Measuring equipment for counting electric quantity of electric energy meter

By using a combination of relay circuit and main processing circuit in the measurement equipment for the power meter to move the electricity, the problem of detection of the power consumption accuracy of the power meter under various operating conditions is solved, and the accuracy of the power meter to move the electricity meter and the Accurate measurement of electricity consumption.

CN221946164UActive Publication Date: 2024-11-01DELIXI GROUP INSTRUMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420325444.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-21
Publication Date
2024-11-01
Estimated Expiration
2034-02-21

AI Technical Summary

Technical Problem

The power meter may cause power loss or inaccurate disconnection when storing the power load. The prior art is difficult to detect the accuracy of the power meter under various working conditions.

Method used

Design a measuring device for the power flow of the electric energy meter, including power supply circuit, pulse acquisition circuit, relay circuit and main processing circuit. Through the switching operation of the relay circuit, the power meter and measuring equipment can measure the power consumption parameters simultaneously to ensure the main chip The main processing circuit obtains an accurate number of pulses after initialization, thereby determining whether the power consumption calculated by the power meter is accurate.

Benefits of technology

The accuracy of the power meter is improved, the accuracy of the power consumption is ensured, and the number of pulses is lost due to incomplete initialization is avoided, providing a basis for judging the accuracy of the power meter calculating the power consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221946164U_ABST
    Figure CN221946164U_ABST
Patent Text Reader

Abstract

The utility model provides measuring equipment for counting electric quantity of an electric energy meter. The measuring equipment comprises a power supply circuit, a pulse acquisition circuit, a relay circuit, a display circuit and a main processing circuit. The pulse input end of the pulse acquisition circuit is electrically connected with the pulse port of the electric energy meter. And the input end of the relay circuit is electrically connected with a table body current inlet wire. And before the first duration, the first output end of the relay circuit is electrically connected with the table body current outgoing line. And after a first duration, the first output end of the relay circuit is electrically disconnected with the table body current outgoing line, and the second output end of the relay circuit is electrically connected with the current input end of the electric energy meter. Therefore, the electric energy meter and the measuring equipment can simultaneously measure the electric energy consumption parameters by disconnecting or connecting the current inlet wire of the electric energy meter, so that the measuring equipment can take the pulse number as a reference basis for judging whether the electric energy consumption calculated by the electric energy meter is accurate or not, and the counting accuracy of the electric energy meter is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of electric power metering, and in particular to a device for measuring the amount of electricity in an electric energy meter. Background Art

[0002] The energy meter can measure the energy consumption of the electrical load. Usually, the metering chip in the energy meter can generate the number of pulses according to the sampled current and voltage, and transmit the number of pulses to the main chip in the energy meter. The main chip can calculate the energy consumption of the electrical load based on the proportional relationship between the number of pulses and the energy consumption. Therefore, the energy meter can display the running power to the user according to the energy consumption of the electrical load.

[0003] However, since the power consumption needs to be stored in a non-volatile memory, and the non-volatile memory has a limited storage number, the power meter does not store the power consumption of the power load in real time. Therefore, the power meter may have problems such as power loss or inaccurate reading due to various reasons.

[0004] Therefore, there is an urgent need to design a device that can detect whether the power consumption obtained by the power meter under various working conditions is accurate. Utility Model Content

[0005] The present application provides a device for measuring the amount of electricity consumed by an electric energy meter, which can use the measured number of pulses as a reference for determining whether the amount of electricity consumed calculated by the electric energy meter is accurate, thereby improving the accuracy of the electric energy meter.

[0006] In a first aspect, the present application provides a device for measuring the amount of electricity in an electric energy meter, the measuring device comprising: a power supply circuit, a pulse acquisition circuit, a relay circuit, a display circuit and a main processing circuit.

[0007] The input end of the power supply circuit is used to electrically connect to the platform body voltage, the voltage input end of the electric energy meter is used to electrically connect to the platform body voltage, and the current output end of the electric energy meter is electrically connected to the platform body current output line.

[0008] The first power supply end of the power supply circuit is electrically connected to the power supply end of the relay circuit, and the second power supply end of the power supply circuit is electrically connected to the power supply end of the pulse acquisition circuit, the power supply end of the main processing circuit and the power supply end of the display circuit respectively.

[0009] The pulse input end of the pulse acquisition circuit is electrically connected to the pulse port of the electric energy meter, and the pulse output end of the pulse acquisition circuit is electrically connected to the pulse input end of the main processing circuit.

[0010] The input end of the relay circuit is electrically connected to the platform current inlet line, and the control end of the relay circuit is electrically connected to the first output end and the second output end of the main processing circuit respectively.

[0011] When the platform body applies a platform voltage to the electric energy meter and the measuring device, and the platform body inputs a platform current to the platform body current input line, and before a first period of time, the first output end of the relay circuit is electrically connected to the platform body current output line, and the second output end of the relay circuit is electrically disconnected from the current input end of the electric energy meter.

[0012] After the first time period has passed, the first output end of the relay circuit is electrically disconnected from the current outlet of the platform body, and the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter.

[0013] The signal input terminal of the display circuit is electrically connected to the third output terminal of the main processing circuit.

[0014] The measuring device of the electric energy meter running quantity provided by the present application is that when the platform body applies the platform body voltage to the electric energy meter and the measuring device, and the platform body inputs the platform body current to the platform body current input line, and before the first time length, the first output end of the relay circuit is electrically connected to the platform body current output line, and the second output end of the relay circuit is electrically disconnected from the current input end of the electric energy meter, and the relay circuit can control the output of the platform body current through the platform body current output line. After the first time length, the main chip and the main processing circuit have completed initialization, the first output end of the relay circuit is electrically disconnected from the platform body current output line, and the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter, and the relay circuit can control the input of the platform body current through the current input end of the electric energy meter into the electric energy meter. With the switching operation of the relay circuit, the electric energy meter and the measuring device can measure the electric energy consumption parameters at the same time. After the main chip and the main processing circuit have completed initialization, the metering chip outputs the number of pulses to the main chip and the pulse acquisition circuit respectively. The initialized main processing circuit can obtain an accurate number of pulses, and the initialized main chip can calculate the accurate electric energy consumption. Thereby, the accuracy of the electric energy consumption calculated by the electric energy meter is ensured, and the accuracy of the number of pulses obtained by the measuring device is ensured, so that the measuring device can judge whether the electric energy consumption calculated by the electric energy meter is accurate based on the number of pulses obtained by itself and the electric energy consumption calculated by the electric energy meter, which is conducive to obtaining an electric energy meter with accurate operation.

