Sliding rail structure of lifting type debris flow blocking device

Through the sliding rail structure and lift control device of the lifting mudslide blocking device, the problem of difficulty in dredging after full silt in the existing fixed barrier dam is solved, and the rapid dredging and barrier function recovery in the mudslide ditch is achieved, which improves the management efficiency and Security.

CN221989232UInactive Publication Date: 2024-11-12GEOLOGICAL & NATURAL DISASTER PREVENTION & CONTROL INST GANSU ACADEMY OF SCI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421081018.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-09-28
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing fixed barrier dam loses its barrier function after being silted in the mudslide channel, making it difficult to achieve rapid dredging and re-blocking, affecting the effect of mudslide control.

Method used

Design a lifting mudslide blocking device, which uses the slide rail structure to make the blocking plate slide up and down, and is equipped with lifting control device and elastic materials to achieve rapid lifting and dredging of the blocking plate, and keep the slide rail groove unobstructed through water pipes. to ensure the stability and reliability of the barrier plate.

Benefits of technology

It realizes rapid dredging after blocking mudslide, restores the barrier function, reduces the difficulty of dredging, extends the service life of the device, and improves the management efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221989232U_ABST
    Figure CN221989232U_ABST
Patent Text Reader

Abstract

The utility model discloses a slide rail structure of a lifting type debris flow blocking device, which comprises slide rails arranged on two side walls of a debris flow channel along the cross section of the debris flow channel, the slide rails are arranged in slide rail grooves, and the slide rail structure is characterized in that elastic sealing skins are respectively and fixedly arranged on two sides of a notch at the upper end of each slide rail groove. The sliding rail groove can be protected, and blocking caused by stone entering is avoided. Meanwhile, the elastic sealing leather does not affect the vertical sliding of the blocking plate.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] This application is a divisional application of the patent "A lifting and lowering debris flow blocking device" with application number 202322652201.7 and application date 2023-09-28. Technical Field

[0002] The utility model relates to the technical field of debris flow control, in particular to a sliding rail structure of a lifting type debris flow blocking device. Background Art

[0003] Debris flow refers to a special torrent of solid materials such as mud, sand, stones and boulders caused by precipitation (rainstorm, glacier, snowmelt) in valleys or hillsides. It is a disastrous geological phenomenon. Debris flow is characterized by suddenness, fast flow rate, large flow, large material capacity and strong destructive power. Debris flow often destroys transportation facilities such as roads and railways and even villages and towns, causing huge losses.

[0004] Setting up a retaining dam in a debris flow channel is a conventional method for debris flow control, especially setting up a retaining dam structure in the channel in the flow area at the middle and rear end of the debris flow, which can intercept and dissipate the debris flow and guide it to complete accumulation quickly. It prevents disorderly scouring and accumulation in the downstream accumulation area, causing damage to the buildings on both sides of the channel. For example, the patent CN207211097U applied for by the applicant discloses a structure of an energy dissipation threshold for debris flow prevention and control; and CN201710359515.4 disclosed an over-flow debris flow retaining dam and dam group, etc., are all of this type of structure.

[0005] The existing fixed retaining dams set up in debris flow channels will lose their retaining function after the retaining dams are full of silt. However, debris flow is a seasonal disaster. Before the source control of the debris flow source area is achieved, debris flow channels often occur multiple times in the same season. Therefore, the existing fixed retaining dam structure is usually difficult to achieve a second interception. If it is to be restored to use, it needs to be desilted in time, but the structure of the retaining dam itself will hinder the desilting work and is not conducive to the desilting.

[0006] Therefore, how to provide a debris flow blocking device that can more conveniently achieve rapid silt removal and restore its blocking function has become a problem that needs to be considered and solved by those skilled in the art. Utility Model Content

[0007] In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is: how to provide a lifting type debris flow blocking device and its slide rail structure which can more conveniently realize rapid silt removal and restore its blocking function.

[0008] In order to solve the above technical problems, the utility model adopts the following technical solutions:

[0009] A lifting type debris flow blocking device includes a blocking plate arranged as a whole along the cross-section of a debris flow channel, characterized in that the blocking plate is composed of two pieces and is arranged opposite to each other on the left and right sides, and the relatively outer side of the blocking plate can be slidably matched up and down on the slide rails arranged on the side walls on both sides of the debris flow channel, and the two blocking plates on the side walls on both sides of the debris flow channel are respectively provided with a lifting control device.

