Bean gravel conveyor for TBM (tunnel boring machine)

By combining a hydraulic cylinder-driven gate and a lateral lifting device, the problem of unstable gravel transfer in TBM equipment was solved, achieving stable feeding and safe conveying, and reducing material waste and construction costs.

CN222006628UActive Publication Date: 2024-11-15CHINA RAILWAY POWER CONSTR HEAVY EQUIP MFG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420798113.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-17
Publication Date
2024-11-15
Estimated Expiration
2034-04-17

AI Technical Summary

Technical Problem

Existing TBM equipment has an unstable discharge rate during the transfer of pea gravel, which is prone to spillage. In addition, the overturning transfer bin is heavy and poses a safety hazard, resulting in material waste and increased construction costs.

Method used

The feeding of pea gravel is controlled by a hydraulic cylinder-driven gate. Stable conveying is achieved through lateral movement and lifting devices to avoid overturning of the transfer bin. The conveying device is used to feed the gravel at a uniform speed. Combined with flexible corrugated baffles and partitions to form a storage hopper, the feeding stability and safety are ensured.

Benefits of technology

This method enables stable conveying of gravel, prevents material spillage, reduces construction costs, and improves construction safety and work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222006628U_ABST
    Figure CN222006628U_ABST
Patent Text Reader

Abstract

The utility model relates to a pea gravel conveyor for a TBM, and belongs to the technical field of tunnel engineering. The transverse moving device is installed on a rack of a TBM trailer, the lifting device is installed on the transverse moving device and connected to the transfer bin, the transfer bin is supported on the trailer through supporting legs, a discharging port is formed in the bottom of the transfer bin, sliding grooves are formed in the two sides of the discharging port, flashboards are installed in the sliding grooves in a sliding mode, and the first hydraulic oil cylinder is installed on the trailer through a support. The first hydraulic oil cylinder is in transmission connection with the flashboard, the conveying device is installed on the trailer, and the front end of the conveying device is in butt joint below a discharge port of the transfer bin. The bottom of the transfer bin drives the flashboard to open and discharge through the first hydraulic oil cylinder, the stable discharge rate is effectively guaranteed, pea gravel is prevented from scattering from the two sides of the conveying device, a storage hopper does not need to be installed at the front end of the conveying device, materials are saved, and cost is reduced. And in the discharging process of the transfer bin, the speed is constant, the stability is good, and the construction safety can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tunnel engineering, and in particular relates to a pea gravel conveyor for TBM. Background Art

[0002] In long-distance, full-section slightly weathered granite strata, it is difficult for shield machines to excavate and the excavation progress is slow. The current solution is to change the slightly weathered strata to mining method blasting, and construct initial support and guide platform to form an empty push section, and then drive the shield machine to empty push along the empty push section and assemble the pipe segments. This construction method not only shortens the construction period but also saves construction costs.

[0003] Generally speaking, after the segments are assembled, there will be a certain gap between the segments and the primary support structure. In order to prevent the gap from causing deformation, misalignment and leakage of the segments, pea gravel needs to be sprayed into the gap. In the prior art, the transportation of pea gravel on TBM is achieved by flipping the transfer bin. During the flipping of the transfer bin, the discharge rate of pea gravel is unstable, and the material is easily scattered, resulting in material waste. During the flipping of the transfer bin, the transfer bin is heavy and unbalanced, which can easily cause danger. Summary of the invention

[0004] In order to overcome the problems in the background technology of unloading by flipping the transfer bin, the bean gravel discharge rate is unstable during the flipping of the transfer bin, the material is easily scattered, resulting in material waste, and the transfer bin is heavy and unbalanced during the flipping of the transfer bin, which is easy to cause danger. The utility model provides a bean gravel conveyor for TBM; the bottom of the transfer bin drives the gate plate to open and discharge the material through the first hydraulic cylinder, which effectively ensures the stability of the discharge rate and prevents the bean gravel from being scattered from both sides of the conveying device. There is no need to install a storage hopper at the front end of the conveying device, which is beneficial to saving materials and reducing costs; there is no need to flip the transfer bin, and the transfer bin has a uniform speed and good stability during the discharge process, which is beneficial to ensuring construction safety.

