By designing a high-position lifting drilling device, the problems of unsafe high-position drilling construction and difficulty in position control were solved, achieving drilling stability and accuracy and reducing construction risks.
Patent Information
- Application Number
- CN202323281591.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-04
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-04
AI Technical Summary
High-level drilling is not safe enough, and the drilling position is difficult to control, especially in places such as windows, where there is a risk of workers falling over and the drilling deviating.
A high-position lifting drilling device was designed, including a column, a lower swing arm, an upper swing arm, a push rod, and a drilling device. The height of the top rod is adjusted by pushing or pulling the push rod to achieve longitudinal movement of the drilling device. Combined with a dust collection hood to collect dust, the drilling position is accurate and stable.
It improves the safety and positioning accuracy of high-level drilling, reduces dust diffusion, and lowers the operational risks and drilling deviations for construction workers.
Smart Images

Figure CN221937180U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of drilling, in particular to a high-position lifting drilling device. Background Art
[0002] During the construction process, many construction contents involve drilling operations. For example, window frame installation requires drilling for expansion nails, wall construction requires drilling for rebar planting, and walls require drilling for water pipes.
[0003] During the drilling operation, there are cases where the drilling position is relatively high, such as drilling holes on the top of the building, drilling holes on the top of the window installation position, etc. The drilling position is relatively high and is considered high-position drilling. Construction workers need to stand on auxiliary tools such as climbing frames and hold electric drills to drill. During the drilling process, the electric drill shakes, shaking the construction workers, and the construction workers are prone to falling on the auxiliary tools, especially when drilling holes at windows, which are close to the outdoors, further increasing the risk. There are also construction workers who tie the electric drill to wooden squares or channel steels, lift the electric drill, and drill holes in the building walls. In this way, the drilling position is easily offset and inaccurate. Utility Model Content
[0004] 1. Technical issues to be solved
[0005] In view of the deficiencies in the prior art, the utility model provides a high-position lifting drilling device, which solves the problems that high-position drilling construction is not safe enough and the drilling position is difficult to control.
[0006] (II) Technical solution
[0007] To achieve the above purpose, the utility model is implemented through the following technical solutions: a high-position lifting drilling device, comprising:
[0008] A column, a lower swing arm and an upper swing arm, wherein the lower swing arm and the upper swing arm are rotatably connected to the middle part and the upper part of the outer wall of the column respectively, and the lower swing arm and the upper swing arm are parallel to each other;
[0009] A push rod, which is rotatably connected to the lower swing arm and the upper swing arm through a pin shaft, and the push rod is parallel to the column;
[0010] A sliding assembly, wherein the sliding assembly is slidably connected to the top of the column, a push rod is arranged on the upper side of the sliding assembly, and the push rod is located on the lower side of the push rod;
[0011] The drilling equipment is installed on a top rod, an elastic member is arranged on the upper side of the drilling equipment, a dust collecting cover is arranged on the upper end of the elastic member, and the dust collecting cover is movably sleeved on the outer side of the drill bit of the drilling equipment.
[0012] Preferably, the lower surface of the column is fixedly connected to a bottom plate, and the lower surface of the bottom plate is horizontally arranged.
[0013] Preferably, one end of the lower swing arm away from the push rod extends outward and is connected to a handle.
[0014] Preferably, two of the columns and sliding assemblies are provided, the two columns are installed in parallel, and the lower swing arm and the upper swing arm are rotatably connected to one of the columns, and the top rod is connected to the upper end between the two sliding assemblies.
[0015] Preferably, the sliding assembly includes a sliding frame and support rods fixedly connected to both sides of the outer wall of the sliding frame, the sliding frame is slidably sleeved on the upper side of the outer wall of the column, the upper end of the support rod is fixedly connected to the lower surface of the top rod, and a limiting flange is provided on the upper side of the outer wall of the column.
[0016] Preferably, a buffer spring is provided between the lower surface of the push rod and the upper surface of the push rod.
[0017] Preferably, the top end of the push rod is rotatably connected to a support roller via a rotating shaft, and the support roller is rollingly supported on the lower side of the push rod.
[0018] (III) Beneficial effects
[0019] The utility model provides a high-position lifting drilling device, which has at least the following beneficial effects compared with the prior art:
[0020] Pushing or pulling the lower swing arm and the upper swing arm upwards or downwards allows the push rod to be pushed upwards or downwards. The rising or falling of the push rod can adjust the height of the push rod. The push rod drives the drilling equipment to move longitudinally, and the drilling equipment drills holes at the drilling positions. Since the drilling equipment moves longitudinally and vertically, the drilling equipment moves smoothly, is not prone to position deviation, has accurate drilling positions, and is not prone to shaking during the drilling process.