[0015] In a possible design, the first duration is greater than or equal to a maximum of an initialization duration of a main chip and an initialization duration of a main processing circuit in the electric energy meter.

[0016] Based on this, after the first time period, the main processing circuit and the main chip are initialized. At this time, the first output end of the relay circuit is disconnected from the current output line of the platform, and the second output end of the relay circuit is connected to the current input end of the electric energy meter, ensuring that the platform current can be input into the electric energy meter.

[0017] In one possible design, the first duration is greater than or equal to 0.5 seconds.

[0018] In one possible design, the relay circuit includes: a relay control chip, a first resistor, a second resistor, and a single-pole double-throw relay.

[0019] The first end of the relay control chip and the fourth end of the relay control chip are used to jointly control the movable contact of the single-pole double-throw relay to disconnect from the first fixed contact and connect to the second fixed contact, so that the first output end of the relay circuit is electrically connected to the platform current output line.

[0020] The first end of the relay control chip and the fourth end of the relay control chip are also used to jointly control the movable contact of the single-pole double-throw relay to disconnect from the second fixed contact and connect to the first fixed contact, so that the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter.

[0021] The second terminal of the relay control chip is grounded.

[0022] The third end of the relay control chip is electrically connected to the first end of the first resistor, and the second end of the first resistor is electrically connected to the first output end of the main processing circuit.

[0023] The fifth terminal of the relay control chip is electrically connected to the first power supply terminal of the power supply circuit.

[0024] The sixth terminal of the relay control chip is electrically connected to the first terminal of the second resistor, and the second terminal of the second resistor is electrically connected to the second output terminal of the main processing circuit.

[0025] Based on this, the relay circuit can control the single-pole double-throw relay through the relay control chip, so that the relay circuit controls the body current to be input into the electric energy meter through the current input terminal of the electric energy meter, or the relay circuit controls the body current to be output through the body current output line.

[0026] In one possible design, the main processing circuit includes: an MCU chip and peripheral circuits.

[0027] In one possible design, the peripheral circuit includes: a crystal oscillator circuit, a filter circuit, a power-off detection circuit, a short-circuit clearing circuit, and a programming circuit.

[0028] In a possible design, the display circuit is a four-digit digital tube, which at least includes: a display screen, a transistor, a resistor, and a capacitor.

[0029] Based on this, the display circuit can display the number of pulses, or information related to the number of pulses.

[0030] In a possible design, the pulse input terminal of the pulse acquisition circuit includes a first pulse input terminal and a second pulse input terminal, and the pulse acquisition circuit includes: a current limiting resistor and a first filter capacitor.

[0031] The first pulse input terminal and the second pulse input terminal are electrically connected to the pulse port of the electric energy meter respectively, the first end of the current limiting resistor is electrically connected to the first pulse input terminal, the second end of the current limiting resistor is electrically connected to the second power supply terminal of the power supply circuit, the second pulse input terminal is also grounded, a pulse output terminal of the pulse acquisition circuit is arranged between the first pulse input terminal and the first end of the current limiting resistor, the first end of the first filter capacitor is electrically connected to the pulse output terminal of the pulse acquisition circuit, a first connection point is arranged between the second pulse input terminal and the ground terminal, and the second end of the first filter capacitor is electrically connected to the first connection point.

[0032] Based on this, the pulse acquisition circuit can receive the number of pulses from the electric energy meter and can also send the number of pulses to the main processing circuit.

[0033] In a possible design, the power supply circuit includes at least: an input resistor, a transformer, a rectifier bridge, a linear voltage regulator tube and an output capacitor.

[0034] The input end of the input resistor is electrically connected to the stage voltage, the output end of the input resistor is electrically connected to the primary side of the transformer, the secondary side of the transformer is electrically connected to the input end of the rectifier bridge, the output end of the rectifier bridge is electrically connected to the input end of the linear voltage regulator tube, a first power supply end of the power supply circuit is arranged between the output end of the rectifier bridge and the input end of the linear voltage regulator tube, the first output end of the linear voltage regulator tube is the second power supply end of the power supply circuit, the second output end of the linear voltage regulator tube is grounded, and the output capacitor is electrically connected in parallel between the first output end and the second output end of the linear voltage regulator tube.

[0035] Based on this, the power supply circuit can provide the required power supply voltage to the relay circuit, pulse acquisition circuit, main processing circuit and display circuit respectively, so that the relay circuit, pulse acquisition circuit, main processing circuit and display circuit can work normally.

[0036] In a possible design, the measuring device further includes: a housing and terminals, wherein the housing is used to fix the measuring device, and the terminals are used to connect the measuring device to other devices. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 A schematic diagram of the structure of a device for measuring the running quantity of an electric energy meter according to an embodiment of the present application;

[0038] Figure 2 A schematic diagram of the circuit structure of a relay circuit according to an embodiment of the present application;

[0039] Figure 3 A schematic diagram of the structure of a pulse acquisition circuit according to an embodiment of the present application;

[0040] Figure 4 A schematic diagram of a power supply circuit structure of an embodiment of the present application.