[0010] In this way, the baffle can be located at the lower end of the slide rail at ordinary times. When a debris flow occurs, the baffle can be used to intercept and dissipate energy, so that the debris flow can be quickly deposited. After a debris flow occurs, the baffle can be lifted up by relying on the lifting control device. The accumulated silt can be quickly desilted or slowly dispersed and dissolved under the action of the channel water flow, so that its blocking function can be restored. When the lifting control device fails due to a debris flow channel with deep accumulation or strong bonding force, the baffle body can be easily disassembled and removed, and then desilted and reused.

[0011] Furthermore, the inner sides of the retaining plates are opposite to each other and are butt joint surfaces. After the retaining plates slide to the lower end of the slide rails, the butt joint surfaces of the two retaining plates can butt joint with each other.

[0012] In this way, the interception effect can be better achieved.

[0013] Furthermore, a docking structure is provided on the docking surface of the baffle plate, and the docking structure is a plug-in protrusion protruding from the docking surface, or a plug-in groove that can match the plug-in protrusion.

[0014] In this way, when the two baffle plates are butt-jointed, the plug-in protrusion is inserted into the plug-in groove, so that the two baffle plates can be better butt-jointed into a whole, thereby improving the interception effect.

[0015] Furthermore, the bottoms of the lower end surfaces of the two baffles (adjacent positions) have drainage culverts formed by being recessed upwards.

[0016] In this way, when there is no debris flow and the baffle is located at the lower end of the slide rail, it is also possible to facilitate the drainage of channel water to avoid accumulation.

[0017] Furthermore, the lower halves of the butt-jointed sides of the two baffle plates are made of elastic material.

[0018] In this way, after the two baffles are connected, the lower part of the middle area is made of elastic material. In this way, when a debris flow occurs, it will rely on its elasticity to be washed away by the debris flow, producing an elastic flow discharge and energy dissipation effect, slowing down the impact of the debris flow on the baffle, and avoiding blocking the ditch and forming a barrier lake when the debris flow is too large.

[0019] Furthermore, the elastic material is a rubber material, which has the characteristics of low cost and reliable elasticity.

[0020] Furthermore, elastic metal strips are vertically embedded in the elastic material. The elastic metal strips are arranged horizontally at intervals. The upper ends of the elastic metal strips are fixed to the baffle body. The flexibility of the elastic metal strips increases gradually from top to bottom.

[0021] In this way, the setting of the elastic metal strip not only provides better support and elastic force for the elastic material, but also makes the elastic force of the elastic material area gradually increase from bottom to top. In this way, when the debris flow is small and the impact force is small, the range of the elastic material being opened is small, but when the debris flow is large and the impact force increases, the range of the elastic material area being opened will increase accordingly. The area where the elastic material is opened and discharged can be automatically adjusted to match the impact force of the debris flow. The stability of the baffle itself is greatly improved. In addition, during installation, the installation and fixation of the elastic material can also be achieved by relying on the connection between the upper end of the elastic metal strip and the baffle body (which can be welded or injection molded or cast as one body), which is convenient and simplified assembly.

[0022] Furthermore, the slide rail is installed in the slide rail groove, and a roller is arranged on the outer lower side of the baffle plate and cooperates with the slide rail.

[0023] In this way, the stability and smoothness of sliding can be better ensured.

[0024] Furthermore, a piece of elastic sealing skin is fixedly arranged on both sides of the groove at the upper end of the slide rail groove.

[0025] In this way, the slide rail groove can be protected to prevent stones from entering and causing blockage. At the same time, the elastic sealing skin does not affect the up and down sliding of the baffle plate.

[0026] Furthermore, the elastic sealing skin is made of rubber material, which has low cost and stable elasticity.

[0027] Furthermore, a gap is left in the middle of the two elastic sealing skins on one side, and a row of elastic fine brushes are extended outward from the ends of the two elastic sealing sheets on one side, and the front ends of the elastic fine brushes are staggered to form a closure.

