Temporary steel pipe supporting and converting device for penetrating floor system structure
By designing a temporary steel pipe support conversion device, using large-size steel pipes and flanges, and combining with the long screw to achieve elevation adjustment, the problem of temporary support in the construction of steel roof stents is solved, avoiding the reservation of large-size holes and improving construction efficiency and structural integrity.
Patent Information
- Application Number
- CN202323346460.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-08
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-08
AI Technical Summary
During the steel roof squad construction in indoor sports venues, the installation and removal of temporary steel support leads to low construction efficiency, and large-sized holes need to be reserved directly through the prefabricated stands plan, which affects the visual and load-bearing capacity of the structure and increases the post-processing workload.
Design a temporary steel pipe support conversion device, including upper and lower segment structures and connection devices, and consists of large-size steel pipes and flanges, improve support performance through through holes and trapezoidal stiffening ribs, and achieve elevation adjustment and fixation through through-length screws. Avoid leaving large-sized holes.
The device does not need to reserve large-sized holes, which reduces the impact on the existing structure, simplifies construction processes, reduces the post-processing workload, ensures the original state of the structure, and improves construction efficiency.
Smart Images

Figure CN221973117U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building structures, in particular to a temporary steel pipe support conversion device for penetrating a floor structure. Background Art
[0002] As people's living standards improve, the public's attention to sports events is increasing, and many indoor sports venues have been built at home and abroad. Most of these sports venues use frame structures, with stepped prefabricated stands indoors and large-span steel truss roofs on the top. Due to the constraints of the construction process, during the construction of the venue, the steel truss roof should be installed after the prefabricated stand panels are installed. Combined with the installation process of the steel truss, temporary steel supports are required to assist the installation of the steel truss during the construction of the steel roof truss. The temporary steel supports generally use large-sized steel pipe column supports or lattice steel supports. Due to the large range of the steel roof truss and the large number of steel supports, the steel supports will inevitably fall within the range of the prefabricated stands. For this reason, in actual projects, the prefabricated stands in the affected area are generally installed after the installation, and the prefabricated stands are directly penetrated.
[0003] For the scheme of installing prefabricated stands after the temporary steel supports are removed, it is an indoor closed installation operation. The lifting equipment will be limited by the existing roof elevation, which will greatly reduce the installation efficiency, thus affecting the construction period and being extremely unfavorable to the on-site construction organization. For the scheme of directly penetrating the prefabricated stands, since the temporary steel supports are larger in size, the outer diameter is generally greater than 600mm, so it is necessary to reserve larger holes on the prefabricated stand board components, which will have an adverse effect on the clear water appearance, bearing capacity and integrity of the prefabricated stand boards. In addition, after the steel supports are removed, the reserved holes need to be processed for the second time, which increases the later work.
[0004] In summary, both the scheme of installing prefabricated stands from behind and the scheme of directly penetrating prefabricated stands have certain limitations. Utility Model Content
[0005] The main purpose of the utility model is to provide a temporary steel pipe support conversion device for penetrating a floor structure, which can effectively solve the problems in the background technology.
[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0007] A temporary steel pipe support conversion device for penetrating a floor structure comprises a No. 2 flange and a No. 3 flange, wherein a lower segment structure is installed at the upper end of the No. 2 flange, a No. 1 flange is installed at the upper end of the lower segment structure, an upper segment structure is installed at the lower end of the No. 3 flange, a No. 4 flange is installed at the lower end of the upper segment structure, and a connecting device is commonly installed at the corresponding ends of the No. 1 flange and the No. 4 flange.
[0008] Preferably, the upper segment structure includes an upper segment large-size steel pipe, a group of No. 1 segment stiffening ribs are installed on the upper and lower outer surfaces of the upper segment large-size steel pipe, the upper segment large-size steel pipe is installed between the No. 3 flange and the No. 4 flange, the No. 3 flange has a group of No. 3 through holes on the upper end, and the No. 4 flange has a group of No. 4 through holes on the upper end. The upper segment structure and the lower segment are both composed of large-size steel pipes and flanges, the upper and lower flanges are welded at both ends of the large-size steel pipe, and multiple through holes are evenly arranged on the outer periphery of the upper and lower flanges, and trapezoidal stiffening ribs are arranged on both sides of each through hole, one side of the stiffening ribs is connected to the upper and lower flanges, and the other side is connected to the outer wall of the large-size steel pipe, thereby improving the supporting performance of the device.