[0041] Description of reference numerals:

[0042] 10——measuring device; 20——electricity meter; 101——power supply circuit; 102——main processing circuit; 103——relay circuit; 104——pulse acquisition circuit; 105——display circuit. DETAILED DESCRIPTION

[0043] In this application, "at least one" means one or more, and "plurality" means two or more. "And / or" describes the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone, where A and B can be singular or plural. The character " / " generally indicates that the associated objects before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single items or plural items. For example, at least one of a, b, or c alone can represent: a, b, c, a and b, a and c, or a, b, and c, where a, b, and c can be single or multiple. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0044] The directions or positional relationships indicated by terms such as "center", "longitudinal", "lateral", "up", "down", "left", "right", "front", and "back" are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present application and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present application.

[0045] The terms "connected" and "connected" should be understood in a broad sense. For example, the "connected" or "connected" of a circuit structure can refer to not only physical connection, but also electrical connection or signal connection. For example, it can be directly connected, that is, physically connected, or indirectly connected through at least one intermediate element, as long as the circuit is connected, or it can be the internal connection of two elements; signal connection can refer to signal connection through a circuit or through a media medium, such as radio waves. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0046] Exemplarily, the present application proposes a device 10 for measuring the amount of electricity in an electric energy meter.

[0047] See also Figure 1 , Figure 1This is a schematic diagram of the structure of a device for measuring the running electricity quantity of an electric energy meter according to an embodiment of the present application. Figure 1 As shown, the measuring device 10 may include: a power supply circuit 101 , a pulse acquisition circuit 104 , a relay circuit 103 , a display circuit 105 and a main processing circuit 102 .

[0048] The input end of the power supply circuit 101 is used to electrically connect to the platform voltage, the voltage input end of the electric energy meter 20 is used to electrically connect to the platform voltage, and the current output end of the electric energy meter 20 is electrically connected to the platform current output line. The first power supply end of the power supply circuit 101 is electrically connected to the power supply end of the relay circuit 103, and the second power supply end of the power supply circuit 101 is electrically connected to the power supply end of the pulse acquisition circuit 104, the power supply end of the main processing circuit 102, and the power supply end of the display circuit 105. The pulse input end of the pulse acquisition circuit 104 is electrically connected to the pulse port of the electric energy meter 20, and the pulse output end of the pulse acquisition circuit 104 is electrically connected to the pulse input end of the main processing circuit 102. The input end of the relay circuit 103 is electrically connected to the platform current input line, and the control end of the relay circuit 103 is electrically connected to the first output end and the second output end of the main processing circuit 102.

[0049] The platform is a work platform for testing, debugging, measuring and verifying electronic equipment or other products. The aforementioned electronic equipment or other products may include: an electric energy meter 20 and a measuring device 10. Thus, the platform can provide the platform voltage and the platform current, etc. to the electric energy meter 20 and the measuring device 10.

[0050] When the platform applies a platform voltage to the electric energy meter 20 and the measuring device, and the platform inputs a platform current to the platform current input line, timing starts from this time. Before the first time period, that is, before the first time period has passed, the first output end of the relay circuit 103 is electrically connected to the platform current output line, and the second output end of the relay circuit 103 is electrically disconnected from the current input end of the electric energy meter 20. After the first time period has passed, the first output end of the relay circuit 103 is electrically disconnected from the platform current output line, and the second output end of the relay circuit 103 is electrically connected to the current input end of the electric energy meter 20.

[0051] After the platform is powered off, the relay returns to its initial state, the first output end of the relay circuit 103 is electrically connected to the platform current output line, and the second output end of the relay circuit 103 is electrically disconnected from the current input end of the electric energy meter 20, waiting for the next test.

[0052] The signal input terminal of the display circuit 105 is electrically connected to the third output terminal of the main processing circuit 102 .

[0053] Figure 1In the figure, the voltage input terminal of the electric energy meter 20 is recorded as 1, the pulse port of the electric energy meter 20 is recorded as 2, the current input terminal of the electric energy meter 20 is recorded as 3, the current output terminal of the electric energy meter 20 is recorded as 4, the input terminal of the power supply circuit 101 is recorded as 1, the first power supply terminal of the power supply circuit 101 is recorded as 2, the second power supply terminal of the power supply circuit 101 is recorded as 3, the power supply terminal of the pulse acquisition circuit 104 is recorded as 1, the pulse input terminal of the pulse acquisition circuit 104 is recorded as 2, the pulse output terminal of the pulse acquisition circuit 104 is recorded as 3, and the power supply terminal of the relay circuit 103 is recorded as is 1, the input terminal of the relay circuit 103 is 2, the control terminal of the relay circuit 103 is 3, the first output terminal of the relay circuit 103 is 4, the second output terminal of the relay circuit 103 is 5, the power supply terminal of the main processing circuit 102 is 1, the pulse input terminal of the main processing circuit 102 is 2, the first output terminal and the second output terminal of the main processing circuit 102 are 3, the third output terminal of the main processing circuit 102 is 4, the power supply terminal of the display circuit 105 is 1, and the signal input terminal of the display circuit 105 is 2.

[0054] The electric energy meter 20 may be a single-phase AC electric energy meter. The electric energy meter 20 may generally include a main chip, a power supply circuit, and a metering chip. The metering chip may transmit the number of pulses to the main chip, and the main chip may calculate the electric energy consumption of the electric load according to the number of pulses, and the power supply circuit may provide working power to the main chip. Thus, the electric energy meter 20 may send the number of pulses to the measuring device 10.

[0055] The number of pulses is the total number of pulse signals output by the metering chip within a set time, and the number of pulses is proportional to the amount of electric energy consumed. For example, 1600imp / kWh means that the metering chip outputs 1600 pulse signals corresponding to 1kWh of electric energy consumption. It can be seen that the number of pulses can be used as a reference for measuring whether the running electric energy of the electric energy meter 20 is accurate.

[0056] The measuring device 10 can be movably or fixedly arranged on the platform through the housing. The measuring device 10 can also be connected to other devices through terminals. The other devices can be calculation devices, which can calculate the power consumption calculated by the power meter 10 and the number of pulses measured by the measuring device 10.

[0057] The power supply circuit 101 can provide the required power supply voltages to the relay circuit 103, the pulse acquisition circuit 104, the main processing circuit 102 and the display circuit 105 respectively, so that the relay circuit 103, the pulse acquisition circuit 104, the main processing circuit 102 and the display circuit 105 can work normally.