[0028] In this way, the elastic fine brush at the front end of the elastic sealing skin completes the sealing, which is not only more conducive to breaking the seal when the baffle plate slides up and down so that it does not affect the sliding. What is more important is that the elastic fine brushes are staggered to seal the guide rail groove, which can ensure that large particles of mud and gravel cannot enter, but running water and fine mud and sand can enter from the fine brushes, which will not only not block the rail, but will lubricate the rail, which is conducive to the up and down sliding of the baffle plate. Combined with the water spraying effect of the water pipe buried in the slide rail groove. In this way, whether before or after the debris flow occurs, the sliding reliability of the baffle plate in the slide groove can be better guaranteed. In this way, when the debris flow hits, even if part of the debris flow passes over the baffle plate and moves downward, it will not cause the slide rail groove to be blocked. During implementation, the elastic fine brush is composed of a plurality of long columnar elastic bodies that are assembled in a bundle and arranged in one or more rows. The material can be made of rubber, metal, elastic plastic and other materials.

[0029] Furthermore, a water pipe is buried in the inner wall of the slide rail groove along the length direction, and a water inlet joint for connecting to a water source is arranged at the upper end of the water pipe. A water outlet is also arranged on the inner wall of the slide rail groove and connected to the water pipe, and the water outlet end of the water outlet is arranged obliquely downward.

[0030] In this way, the water pipe can flush the silt that enters the slide rail groove to ensure the stability of the slide rail. In particular, dredging requires a certain amount of time. After dredging, the silt that enters the slide rail groove may have settled and dried, affecting the normal operation of the slide rail. At this time, the silt in the slide rail groove can be moistened by spraying water through the water pipe, because the unique sealing structure at the upper end of the slide rail groove can ensure that the silt that settles in the slide rail groove is relatively fine, and it can quickly form a slurry after spraying water, which no longer affects the lowering of the baffle. In this way, under the premise of ensuring the smooth sliding of the slide rail, there is no need to set an additional auxiliary support matching structure between the lower end of the baffle and the slide rail groove. The lower end of the baffle is in the shape of a straight plate with a width smaller than the slide rail groove and is directly plugged into the slide rail groove to press the roller on the guide rail. The roller and the guide rail can be matched with a convex wheel or a concave wheel, so that it does not restrict the baffle from being lifted up from the slide rail groove. In this way, the baffle plate can be supported and maintained by the elastic sealing skin on both sides of the baffle plate, and a gap is left between the slide rail groove. Therefore, it is only necessary to maintain the slide rail groove at a certain depth, usually 10-30cm, to ensure the stability and reliability of the sliding fit of the baffle plate in the slide rail groove, and it is very convenient to lift the baffle plate to the upper end of the slide rail groove and directly take it out of the slide rail groove to complete the disassembly.

[0031] Furthermore, a water pipe is buried in the upper part of the inner side walls on both sides of the slide rail groove, and multiple water outlets on the two water pipes are arranged at intervals and staggered front to back.

[0032] In this way, when the water pipe is used to flush the sediment, it can better avoid the formation of a dead zone on one side of the water pipe. More importantly, when the debris flow stops and the baffle needs to be pulled up out of the bottom of the channel, the water pipes on both sides can be used to lubricate both sides of the baffle located in the slide rail groove at the same time, ensuring that the lubrication effect on both sides of the baffle is consistent and the force is stable during the pulling process. The baffle can be pulled up more smoothly.

[0033] Furthermore, a prefabricated fixed retaining wall protruding upward is provided on the downstream side of the lower half of the slide rail groove along the edge of the slide rail groove.

[0034] In this way, the prefabricated fixed retaining wall can provide sufficient support for the sliding retaining plate, ensuring sufficient stability in the process of blocking the debris flow.

[0035] Furthermore, the lifting control device includes a winch installed on the upper end of the side wall of the debris flow channel, and the drum at the output end of the winch is connected to the baffle plate through a pull rope.

[0036] In this way, the winch output power can be relied on to control the pull rope to pull the baffle plate upwards. When the baffle plate needs to be controlled downwards, the winch releases the pull rope and performs traction, and the baffle plate can slide down along the slide rail under the action of its own weight. Therefore, it has the advantages of simple structure, convenient control, stable and reliable operation.

