BIM (Building Information Modeling) technology strong current box prefabricated concrete structure

By setting up rebar sleeves and bolts in the precast concrete structure, the installation inadequacy problem when the size of the strong electric box is smaller than the hole is solved, and the stable installation and structural stability of the strong electric box are achieved.

CN222009473UActive Publication Date: 2024-11-15CHINA MCC17 GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420014781.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-04
Publication Date
2024-11-15
Estimated Expiration
2034-01-04

AI Technical Summary

Technical Problem

In the prior art, the installation misfit problem when the size of the strong electric box is smaller than the hole is not effectively solved.

Method used

Precast concrete structure, including precast beams, precast bottom support and side walls, is equipped with rebar sleeves and bolts. The strong electric box is fixed by adjusting the installation depth of the bolts, and the opening is reserved for pipeline installation, and C25 concrete is used to improve it. Structural stability.

Benefits of technology

It effectively solves the installation inadequacy problem when the size of the strong electric box is smaller than the hole, simplifies the installation process, and improves the stability and installation efficiency of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009473U_ABST
    Figure CN222009473U_ABST
Patent Text Reader

Abstract

The utility model discloses a BIM technology strong current box precast concrete structure, and relates to the field of strong current box reserved holes. The prefabricated structure comprises a prefabricated beam, a prefabricated bottom support, a side wall and a hole formed by the prefabricated beam, the bottom support and the side wall, the strong current box is arranged in the hole, the prefabricated beam, the prefabricated bottom support and the side wall are arranged on a brick wall body, and the prefabricated structure is provided with a threaded steel sleeve. According to the utility model, the problem of adaptability of installation of the strong current box with the size smaller than that of the hole is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building construction, in particular to a BIM technology strong electric box prefabricated concrete structure. Background Art

[0002] On November 13, 2018, Chinese patent CN208088562U disclosed a "new type of reserved hole structure for a strong electric box". This technical solution provides a new type of reserved hole structure for a strong electric box, including a wall and a rectangular hole provided on the wall. The use of a prefabricated concrete electric box lintel eliminates a series of complex processes such as opening holes, cutting grooves, supporting the hole template, tying steel bars, and pouring concrete for interlocking blocks in the traditional masonry process. Instead, a simple, fast and mass-produced process is used. However, this technical solution does not solve the problem of adaptability of the strong electric box to be installed when the size is smaller than the hole. Utility Model Content

[0003] The technical problem that the utility model needs to solve is to overcome the shortcomings of the background technology and provide a precast concrete structure of a high-voltage box that can solve the adaptability problem of the high-voltage box size being smaller than the hole for installation. To achieve the above purpose, the utility model provides the following technical solutions: a precast concrete structure of a high-voltage box using BIM technology, comprising a precast beam, a precast bottom bracket, and a side wall. The hole formed by the precast beam, the precast bottom bracket and the side wall is used to support the threaded steel bars of the precast concrete structure. The high-voltage box is arranged in the reserved hole. The precast beam, the precast bottom bracket and the side wall are provided with a threaded steel sleeve, and bolts are installed in the threaded steel sleeve.

[0004] A further technical solution is that the prefabricated beam, prefabricated base and side wall are each provided with at least four threaded steel sleeves.

[0005] A further technical solution is that the threaded steel sleeve has a bolt, the end of the bolt is located inside the hole, and the end is abutted against the high-voltage box, which solves the problem of incompatibility when the high-voltage box is smaller than the hole for installation.

[0006] A further technical solution is that the prefabricated beam has an opening reserved at the front end above the hole.

[0007] A further technical solution is that the prefabricated base has an opening reserved at the front end of the bottom of the hole for installing the high-voltage box pipeline.

[0008] A further technical solution is that the depth of the openings of the prefabricated beams and prefabricated bases is half the thickness of the wall.

[0009] A further technical solution is that the prefabricated beam and the prefabricated base are both provided with two threaded steel bars with a diameter of 12 mm to improve the stability of the structure.

[0010] A further technical solution is that the prefabricated beams, prefabricated bases and side walls are cast with C25 concrete to improve the stability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a structural schematic diagram of the utility model.

