Double-truss rib laminated slab foundation pit support structure
By designing a double truss rib laminated plate structure in the prefabricated foundation pit enclosure structure, combining the stiff I-shaped steel beams and slightly expanded high-strength concrete, the reliable connection, construction safety and water stop of the foundation pit enclosure structure are solved, and the problem of reliable connection, construction safety and water stop of the foundation pit enclosure structure is achieved. Efficient and safe construction results.
Patent Information
- Application Number
- CN202420508899.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-15
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-03-15
AI Technical Summary
Problems of reliable connection and fixation of prefabricated wall panels in prefabricated foundation pit enclosure structures, deformation or failure caused by improper connection of support systems, safety and economic problems of lifting construction of layered and segmented enclosure structures, enclosure structure and main body The problem of structural construction integration and load bearing and water stopping.
Design a double-truss rib laminated plate foundation pit enclosure structure, including inner truss rib laminated plate, outer truss rib laminated plate, anchor rod and rigid I-shaped steel beam, and use adjustment pad plate and internal thread sleeve to realize the structure Flexible installation, combining micro-expanded high-strength concrete and anchors, enhance the structural stress performance and achieve water stopping effect through strong I-shaped steel beams.
It improves construction quality and efficiency, enhances the safety and stress performance of the structure, achieves rapid installation and good economic benefits, and ensures reliable connection and water stopping of the enclosure structure.
Smart Images

Figure CN221941371U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of foundation pit enclosure, in particular to a double-truss rib composite plate foundation pit enclosure structure. Background Art
[0002] Gao Luheng's team from Jiangsu Engineering Vocational and Technical College and Wang Baohua's team from Jiangsu Shenggong Construction Group Co., Ltd. have opened up new directions for the development of the industry in terms of "key technologies for the construction of prefabricated deep foundation pit retaining structures" and formed a systematic system of multiple key technologies. In order to solve the industry pain points in the prefabricated deep foundation pit support system, such as the reliable connection and fixation of prefabricated wall panels in the prefabricated foundation pit retaining structure, the problem of excessive deformation or failure of the support structure due to loose connection of the support system, the safety and economy of the hoisting construction of layered and segmented retaining structure, the bearing and water stopping of the retaining structure, and the integration of the construction of the retaining structure and the main structure. Our team has deeply studied the technical premise of relevant scholars and proposed "a prefabricated foundation pit retaining system support structure". This technology is the research result of the 2023 Nantong Science and Technology Plan Project undertaken by Zhu Miaomiao's team from Jiangsu Engineering Vocational and Technical College: Research and Application of Assembly Construction Technology of Pile-Beam-Wall-Anchor Prestressed Retaining Structure of Deep Foundation Pit of High-rise Buildings (Project No.: MSZ2023171). We hope that through school-enterprise cooperation, we can jointly make certain innovative efforts for the safe construction of prefabricated deep foundation pit retaining structures in my country, innovate structural design, optimize construction technology, and make certain contributions to the high-quality development of the construction field of prefabricated foundation pit retaining structures in my country. Utility Model Content
[0003] The utility model aims to provide a double-truss rib composite plate foundation pit enclosure structure to solve the problems raised by the background technology.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a double-truss rib composite plate foundation pit retaining structure, which is arranged between two adjacent precast piles, and the foundation pit retaining structure includes an inner truss rib composite plate, an outer truss rib composite plate and an anchor rod, the inner truss rib composite plate and the outer truss rib composite plate are relatively arranged and respectively connected to the precast piles to form a double-truss rib composite plate structure; a plurality of mutually parallel rigid I-shaped steel beams are arranged between the inner truss rib composite plate and the outer truss rib composite plate, and adjustment pads are connected at both ends of the rigid I-shaped steel beam, and the adjustment pads are arranged on the precast piles; micro-expansion high-strength concrete is poured in the cavity of the double-truss rib composite plate structure; the anchor rods are driven into the soil layer and staggered at the installation position of the rigid I-shaped steel beam.