[0005] To achieve the above-mentioned purpose, the utility model is implemented through the following technical scheme: a bean gravel conveyor for TBM mainly comprises a transverse movement device 1, a lifting device 2, a transfer bin 3, a first hydraulic cylinder 4, and a conveying device 5. The transverse movement device 1 is installed on the frame of the TBM trailer, the lifting device 2 is installed on the transverse movement device 1, the lifting device 2 is connected to the transfer bin 3, the transfer bin 3 is supported on the trailer by legs 34, a discharge port 31 is provided at the bottom of the transfer bin 3, slide grooves 32 are provided on both sides of the discharge port 31, and gate plates 33 are slidably installed in the slide grooves 32. The first hydraulic cylinder 4 is installed on the trailer through a support, the first hydraulic cylinder 4 is transmission-connected to the gate plate 33, the conveying device 5 is installed on the trailer, the front end of the conveying device 5 is docked below the discharge port 31 of the transfer bin 3, and the end of the conveying device 5 is connected to the storage bin of the bean gravel feeding device.

[0006] Furthermore, the transverse movement device 1 includes a fixed frame 11, a sliding frame 12, and a second hydraulic cylinder 13. The fixed frame 11 is fixedly installed on the frame of the TBM trailer. First slide rails 14 are provided on the inner sides of both ends of the fixed frame 11. Both ends of the sliding frame 12 can be slidably installed in the first slide rails 14. The second hydraulic cylinder 13 is installed on one side of the fixed frame 11, and the sliding frame 12 is transmission-connected to the second hydraulic cylinder 13; the lifting device 2 is installed on the sliding frame 12.

[0007] Furthermore, the lifting device 2 includes a slider 21, a third hydraulic cylinder 22, a pulley 23, and a traction chain 24. A second slide rail 15 is provided on the inner side of the sliding frame 12. Both ends of the slider 21 can be slidably installed in the second slide rail 15. The slider 21 and the sliding frame 12 are connected to each other through the third hydraulic cylinder 22. The pulley 23 is installed at both ends of the sliding frame 12. One end of the traction chain 24 is connected to the slider 21. The traction chain 24 is connected to the transfer warehouse 3 after being wrapped around the pulley 23.

[0008] Furthermore, a hook 25 is provided at the bottom end of the traction chain 24 , and double earrings 26 connected to the hook 25 are provided at both ends of the transfer bin 3 .

[0009] Furthermore, the transfer bin 3 has a plurality of discharge ports 31 evenly arranged at the bottom along the length direction, the spacing between the discharge ports 31 is greater than twice the length of the discharge ports 31 , and the gate plate 33 is evenly provided with through holes matching the discharge ports 31 .

[0010] Furthermore, fixed support seats 6 for supporting the transfer bin 3 are installed on both sides of the conveying device 5 , and the fixed support seats 6 are at the same height as the conveying device 5 .

[0011] Furthermore, a limiting groove 61 for limiting the support leg 34 of the transfer bin 3 is provided on the top of the fixed support seat 6, and the limiting groove 61 is connected to the support leg 34 by inserting a pin shaft.

[0012] Furthermore, the conveying device 5 includes a bracket 51, a rotating shaft 52, a drive roller, a conveyor belt 54, a flexible corrugated baffle 55, and a partition 56. The bracket 51 is installed on a trailer, and the conveyor belt 54 is installed on the bracket 51 through the drive roller and the rotating shaft 52. The conveyor belt 54 includes a horizontal conveying section and a lifting section. The flexible corrugated baffle 55 is installed on both sides of the conveyor belt 54. The partition 56 is evenly and laterally installed on the conveyor belt 54. A storage hopper is formed between the flexible corrugated baffle 55 and the partition 56.

[0013] Furthermore, the rotating shaft 52 and the driving roller are installed through bearings, a sprocket 57 is installed on the rotating shaft 52, and conveyor chains 58 are fixedly installed on both sides of the conveyor belt 54, and the sprocket 57 is connected to the conveyor chain 58 through driving.

[0014] Furthermore, protective plates 59 are installed on the bracket 51 and are located on both sides of the conveyor belt 54 .