[0009] Preferably, the lower segment structure includes a lower segment large-size steel pipe, and a group of No. 2 segment stiffening ribs are installed on the upper and lower parts of the outer surface of the lower segment large-size steel pipe. The lower segment large-size steel pipe is installed between a No. 1 flange and a No. 2 flange, and a group of No. 1 through holes are opened at the upper end of the No. 1 flange, and a group of No. 2 through holes are opened at the upper end of the No. 2 flange.
[0010] Preferably, the connecting device comprises a through-length screw, and there are four through-length screws, two upper mounting nuts are installed on the upper part of the outer surface of the four through-length screws, and two lower mounting nuts are installed on the lower part of the outer surface of the four through-length screws, and the four through-length screws are installed between the No. 1 flange and the No. 4 flange. The middle part of the through-length screw is a uniform thread, and the two ends are rectangular ends. Two pairs of nuts and pads are provided near the two ends of the screw. The two ends of the through-length screw respectively penetrate the flange through hole of the upper segment and the flange through hole of the lower segment, and the flange is tightened by the mounting nut on the through-length screw to fix the elevation position of the upper segment and the lower segment. In addition, the elevation adjustment between the upper and lower segments is achieved by rotating the relative positions of the two pairs of nuts on the connecting screw.
[0011] Preferably, the stiffening rib of segment No. 1 is trapezoidal in shape.
[0012] Preferably, the four through-length screws are symmetrically distributed in pairs.
[0013] Compared with the prior art, the utility model has the following beneficial effects:
[0014] 1. The upper segment structure and the lower segment are composed of large-size steel pipes and flanges. The upper and lower flanges are welded at both ends of the large-size steel pipes. Multiple through holes are evenly arranged on the outer periphery of the upper and lower flanges. Trapezoidal stiffening ribs are arranged on both sides of each through hole. One side of the stiffening rib is connected to the upper and lower flanges, and the other side is connected to the outer wall of the large-size steel pipe. The through-length screw on the connecting device has a uniform thread in the middle and rectangular ends at both ends. Two pairs of nuts and gaskets are arranged near the two ends of the screw. The two ends of the through-length screw pass through the flange through hole of the upper segment and the flange through hole of the lower segment respectively, and pass through the installation on the through-length screw. Nuts are installed to tighten the flange to fix the elevation positions of the upper and lower sections. In addition, the elevation adjustment between the upper and lower sections is achieved by rotating the relative positions of the two pairs of nuts on the connecting screws. Compared with the prior art, the present application does not require the reservation of large-sized holes in the existing structure or the existing stands. It is only necessary to reserve a few small-sized holes at the corresponding positions through which the connecting screws can pass. Since the diameter of the full-length screw is small and the corresponding hole size is small, the impact of the hole on the existing structure and the stands can be minimized to the greatest extent. After the later demolition, the small-sized holes can be handled relatively simply without increasing the workload.
[0015] 2. This application scheme is combined with traditional steel pipe supports and can be used in scenarios where temporary steel supports are set up in subsequent processes during the structural construction stage and need to penetrate or affect existing structures. This application scheme can effectively avoid the problem of reserving large-sized openings when penetrating existing structures, reduce the impact between processes, ensure the original state of existing structures, and simplify temporary support operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the overall structure of a temporary steel pipe support conversion device for penetrating a floor structure according to the utility model;
[0017] Figure 2 This is a schematic diagram of the overall structure of an upper segment structure of a temporary steel pipe support conversion device for penetrating a floor structure according to the utility model;
[0018] Figure 3 This is a schematic diagram of the overall structure of the lower segment structure of a temporary steel pipe support conversion device for penetrating a floor structure according to the utility model;
[0019] Figure 4 The utility model is a schematic diagram of the overall structure of a connection device for a temporary steel pipe support conversion device that penetrates a floor structure.