[0058] For example, the power supply voltage provided by the power supply circuit 101 to the relay circuit 103 may be 14V, and the power supply voltage provided by the power supply circuit 101 to the pulse acquisition circuit 104, the main processing circuit 102 and the display circuit 105 may be 5V.

[0059] When the power supply circuit provides working power to the main chip, the main chip starts to be initialized.

[0060] When the power supply circuit 101 supplies power supply voltage to the main processing circuit 102 , the main processing circuit 102 starts initialization.

[0061] When the main processing circuit 102 and / or the main chip have not completed initialization, the relay circuit 103 can be used to prevent the main chip from measuring the power consumption parameters of the platform, and the main processing circuit 102 can be used to prevent the power consumption parameters of the platform from being measured.

[0062] That is, before the main chip and / or the main processing circuit 102 are initialized, the electric energy meter 20 and the measuring device 10 may not measure the electric energy consumption parameters of the platform.

[0063] Thus, the loss of pulses during the initialization of the main processing circuit 102 is avoided.

[0064] The power consumption parameters of the platform may include the number of pulses and the power consumption.

[0065] After the main chip and the main processing circuit 102 are initialized, the main chip can measure the power consumption parameters of the platform through the relay circuit 103. At the same time, the main processing circuit 102 can measure the power consumption parameters of the platform.

[0066] That is to say, after the main chip and the main processing circuit 102 are initialized, the electric energy meter 20 and the measuring device 10 can measure the electric energy consumption parameters of the platform at the same time.

[0067] Based on this, through the electrical connection between the pulse input end of the pulse acquisition circuit 104 and the pulse port of the metering chip, the pulse acquisition circuit 104 can obtain the number of pulses from the pulse port of the metering chip, and the pulse acquisition circuit 104 can transmit the number of pulses to the main processing circuit 102. In this way, the main processing circuit 102 will not lose the number of pulses when the initialization is not completed, which is conducive to the measurement device 10 to obtain an accurate number of pulses, and the main chip will not lose the number of pulses when the initialization is not completed, which is conducive to the electric energy meter 20 to calculate and obtain accurate electric energy consumption.

[0068] Furthermore, the main processing circuit 102 may transmit the number of pulses to the display circuit 105 , so that the display circuit 105 displays the number of pulses or information related to the number of pulses.

[0069] The display circuit 105 may include multiple implementations. In some examples, the display circuit 105 may include a four-digit digital tube, which includes at least: a display screen, a triode, a resistor, and a capacitor.

[0070] In this way, the operator can obtain the power consumption of the platform according to the displayed pulse number or the above information. The operator can then compare the power consumption of the platform measured by the measuring device 10 with the power consumption of the platform measured by the power meter 20 to see whether the error is within the set range, and judge whether the movement of the power meter 20 is accurate.

[0071] Alternatively, the measuring device 10 may send the number of pulses to the computing device. The computing device may compare the power consumption of the platform measured by the measuring device 10 with the power consumption of the platform measured by the power meter 20 to determine whether the error is within a set range, so as to determine whether the reading of the power meter 20 is accurate.

[0072] When the error exceeds the set range, the energy consumption measured by the energy meter 20 is inaccurate, that is, the energy meter 20 is inaccurate. When the error is within the set range, the energy consumption measured by the energy meter 20 is relatively accurate, that is, the energy meter 20 is accurate.

[0073] The above error can be set to a smaller value according to the application scenario of the electric energy meter. For example, the error can be set to 0.5%, and the setting range can be (-0.5%, 0.5%). Correspondingly, if the electric energy consumption is 1000 kWh, the electric energy consumption calculated by the electric energy meter is between 995 kWh and 1005 kWh, and the electric energy meter is accurate.

[0074] In addition, the above-mentioned errors may also be displayed on a display of the computing device.

[0075] Therefore, the measuring device 10 can use the measured number of pulses as a reference for determining whether the electric energy consumption calculated by the electric energy meter 20 is accurate.

[0076] In summary, the measuring device 10 can ensure the accuracy of the measured number of pulses, and the specific process is as follows:

[0077] When the platform applies the platform voltage to the electric energy meter 20 and the measuring device 10, and the platform inputs the platform current to the platform current input line, the main chip starts to initialize when the platform voltage is present. The main processing circuit 102 starts to initialize when the platform voltage and the platform current are present, and the main processing circuit 102 starts timing from this point.

[0078] The timings of applying the platform current and the platform voltage are usually set to be simultaneous.

[0079] During the first time period, the first output terminal of the relay circuit 103 is electrically connected to the platform current output line, and the second output terminal of the relay circuit 103 is electrically disconnected from the current input terminal of the electric energy meter 20. Based on this, the relay circuit 103 can control the platform current to be output through the platform current output line, ensuring that the platform current is not input into the electric energy meter 20, so that the electric energy meter 20 and the measuring device 10 will not measure the electric energy consumption parameters of the platform, thereby avoiding the inaccurate number of pulses calculated by the metering chip when the main chip is initialized, and also avoiding the inaccurate number of pulses obtained by the main processing circuit 102 from the metering chip.

[0080] The first duration may be greater than or equal to the maximum of the initialization duration of the main chip in the electric energy meter 20 and the initialization duration of the main processing circuit 102. For example, when the initialization duration of the main chip is 0.5 seconds and the initialization duration of the main processing circuit 102 is 0.4 seconds, the first duration is greater than or equal to 0.5 seconds. Thus, it is effectively ensured that the main chip and the main processing circuit 102 can be initialized after the first duration.

[0081] After the first time period, the main processing circuit 102 and the main chip are initialized. At this time, the first output end of the relay circuit 103 is disconnected from the platform current output line, and the second output end of the relay circuit 103 is connected to the current input end of the electric energy meter 20, ensuring that the platform current can be input into the electric energy meter 20.

