Foldable temporary support beam trimmer
By designing a foldable beam support, the problem of fixed integrated beam supports being unable to be flipped and placed was solved, enabling rapid installation and disassembly and improving construction efficiency.
Patent Information
- Application Number
- CN202420432110.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-06
AI Technical Summary
The existing beam support is a fixed integrated structure that cannot be flipped and placed at the rear of the tunneling machine's cutting arm, which means that it must be installed, disassembled, and lifted every time it is used, which is time-consuming and labor-intensive.
A foldable temporary support beam was designed, which consists of two short arms connected by a rotating pin and a fixed pin. It can be folded, flipped, and placed at the rear of the tunneling machine's cutting arm without disassembly or lifting.
It enables rapid installation and disassembly of the beam support, reducing operation time and labor intensity, and improving construction efficiency.
Smart Images

Figure CN221973515U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of temporary support of tunnel boring machines, and in particular relates to a foldable temporary support beam support device. Background Art
[0002] The comprehensive excavation of coal mine tunnels uses a comprehensive excavation machine for cutting. After the cutting is completed, a beam support is set up from the front of the cutting arm of the tunnel boring machine to the cutting head of the tunnel boring machine. The beam support is used to support the π-shaped beam for temporary support. The existing beam support is a fixed integrated structure. Due to the height of the tunnel, the fixed integrated beam support cannot be placed at the rear of the cutting arm by flipping, and the tunnel boring machine cannot cut without disassembling the beam support. Therefore, it must be installed every time temporary support is performed, and then disassembled after the temporary support is used, which is time-consuming and labor-intensive. Utility Model Content
[0003] The utility model aims to solve the problem that the existing beam support device adopts a fixed integrated structure. Due to the influence of the length of the beam support device and the height of the tunnel, the integrated beam support device cannot be flipped and placed on the cutting arm of the unit, and each time it is used, it must be installed, disassembled and carried, which is time-consuming and laborious.
[0004] The utility model provides the following technical solutions: a foldable temporary support beam support device, comprising a support arm and a drag beam groove; the support arm comprises a plurality of short arms, the plurality of short arms are connected by hinged joints, the first short arm is connected to a tunnel boring machine body, the drag beam groove is installed on the last short arm, after the plurality of short arms are unfolded, they cross the tunnel boring machine cutting arm to cantilever and support the drag beam groove, the last short arm is extended to above the tunnel boring machine cutting head, and after the plurality of short arms are folded, they are retracted into the rear of the tunnel boring machine cutting arm.
[0005] Furthermore, the articulated joint includes a fixed pin, a rotating pin, two outer splints, two inner splints, a first pin hole and a second pin hole. The two outer splints are fixed on the rear short arm of two adjacent short arms, and the two inner splints are fixed on the front short arm of two adjacent short arms. The two inner splints extend between the two outer splints. The first pin hole and the second pin hole pass through the two outer splints and the two inner splints. The rotating pin is inserted into the second pin hole, and the fixed pin is inserted into the first pin hole. After the fixed pin is pulled out, the rear short arm folds back to the front short arm around the rotating pin.
[0006] Furthermore, a beam support base is fixed on the tunnel boring machine body, an end of the first short arm is hinged to the beam support base, and the first short arm is placed on the tunnel boring machine body to provide supporting force.
[0007] Furthermore, the beam support base includes a bottom plate, a rotating shaft and two ear plates. The bottom plate is fixed on the tunnel boring machine body. The two ear plates are vertically fixed on the bottom plate. The end of the first short arm is a pointed end, which extends between the two ear plates. A connecting hole is provided at the tip of the end, and the rotating shaft passes through the ear plate and the connecting hole.
[0008] Furthermore, the supporting arm is composed of two short arms.
[0009] Furthermore, the short arm is an H-shaped steel.
[0010] Compared with the prior art, the advantages of the present invention are:
[0011] The utility model provides a foldable temporary supporting beam support device, which adopts a two-section structure. The two short arms are connected by a rotating pin and a fixed pin. After the fixed pin is removed, the beam support device can be folded and turned around the rotating pin, and then placed at the rear of the cutting arm of the tunnel boring machine without disassembly and lifting. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the structure of the utility model;
[0013] Figure 2 This is a schematic diagram of the installation of the outer plywood;
[0014] Figure 3 This is a schematic diagram of the inner plywood installation;
[0015] Figure 4 It is a structural diagram of an articulated joint;
[0016] Figure 5 It is a structural schematic diagram of the beam support base.
[0017] In the figure: 1-support arm; 1.1-short arm; 1.2-connecting hole; 2-articulated joint; 2.1-outer splint; 2.2-inner splint; 2.3-first pin hole; 2.4-second pin hole; 2.5-fixed pin shaft; 2.6-rotating pin shaft; 3-drag beam groove; 4-beam support base; 4.1-bottom plate; 4.2-ear plate; 4.3-rotating shaft; 5-tunnel boring machine body; 6-tunnel boring machine cutting head; 7-tunnel boring machine cutting arm. DETAILED DESCRIPTION
[0018] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0019] like Figure 1 As shown: a foldable temporary support beam support device, including a support arm 1 and a drag beam groove 3; the support arm 1 includes a plurality of short arms 1.1, and the plurality of short arms 1.1 are connected by an articulated joint 2, the first short arm 1.1 is connected to a tunnel boring machine body 5, and the drag beam groove 3 is installed on the last short arm 1.1, and the plurality of short arms 1.1 are unfolded to cross the tunnel boring machine cutting arm 7 to cantilever and support the drag beam groove 3, and the last short arm 1.1 is extended to above the tunnel boring machine cutting head 6, and the plurality of short arms 1.1 are folded and retracted into the rear of the tunnel boring machine cutting arm 7.
