Pipe gallery ACU control unit

By integrating intrusion alarms, security switches, UPS power supplies and other equipment in the pipe gallery control cabinet, the problem of insufficient space and equipment communication and power supply is solved, and the continuous operation and safety protection of the equipment are achieved.

CN221901180UActive Publication Date: 2024-10-25WUHAN JUPITER AUTOMATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323415669.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-13
Publication Date
2024-10-25
Estimated Expiration
2033-12-13

AI Technical Summary

Technical Problem

The existing pipe gallery control cabinet has a small space and cannot be installed with necessary equipment such as intrusion alarm host, security switch, UPS power supply, etc. As a result, the equipment cannot communicate and supply power in a timely manner, is susceptible to theft, and cannot work during a power outage or short circuit.

Method used

Design an ACU control unit for a pipe gallery, including an intrusion alarm, a security switch, a UPS power supply, an intelligent gateway, a temperature controller and an emergency phone host. It is separated and arranged by a glass plate, and a wireless AP switch and battery are set up in the control cabinet to ensure Continuous operation of equipment and communication processing.

Benefits of technology

It realizes the integration of multiple devices in a small space, ensures continuous communication and power supply for the equipment in the pipe gallery, prevents theft, and protects the equipment through temperature and humidity control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221901180U_ABST
    Figure CN221901180U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipe gallery ACU control unit, which is characterized in that a control cabinet (21) is internally divided into an upper layer and a lower layer, the upper layer and the lower layer of the control cabinet (21) are separated by a glass plate, an intrusion alarm host (1) is placed on the glass plate, a security switch (2), an optical fiber distribution box (17), a UPS power supply (3) and a battery (18) are sequentially stacked below the glass plate from top to bottom, and the upper layer and the lower layer of the control cabinet (21) are separated by the glass plate. An intelligent gateway (4) and a temperature controller (5) are installed in the control cabinet (21), a wireless AP switch (6) and an emergency telephone host (7) are installed on the two sides of a cabinet body of the control cabinet (21), the defect that in the prior art, two control cabinets which are arranged side by side are difficult to place in an existing space is overcome, the temperature and humidity in the cabinet can be accurately controlled, and the temperature and humidity in the cabinet can be accurately controlled. And the influence on the work of other components due to over-high humidity or over-high temperature in the cabinet is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of control cabinets, and more specifically to a pipe gallery ACU control unit. Background Art

[0002] The available area of ​​the existing project is very small, and it is difficult to place two control cabinets arranged side by side in the existing space. However, the required functions require two control cabinets to operate. For example, components such as intrusion alarm host, security switch, fiber optic distribution box, UPS power supply, emergency telephone host, etc. can no longer be placed in one existing control cabinet.

[0003] When a short circuit or power outage occurs in an existing control cabinet, the control cabinet and the equipment inside the control cabinet cannot work. Since the control cabinet itself cannot be powered, the control equipment related to the control cabinet cannot work either.

[0004] In the control cabinets related to the pipe gallery, there is generally no wireless AP switch.

[0005] External devices cannot communicate with devices in the control cabinet in a timely manner, so related signals of other communication devices cannot be processed in a timely manner.

[0006] In existing control cabinets related to pipe corridors, intrusion alarm hosts are usually not installed. Once an outsider opens the control cabinet at will, the staff cannot detect it in the first time, causing the control cabinet to be stolen and causing huge property losses.

[0007] The existing control cabinet is continuously powered by an external 220V factory power supply. However, once the factory power fails or a short circuit occurs in the equipment, the control cabinet will stop working, i.e., it will be unable to supply power to other equipment.

[0008] Therefore, a device is provided to solve the above problems. Summary of the invention

[0009] The purpose of the utility model is to overcome the shortcomings of the above-mentioned background technology and to provide a pipe gallery ACU control unit.

[0010] The purpose of the utility model is implemented through the following technical solutions: a pipe gallery ACU control unit, which is installed in a control cabinet, and includes an intrusion alarm, a security switch, a UPS power supply, an intelligent gateway, a temperature controller, a wireless AP switch and an emergency telephone host.

[0011] The control cabinet is divided into two layers, the upper and lower layers of the control cabinets are separated by glass plates.

[0012] The intrusion alarm host is placed on a glass plate, and a security switch, a fiber optic distribution box, a UPS power supply and a battery are stacked in order from top to bottom under the glass plate.