[0082] In this way, after the main processing circuit 102 and the main chip are initialized, the electric energy meter 20 and the measuring device 10 can simultaneously measure the electric energy consumption parameters of the platform. For the electric energy meter 20, the metering chip can send the accurate number of pulses to the initialized main chip, so that the main chip can calculate the electric energy consumption of the platform based on the accurate number of pulses, avoiding the problem of losing the number of pulses due to the failure of the main chip to complete the initialization operation. For the measuring device 10, the initialized main processing circuit 102 can obtain the accurate number of pulses from the pulse port of the metering chip, avoiding the problem of losing the number of pulses due to the failure of the main processing circuit 102 to complete the initialization operation.

[0083] When a certain working condition test is completed and the next test condition is switched, the platform is powered off, the single-pole double-throw relay contacts return to their original positions, the first output end of the relay is electrically connected to the platform current output line, and the second output end of the relay is electrically disconnected from the current input end of the electric energy meter. Until the next test platform is powered on, the process of waiting for the first time is repeated. Repeat the above steps until the test is completed.

[0084] Therefore, the measuring device 10 can use the accurate number of pulses as a reference for determining whether the electric energy meter 20 is measuring accurately.

[0085] The measuring device of the electric energy meter running quantity provided by the present application is that when the platform body applies the platform body voltage to the electric energy meter and the measuring device, and the platform body inputs the platform body current to the platform body current input line, and before the first time length, the first output end of the relay circuit is electrically connected to the platform body current output line, and the second output end of the relay circuit is electrically disconnected from the current input end of the electric energy meter, and the relay circuit can control the output of the platform body current through the platform body current output line. After the first time length, the main chip and the main processing circuit have completed initialization, the first output end of the relay circuit is electrically disconnected from the platform body current output line, and the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter, and the relay circuit can control the input of the platform body current through the current input end of the electric energy meter into the electric energy meter. With the switching operation of the relay circuit, the electric energy meter and the measuring device can measure the electric energy consumption parameters at the same time. After the main chip and the main processing circuit have completed initialization, the metering chip outputs the number of pulses to the main chip and the pulse acquisition circuit respectively. The initialized main processing circuit can obtain an accurate number of pulses, and the initialized main chip can calculate the accurate electric energy consumption. Thereby, the accuracy of the electric energy consumption calculated by the electric energy meter is ensured, and the accuracy of the number of pulses obtained by the measuring device is ensured, so that the measuring device can judge whether the electric energy consumption calculated by the electric energy meter is accurate based on the number of pulses obtained by itself and the electric energy consumption calculated by the electric energy meter, which is conducive to obtaining an electric energy meter with accurate operation.

[0086] The relay circuit 103 can be implemented by a single-pole double-throw magnetic latching relay or a single-pole double-throw electromagnetic relay. Figure 2 , taking the relay circuit 103 being implemented by a single-pole double-throw electromagnetic relay as an example, a relay circuit 103 proposed in an embodiment of the present application is described in detail.

[0087] See also Figure 2 , Figure 2 FIG. 1 is a schematic diagram of a circuit structure of a relay circuit according to an embodiment of the present application. Figure 2 As shown, the relay circuit 103 may include: a relay control chip U1, a first resistor R1, a second resistor R2, and a single-pole double-throw relay JDQ.

[0088] The first end of the relay control chip U1 and the fourth end of the relay control chip U1 are used to jointly control the movable contact X of the single-pole double-throw relay JDQ to be disconnected from the first fixed contact Y and connected to the second fixed contact Z, so that the first output end of the relay circuit 103 is electrically connected to the current output line of the platform body. The first end of the relay control chip U1 and the fourth end of the relay control chip U1 are also used to jointly control the movable contact X of the single-pole double-throw relay JDQ to be disconnected from the second fixed contact Z and connected to the first fixed contact Y, so that the second output end of the relay circuit 103 is electrically connected to the current input end of the electric energy meter 20. The second end of the relay control chip U1 is grounded. The third end of the relay control chip U1 is electrically connected to the first end of the first resistor R1, and the second end of the first resistor R1 is electrically connected to the first output end of the main processing circuit 102. The fifth end of the relay control chip U1 is electrically connected to the first power supply end of the power supply circuit 101. The sixth terminal of the relay control chip U1 is electrically connected to the first terminal of the second resistor R2 , and the second terminal of the second resistor R2 is electrically connected to the second output terminal of the main processing circuit 102 .

[0089] Figure 2 In the figure, the first end of the relay control chip U1 is recorded as 1, the second end of the relay control chip U1 is recorded as 2, the third end of the relay control chip U1 is recorded as 3, the fourth end of the relay control chip U1 is recorded as 4, the fifth end of the relay control chip U1 is recorded as 5, the sixth end of the relay control chip U1 is recorded as 6, the first voltage provided by the first power supply end of the power supply circuit 101 is recorded as VHH, the point where the second end of the second resistor R2 is electrically connected to the second output end of the main processing circuit 102 is the first control end of the relay circuit 103, and the first control end of the relay circuit 103 is recorded as REOFF, the point where the second end of the first resistor R1 is electrically connected to the first output end of the main processing circuit 102 is the second control end of the relay circuit 103, and the second control end of the relay circuit 103 is recorded as RELON. The single-pole double-throw relay is denoted as S, the movable contact is denoted as X, the first fixed contact is denoted as Y, the second fixed contact is denoted as Z, the first end of the relay control chip U1 is connected to the first input end JDQ1 of the single-pole double-throw relay, and the fourth end of the relay control chip U1 is connected to the second input end JDQ2 of the single-pole double-throw relay.

[0090] The relay control chip U1 may be an integrated circuit for controlling a single-pole double-throw relay S. The relay control chip U1 may convert the voltage signal output by the main processing circuit 102 into a voltage that may control the single-pole double-throw relay JDQ. Thus, the relay control chip U1 may control the single-pole double-throw relay JDQ to connect to the current output line of the platform or to the current input terminal of the electric energy meter 20 according to the aforementioned voltage.