[0005] Preferably, it also includes an internal threaded sleeve, and the adjusting pad is fixed to the prefabricated pile through the internal threaded sleeve to achieve flexible on-site installation of prefabricated components of the foundation pit retaining structure and improve construction quality and efficiency.
[0006] Preferably, a rigid I-shaped steel beam and an adjustment pad are provided between the upper and lower adjacent sections of the foundation pit retaining structure. The rigid I-shaped steel beam also serves as a water-stopping steel plate, which can achieve the purpose of strengthening the upper and lower retaining structures to achieve reliable connection at their joints after hoisting construction, and can also achieve the purpose of water-stopping the retaining structure.
[0007] Preferably, the thickness of the web and flange of the rigid I-shaped steel beam is not less than 12 mm, and the width of the flange is not less than 60 mm; the beam height of the rigid I-shaped steel beam is not less than 220 mm, and one is installed every 450 mm along the depth direction of the foundation pit.
[0008] Preferably, the strength of the slightly expansive high-strength concrete is higher than that of the inner truss rib composite plate and the outer truss rib composite plate, and the grade is not lower than C50.
[0009] The beneficial effects of the utility model are: reasonable structure, good safety performance, prefabricated internal and external truss rib composite plate hoisting, built-in rigid I-shaped steel beams, and grouting method is used to complete the on-site installation and construction of the enclosure structure. The structure has good stress performance, fast installation and construction speed, saves construction time, and has good economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 It is a structural schematic diagram of an embodiment of the utility model;
[0011] Figure 2 yes Figure 1 Schematic diagram of the structure of the inner truss rib composite plate or the outer truss rib composite plate. DETAILED DESCRIPTION
[0012] See also Figure 1 In an embodiment of the utility model, a double truss rib composite plate foundation pit retaining structure is disclosed, which is arranged between two adjacent precast piles 1, and includes an inner truss rib composite plate 2, an outer truss rib composite plate 3, a rigid I-shaped steel beam 4, an adjustment pad 5, an internal threaded sleeve 6 and an anchor rod 7.
[0013] An inner truss rib composite plate 2 and an outer truss rib composite plate 3 are provided between adjacent precast piles 1. The inner truss rib composite plate 2 and the outer truss rib composite plate 3 are connected to the precast pile 1 through angle steel to form a double truss rib composite plate structure. A rigid I-shaped steel beam 4 is provided inside the inner truss rib composite plate 2 and the outer truss rib composite plate 3. Both ends of the rigid I-shaped steel beam 4 are welded to the adjustment pad 5. The adjustment pad 5 is fixed to the precast pile 1 through an internal threaded sleeve 6 to achieve flexible on-site installation of precast components of the foundation pit retaining structure and improve construction quality and efficiency. The web and flange thickness of the rigid I-shaped steel beam 4 are not less than 12 mm, the flange width is not less than 60 mm, the beam height of the rigid I-shaped steel beam 4 is not less than 220 mm, and one is installed every 450 mm along the depth direction of the foundation pit.
[0014] The integral enclosure structure is also provided with anchor rods 7 driven inside the soil layer, and the driving position of the anchor rods 7 is staggered with the installation position of the rigid I-shaped steel beam 4, so as not to collide with each other. After the installation is completed, micro-expansion high-strength concrete is poured in the cavity between the double truss rib composite plates. The strength of the micro-expansion high-strength concrete should be one grade higher than that of the inner truss rib composite plates 2 and the outer truss rib composite plates 3, and not less than C50.