[0021] The dust collecting hood is set to cover the periphery of the drill bit to collect dust generated during the drilling process to prevent the dust from being scattered everywhere. Under the elastic support of the elastic member, the dust collecting hood can move up and down outside the drill bit without affecting the drilling of the drill bit. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the structure of the utility model;
[0023] Figure 2 It is a structural schematic diagram of the sliding frame, support rods and top rods of the utility model.
[0024] In the figure: 1. column; 2. bottom plate; 3. lower swing arm; 4. upper swing arm; 5. handle; 6. push rod; 7. support roller; 8. sliding frame; 9. support rod; 10. push rod; 11. limit flange; 12. buffer spring; 13. drilling equipment; 14. dust cover; 15. elastic member. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] Embodiment 1:
[0027] See also Figure 1-2 The utility model provides a technical solution: a high-position lifting drilling device, comprising: a column 1, a lower swing arm 3, an upper swing arm 4, a push rod 6, a sliding assembly, and a drilling device 13;
[0028] The lower swing arm 3 and the upper swing arm 4 are rotatably connected to the middle and upper parts of the outer wall of the column 1 respectively, and the lower swing arm 3 and the upper swing arm 4 are parallel to each other. The push rod 6 is rotatably connected to the lower swing arm 3 and the upper swing arm 4 through a pin shaft, and the push rod 6 is parallel to the column 1. The sliding assembly is slidably connected to the top of the column 1, and a push rod 10 is provided on the upper side of the sliding assembly. The push rod 6 is located on the lower side of the push rod 10. The drilling equipment 13 is installed on the push rod 10, and an elastic member 15 is provided on the upper side of the drilling equipment 13. A dust hood 14 is provided on the upper end of the elastic member 15, and the dust hood 14 is movably sleeved on the outer side of the drill bit of the drilling equipment 13.
[0029] Analysis of the above content: move the high-position lifting drilling equipment to the lower side of the place where a hole needs to be drilled, push the push rod 6 up in advance, and the push rod 6 pushes the top rod 10 and the drilling equipment 13 up, so that the drill bit of the drilling equipment 13 contacts the position where a hole needs to be drilled first, and conduct a preliminary drill. Adjust the position of the column 1 from the bottom until the drill bit corresponds to the position where a hole needs to be drilled. In this way, in the subsequent drilling process, the drill bit will remain consistent with the position where a hole needs to be drilled.
[0030] When drilling, the push rod 6 is pushed up (this can be achieved by swinging the lower swing arm 3), and the push rod 6 pushes the top rod 10 and the drilling equipment 13 up. The control switch of the drilling equipment 13 can be extended downward to facilitate the control of the construction personnel on the lower side. The dust cover 14 is covered at the position where the hole needs to be drilled. The dust generated during the drilling process falls into the dust cover 14. The lower push rod 6 continues to push up with force, and the drill bit gradually rises. As the hole is drilled deeper, the drill bit rises, and the elastic member 15 is gradually compressed and shortened. The dust cover 14 is funnel-shaped, and the lower side opening of the dust cover 14 is larger than the outer wall diameter of the drill bit. Therefore, when the drill bit rotates, it will not rub against the dust cover 14.
[0031] Embodiment 2:
[0032] See also Figure 1-2 The utility model provides a technical solution based on the first embodiment: the lower surface of the column 1 is fixedly connected with the bottom plate 2, and the lower surface of the bottom plate 2 is horizontally arranged.
[0033] Analysis of the above content: The setting of the bottom plate 2 enables the column 1 to be stable when in use. The column 1 is usually set to be perpendicular to the bottom plate 2. According to the use situation, when the column 1 and the bottom plate 2 need to be set to be inclined, the column 1 and the bottom plate 2 can be welded at an angle.
[0034] Embodiment three:
[0035] See also Figure 1-2 The utility model provides a technical solution based on the first embodiment: the end of the lower swing arm 3 away from the push rod 6 extends outward and is connected to the handle 5.
[0036] Analysis of the above content: The extended setting of the handle 5 and the lower swing arm 3 increases the force arm, making the swing control of the lower swing arm 3 more labor-saving.
[0037] Embodiment 4:
[0038] See also Figure 1-2 The utility model provides a technical solution based on the first embodiment: the columns 1 and the sliding components are both provided with two, the two columns 1 are installed in parallel, and the lower swing arm 3 and the upper swing arm 4 are rotatably connected to one of the columns 1, and the top rod 10 is connected to the upper end between the two sliding components.