[0037] Furthermore, auxiliary traction devices are provided on both sides of the upper part of the slide rail, and the auxiliary traction devices include fixed piles fixed on the side walls of both sides of the debris flow channel, and also include an elastic traction rope with one end connected to the fixed piles and the other end connected to the side of the baffle.

[0038] In this way, the stability of the baffle during the lowering process can be better maintained by relying on the traction ropes to assist traction on both sides.

[0039] During implementation, one end of the pull rope and the traction rope connected to the baffle plate is tied to the pull ear on the baffle plate, so that the baffle plate can be further quickly disassembled after being pulled out of the bottom of the channel.

[0040] Furthermore, it also includes a control center, one end of which is connected to the rainfall monitoring system, and the other end of which is connected to the winch.

[0041] In this way, when the rainfall is not large, the baffle can be folded up on the slope to allow the water to flow smoothly. When the rainfall is about to reach the starting amount of the debris flow, the rainfall monitoring system sends a signal to the control center, and the control center sends a signal to the winch (and the jack), and the winch lowers the baffle (at the same time, the jack extends to support the baffle), forming a stable baffle. This control is more convenient and intelligent. Of course, during implementation, the baffle can also be kept in a lowered state at ordinary times, and after the debris flow is intercepted, it can be raised again to facilitate dredging. During implementation, multiple baffles are arranged at intervals along the length of the debris flow channel. In this way, the graded interception and step-by-step energy dissipation of the debris flow can be achieved, which can better improve the interception effect of the debris flow and dissipate its impact energy.

[0042] In summary, the utility model can more conveniently realize rapid dredging of the debris flow channel after the debris flow is intercepted, so as to restore its blocking function. The device has the advantages of being able to automatically close according to the rainfall, facilitating the subsequent dredging, increasing the use efficiency, extending the effective service life, being detachable and reusable, and reducing the cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 This is a schematic diagram of the structure of a specific implementation of the utility model, in which the baffle plate is in a raised state.

[0044] Figure 2 It is a structural schematic diagram of a specific implementation manner of the utility model, in which the baffle plate is in a dropped state.

[0045] Figure 3 yes Figure 1 Cross-sectional view of a separate rail groove section.

[0046] Figure 4 yes Figure 3 Schematic diagram of the structure after the slide rail groove is disassembled and the baffle plate is removed. DETAILED DESCRIPTION

[0047] The present invention will be further described in detail below in conjunction with specific implementation methods.

[0048] Best practice: See Figure 1-4 A lifting debris flow blocking device includes a blocking plate 1 which is arranged along the cross section of a debris flow channel as a whole. The blocking plate 1 is characterized in that the blocking plate 1 is composed of two pieces and is arranged opposite to each other on the left and right sides. The relatively outer side of the blocking plate can be slidably matched up and down on the slide rails 2 arranged on the side walls of both sides of the debris flow channel. The two corresponding blocking plates 1 on the side walls of both sides of the debris flow channel are also respectively provided with a lifting control device.

[0049] In this way, the baffle can be located at the lower end of the slide rail at ordinary times. When a debris flow occurs, the baffle can be used to intercept and dissipate energy, so that the debris flow can be quickly deposited. After a debris flow occurs, the baffle can be lifted up by relying on the lifting control device. The accumulated silt can be quickly desilted or slowly dispersed and dissolved under the action of the channel water flow, so that its blocking function can be restored. When the lifting control device fails due to a debris flow channel with deep accumulation or strong bonding force, the baffle body can be easily disassembled and removed, and then desilted and reused.

[0050] The inner sides of the retaining plates 1 are opposite to each other and are butt joint surfaces. After the retaining plates slide to the lower ends of the slide rails 2, the butt joint surfaces of the two retaining plates can butt joint with each other.

[0051] In this way, the interception effect can be better achieved.

[0052] Wherein, a docking structure is arranged on the docking surface of the baffle plate, and the docking structure is a plug-in protrusion 4 protruding from the docking surface, or a plug-in groove 3 that can match the plug-in protrusion.

[0053] In this way, when the two baffle plates are butt-jointed, the plug-in protrusion is inserted into the plug-in groove, so that the two baffle plates can be better butt-jointed into a whole, thereby improving the interception effect.