[0020] In the figure: 1. upper segment structure; 2. lower segment structure; 3. connecting device; 4. flange No. 1; 5. flange No. 2; 6. flange No. 3; 7. flange No. 4; 10. large-size steel pipe of upper segment; 11. through hole No. 3; 12. through hole No. 4; 13. stiffening rib of segment No. 1; 20. large-size steel pipe of lower segment; 21. through hole No. 1; 22. through hole No. 2; 23. stiffening rib of segment No. 2; 30. full-length screw; 31. upper mounting nut; 32. lower mounting nut. DETAILED DESCRIPTION
[0021] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0022] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0023] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0024] like Figure 1-4 As shown, a temporary steel pipe support conversion device for penetrating a floor structure includes a No. 2 flange 5 and a No. 3 flange 6, a lower segment structure 2 is installed on the upper end of the No. 2 flange 5, a No. 1 flange 4 is installed on the upper end of the lower segment structure 2, an upper segment structure 1 is installed on the lower end of the No. 3 flange 6, a No. 4 flange 7 is installed on the lower end of the upper segment structure 1, and a connecting device 3 is installed on the corresponding ends of the No. 1 flange 4 and the No. 4 flange 7.
[0025] The upper segment structure 1 includes an upper segment large-size steel pipe 10, a group of No. 1 segment stiffening ribs 13 are installed on the upper and lower outer surfaces of the upper segment large-size steel pipe 10, and the upper segment large-size steel pipe 10 is installed between the No. 3 flange 6 and the No. 4 flange 7. The No. 3 flange 6 has a group of No. 3 through holes 11 at the upper end, and the No. 4 flange 7 has a group of No. 4 through holes 12 at the upper end; the No. 1 segment stiffening rib 13 is trapezoidal in shape. The upper segment structure 1 and the lower segment structure 2 are both composed of large-size steel pipes and flanges. The upper and lower flanges are welded at both ends of the large-size steel pipes, and multiple through holes are evenly arranged on the outer periphery of the upper and lower flanges. Trapezoidal stiffening ribs are arranged on both sides of each through hole. One side of the stiffening rib is connected to the upper and lower flanges, and the other side is connected to the outer wall of the large-size steel pipe, thereby improving the supporting performance of the device.
[0026] The lower segment structure 2 includes a lower segment large-size steel pipe 20, and a group of No. 2 segment stiffening ribs 23 are installed on the upper and lower parts of the outer surface of the lower segment large-size steel pipe 20. The lower segment large-size steel pipe 20 is installed between the No. 1 flange 4 and the No. 2 flange 5. A group of No. 1 through holes 21 are opened at the upper end of the No. 1 flange 4, and a group of No. 2 through holes 22 are opened at the upper end of the No. 2 flange 5.
[0027] The connecting device 3 includes a through-length screw 30, and there are four through-length screws 30. Two upper mounting nuts 31 are installed on the upper part of the outer surface of the four through-length screws 30, and two lower mounting nuts 32 are installed on the lower part of the outer surface of the four through-length screws 30. The four through-length screws 30 are installed between the No. 1 flange 4 and the No. 4 flange 7; the four through-length screws 30 are symmetrically distributed in pairs. The middle part of the through-length screw 30 is a uniform thread, and the two ends are rectangular ends. Two pairs of nuts and pads are provided near the two ends of the screw. The two ends of the through-length screw 30 respectively penetrate the flange through hole of the upper segment and the flange through hole of the lower segment, and the flange is tightened by the mounting nut on the through-length screw 30 to fix the elevation position of the upper segment and the lower segment. In addition, the elevation adjustment between the upper and lower segments is achieved by rotating the relative positions of the two pairs of nuts on the connecting screw.