[0015] The rigid I-shaped steel beam 4 is installed on the inner side of the retaining structure and is wrapped with high-strength concrete grouting to enhance the stress-bearing performance of the retaining structure. A set of rigid I-shaped steel beams 4 and adjustment pads 5 are welded at the joints of the double-truss rib superimposed plates of the upper and lower adjacent sections of the foundation pit retaining structure. The structure is set with reference to the rigid I-shaped steel beams 4 and adjustment pads 5 inside the foundation pit retaining structure. At the same time, the structure can use the rigid I-shaped steel beams 4 as water-stopping steel plates for the retaining structure, achieving the dual effects of combining the load-bearing and water-stopping of the retaining structure, strengthening the reliable connection at the joints of the upper and lower sections of the foundation pit retaining structure after hoisting and construction, and achieving the purpose of water-stopping of the retaining structure.
[0016] The precast pile 1 is prefabricated in an integrated manner in the PC factory. In order to meet the needs of the quick installation of the adjustment pad 5 at a later stage, the internal threaded sleeve 6 is accurately pre-buried during the production of the precast pile. The inner truss rib composite plate 2 and the outer truss rib composite plate 3 are also centrally prefabricated in the PC factory. The connecting angle steels are pre-buried at both ends of the inner truss rib composite plate 2 and the outer truss rib composite plate 3. During the prefabrication process, the inner truss rib composite plate 2 and the outer truss rib composite plate 3 also reserve the perforation positions of the bolts 7 in the subsequent process, and the reserved bolt perforation positions on the inner truss rib composite plate 2 and the outer truss rib composite plate 3 correspond to each other.
[0017] In summary, the utility model has a reasonable structure, good safety performance, prefabricated internal and external truss rib composite plates for hoisting, built-in rigid I-shaped steel beams, and adopts the grouting method to complete the on-site installation and construction of the enclosure structure. The structure has good stress performance, fast installation and construction speed, saves construction period, and has good economic and social benefits. The installation and construction speed is fast, saves construction period, and has good economic and social benefits.
[0018] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A double truss rib composite plate foundation pit retaining structure, arranged between two adjacent precast piles (1), Features: The foundation pit retaining structure comprises an inner truss rib composite plate (2), an outer truss rib composite plate (3) and an anchor rod (7); the inner truss rib composite plate (2) and the outer truss rib composite plate (3) are arranged opposite to each other and are respectively connected to the precast piles (1) to form a double truss rib composite plate structure; a plurality of mutually parallel rigid I-shaped steel beams (4) are arranged between the inner truss rib composite plate (2) and the outer truss rib composite plate (3); both ends of the rigid I-shaped steel beam (4) are connected to adjustment pads (5), and the adjustment pads (5) are arranged on the precast piles (1); micro-expansion high-strength concrete is poured in the cavity of the double truss rib composite plate structure; the anchor rod (7) is driven into the soil layer and is staggered at the installation position of the rigid I-shaped steel beam (4).
2. The foundation pit retaining structure according to claim 1, Features: It also comprises an internal thread sleeve (6), and the adjusting pad (5) is fixed on the prefabricated pile (1) through the internal thread sleeve (6).
3. The foundation pit retaining structure according to claim 2, Features: A rigid I-shaped steel beam (4) and an adjusting pad (5) are also arranged between the upper and lower adjacent sections of the foundation pit retaining structure, and the rigid I-shaped steel beam (4) also serves as a water-stopping steel plate.
4. The foundation pit retaining structure according to claim 1 or 3, Features: The web and flange thicknesses of the rigid I-shaped steel beam (4) are not less than 12 mm, and the flange width is not less than 60 mm; the beam height of the rigid I-shaped steel beam (4) is not less than 220 mm, and one is installed at intervals of 450 mm along the depth direction of the foundation pit.
5. The foundation pit retaining structure according to claim 1, Features: The strength of the micro-expansion high-strength concrete is at least one level higher than that of the inner truss rib composite plate (2) and the outer truss rib composite plate (3), and the level is not lower than C50, so as to ensure the overall quality of the enclosure structure after on-site installation and post-casting construction.
Citation Information
Cited By
Post-tensioning prestressed foundation pit enclosure structure with top deformation controlled and construction method thereof
CN122728299B
Construction method of T-shaped pile supporting assembled monolithic foundation pit enclosure structure
CN122960149A