[0091] The first resistor R1 and the second resistor R2 can limit the current between the relay control chip U1 and the MCU chip to prevent the relay control chip U1 and the MCU chip from being damaged due to excessive current. For example, the first resistor R1 and the second resistor R2 can both be set to 1 kΩ.

[0092] The single-pole double-throw relay JDQ may include a coil, a spring, a movable contact X and two fixed contacts. The two fixed contacts include a first fixed contact Y and a second fixed contact Z.

[0093] The coil is arranged near the first fixed contact Y, and the coil can attract the movable contact X under the principle of electromagnetic induction, so that the movable contact X contacts the first fixed contact Y.

[0094] The spring is disposed near the second fixed contact Z, and the spring can pull the movable contact X so that the movable contact X contacts the second fixed contact Z.

[0095] The movable contact X may be a movable iron sheet, and the coil can attract the movable iron sheet under the action of the electromagnetic induction principle.

[0096] The main processing circuit 102 simultaneously sends a voltage signal to the first control terminal and the second control terminal of the relay circuit 103. Through the voltage signal, the relay control chip U1 outputs a voltage that can control the single-pole double-throw relay JDQ.

[0097] The voltage of the single-pole double-throw relay JDQ is input to both ends of the coil through the first input end JDQ1 and the second input end JDQ2 of the single-pole double-throw relay, and the voltage across the input coil has a certain voltage difference. The voltage difference can control the single-pole double-throw relay JDQ to connect to the current input end of the electric energy meter 20.

[0098] When the relay control chip U1 applies a voltage difference to both ends of the coil, current flows through the coil, and the current generates a magnetic field around the coil. The magnetic field can attract the movable contact X, so that the movable contact X is separated from the contact with the second fixed contact Z, and the movable contact X contacts the first fixed contact Y. In this way, the second output end of the relay circuit 103 is electrically connected to the current input end of the electric energy meter 20, so that the table body current is input into the electric energy meter 20 through the current input end of the electric energy meter 20.

[0099] When the relay control chip U1 does not apply a voltage difference to the two ends of the coil, there is no current flowing in the coil, and no magnetic field can be generated around the coil. The coil does not attract the movable contact X to contact the first fixed contact Y, and the spring can pull the movable contact X to contact the second fixed contact Z. In this way, the first output end of the relay circuit 103 is electrically connected to the platform current output line, so that the platform current is output through the platform current output line, and the platform current is not input into the energy meter 20, and the energy meter 20 and the measuring device 10 will not measure the energy consumption parameters of the platform.

[0100] Therefore, the relay circuit 103 can control the single-pole double-throw relay JDQ through the relay control chip U1, so that the relay circuit 103 controls the body current to be input into the electric energy meter 20 through the current input terminal of the electric energy meter 20, or the relay circuit 103 controls the body current to be output through the body current output line.

[0101] Next, combine Figure 3 , a pulse acquisition circuit 104 proposed in an embodiment of the present application is described in detail.

[0102] See also Figure 3 , Figure 3 FIG. 1 is a schematic diagram of a pulse acquisition circuit structure of an embodiment of the present application. Figure 3 As shown, the pulse input terminal of the pulse acquisition circuit 104 may include a first pulse input terminal P+1 and a second pulse input terminal P-1, and the pulse acquisition circuit 104 may include: a current limiting resistor R3 and a first filtering capacitor C1.

[0103] The first pulse input terminal P+1 and the second pulse input terminal P-1 are electrically connected to the pulse port of the electric energy meter 20 respectively, the first end of the current limiting resistor R3 is electrically connected to the first pulse input terminal P+1, the second end of the current limiting resistor R3 is electrically connected to the second power supply terminal of the power supply circuit 101, the second pulse input terminal P-1 is also grounded, the pulse output terminal MCU_PF of the pulse acquisition circuit 104 is arranged between the first pulse input terminal P+1 and the first end of the current limiting resistor R3, the first end of the first filter capacitor C1 is electrically connected to the pulse output terminal MCU_PF of the pulse acquisition circuit, a first connection point I is arranged between the second pulse input terminal P-1 and the ground terminal, and the second end of the first filter capacitor C1 is electrically connected to the first connection point.

[0104] The current limiting resistor R3 may be a resistor that can limit the current of the second power supply terminal VDD input pulse acquisition circuit 104 to prevent excessive current from damaging components in the main processing circuit 103 .

[0105] The second power supply terminal of the power supply circuit 101 provides a second voltage VDD to the pulse acquisition circuit 104 , and the metering chip outputs a switch signal to the first pulse input terminal P+1 and the second pulse input terminal P−1 of the pulse acquisition circuit 104 .

[0106] When the metering chip outputs a switch signal representing a closed state to the pulse acquisition circuit 104 , the first pulse input terminal P+1 and the second pulse input terminal P−1 are turned on.

[0107] When the metering chip outputs a switch signal representing disconnection to the pulse acquisition circuit 104 , the first pulse input terminal P+1 and the second pulse input terminal P−1 are not conducting.

[0108] In this way, the electric energy meter can control the switch signal, so that the electric energy meter controls the first pulse input terminal P+1 and the second pulse input terminal P-1 to be conductive or non-conductive.

[0109] Since the second pulse input terminal P-1 is grounded, when the first pulse input terminal P+1 and the second pulse input terminal P-1 are turned on, the pulse output terminal MCU_PF connected to the first pulse input terminal P+1 is grounded through the second pulse input terminal P-1, and the pulse output terminal MCU_PF of the pulse acquisition circuit 104 is at a low level.

[0110] When the first pulse input terminal P+1 and the second pulse input terminal P-1 are not conducting, the pulse output terminal MCU_PF of the pulse acquisition circuit 104 is connected to the first terminal of R3, the second terminal of R3 is connected to VDD, and the pulse output terminal MCU_PF of the pulse acquisition circuit 104 is at a high level.