[0015] Beneficial effects of the utility model:

[0016] The bottom of the transfer bin of the utility model drives the gate plate to open and discharge materials through the first hydraulic cylinder, which effectively ensures the stability of the discharge rate and prevents the gravel from being scattered from both sides of the conveying device. There is no need to install a storage hopper at the front end of the conveying device, which is beneficial to saving materials and reducing costs. There is no need to flip the transfer bin, and the transfer bin has a uniform speed and good stability during the discharge process, which is beneficial to ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a three-dimensional schematic diagram of the main axis measurement of the utility model.

[0018] Figure 2 It is a rear axle-measured stereoscopic schematic diagram of the utility model.

[0019] Figure 3 yes Figure 2 A partial enlarged schematic diagram in the middle.

[0020] Figure 4 It is a three-dimensional schematic diagram of the transfer warehouse of the utility model.

[0021] Figure 5 It is a partial structural schematic diagram of the conveying device of the utility model. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings to facilitate understanding by technicians.

[0023] The utility model discloses a bean gravel conveyor for TBM, which mainly comprises a transverse movement device 1, a lifting device 2, a transfer bin 3, a first hydraulic cylinder 4, and a conveying device 5. The transverse movement device 1 is installed on the frame of the TBM trailer, the lifting device 2 is installed on the transverse movement device 1, the lifting device 2 is connected to the transfer bin 3, the transfer bin 3 is supported on the trailer by legs 34, a discharge port 31 is provided at the bottom of the transfer bin 3, slide grooves 32 are provided on both sides of the discharge port 31, a gate plate 33 is slidably installed in the slide groove 32, the first hydraulic cylinder 4 is installed on the trailer through a support, the first hydraulic cylinder 4 is connected to the gate plate 33 by transmission, the conveying device 5 is installed on the trailer, the front end of the conveying device 5 is docked below the discharge port 31 of the transfer bin 3, and the end of the conveying device 5 is connected to the storage bin of the bean gravel feeding device; The bean gravel is transported to the trailer by the transfer bin 3 through the rail car and the driving vehicle, the lifting device 2 is connected to the transfer bin 3, the transfer bin 3 is lifted by the lifting device 2, the transfer bin 3 is moved to the upper part of the front end of the conveying device 5 by the transverse movement device 1, the first hydraulic cylinder 4 is connected to the gate plate 33, the gate plate 33 is driven to open by the first hydraulic cylinder 4, and the bean gravel is discharged to the conveying device 5, and the bean gravel is conveyed to the storage bin of the bean gravel feeding device by the conveying device 5. The bottom of the transfer bin 3 is driven by the first hydraulic cylinder 4 to open the gate plate 33 and discharge the material, which effectively ensures the stability of the discharge rate and prevents the bean gravel from being scattered from both sides of the conveying device 5. There is no need to install a storage hopper at the front end of the conveying device 5, which is beneficial to saving materials and reducing costs; there is no need to flip the transfer bin 3, and the transfer bin 3 has a uniform speed and good stability during the discharge process, which is beneficial to ensuring construction safety.

[0024] The transverse movement device 1 includes a fixed frame 11, a sliding frame 12, and a second hydraulic cylinder 13. The fixed frame 11 is fixedly installed on the frame of the TBM trailer. A first slide rail 14 is provided on the inner side of both ends of the fixed frame 11. Both ends of the sliding frame 12 can be slidably installed in the first slide rail 14. The second hydraulic cylinder 13 is installed on one side of the fixed frame 11, and the sliding frame 12 is transmission-connected to the second hydraulic cylinder 13; the lifting device 2 is installed on the sliding frame 12; the transverse movement of the transfer bin 3 is realized by the fixed frame 11, the sliding frame 12 and the second hydraulic cylinder 13, ensuring that the transfer bin 3 moves smoothly and operates reliably.

[0025] The lifting device 2 includes a slider 21, a third hydraulic cylinder 22, a pulley 23, and a traction chain 24. A second slide rail 15 is provided on the inner side of the sliding frame 12. Both ends of the slider 21 can be slidably installed in the second slide rail 15. The slider 21 and the sliding frame 12 are connected through the third hydraulic cylinder 22. The pulley 23 is installed at both ends of the sliding frame 12. One end of the traction chain 24 is connected to the slider 21. The traction chain 24 is connected to the transfer warehouse 3 after winding around the pulley 23. The transfer warehouse 3 is connected through the traction chain 24. The third hydraulic cylinder 22 drives the slider 21 to slide, thereby pulling the traction chain 24 and the transfer warehouse 3. The structure is simple, the operation is convenient, and it is easy to maintain and reduce costs.

