Dry coil pipe mounting structure of clean room

By introducing a fixing mechanism and a moisture removal mechanism into the dry coil installation structure of the clean room, the difficulty of dry coil replacement and dust production during the installation process is solved, the practicality and airtightness of the clean room are improved, and the dry coil is ensured. Stable operation.

CN221944466UActive Publication Date: 2024-11-01BEIJING TAIWEI METAL STRUCTURE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323405869.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-14
Publication Date
2024-11-01
Estimated Expiration
2033-12-14

AI Technical Summary

Technical Problem

The existing clean room dry coil installation structure has difficulties in replacing dry coils, which leads to reduced practicality and requires multiple holes to be drilled during the installation process, which can easily lead to dust production.

Method used

A dry coil mounting structure including a fixing mechanism and a mounting mechanism is designed, the dry coil is fixed by a second bolt and a fixing edge, and the upper fixing block and the lower fixing block are connected by a first bolt to fix the steel plate and the load-bearing steel frame. Color steel plates are used to strengthen the compression resistance of the steel plates, and a moisture removal mechanism is installed in the return air clamp to prevent the air from being wet.

Benefits of technology

It realizes convenient replacement of dry coils, avoids large-scale dust production during installation, improves the practicality and airtightness of the clean room, and prevents the formation of condensation through the moisture removal mechanism.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221944466U_ABST
    Figure CN221944466U_ABST
Patent Text Reader

Abstract

The utility model discloses a clean room dry coil pipe installation structure, and belongs to the field of clean room structures, the clean room dry coil pipe installation structure comprises a dry coil pipe, a fixing mechanism is arranged outside the dry coil pipe, the fixing mechanism comprises a fixing edge, the fixing edge is fixedly connected with the dry coil pipe, the interior of the fixing edge is in threaded connection with a second bolt, and the second bolt is fixedly connected with the dry coil pipe. An installation mechanism is arranged outside the fixing edge and horizontally arranged at the top of the air return passageway, the air return passageway is composed of a first steel plate and a second steel plate and is provided with at least one obliquely-arranged second steel plate, a dehumidification mechanism is arranged in the air return passageway, and a clean room is arranged outside the air return passageway. And by arranging second bolts and fixing edges, the problem that according to an existing clean room dry coil pipe mounting structure, when a dry coil pipe needs to be replaced, the dry coil pipe cannot be replaced is solved, and the practicability of the clean room dry coil pipe mounting structure is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of clean room structures, and in particular to a clean room dry coil installation structure. Background Art

[0002] In the patent with the published authorization announcement number CN216953323U, the utility model discloses a dry coil return air duct structure for a clean room, including a dry coil and a return air duct, wherein the dry coil is horizontally arranged under the ceiling of the clean room, and the return air duct is defined by at least one steel plate, and has at least one inclined first steel plate, one end of which is connected to the outer wall of the dry coil and forms an acute angle with the dry coil, and also has a second steel plate, which is connected to the other end of the first steel plate. The dry coil return air duct structure can reduce the occupied space of the return air duct and increase the actual practical area of ​​the clean room.

[0003] When the above device is implemented, it is found during the maintenance process that the dry coil is damaged and needs to be replaced. However, the existing clean room dry coil installation structure cannot replace the dry coil when it needs to be replaced, resulting in a reduction in the practicality of the clean room dry coil installation structure. Utility Model Content

[0004] In view of the deficiencies of the prior art, the utility model provides a clean room dry coil installation structure, which overcomes the deficiencies of the prior art and aims to solve the problems in the background technology.

[0005] In order to achieve the above-mentioned purpose, the present application adopts the following technical scheme: a clean room dry coil installation structure, including a dry coil, a fixing mechanism is provided on the outside of the dry coil, the fixing mechanism includes a fixing edge, the fixing edge is fixedly connected to the dry coil, the internal thread of the fixing edge is connected with a second bolt, the fixing edge is provided with an installation mechanism on the outside, the installation mechanism is horizontally arranged on the top of the return air duct, the return air duct is composed of a first steel plate and a second steel plate, and has at least one inclined second steel plate, a dehumidification mechanism is provided on the inside of the return air duct, and a clean room is provided on the outside of the return air duct.

[0006] As a preferred embodiment, the mounting mechanism includes an upper fixed block, which is fixedly connected to the first steel plate, the internal thread of the upper fixed block is connected to a first bolt, the external thread of the first bolt is connected to a lower fixed block, and one side of the lower fixed block is fixedly connected to a load-bearing steel frame.

[0007] By adopting the above technical solution, the upper fixing block and the lower fixing block are connected and fixed by the first bolt, the first steel plate is fixed by the upper fixing block, and the load-bearing steel frame is fixed by the lower fixing block, so that the load-bearing steel frame and the first steel plate can be better connected and fixed.