[0013] An intelligent gateway and a temperature controller are installed in the control cabinet, and wireless AP switches and emergency telephone hosts are installed on both sides of the control cabinet.

[0014] In the above technical solution: the control cabinet located on the upper layer is divided into four layers. The first layer is equipped with a switching power supply, an air switch, a first wiring terminal, a fuse terminal and a temperature controller from left to right.

[0015] The second layer is installed with PLC controller relays, sockets, and intelligent gateways from left to right.

[0016] The third layer is equipped with a plurality of third wiring terminals arranged side by side, and a ground bar is installed on one side of the third wiring terminals.

[0017] In the above technical solution: one side of the circuit breaker is connected to the external factory power through a cable, and the other side is connected to the adjacent switch power supply through a cable.

[0018] The first terminal is connected to a wireless AP switch and a switching power supply arranged on one side through a cable.

[0019] One side of the temperature controller is connected to the electric fan via a cable, and the other side is connected to an air switch arranged on one side via a cable.

[0020] One side of the PLC controller is connected to the second wiring terminal and the circuit breaker arranged above through cables.

[0021] The output end of the PLC controller is connected to the second wiring terminal and a relay arranged on one side through a cable.

[0022] The relay is connected to the second terminal and the third terminal via a cable.

[0023] The input end of the PLC controller is connected to the second wiring terminal and the third wiring terminal respectively through cables.

[0024] In the above technical solution: there are several sockets arranged side by side, one end of the socket is connected to the circuit breaker through a cable,

[0025] The UPS power supply, security switch and emergency telephone host are all connected to the socket through a plug.

[0026] In the above technical solution: the intelligent gateway is connected to the second terminal via a cable, and the third terminal is connected to the PLC controller via a cable.

[0027] In the above technical solution: the intrusion alarm host is connected to the external alarm device through a cable, the security switch is connected to the wireless AP switch set on one side through a cable and is connected to the optical fiber distribution box through an optical fiber.

[0028] In the above technical solution: the fiber optic distribution box is connected to the optical cable through optical fiber, and the optical fiber led out on the other side is connected to the wireless AP switch, intelligent gateway, emergency phone host, intrusion alarm host, security switch, UPS power supply through cables and sockets, and the battery is connected to the UPS power supply arranged above through cables.

[0029] In the above technical solution: an electric fan is installed on one side of the control cabinet, and a ground bar built into the control cabinet is grounded through a wire.

[0030] The utility model has the following advantages: 1. The utility model utilizes the existing space to assemble two control cabinets, and at the same time, according to customer needs, adds wireless AP switches, intrusion alarm hosts, intelligent gateways and other components, which can basically realize the control of related equipment in the corridor.

[0031] 2. The utility model connects the equipment in the pipe gallery through the internally arranged intrusion alarm host, security switch, intelligent gateway, emergency telephone host, and wireless AP switch, thereby realizing the control of the equipment in the pipe gallery and the communication processing of related equipment.

[0032] 3. The utility model ensures the continuous operation of relevant equipment in the pipe gallery by setting up UPS power supply and battery, thus avoiding the disadvantage of being unable to work once power is cut off.

[0033] 4. The utility model realizes precise control of the temperature and humidity in the cabinet by setting a temperature controller and a fan, thereby preventing the operation of other components from being affected by excessive humidity or temperature in the cabinet.

[0034] 5. In the existing overly narrow pipe gallery, the existing control cabinet cannot control all the equipment in the pipe gallery, and power outages often occur. After using the device of the utility model, the above problems can be basically solved, and continuous control and communication of the equipment in the pipe gallery can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a structural schematic diagram of the utility model.

[0036] In the figure: intrusion alarm 1, security switch 2, UPS power supply 3, intelligent gateway 4, temperature controller 5, wireless AP switch 6, emergency phone host 7, switch power supply 8, circuit breaker 9, first terminal 10, fuse terminal 11, second terminal 12, PLC 13, relay 14, socket 15, third terminal 16, fiber optic distribution box 17, battery 18, electric fan 19, ground bus 20, control cabinet 21. DETAILED DESCRIPTION

[0037] The following describes the implementation of the present invention in detail with reference to the accompanying drawings, but they do not constitute a limitation of the present invention and are only used as examples. At the same time, the advantages of the present invention will become clearer and easier to understand through the description.

[0038] Reference Figure 1 As shown: a pipe gallery ACU control unit, which is installed in a control cabinet 21, and includes an intrusion alarm 1, a security switch 2, a UPS power supply 3, an intelligent gateway 4, a temperature controller 5, a wireless AP switch 6 and an emergency telephone host 7,

[0039] The control cabinet 21 is divided into two layers, the upper and lower layers of the control cabinets 21 are separated by a glass plate.