[0111] Therefore, the electric energy meter controls the pulse output terminal MCU_PF of the pulse acquisition circuit 104 to be high level or low level through the output switching signal. The aforementioned low level is a sign of power generation, and the change between the levels can be output to the main processing circuit 102 through the pulse output terminal MCU_PF of the pulse acquisition circuit 104.

[0112] Therefore, the pulse acquisition circuit 104 can receive the number of pulses from the electric energy meter 20 and can also send the number of pulses to the main processing circuit 102 .

[0113] Next, combine Figure 4 , a power supply circuit 101 proposed in an embodiment of the present application is described in detail.

[0114] See also Figure 4 , Figure 4 FIG. 1 is a schematic diagram of a power supply circuit structure of an embodiment of the present application. Figure 4 As shown, the power supply circuit 101 at least includes: an input resistor, a transformer T1, a rectifier bridge BD1, a linear voltage regulator U2 and an output capacitor.

[0115] The input end of the input resistor is electrically connected to the stage voltage, the output end of the input resistor is electrically connected to the primary side of the transformer T1, the secondary side of the transformer T1 is electrically connected to the input end of the rectifier bridge BD1, the output end of the rectifier bridge BD1 is electrically connected to the input end of the linear voltage regulator U2, a first power supply end of the power supply circuit 101 is arranged between the output end of the rectifier bridge BD1 and the input end of the linear voltage regulator U2, the first output end of the linear voltage regulator U2 is the second power supply end of the power supply circuit 101, the second output end of the linear voltage regulator U2 is grounded, and the output capacitor is electrically connected in parallel between the first output end and the second output end of the linear voltage regulator U2.

[0116] Figure 4 In the figure, the input end of the linear voltage regulator tube U2 is marked as 1, the first output end of the linear voltage regulator tube U2 is marked as 2, and the second output end of the linear voltage regulator tube U2 is marked as 3.

[0117] The platform voltage may be a single-phase two-wire voltage, an AC power supply having one phase line and one neutral line outputting the platform voltage. For example, the platform voltage may be 220V.

[0118] The input resistor may include a first input resistor R4 and a second input resistor R5. The first input resistor R4 and the second input resistor R5 may both be adjustable resistors. The first input resistor R4 may be a varistor, and the second input resistor R5 may be a thermistor. The first input resistor R4 and the second input resistor R5 may adjust their own resistance values ​​under special or abnormal circumstances, thereby protecting subsequent circuits.

[0119] The transformer T1 may be composed of a primary coil and a secondary coil. The stage voltage generates a magnetic field through the primary coil, and the transformer T1 changes the stage voltage according to the ratio of the number of turns of the primary coil and the secondary coil. For example, the transformer T1 may step down the stage voltage of 220V to a voltage of 12V to 14V.

[0120] The rectifier bridge BD1 can convert the stepped-down voltage into a DC voltage. The rectifier bridge BD1 is composed of different numbers of diodes, and the number of diodes can be greater than or equal to 4. The four diodes can convert both the negative half-cycle and the positive half-cycle of the stage voltage into a unidirectional voltage. In the rectifier bridge BD1, the four diodes are turned on in turn, and the rectifier bridge BD1 outputs a first voltage VHH.

[0121] The linear voltage regulator U2 can convert the voltage, and the linear voltage regulator U2 outputs the converted voltage. For example, the linear voltage regulator U2 can convert a voltage of 12V to 14V into a voltage of 5V.

[0122] The output capacitor may include one or more capacitors. For example, the output capacitor includes a first output capacitor C4 and a second output capacitor C5. The output capacitor may filter out high-frequency noise of the voltage and improve the signal-to-noise ratio of the power supply circuit 101. In this way, the output capacitor outputs the second voltage VDD.

[0123] The stage voltage is input to the power supply circuit 101, and the stage voltage is stepped down by the transformer T1. The transformer T1 outputs the stepped-down voltage, and the stepped-down voltage is converted into the first voltage VHH through the rectifier bridge BD1. The first voltage VHH is output to the relay circuit 103 through the first power supply terminal of the power supply circuit 101, thereby providing the power supply voltage to the relay circuit 103. The first voltage VHH is also output to the output capacitor through the linear voltage regulator U2. The output capacitor filters the voltage to obtain the second voltage VDD, and then provides the second voltage VDD as the power supply voltage to the pulse acquisition circuit 104, the main processing circuit 102 and the display circuit 105.

[0124] Figure 4 In the embodiment, a second filter capacitor C2 is electrically connected in parallel between the input end of the linear voltage regulator tube U2 and the second output end of the linear voltage regulator tube U2. The second filter capacitor C2 realizes energy storage and filtering through the connection with the linear voltage regulator tube U2.

[0125] Continue to combine Figure 4 The first power supply terminal of the power supply circuit 101 can also be connected to the energy storage capacitor C3. When the SPDT relay is a SPDT magnetic latching relay, the electric energy stored in the energy storage capacitor C3 can ensure that the relay control chip U1 can turn off the SPDT relay.

[0126] Therefore, the power supply circuit 101 can provide the relay circuit 103, the pulse acquisition circuit 104, the main processing circuit 102 and the display circuit 105 with the power supply voltages they need.

[0127] Next, a main processing circuit 102 proposed in an embodiment of the present application is described in detail.

[0128] The main processing circuit 102 may include: a microcontroller unit (MCU) chip and peripheral circuits. The peripheral circuits may include: a crystal oscillator circuit, a filter circuit, a power failure detection circuit, a short circuit clearing circuit and a programming circuit.

[0129] The crystal oscillator circuit can provide accurate clock signal to the MCU chip.

[0130] The filter circuit can eliminate the noise of the MCU chip and improve the anti-interference ability of the MCU chip.

[0131] The short-circuit clearing circuit can clear the detection data after completing a power consumption detection by short-circuiting, so that the measuring equipment can accurately detect the power consumption of the energy meter next time.

[0132] The programming circuit enables the operator to program and debug the MCU chip. For example, the operator can burn the program into the MCU chip through the programming circuit, debug the program in the MCU chip through the programming circuit, and download the data in the MCU chip through the programming circuit.