[0054] There is a drainage culvert 17 formed by an upward depression at the adjacent positions of the bottom of the lower end surfaces of the two baffle plates 1 .

[0055] In this way, when there is no debris flow and the baffle is located at the lower end of the slide rail, it is also possible to facilitate the drainage of channel water to avoid accumulation.

[0056] The lower halves of the butt joint sides of the two baffle plates are made of elastic material 8 .

[0057] In this way, after the two baffles are connected, the lower part of the middle area is made of elastic material. In this way, when a debris flow occurs, it will rely on its elasticity to be washed away by the debris flow, producing an elastic flow discharge and energy dissipation effect, slowing down the impact of the debris flow on the baffle, and avoiding blocking the ditch and forming a barrier lake when the debris flow is too large.

[0058] The elastic material is a rubber material, which has the characteristics of low cost and reliable elasticity.

[0059] Among them, elastic metal strips 16 are vertically embedded inside the elastic material 8. The elastic metal strips 16 are multiple and arranged at intervals in the horizontal direction. The upper ends of the elastic metal strips are fixed to the baffle body, and the flexibility of the elastic metal strips gradually increases from top to bottom.

[0060] In this way, the setting of the elastic metal strip not only provides better support and elastic force for the elastic material, but also makes the elastic force of the elastic material area gradually increase from bottom to top. In this way, when the debris flow is small and the impact force is small, the range of the elastic material being opened is small, but when the debris flow is large and the impact force increases, the range of the elastic material area being opened will increase accordingly. The area where the elastic material is opened and discharged can be automatically adjusted to match the impact force of the debris flow. The stability of the baffle itself is greatly improved. In addition, during installation, the installation and fixation of the elastic material can also be achieved by relying on the connection between the upper end of the elastic metal strip and the baffle body (which can be welded or injection molded or cast as one body), which is convenient and simplified assembly.

[0061] Disclosed here, the utility model is also equivalent to disclosing a baffle plate structure for blocking debris flow, and its basic structural scheme is that it includes a baffle plate that is in the shape of an inverted right-angled trapezoidal plate as a whole, one side of the right angle of the baffle plate is a vertical docking side, and the other side is a roller installation side that is inclined downward, and a roller is installed on the roller installation side. In this way, the baffle plates of this structure are convenient for individual production and processing, and can be installed in pairs to form the above-mentioned lifting type debris flow blocking device, so as to achieve lifting type interception of debris flow and facilitate dredging after interception. Furthermore, the docking structure, drainage culvert, elastic material structure, and pull ears on the baffle plate can all be used as a scheme for further structural improvement of the baffle plate, and will not be repeated here.

[0062] The slide rail 2 is installed in the slide rail groove 5 , and a roller 6 is provided on the outer lower side of the baffle plate 1 and matched on the slide rail 2 .

[0063] In this way, the stability and smoothness of sliding can be better ensured.

[0064] Wherein, an elastic sealing skin 18 is fixedly arranged on both sides of the upper end notch of the slide rail groove 5 .

[0065] In this way, the slide rail groove can be protected to prevent stones from entering and causing blockage. At the same time, the elastic sealing skin does not affect the up and down sliding of the baffle plate.

[0066] The elastic sealing skin 18 is made of rubber material, which has low cost and stable elasticity.

[0067] There is a gap in the middle of the two elastic sealing skins 18 on opposite sides, and a row of elastic fine brushes 19 are extended outward from the ends of the two elastic sealing sheets on opposite sides, and the front ends of the elastic fine brushes are staggered to form a seal.

[0068] In this way, the elastic fine brush at the front end of the elastic sealing skin completes the sealing, which is not only more conducive to breaking the seal when the baffle plate slides up and down so that it does not affect the sliding. What is more important is that the elastic fine brushes are staggered to seal the guide rail groove, which can ensure that large particles of mud and gravel cannot enter, but running water and fine mud and sand can enter from the fine brushes, which will not only not block the rail, but will lubricate the rail, which is conducive to the up and down sliding of the baffle plate. Combined with the water spraying effect of the water pipe buried in the slide rail groove. In this way, whether before or after the debris flow occurs, the sliding reliability of the baffle plate in the slide groove can be better guaranteed. In this way, when the debris flow hits, even if part of the debris flow passes over the baffle plate and moves downward, it will not cause the slide rail groove to be blocked. During implementation, the elastic fine brush is composed of a plurality of long columnar elastic bodies that are assembled in a bundle and arranged in one or more rows. The material can be made of rubber, metal, elastic plastic and other materials.