[0040] The intrusion alarm host 1 is placed on a glass plate, and a security switch 2, a fiber optic distribution box 17, a UPS power supply 3 and a battery 18 are stacked in order from top to bottom under the glass plate.

[0041] The control cabinet 21 is provided with an intelligent gateway 4 and a temperature controller 5 , and both sides of the control cabinet 21 are provided with a wireless AP switch 6 and an emergency telephone host 7 .

[0042] The control cabinet 21 located on the upper layer is divided into four layers. The first layer is equipped with a switch power supply 8, a circuit breaker 9, a first wiring terminal 10, a fuse terminal 11 and a temperature controller 5 from left to right.

[0043] The second layer is equipped with PLC controller 13, relay 14, socket 15, and intelligent gateway 4 from left to right.

[0044] The third layer is provided with a plurality of third wiring terminals 16 arranged side by side, and a ground bar 20 is provided on one side of the third wiring terminals 16 .

[0045] One side of the circuit breaker 9 is connected to the external factory power through a cable, and the other side is connected to the adjacently arranged switching power supply 8 through a cable. The function of the circuit breaker 9 is to provide 24V power supply and 220V power supply respectively. The switching power supply 8 is connected to the circuit breaker 9, and the switching power supply 8 mainly provides 24V power supply.

[0046] The first wiring terminal 10 is connected to the wireless AP switch 6 and the switch power supply 8 arranged on one side through a cable. The first wiring terminal 10 is actually a power supply terminal to provide power to the connected components.

[0047] One side of the temperature controller 5 is connected to the electric fan 19 via a cable, and the other side is connected to the circuit breaker 9 provided at one side via a cable.

[0048] One side of the PLC controller 13 is connected to the second wiring terminal 12 and the circuit breaker 9 provided above through cables.

[0049] The output end of the PLC controller 13 is connected to the second terminal 12 and the relay 14 provided on one side through cables. The PLC processes the input data and then outputs it to the relevant equipment in the pipe gallery.

[0050] The relay 14 is connected to the second terminal 12 and the third terminal 16 via a cable.

[0051] The input end of the PLC controller 13 is connected to the second wiring terminal 12 and the third wiring terminal 16 through cables.

[0052] There are several sockets 15 arranged side by side. One of the sockets 15 is connected to the circuit breaker 9 through a cable on one side. The circuit breaker 9 is connected to an external 220V factory power supply to supply power to all components connected to the socket 15.

[0053] One end of the socket 15 is connected to the circuit breaker 9 via a cable.

[0054] The UPS power supply 3, the security switch 2 and the emergency telephone host 7 are all connected to the socket 15 via a plug.

[0055] The intelligent gateway 4 is connected to the second wiring terminal 12 through a cable, and the third wiring terminal 16 is connected to the PLC controller 13 through a cable. The second wiring terminal 12 actually also has a power supply function, and also provides power to the connected components.

[0056] The intrusion alarm host 1 is connected to the external alarm device through a cable, and the security switch 2 is connected to the wireless AP switch 6 set on one side through a cable and connected to the optical fiber distribution box 17 through an optical fiber. The intrusion alarm host 1 is placed to artificially damage the cabinet of the utility model. Once external force damage occurs, an alarm is issued in time.

[0057] The optical fiber distribution box 17 is connected to the optical cable through optical fiber, and the optical fiber led out from the other side is respectively connected to the wireless AP switch 6, the intelligent gateway 4, the emergency phone host 7, the intrusion alarm host 1, the security switch 2, and the UPS power supply 3 through the cable and the socket 15, and the battery 18 is connected to the UPS power supply 3 arranged above through the cable. The external optical fiber is connected to the optical fiber distribution box 17, and then enters the components that need WiFi signals to realize the communication transmission of the above components.

[0058] A fan 19 is installed on one side of the control cabinet 21, and the fan 19 transfers the heat in the control cabinet 21. The built-in ground bar 20 in the control cabinet 21 is grounded through a wire. The grounding protects the equipment in the utility model to prevent contacts and short circuits when people use the utility model.

[0059] Environmental monitoring: PLC controller 13 can detect oxygen, temperature and humidity, methane, hydrogen sulfide and other conditions in the tunnel. If they are too high or too low, the fan will be started to adjust to maintain a safe environment in the tunnel.