[0026] A hook 25 is provided at the bottom end of the traction chain 24, and double earrings 26 connected to the hook 25 are provided at both ends of the transfer bin 3, which are convenient for connection and disconnection and easy to operate.

[0027] The transfer bin 3 has a plurality of discharge ports 31 evenly arranged at the bottom along the length direction, the spacing between the discharge ports 31 is greater than twice the length of the discharge ports 31 , and the gate plate 33 is evenly provided with through holes matching the discharge ports 31 .

[0028] Fixed support seats 6 for supporting the transfer bin 3 are installed on both sides of the conveying device 5. The fixed support seats 6 are consistent in height with the conveying device 5. After the transfer bin 3 is lifted into place, it can be supported on the fixed support seats 6, which can effectively reduce the lifting and lowering distance of the transfer bin 3, which is beneficial to reducing energy consumption, improving work efficiency and reducing the risk factor.

[0029] The top of the fixed support seat 6 is provided with a limiting groove 61 for limiting the support leg 34 of the transfer bin 3. The limiting groove 61 is connected to the support leg 34 by inserting a pin shaft to ensure stable, safe and reliable support during the unloading process.

[0030] The conveying device 5 includes a bracket 51, a rotating shaft 52, a driving roller, a conveyor belt 54, a flexible corrugated baffle 55, and a partition 56. The bracket 51 is installed on a trailer, and the conveyor belt 54 is installed on the bracket 51 through the driving roller and the rotating shaft 52. The conveyor belt 54 includes a horizontal conveying section and a lifting section. The flexible corrugated baffle 55 is installed on both sides of the conveyor belt 54, and the partition 56 is evenly installed on the conveyor belt 54 laterally. A storage hopper is formed between the flexible corrugated baffle 55 and the partition 56. The flexible corrugated baffle 55 is used to limit the positions of the two sides of the pea gravel to prevent the pea gravel from being scattered. At the same time, the flexible corrugated baffle 55 can meet the small arc support and deformation matching the conveyor belt end and the driving roller. A storage hopper is formed between the flexible corrugated baffle 55 and the partition 56, which effectively limits the position of the pea gravel in the lifting section to ensure the lifting efficiency of the pea gravel.

[0031] The rotating shaft 52 and the driving roller are installed through bearings, a sprocket 57 is installed on the rotating shaft 52, and conveyor chains 58 are fixedly installed on both sides of the conveyor belt 54. The sprocket 57 is connected with the conveyor chain 58 for transmission. The transmission is through the sprocket 57 and the conveyor chain 58, which effectively avoids the slippage of the conveyor belt and prevents the accumulation of materials at the front end of the conveying device 5 due to slippage.

[0032] The support 51 is provided with protective plates 59 on both sides of the conveyor belt 54 .

[0033] Working process:

[0034] The bean gravel is transported to the trailer by the transfer bin 3 through the rail car and the driving vehicle, the lifting device 2 is connected to the transfer bin 3, the transfer bin 3 is lifted by the lifting device 2, the transfer bin 3 is moved to the upper part of the front end of the conveying device 5 by the transverse movement device 1, the first hydraulic cylinder 4 is connected to the gate plate 33, the gate plate 33 is driven to open by the first hydraulic cylinder 4, and the bean gravel is discharged to the conveying device 5, and the bean gravel is conveyed to the storage bin of the bean gravel feeding device by the conveying device 5. The bottom of the transfer bin 3 is driven by the first hydraulic cylinder 4 to open the gate plate 33 and discharge the material, which effectively ensures the stability of the discharge rate and prevents the bean gravel from being scattered from both sides of the conveying device 5. There is no need to install a storage hopper at the front end of the conveying device 5, which is beneficial to saving materials and reducing costs; there is no need to flip the transfer bin 3, and the transfer bin 3 has a uniform speed and good stability during the discharge process, which is beneficial to ensuring construction safety.

[0035] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the utility model.