[0133] The MCU chip can control the switching operation of the relay circuit, so that the energy meter and the measuring device can measure the energy consumption parameters at the same time. At the same time, the MCU chip can receive the number of pulses transmitted by the pulse acquisition circuit 104, and the MCU chip can also transmit the number of pulses to the display circuit 105, so that the display circuit 105 displays the number of pulses or information related to the number of pulses.

[0134] Finally, it should be noted that the above embodiments are only specific implementation methods of the present application, but the protection scope of the present application is not limited thereto, and any changes or substitutions within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A device for measuring the amount of electricity in an electric energy meter. It is characterized in that The measuring device comprises: a power supply circuit, a pulse acquisition circuit, a relay circuit, a display circuit and a main processing circuit; The input end of the power supply circuit is used to electrically connect to the platform voltage, the voltage input end of the electric energy meter is used to electrically connect to the platform voltage, and the current output end of the electric energy meter is electrically connected to the platform current output line; The first power supply end of the power supply circuit is electrically connected to the power supply end of the relay circuit, and the second power supply end of the power supply circuit is electrically connected to the power supply end of the pulse acquisition circuit, the power supply end of the main processing circuit and the power supply end of the display circuit respectively; The pulse input end of the pulse acquisition circuit is electrically connected to the pulse port of the electric energy meter, and the pulse output end of the pulse acquisition circuit is electrically connected to the pulse input end of the main processing circuit; The input end of the relay circuit is electrically connected to the platform current inlet line, and the control end of the relay circuit is electrically connected to the first output end and the second output end of the main processing circuit respectively; When the platform applies the platform voltage to the electric energy meter and the measuring device, and the platform inputs the platform current to the platform current inlet line, and before the first time period, the first output end of the relay circuit is electrically connected to the platform current outlet line, and the second output end of the relay circuit is electrically disconnected from the current input end of the electric energy meter; After the first time period has passed, the first output end of the relay circuit is electrically disconnected from the current outlet of the table body, and the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter; The signal input terminal of the display circuit is electrically connected to the third output terminal of the main processing circuit.

2. The measuring device according to claim 1, It is characterized in that The first duration is greater than or equal to a maximum of an initialization duration of a main chip in the electric energy meter and an initialization duration of the main processing circuit.

3. The measuring device according to claim 2, It is characterized in that The first duration is greater than or equal to 0.5 seconds.

4. The measuring device according to any one of claims 1 to 3, It is characterized in that The relay circuit comprises: a relay control chip, a first resistor, a second resistor, and a single-pole double-throw relay; The first end of the relay control chip and the fourth end of the relay control chip are used to jointly control the movable contact of the single-pole double-throw relay to be disconnected from the first fixed contact and connected to the second fixed contact, so that the first output end of the relay circuit is electrically connected to the current outlet line of the platform body; The first end of the relay control chip and the fourth end of the relay control chip are also used to jointly control the movable contact of the single-pole double-throw relay to be disconnected from the second fixed contact and connected to the first fixed contact, so that the second output end of the relay circuit is electrically connected to the current input end of the electric energy meter; The second terminal of the relay control chip is grounded; The third end of the relay control chip is electrically connected to the first end of the first resistor, and the second end of the first resistor is electrically connected to the first output end of the main processing circuit; The fifth terminal of the relay control chip is electrically connected to the first power supply terminal of the power supply circuit; The sixth end of the relay control chip is electrically connected to the first end of the second resistor, and the second end of the second resistor is electrically connected to the second output end of the main processing circuit.

5. The measuring device according to any one of claims 1 to 3, It is characterized in that The main processing circuit includes: an MCU chip and peripheral circuits.

6. The measuring device according to claim 5, It is characterized in that The peripheral circuit includes: a crystal oscillator circuit, a filter circuit, a power-off detection circuit, a short-circuit clearing circuit and a programming circuit.

7. The measuring device according to any one of claims 1 to 3, It is characterized in that The display circuit is a four-digit digital tube, which at least includes: a display screen, a triode, a resistor and a capacitor.

8. The measuring device according to any one of claims 1 to 3, It is characterized in that The pulse input terminal of the pulse acquisition circuit includes a first pulse input terminal and a second pulse input terminal, and the pulse acquisition circuit includes: a current limiting resistor and a first filter capacitor; The first pulse input terminal and the second pulse input terminal are electrically connected to the pulse port of the electric energy meter respectively, the first end of the current limiting resistor is electrically connected to the first pulse input terminal, the second end of the current limiting resistor is electrically connected to the second power supply terminal of the power supply circuit, the second pulse input terminal is also grounded, the pulse output terminal of the pulse acquisition circuit is arranged between the first pulse input terminal and the first end of the current limiting resistor, the first end of the first filter capacitor is electrically connected to the pulse output terminal of the pulse acquisition circuit, a first connection point is arranged between the second pulse input terminal and the ground terminal, and the second end of the first filter capacitor is electrically connected to the first connection point.

9. The measuring device according to any one of claims 1 to 3, It is characterized in that The power supply circuit at least includes: an input resistor, a transformer, a rectifier bridge, a linear voltage regulator tube and an output capacitor; The input end of the input resistor is electrically connected to the stage voltage, the output end of the input resistor is electrically connected to the primary side of the transformer, the secondary side of the transformer is electrically connected to the input end of the rectifier bridge, the output end of the rectifier bridge is electrically connected to the input end of the linear voltage regulator tube, the first power supply end of the power supply circuit is arranged between the output end of the rectifier bridge and the input end of the linear voltage regulator tube, the first output end of the linear voltage regulator tube is the second power supply end of the power supply circuit, the second output end of the linear voltage regulator tube is grounded, and the output capacitor is electrically connected in parallel between the first output end and the second output end of the linear voltage regulator tube.

10. The measuring device according to any one of claims 1 to 3, It is characterized in that The measuring device further comprises: a housing and terminals, wherein the housing is used to fix the measuring device, and the terminals are used to connect the measuring device to other devices.