[0020] like Figure 2 , Figure 3 , Figure 4 As shown: the articulated joint 2 includes a fixed pin 2.5, a rotating pin 2.6, two outer splints 2.1, two inner splints 2.2, a first pin hole 2.3 and a second pin hole 2.4. The two outer splints 2.1 are fixed on the rear short arm 1.1 of two adjacent short arms 1.1, and the two inner splints 2.2 are fixed on the front short arm 1.1 of two adjacent short arms 1.1. The two inner splints 2.2 extend between the two outer splints 2.1, and the first pin hole 2.3 and the second pin hole 2.4 penetrate the two outer splints 2.1 and the two inner splints 2.2. The rotating pin 2.6 is inserted into the second pin hole 2.4, and the fixed pin 2.5 is inserted into the first pin hole 2.3. After the fixed pin 2.5 is pulled out, the rear short arm 1.1 is folded back to the front short arm 1.1 around the rotating pin 2.6.
[0021] The fixed pin 2.5 and the rotating pin 2.6 are bolts.
[0022] A beam support base 4 is fixed on the tunnel boring machine body 5, and an end of the first short arm 1.1 is hinged to the beam support base 4. The first short arm 1.1 is placed on the tunnel boring machine body 5 to provide supporting force.
[0023] like Figure 5 As shown: the beam support base 4 includes a bottom plate 4.1, a rotating shaft 4.3 and two ear plates 4.2. The bottom plate 4.1 is fixed on the tunnel boring machine body 5. The two ear plates 4.2 are vertically fixed on the bottom plate 4.1. The end of the first short arm 1.1 is a pointed end. The end of the first short arm 1.1 extends between the two ear plates 4.2. The tip of the end is provided with a connecting hole 1.2. The rotating shaft 4.3 passes through the ear plate 4.2 and the connecting hole 1.2.
[0024] The supporting arm 1 is composed of two short arms 1.1.
[0025] The short arm 1.1 is an H-shaped steel.
[0026] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A foldable temporary support beam support, characterized in that: The invention comprises a support arm (1) and a drag beam groove (3); the support arm (1) comprises a plurality of short arms (1.1), the plurality of short arms (1.1) are connected to each other via an articulated joint (2), the first short arm (1.1) is connected to a tunnel boring machine body (5), the drag beam groove (3) is installed on the last short arm (1.1), the plurality of short arms (1.1) are unfolded to cross over a tunnel boring machine cutting arm (7) to cantilever and support the drag beam groove (3), the last short arm (1.1) is extended to above a tunnel boring machine cutting head (6), and the plurality of short arms (1.1) are folded and stored in the rear of the tunnel boring machine cutting arm (7).
2. A foldable temporary support beam support device according to claim 1, characterized in that: The articulated joint (2) comprises a fixed pin shaft (2.5), a rotating pin shaft (2.6), two outer clamping plates (2.1), two inner clamping plates (2.2), a first pin hole (2.3) and a second pin hole (2.4), wherein the two outer clamping plates (2.1) are fixed on the rear short arm (1.1) of two adjacent short arms (1.1), the two inner clamping plates (2.2) are fixed on the front short arm (1.1) of the two adjacent short arms (1.1), and the two inner clamping plates are fixed on the rear short arm (1.1) of the two adjacent short arms (1.1). (2.2) extends between the two outer clamping plates (2.1), the first pin hole (2.3) and the second pin hole (2.4) penetrate the two outer clamping plates (2.1) and the two inner clamping plates (2.2), the rotating pin shaft (2.6) is inserted into the second pin hole (2.4), the fixed pin shaft (2.5) is inserted into the first pin hole (2.3), and after the fixed pin shaft (2.5) is pulled out, the rear short arm (1.1) is folded back to the front short arm (1.1) around the rotating pin shaft (2.6).
3. A foldable temporary support beam support according to claim 1 or 2, characterized in that: A beam support base (4) is fixed on the tunnel boring machine body (5), the end of the first short arm (1.1) is hinged to the beam support base (4), and the first short arm (1.1) is placed on the tunnel boring machine body (5) to provide supporting force.
4. A foldable temporary support beam support device according to claim 3, characterized in that: The beam support base (4) comprises a bottom plate (4.1), a rotating shaft (4.3) and two ear plates (4.2); the bottom plate (4.1) is fixed on a tunnel boring machine body (5); the two ear plates (4.2) are vertically fixed on the bottom plate (4.1); the end of the first short arm (1.1) is a pointed end; the end of the first short arm (1.1) extends between the two ear plates (4.2); a connecting hole (1.2) is provided at the tip of the end; and the rotating shaft (4.3) passes through the ear plate (4.2) and the connecting hole (1.2).
5. The foldable temporary support beam support device according to claim 1, characterized in that: The support arm (1) is composed of two short arms (1.1).
6. The foldable temporary support beam support device according to claim 1, characterized in that: The short arm (1.1) is an H-shaped steel.