[0008] As a preferred embodiment, the dehumidification mechanism includes a drawer, which is slidably connected to the first steel plate, a handle is fixedly connected to the outside of the drawer, a ventilation hole is provided at the bottom of the drawer, and a desiccant is provided inside the drawer.

[0009] By adopting the above technical solution, the desiccant is placed in a drawer, ventilation is carried out through the ventilation holes at the bottom of the drawer, and the drawer is driven by pulling the handle, so that the air inside the return air duct can be better dehumidified to prevent the air from being too humid, which will cause condensation water to appear on the outside of the dry coil during operation.

[0010] As a preferred implementation, the first steel plate and the second steel plate are both made of color steel plates.

[0011] By adopting the above technical solution, since both the first steel plate and the second steel plate are made of colored steel plates, the ceiling can be better loaded and the compression resistance of the steel plates can be enhanced.

[0012] As a preferred implementation, a ventilation hole is provided on one side of the first steel plate.

[0013] By adopting the above technical solution, ventilation holes are provided on one side of the first steel plate, and ventilation is performed through the ventilation holes, so that the air inside the clean room can flow into the interior of the return air duct better.

[0014] As a preferred implementation, the joints between the dry coil, the fixed edge and the load-bearing steel frame are all coated with sealant.

[0015] By adopting the above technical solution, the joints of the dry coil, the fixed edge and the load-bearing steel frame are coated with sealant, and the sealant is used to ensure air tightness, which can better improve the air tightness of the clean room and the return air duct.

[0016] Beneficial effects of this application:

[0017] 1. The clean room dry coil installation structure is provided with a second bolt and a fixed edge, the fixed edge is fixed by the dry coil, the second bolt is fixed by the fixed edge, and the fixed edge is connected to the load-bearing steel frame by the second bolt, thereby avoiding the problem of the existing clean room dry coil installation structure that the dry coil cannot be replaced when it is needed, and improving the practicality of the clean room dry coil installation structure.

[0018] 2. The clean room dry coil installation structure is provided with an upper fixing block, a lower fixing block, a first bolt and a load-bearing steel frame. The upper fixing block and the lower fixing block are connected and fixed by the first bolt, and then the upper fixing block fixes the first steel plate, and then the lower fixing block fixes the load-bearing steel frame. This avoids the problem of the existing clean room dry coil installation structure that multiple holes need to be drilled when multiple dry coils are installed, improves the practicability of the clean room dry coil installation structure, and avoids large-area dust-generating operations during installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is a schematic diagram of the structure of the clean room dry coil installation structure for this application;

[0020] Figure 2 This is a schematic diagram of the fixing mechanism structure of this application;

[0021] Figure 3 For this application Figure 1 A schematic diagram of the enlarged structure of .

[0022] Numbers in the figure: 1. Dry coil; 2. Clean room; 3. Return air duct; 4. First steel plate; 5. Dehumidification mechanism; 51. Handle; 52. Drawer; 6. Installation mechanism; 61. Upper fixing block; 62. Lower fixing block; 63. First bolt; 64. Load-bearing steel frame; 7. Fixing mechanism; 71. Second bolt; 72. Fixing edge; 8. Second steel plate. DETAILED DESCRIPTION

[0023] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments.

[0024] Reference Figure 1-Figure 3 The installation structure of the dry coil in a clean room includes a dry coil 1. A fixing mechanism 7 is provided on the outside of the dry coil 1. The fixing mechanism 7 includes a fixing edge 72. The fixing edge 72 is fixedly connected to the dry coil 1. The internal thread of the fixing edge 72 is connected with a second bolt 71. A mounting mechanism 6 is provided on the outside of the fixing edge 72. The mounting mechanism 6 is horizontally arranged on the top of the return air duct 3. The return air duct 3 is composed of a first steel plate 4 and a second steel plate 8. The mounting mechanism 6 includes an upper fixing block 61. The upper fixing block 61 is fixedly connected to the first steel plate 4. The internal thread of the upper fixing block 61 is connected with a first bolt 63. The external thread of the first bolt 63 is connected with a lower fixing block 62. One side of the lower fixing block 62 is fixedly connected with a load-bearing steel frame 64; the upper fixing block 61 and the lower fixing block 62 are connected and fixed by the first bolt 63, and the first steel plate 4 is fixed by the upper fixing block 61, and the load-bearing steel frame 64 is fixed by the lower fixing block 62, so that the load-bearing steel frame 64 and the first steel plate 4 can be better connected and fixed.

[0025] Reference Figure 1 , one side of the second steel plate 8 is provided with ventilation holes; through the second steel plate 8 is provided with ventilation holes on one side, and then ventilation is performed through the ventilation holes, so that the air inside the clean room 2 can flow into the interior of the return air duct 3 better.