[0012] Figure 2 It is a schematic diagram of installation when the size of the high-voltage box of the utility model matches the size of the hole.

[0013] Figure 3 It is a schematic diagram of installation when the size of the high-voltage box of the utility model is smaller than the size of the hole.

[0014] Among them: 1. Precast concrete beam; 2. Precast concrete base; 3. Side wall; 4. Opening; 5. Threaded steel bar; 6. Threaded steel sleeve; 7. Power box; 8. Bolts. DETAILED DESCRIPTION

[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0016] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0017] Example 1

[0018] See attached Figure 1 , Figure 2As shown, the size of the high-voltage box 7 matches the size of the opening 4: In the utility model, the wall is built with interlocking blocks, and a precast concrete structure is provided on the wall. The precast concrete structure is composed of a precast beam 1, a precast base 2 and a side wall 3, which eliminates the process of opening a hole and reduces dust pollution. The precast beam 1, the precast base 2 and the side wall 3 form the opening 4. The precast beam 1 and the precast base 2 have grooves at the opening of the opening 4. The depth of the opening groove is half of the wall, which is convenient for the installation of the threading pipe. The structure is made of C25 fine stone concrete, and two 12mm threaded steel bars 5 are provided in the precast concrete beam 1. At the same time, two 12mm threaded steel bars 5 are provided at the bottom of the precast concrete base 2. The lengths of the threaded steel bars 5 are the same as those of the beam 1 and the base 2, respectively. The threaded steel bars are used to improve the stability of the structure. During construction, the high-voltage box 7 is installed in the opening 4, and the embedded pipelines are installed through the openings reserved by the precast concrete beams 1 and the precast concrete base 2. Finally, the reserved openings are cast and sealed to complete the installation of the entire high-voltage meter box.

[0019] Embodiment 2 is different in that the size of the high-voltage box 7 is smaller than the size of the opening 4 .

[0020] See attached Figure 1 , Figure 3 As shown, bolts 8 are arranged in the threaded steel sleeves 6 of the prefabricated base 2 and the single-side side wall 3. The installation depth of the bolts 8 is adjusted to fix the high-voltage box 7, thereby completing the installation of the entire high-voltage box.

Claims

1. A BIM technology strong electric box prefabricated concrete structure, characterized by: The invention comprises a prefabricated beam (1), a prefabricated bottom bracket (2) and a side wall (3); an opening (4) formed by the prefabricated beam (1), the prefabricated bottom bracket (2) and the side wall (3); threaded steel bars (5) are arranged in the prefabricated beam (1) and the prefabricated bottom bracket (2); and threaded steel sleeves (6) are arranged on the prefabricated beam (1), the prefabricated bottom bracket (2) and the side wall (3).

2. According to the BIM technology prefabricated concrete structure of the strong electric box of claim 1, it is characterized by: The prefabricated beam (1), the prefabricated base (2) and the side wall (3) are all provided with at least four threaded steel sleeves (6).

3. According to claim 2, a BIM technology strong electric box prefabricated concrete structure is characterized by: The threaded steel sleeve (6) is threadedly connected with a bolt (8), and the end of the bolt (8) is located inside the hole (4), and the end is in contact with the high-voltage box (7).

4. According to the BIM technology prefabricated concrete structure of the strong electric box of claim 1, it is characterized by: The prefabricated beam (1) is provided with an opening at the front end above the hole (4).

5. According to the BIM technology prefabricated concrete structure of the strong electric box of claim 1, it is characterized by: The prefabricated base (2) has an opening reserved at the front end of the bottom of the hole (4).

6. A BIM technology strong electric box prefabricated concrete structure according to claim 4 or 5, characterized in that: The depth of the openings of the prefabricated beam (1) and the prefabricated base (2) is half the thickness of the wall.

7. A BIM technology strong electric box prefabricated concrete structure according to claim 4 or 5, characterized in that: The prefabricated beam (1) and the prefabricated base (2) are both provided with two threaded steel bars (5) with a diameter of 12 mm.

8. A BIM technology strong electric box prefabricated concrete structure according to claim 4 or 5, characterized in that: The prefabricated beam (1), prefabricated base (2) and side wall (3) are cast using C25 concrete.