[0039] Analysis of the above content: through the arrangement of two parallel columns 1, when the push rod 6 pushes the push rod 10, the push rod 10 moves up smoothly, and it is not easy for the sliding component and the column 1 to get stuck.
[0040] Embodiment five:
[0041] See also Figure 1-2 The utility model provides a technical solution based on the first embodiment: the sliding assembly includes a sliding frame 8 and a support rod 9 fixedly connected to both sides of the outer wall of the sliding frame 8, the sliding frame 8 is slidably sleeved on the upper side of the outer wall of the column 1, the upper end of the support rod 9 is fixedly connected to the lower surface of the push rod 10, and a limited flange 11 is provided on the upper side of the outer wall of the column 1. A buffer spring 12 is provided between the lower surface of the push rod 10 and the upper surface of the push rod 10.
[0042] Analysis of the above content: Lubricating oil is applied inside the sliding frame 8, and the sliding frame 8 can be slidably connected to the upper end of the column 1. The setting of the limiting flange 11 can prevent the sliding frame 8 from detaching from the column 1. Since the sliding assembly, the push rod 10, and the drilling equipment 13 are heavier as a whole, they are supported between the push rod 10 and the column 1 by the buffer spring 12. When the sliding assembly, the push rod 10, and the drilling equipment 13 descend, they play a buffering role for the sliding assembly, the push rod 10, and the drilling equipment 13.
[0043] Embodiment six:
[0044] See also Figure 1-2 The utility model provides a technical solution based on the first embodiment: the top end of the push rod 6 is rotatably connected to a support roller 7 via a rotating shaft, and the support roller 7 is rollingly supported on the lower side of the push rod 10.
[0045] Analysis of the above content: through the setting of the support roller 7, the push rod 6 and the push rod 10 are rollingly supported by the support roller 7 to reduce friction resistance.
[0046] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0047] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A high-position lifting drilling device, characterized in that: include: A column (1), a lower swing arm (3) and an upper swing arm (4), wherein the lower swing arm (3) and the upper swing arm (4) are rotatably connected to the middle and upper parts of the outer wall of the column (1) respectively, and the lower swing arm (3) and the upper swing arm (4) are parallel to each other; A push rod (6), wherein the push rod (6) is rotatably connected to the lower swing arm (3) and the upper swing arm (4) via a pin shaft, and the push rod (6) is parallel to the column (1); A sliding assembly, the sliding assembly being slidably connected to the top end of the column (1), a push rod (10) being arranged on the upper side of the sliding assembly, and the push rod (6) being located on the lower side of the push rod (10); A drilling device (13), the drilling device (13) being mounted on a mandrel (10), an elastic member (15) being arranged on the upper side of the drilling device (13), a dust collecting hood (14) being arranged at the upper end of the elastic member (15), and the dust collecting hood (14) being movably sleeved on the outer side of a drill bit of the drilling device (13).
2. The high-position lifting drilling equipment according to claim 1 is characterized in that: The lower surface of the column (1) is fixedly connected to a bottom plate (2), and the lower surface of the bottom plate (2) is arranged horizontally.
3. The high-position lifting drilling equipment according to claim 1 is characterized in that: One end of the lower swing arm (3) away from the push rod (6) extends outward and is connected to a handle (5).
4. The high-position lifting drilling equipment according to claim 1 is characterized in that: The columns (1) and sliding components are both provided with two, the two columns (1) are installed in parallel, and the lower swing arm (3) and the upper swing arm (4) are rotatably connected to one of the columns (1), and the top rod (10) is connected to the upper end between the two sliding components.
5. The high-position lifting drilling equipment according to claim 1 is characterized in that: The sliding assembly comprises a sliding frame (8) and support rods (9) fixedly connected to both sides of the outer wall of the sliding frame (8); the sliding frame (8) is slidably sleeved on the upper side of the outer wall of the column (1); the upper end of the support rod (9) is fixedly connected to the lower surface of the top rod (10); and a limiting flange (11) is provided on the upper side of the outer wall of the column (1).
6. The high-position lifting drilling equipment according to claim 5, characterized in that: A buffer spring (12) is provided between the lower surface of the push rod (10) and the upper surface of the push rod (10).
7. The high-position lifting drilling equipment according to claim 1, characterized in that: The top end of the push rod (6) is rotatably connected to a support roller (7) via a rotating shaft, and the support roller (7) is rollingly supported on the lower side of the push rod (10).