Claims

1. A pea gravel conveyor for TBM, characterized by: The bean gravel conveyor for TBM comprises a transverse movement device (1), a lifting device (2), a transfer bin (3), a first hydraulic cylinder (4), and a conveying device (5). The transverse movement device (1) is mounted on a frame of a TBM trailer, the lifting device (2) is mounted on the transverse movement device (1), the lifting device (2) is connected to the transfer bin (3), the transfer bin (3) is supported on the trailer via legs (34), a discharge port (31) is provided at the bottom of the transfer bin (3), slide grooves (32) are provided on both sides of the discharge port (31), a gate plate (33) is slidably mounted in the slide groove (32), the first hydraulic cylinder (4) is mounted on the trailer via a support, the first hydraulic cylinder (4) is transmission-connected to the gate plate (33), the conveying device (5) is mounted on the trailer, the front end of the conveying device (5) is docked below the discharge port (31) of the transfer bin (3), and the rear end of the conveying device (5) is connected to a storage bin of a bean gravel feeding device.

2. A pea gravel conveyor for TBM according to claim 1, characterized in that: The transverse movement device (1) comprises a fixed frame (11), a sliding frame (12), and a second hydraulic cylinder (13); the fixed frame (11) is fixedly mounted on the frame of the TBM trailer; first slide rails (14) are provided on the inner sides of both ends of the fixed frame (11); both ends of the sliding frame (12) can be slidably mounted in the first slide rails (14); the second hydraulic cylinder (13) is mounted on one side of the fixed frame (11); the sliding frame (12) is transmission-connected to the second hydraulic cylinder (13); and the lifting device (2) is mounted on the sliding frame (12).

3. A pea gravel conveyor for TBM according to claim 2, characterized in that: The lifting device (2) comprises a slider (21), a third hydraulic cylinder (22), a pulley (23), and a traction chain (24). A second slide rail (15) is provided inside the sliding frame (12). Both ends of the slider (21) can be slidably mounted in the second slide rail (15). The slider (21) and the sliding frame (12) are connected to each other through the third hydraulic cylinder (22). The pulley (23) is mounted at both ends of the sliding frame (12). One end of the traction chain (24) is connected to the slider (21). The traction chain (24) is connected to the transfer bin (3) after being wound around the pulley (23).

4. A pea gravel conveyor for TBM according to claim 3, characterized in that: The bottom end of the traction chain (24) is provided with a hook (25), and both ends of the transfer bin (3) are provided with double earrings (26) connected to the hook (25).

5. A pea gravel conveyor for TBM according to any one of claims 1 to 4, characterized in that: The transfer bin (3) has a plurality of discharge ports (31) evenly arranged at the bottom along the length direction, the spacing between the discharge ports (31) is greater than twice the length of the discharge ports (31), and the gate plate (33) is evenly provided with through holes matching the discharge ports (31).

6. A pea gravel conveyor for TBM according to claim 5, characterized in that: Fixed support seats (6) for supporting the transfer bin (3) are installed on both sides of the conveying device (5), and the fixed support seats (6) are at the same height as the conveying device (5).

7. A pea gravel conveyor for TBM according to claim 6, characterized in that: The top of the fixed support seat (6) is provided with a limiting groove (61) for limiting the support leg (34) of the transfer bin (3), and the limiting groove (61) and the support leg (34) are connected by inserting a pin shaft.

8. A pea gravel conveyor for TBM according to any one of claims 1 to 4, 6 and 7, characterized in that: The conveying device (5) comprises a bracket (51), a rotating shaft (52), a driving roller, a conveyor belt (54), a flexible corrugated baffle (55), and a partition (56). The bracket (51) is mounted on a trailer. The conveyor belt (54) is mounted on the bracket (51) via the driving roller and the rotating shaft (52). The conveyor belt (54) comprises a horizontal conveying section and a lifting section. The flexible corrugated baffle (55) is mounted on both sides of the conveyor belt (54). The partition (56) is evenly and laterally mounted on the conveyor belt (54). A storage hopper is formed between the flexible corrugated baffle (55) and the partition (56).

9. A pea gravel conveyor for TBM according to claim 8, characterized in that: The rotating shaft (52) and the driving roller are installed via bearings. A sprocket (57) is installed on the rotating shaft (52). Conveying chains (58) are fixedly installed on both sides of the conveying belt (54). The sprocket (57) is connected to the conveying chain (58) in a driving manner.

10. A pea gravel conveyor for TBM according to claim 9, characterized in that: The support (51) is provided with protective plates (59) located on both sides of the conveyor belt (54).