[0026] Reference Figure 1-Figure 3 The joints of the dry coil 1, the fixed edge 72 and the load-bearing steel frame 64 are all coated with sealant; the joints of the dry coil 1, the fixed edge 72 and the load-bearing steel frame 64 are all coated with sealant, and the sealant is used to ensure air tightness, which can better improve the air tightness of the clean room 2 and the return air duct 3.

[0027] Reference Figure 1 , having at least one second steel plate 8 arranged obliquely, a dehumidification mechanism 5 is arranged inside the return air duct 3, the dehumidification mechanism 5 includes a drawer 52, the drawer 52 is slidably connected to the first steel plate 4, a handle 51 is fixedly connected to the outside of the drawer 52, a ventilation hole is arranged at the bottom of the drawer 52, and a desiccant is arranged inside the drawer 52; the desiccant is placed in the drawer 52, and ventilation is performed through the ventilation holes at the bottom of the drawer 52, and the drawer 52 is driven by pulling the handle 51, so that the air inside the return air duct 3 can be better dehumidified to prevent the air from being too humid, resulting in condensation water on the outside of the dry coil 1 during operation.

[0028] Reference Figure 1 The first steel plate 4 and the second steel plate 8 are both made of colored steel plates; by making the first steel plate 4 and the second steel plate 8 both made of colored steel plates, the ceiling can be better loaded and the compression resistance of the steel plates can be enhanced.

[0029] Reference Figure 1 A clean room 2 is provided outside the return air duct 3.

[0030] Working principle: The fixed edge 72 is fixed by the dry coil 1, and the second bolt 71 is fixed by the fixed edge 72, and the fixed edge 72 is connected to the load-bearing steel frame 64 by the second bolt 71, and the upper fixed block 61 and the lower fixed block 62 are connected and fixed by the first bolt 63, and the first steel plate 4 is fixed by the upper fixed block 61, and the load-bearing steel frame 64 is fixed by the lower fixed block 62. The return air duct 3 is composed of the first steel plate 4 and the second steel plate 8. The air inside the clean room 2 flows into the return air duct 3, and the desiccant is placed through the drawer 52, and then the drawer 52 is ventilated. The drawer 52 is driven by pulling the handle 51, so that the air inside the return air duct 3 can be better dehumidified to avoid excessive humidity of the air, which causes condensation water to appear on the outside of the dry coil 1 during operation, and the return air of the dry coil 1 provides cooling or heat.

[0031] The above is only a preferred specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can make equivalent substitutions or changes within the technical scope disclosed in the present application according to the technical solution and utility model concept of the present application, which should be covered by the protection scope of the present application.

Claims

1. A clean room dry coil installation structure, comprising a dry coil (1), characterized in that: A fixing mechanism (7) is provided on the outside of the dry coil (1), the fixing mechanism (7) comprising a fixing edge (72), the fixing edge (72) being fixedly connected to the dry coil (1), the fixing edge (72) being internally threadedly connected to a second bolt (71), a mounting mechanism (6) is provided on the outside of the fixing edge (72), the mounting mechanism (6) being horizontally arranged on the top of a return air duct (3), the return air duct (3) being composed of a first steel plate (4) and a second steel plate (8), and having at least one second steel plate (8) arranged obliquely, a dehumidification mechanism (5) being provided on the inside of the return air duct (3), and a clean room (2) being provided on the outside of the return air duct (3).

2. The clean room dry coil installation structure according to claim 1, characterized in that: The mounting mechanism (6) comprises an upper fixing block (61), the upper fixing block (61) being fixedly connected to the first steel plate (4), the internal thread of the upper fixing block (61) being connected to a first bolt (63), the external thread of the first bolt (63) being connected to a lower fixing block (62), and one side of the lower fixing block (62) being fixedly connected to a load-bearing steel frame (64).

3. The clean room dry coil installation structure according to claim 1, characterized in that: The dehumidification mechanism (5) comprises a drawer (52), the drawer (52) being slidably connected to the first steel plate (4), a handle (51) being fixedly connected to the outside of the drawer (52), a ventilation hole being provided at the bottom of the drawer (52), and a desiccant being provided inside the drawer (52).

4. The clean room dry coil installation structure according to claim 1, characterized in that: The first steel plate (4) and the second steel plate (8) are both made of color-coated steel plates.

5. The clean room dry coil installation structure according to claim 1, characterized in that: A ventilation hole is provided on one side of the second steel plate (8).

6. The clean room dry coil installation structure according to claim 1, characterized in that: The joints between the dry coil (1), the fixed edge (72) and the load-bearing steel frame (64) are all coated with sealant.