[0069] Among them, a water pipe 20 is buried in the inner wall of the slide rail groove along the length direction, and a water inlet joint for connecting to a water source is arranged at the upper end of the water pipe. A water outlet 21 is also arranged on the inner wall of the slide rail groove and connected to the water pipe 20, and the water outlet end of the water outlet is arranged obliquely downward.

[0070] In this way, the water pipe can flush the silt that enters the slide rail groove to ensure the stability of the slide rail. In particular, dredging requires a certain amount of time. After dredging, the silt that enters the slide rail groove may have settled and dried, affecting the normal operation of the slide rail. At this time, the silt in the slide rail groove can be moistened by spraying water through the water pipe, because the unique sealing structure at the upper end of the slide rail groove can ensure that the silt that settles in the slide rail groove is relatively fine, and it can quickly form a slurry after spraying water, which no longer affects the lowering of the baffle. In this way, under the premise of ensuring the smooth sliding of the slide rail, there is no need to set an additional auxiliary support matching structure between the lower end of the baffle and the slide rail groove. The lower end of the baffle is in the shape of a straight plate with a width smaller than the slide rail groove and is directly plugged into the slide rail groove to press the roller on the guide rail. The roller and the guide rail can be matched with a convex wheel or a concave wheel, so that it does not restrict the baffle from being lifted up from the slide rail groove. In this way, the baffle plate can be supported and maintained by the elastic sealing skin on both sides of the baffle plate, and a gap is left between the slide rail groove. Therefore, it is only necessary to maintain the slide rail groove at a certain depth, usually 10-30cm, to ensure the stability and reliability of the sliding fit of the baffle plate in the slide rail groove, and it is very convenient to lift the baffle plate to the upper end of the slide rail groove and directly take it out of the slide rail groove to complete the disassembly.

[0071] A water pipe 20 is buried in the upper part of the inner side walls on both sides of the slide rail groove, and a plurality of water outlets 21 on the two water pipes are arranged at intervals and staggered front to back.

[0072] In this way, when the water pipe is used to flush the sediment, it can better avoid the formation of a dead zone on one side of the water pipe. More importantly, when the debris flow stops and the baffle needs to be pulled up out of the bottom of the channel, the water pipes on both sides can be used to lubricate both sides of the baffle located in the slide rail groove at the same time, ensuring that the lubrication effect on both sides of the baffle is consistent and the force is stable during the pulling process. The baffle can be pulled up more smoothly.

[0073] Wherein, a prefabricated fixed retaining wall 7 protruding upward is arranged on the downstream side of the lower half of the slide rail groove 5 along the edge of the slide rail groove.

[0074] In this way, the prefabricated fixed retaining wall can provide sufficient support for the sliding retaining plate, ensuring sufficient stability in the process of blocking the debris flow.

[0075] Disclosed here, the utility model is also equivalent to disclosing a slide rail groove structure for installation and cooperation of a debris flow baffle plate, and its basic structural scheme is that the slide rail groove is arranged on the side wall of the debris flow channel along the cross-sectional direction, and a slide rail for cooperating with the roller below the debris flow baffle plate is installed in the slide rail groove, and an elastic sealing skin is fixedly arranged on both sides of the notch at the upper end of the slide rail groove. In this way, the slide rail groove can not only realize the sliding cooperation of the debris flow baffle plate, but also can well protect the slide rail groove to prevent stones from entering and causing blockage. At the same time, the elastic sealing skin can form support for both sides of the lower end of the debris flow baffle plate, so that it keeps a distance from the side wall of the slide rail groove, making it more convenient for the baffle plate to slide up and down. Furthermore, the elastic fine brush on the elastic sealing skin, the water pipe buried in the inner side wall of the slide rail groove, and the prefabricated fixed retaining wall arranged at the lower end of the slide rail groove can all be used as a scheme for further structural improvement of the slide rail groove, which will not be repeated here.