[0028] It should be noted that the utility model is a temporary steel pipe support conversion device for penetrating a floor structure, wherein the upper segment structure 1 and the lower segment structure 2 are both composed of a large-size steel pipe and a flange, and the upper and lower flanges are respectively welded and connected at both ends of the large-size steel pipe, and a plurality of through holes are evenly arranged on the outer periphery of the upper and lower flanges, and trapezoidal stiffening ribs are arranged on both sides of each through hole, and one side of the stiffening rib is connected to the upper and lower flanges, and the other side is connected to the outer wall of the large-size steel pipe, and the through-length screw 30 on the connecting device 3 has a uniform thread in the middle and rectangular ends at both ends, and two pairs of nuts and gaskets are arranged near the two ends of the screw, and the two ends of the through-length screw 30 respectively penetrate the flange through hole of the upper segment and the lower segment. The flange of the segment is penetrated through the hole, and the flange is tightened by the mounting nut on the through-length screw 30 to fix the elevation position of the upper segment and the lower segment. In addition, the elevation adjustment between the upper and lower segments is achieved by rotating the relative positions of the two pairs of nuts on the connecting screw. Compared with the prior art, the present application does not need to reserve large-sized holes in the existing structure or the existing stands. It is only necessary to reserve several small-sized holes at the corresponding positions through which the connecting screws can be penetrated. Since the diameter of the through-length screw 30 is small and the corresponding hole size is small, the impact of the hole on the existing structure and the stands can be minimized to the greatest extent. After the later demolition, the small-sized hole processing is also relatively simple and will not increase too much workload.
[0029] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A temporary steel pipe support conversion device for penetrating a floor structure, comprising a second flange (5) and a third flange (6), characterized in that: The upper end of the No. 2 flange (5) is mounted with a lower segment structure (2), the upper end of the lower segment structure (2) is mounted with a No. 1 flange (4), the lower end of the No. 3 flange (6) is mounted with an upper segment structure (1), the lower end of the upper segment structure (1) is mounted with a No. 4 flange (7), and the corresponding ends of the No. 1 flange (4) and the No. 4 flange (7) are jointly mounted with a connecting device (3).
2. A temporary steel pipe support conversion device for penetrating a floor structure according to claim 1, characterized in that: The upper segment structure (1) comprises an upper segment large-size steel pipe (10), a group of No. 1 segment stiffening ribs (13) are installed on the upper and lower parts of the outer surface of the upper segment large-size steel pipe (10), the upper segment large-size steel pipe (10) is installed between a No. 3 flange (6) and a No. 4 flange (7), a group of No. 3 through holes (11) are opened at the upper end of the No. 3 flange (6), and a group of No. 4 through holes (12) are opened at the upper end of the No. 4 flange (7).
3. A temporary steel pipe support conversion device for penetrating a floor structure according to claim 1, characterized in that: The lower segment structure (2) comprises a lower segment large-size steel pipe (20), a group of No. 2 segment stiffening ribs (23) are installed on the upper and lower parts of the outer surface of the lower segment large-size steel pipe (20), the lower segment large-size steel pipe (20) is installed between a No. 1 flange (4) and a No. 2 flange (5), a group of No. 1 through holes (21) are opened at the upper end of the No. 1 flange (4), and a group of No. 2 through holes (22) are opened at the upper end of the No. 2 flange (5).
4. A temporary steel pipe support conversion device for penetrating a floor structure according to claim 1, characterized in that: The connecting device (3) comprises a through-length screw rod (30), wherein four through-length screw rods (30) are provided, two upper mounting nuts (31) are mounted on the upper portions of the outer surfaces of the four through-length screw rods (30), two lower mounting nuts (32) are mounted on the lower portions of the outer surfaces of the four through-length screw rods (30), and the four through-length screw rods (30) are mounted between a No. 1 flange (4) and a No. 4 flange (7).
5. A temporary steel pipe support conversion device for penetrating a floor structure according to claim 2, characterized in that: The first segment stiffening rib (13) is trapezoidal in shape.
6. A temporary steel pipe support conversion device for penetrating a floor structure according to claim 4, characterized in that: The four through-length screws (30) are symmetrically distributed in pairs.