connecting groove 108.

[0026] Again, the power plate 113 is fixedly mounted on the side of the locking rod 109 away from the movable plate 105, the handle 114 is fixedly mounted on the power plate 113, and the protective element is arranged on the connecting plate 104. The power plate 113 is driven to move by the handle 114, and the movement of the power plate 113 drives the locking rod 109 to move, thereby making the locking rod 109 move out of the connecting groove 108.

[0027] At the same time, the insulating layer 115 is fixedly installed on the connecting plate 104, and the protective pad 116 is fixedly installed on the side of the insulating layer 115 away from the connecting plate 104. The insulating layer 115 is used to separate the tower body 101 and the detection mechanism 103, and the protective pad 116 is used to increase the friction between the connecting plate 104 and the tower body 101.

[0028] When the tower crane verticality detection device described in this embodiment is used for installation, the connecting block 107 is slowly placed into the locking groove 110, and the connecting block 107 contacts the locking rod 109 while driving the locking rod 109 to move in the movable plate 105. The movement of the locking rod 109 drives the disc 111 to move, and drives the disc 111 to move and compress the spring 112 until the connecting block 107 is no longer in contact with the locking. The spring 112 is deformed and resets, driving the disc 111 to reset and the locking rod 109 to reset, thereby driving the locking rod 109 to be inserted into the movable plate 105. The connecting plate 104 and the movable plate 105 are connected to each other on one side by the connecting groove 108. When disassembly is required, the power plate 113 is moved by the handle 114, and the movement of the power plate 113 drives the locking rod 109 to move, so that after the locking rod 109 is removed from the connecting groove 108, the connecting block 107 is removed. This solves the problem found in the existing device during use that when the position of the detection device needs to be adjusted as the tower crane continues to increase in height, since the detection device is installed on the tower body 101 by bolts, it takes a lot of time to disassemble and reinstall, thereby reducing work efficiency.

[0029] The second embodiment of the present application is:

[0030] See also Figure 4 , Figure 4 It is a structural schematic diagram of a tower crane verticality detection device according to a second embodiment of the utility model.

[0031] On the basis of the first embodiment, the connection assembly of this embodiment further includes an auxiliary component, and the auxiliary component includes a magnet 1 201 and a magnet 2 202 .

[0032] Among them, the magnet 1 201 is fixedly installed on the movable plate 105, and the magnet 2 202 is fixedly installed on the connecting plate 104. The connecting plate 104 and the movable plate 105 have magnet grooves matching the magnet 1 201 and the magnet 2 202. The magnet 1 201 and the magnet 2 202 are magnetically connected. Through the magnetic connection between the magnet 1 201 and the magnet 2 202, the connection stability between the connecting plate 104 and the movable plate 105 is improved.

[0033] What is disclosed above is only one or more preferred embodiments of the present application, and cannot be used to limit the scope of rights of the present application. Ordinary technicians in this field can understand that all or part of the processes of implementing the above embodiments and equivalent changes made according to the claims of the present application are still within the scope covered by the present application.

Claims

1. A tower crane verticality detection device, comprising a tower body, a fixing plate and a detection mechanism, wherein the detection mechanism is mounted on the fixing plate, and is characterized in that: Also included are connection components; The connecting assembly includes a connecting plate, a movable plate, a connecting rod, a connecting block, a locking rod and a reset member, the connecting plate is located on the outside of the tower body, the connecting rod is fixedly mounted on the connecting plate, the connecting block is fixedly mounted on the side of the connecting rod away from the connecting plate, the movable plate is connected to the connecting plate through the connecting block, the locking rod is slidably mounted on the connecting block, the connecting block has a connecting groove, the locking rod cooperates with the connecting groove, the movable plate has a locking groove, the locking groove cooperates with the connecting block, and the reset member is arranged on the movable plate.

2. The tower crane verticality detection device according to claim 1, characterized in that: The reset component comprises a disc, a spring and a power component. The disc is slidably mounted on the movable plate. Two ends of the spring are respectively connected to the disc and the movable plate. The power component is arranged on the locking rod.

3. The tower crane verticality detection device according to claim 2, characterized in that: The power component includes a power plate, a handle and a protective element. The power plate is fixedly mounted on the side of the locking rod away from the movable plate, the handle is fixedly mounted on the power plate, and the protective element is arranged on the connecting plate.

4. The tower crane verticality detection device according to claim 3, characterized in that: The protective element comprises an insulating layer and a protective pad. The insulating layer is fixedly mounted on the connecting plate, and the protective pad is fixedly mounted on a side of the insulating layer away from the connecting plate.

5. The tower crane verticality detection device according to claim 4, characterized in that: The connecting assembly also includes an auxiliary component, which includes magnet one and magnet two. The magnet one is fixedly mounted on the movable plate, and the magnet two is fixedly mounted on the connecting plate. The magnet one and the magnet two are magnetically connected.