[0076] The lifting control device comprises a winch 9 installed at the upper end of the side wall of the debris flow channel, and the drum at the output end of the winch 9 is connected to the baffle plate 1 through a pull rope 10.

[0077] In this way, the winch output power can be relied on to control the pull rope to pull the baffle plate upwards. When the baffle plate needs to be controlled downwards, the winch releases the pull rope and performs traction, and the baffle plate can slide down along the slide rail under the action of its own weight. Therefore, it has the advantages of simple structure, convenient control, stable and reliable operation.

[0078] Auxiliary traction devices are also provided on both sides of the upper part of the slide rail, which include fixed piles 11 fixed on the side walls of the debris flow channel, and an elastic traction rope 12 with one end connected to the fixed piles and the other end connected to the side of the baffle.

[0079] In this way, the stability of the baffle during the lowering process can be better maintained by relying on the traction ropes to assist traction on both sides.

[0080] During implementation, one end of the pull rope and the traction rope connected to the baffle plate is tied to the pull ear on the baffle plate, so that the baffle plate can be further quickly disassembled after being pulled out of the bottom of the channel.

[0081] The control center 13 is also included, one end of the control center is connected to the rainfall monitoring system 14, and the other end is connected to the winch.

[0082] In this way, when the rainfall is not large, the baffle can be folded up on the slope to allow the water to flow smoothly. When the rainfall is about to reach the starting amount of the debris flow, the rainfall monitoring system sends a signal to the control center, and the control center sends a signal to the winch (and the jack), and the winch lowers the baffle (at the same time, the jack extends out to support the baffle), forming a stable baffle. This control is more convenient and intelligent. Of course, during implementation, the baffle can also be kept in a lowered state at ordinary times, and after the debris flow is intercepted, it can be raised again to facilitate dredging. In addition, during implementation, multiple baffles are arranged at intervals along the length of the debris flow channel. In this way, the graded interception and step-by-step energy dissipation of the debris flow can be achieved, which can better improve the interception effect of the debris flow and dissipate its impact energy.

Claims

1. A slide rail structure of a lifting type debris flow blocking device, comprising slide rails arranged on the side walls of both sides of the debris flow channel along the cross section of the debris flow channel, the slide rails being installed in the slide rail grooves, characterized in that: A piece of elastic sealing skin is fixedly arranged on both sides of the notch at the upper end of the slide rail groove.

2. The slide rail structure of the lifting type debris flow blocking device according to claim 1, characterized in that: The elastic sealing skin is made of rubber material.

3. The slide rail structure of the lifting type debris flow blocking device according to claim 1, characterized in that: A gap is left in the middle of the two elastic sealing skins on the opposite side, and a row of elastic fine brushes are respectively extended outwards at the ends of the two elastic sealing sheets on the opposite side, and the front ends of the elastic fine brushes are staggered to form a closure.

4. The slide rail structure of the lifting type debris flow blocking device according to claim 3, characterized in that: The elastic fine brush is composed of a plurality of long columnar elastic bodies which are assembled in a bundle and arranged in one row or multiple rows.

5. The slide rail structure of the lifting type debris flow blocking device according to claim 3, characterized in that: The material of the elastic fine brush is rubber, metal or elastic plastic.

6. The slide rail structure of the lifting type debris flow blocking device according to claim 1, characterized in that: A water pipe is also buried in the inner wall of the slide rail groove along the length direction, and a water inlet joint for connecting to a water source is arranged at the upper end of the water pipe. A water outlet is also arranged on the inner wall of the slide rail groove and connected to the water pipe, and the water outlet end of the water outlet is arranged obliquely downward.

7. The slide rail structure of the lifting type debris flow blocking device according to claim 6, characterized in that: The depth of the slide rail groove is 10-30cm.

8. The slide rail structure of the lifting type debris flow blocking device according to claim 6, characterized in that: A water pipe is buried in the upper part of the inner side walls on both sides of the slide rail groove, and a plurality of water outlets on the two water pipes are arranged at intervals and staggered front to back.

9. The slide rail structure of the lifting type debris flow blocking device according to claim 6, characterized in that: A prefabricated fixed retaining wall protruding upward is arranged on the downstream side of the lower half of the slide rail groove along the edge of the slide rail groove.