[0060] Security system: The security exchange host 2 is connected to the external camera to aggregate the videos of each camera in the corridor, so that the situation in the corridor can be better viewed and whether there are any outsiders entering.

[0061] Communication system: The emergency telephone host 7 is connected to the external emergency telephone and the wireless AP switch 7. There is generally no signal in the corridor. If there is an emergency in the corridor or debugging is required with personnel outside the corridor, the emergency telephone can be used for communication.

[0062] Power monitoring: The smart gateway 4 is used to detect the electric meters in the equipment connected to the control cabinet. It can monitor the voltage and current parameters of each distribution cabinet to prevent problems before they occur.

[0063] The parts not described in detail above are all prior art.

Claims

1. A pipe gallery ACU control unit, which is installed in a control cabinet (21), characterized in that: It includes an intrusion alarm host (1), a security switch (2), a UPS power supply (3), an intelligent gateway (4), a temperature controller (5), a wireless AP switch (6) and an emergency telephone host (7). The control cabinet (21) is divided into two layers, the upper and lower layers of the control cabinet (21) are separated by a glass plate. The intrusion alarm host (1) is placed on a glass plate, and a security switch (2), an optical fiber distribution box (17), a UPS power supply (3) and a battery (18) are stacked in order from top to bottom under the glass plate. An intelligent gateway (4) and a temperature controller (5) are installed in the control cabinet (21), and a wireless AP switch (6) and an emergency telephone host (7) are installed on both sides of the control cabinet (21).

2. A pipe gallery ACU control unit according to claim 1, characterized in that: The control cabinet (21) located on the upper layer is divided into four layers. The first layer is equipped with a switch power supply (8), a circuit breaker (9), a first wiring terminal (10), a fuse terminal (11) and a temperature controller (5) from left to right. The second layer is equipped with PLC controller (13), relay (14), socket (15), and intelligent gateway (4) from left to right. The third layer is equipped with a plurality of third wiring terminals (16) arranged side by side, and a ground bar (20) is installed on one side of the third wiring terminals (16).

3. A pipe gallery ACU control unit according to claim 2, characterized in that: One side of the circuit breaker (9) is connected to the external factory power supply through a cable, and the other side is connected to the adjacent switch power supply (8) through a cable. The first connection terminal (10) is connected to a wireless AP switch (6) and a switch power supply (8) arranged on one side through a cable. One side of the temperature controller (5) is connected to the electric fan (19) via a cable, and the other side is connected to a circuit breaker (9) provided on one side via a cable. One side of the PLC controller (13) is connected to the second wiring terminal (12) and the circuit breaker (9) arranged above through cables. The output end of the PLC controller (13) is connected to the second wiring terminal (12) and the relay (14) provided on one side through cables. The relay (14) is connected to the second terminal (12) and the third terminal (16) via a cable. The input end of the PLC controller (13) is respectively connected to the second wiring terminal (12) and the third wiring terminal (16) through cables.

4. A pipe gallery ACU control unit according to claim 3, characterized in that: There are a plurality of sockets (15) arranged side by side, and one end of the sockets (15) is connected to the circuit breaker (9) via a cable. The UPS power supply (3), the security switch (2) and the emergency telephone host (7) are all connected to the socket (15) via a plug.

5. A pipe gallery ACU control unit according to claim 4, characterized in that: The intelligent gateway (4) is connected to the second wiring terminal (12) via a cable, and the third wiring terminal (16) is connected to the PLC controller (13) via a cable.

6. A pipe gallery ACU control unit according to claim 5, characterized in that: The intrusion alarm host (1) is connected to an external alarm device via a cable, and the security switch (2) is connected to a wireless AP switch (6) arranged on one side via a cable and is connected to an optical fiber distribution box (17) via an optical fiber.

7. A pipe gallery ACU control unit according to claim 6, characterized in that: The optical fiber distribution box (17) is connected to the optical cable via an optical fiber, and the optical fiber led out from the other side is respectively connected to the wireless AP switch (6), the intelligent gateway (4), the emergency telephone host (7), the intrusion alarm host (1), the security switch (2), and the UPS power supply (3) via a cable and a socket (15), and the battery (18) is connected to the UPS power supply (3) arranged above via a cable.

8. A pipe gallery ACU control unit according to claim 1, characterized in that: An electric fan (19) is installed on one side of the control cabinet (21), and a ground bar (20) built into the control cabinet (21) is grounded via a wire.