Concrete pouring device for building construction
By introducing an adjustment device into the concrete pouring device to adjust the height of the protective cover, the problem of concrete sputtering damage when the protective cover is high from the casting surface is solved, achieving a more efficient protection effect and reducing the cost of use.
Patent Information
- Application Number
- CN202420446816.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-08
AI Technical Summary
The existing concrete pouring device for construction construction may still harm the construction personnel when the protective cover is high from the pouring surface.
A concrete pouring device including feed pipe, guide pipe, adjustment pipe, protective cover and adjustment device is designed. The height of the protective cover can be adjusted through the adjustment device to ensure that concrete sputtering is effectively protected.
It effectively avoids the damage caused by concrete sputtering to construction workers, and reduces the cost of use by separately replacing the adjustment device and protective cover, improving the convenience of operation and protective effect.
Smart Images

Figure CN222009626U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, and more specifically discloses a concrete pouring device for building construction. Background Art
[0002] Concrete is abbreviated as concrete, which is a general term for engineering composite materials in which aggregates are bonded into a whole by cementitious materials. The term concrete usually refers to cement as a cementitious material, sand and stone as aggregates, and water (which may contain admixtures and additives) in a certain proportion. The cement concrete obtained by mixing is also called ordinary concrete. It is widely used in civil engineering. Concrete has the characteristics of abundant raw materials, low price and simple production process, so its usage is increasing. At the same time, concrete also has the characteristics of high compressive strength, good durability and wide range of strength grades. These characteristics make its scope of use very wide. It is not only used in various civil engineering projects, Concrete is also an important material in shipbuilding, machinery industry, ocean development and geothermal engineering. With the development of society and the increasing number of equipment in the field of construction, concrete pouring in major construction sites now mostly uses pump trucks to apply sufficient pressure to the concrete and inject it into the formwork. However, the existing concrete pouring device will cause concrete splashing due to the huge pressure of the pump truck during use. The protective measures taken by the construction personnel often cannot provide comprehensive protection. The cement in the concrete is corrosive to a certain extent. The splashing of concrete may cause burns to the skin of the construction personnel, causing inevitable skin damage.
[0003] In view of the above problems, the prior art (publication number CN213449525U) discloses a concrete pouring device for construction, including a feed pipe, the outer wall of the feed pipe is fixedly connected with a slide rail, one side of the slide rail is provided with a slide groove, the inner wall of the slide groove is movably connected with a slider, one side of the slider is fixedly connected with a gripping mechanism, and the outer wall of the feed pipe is fixedly connected with a fixing plate. The concrete pouring device for construction fixes the mounting plate and the bottom fixed protective cover to the outer wall of the feed pipe by installing nuts, and then fixes the protective cover and the mounting plate by installing nuts. The concrete flowing in the feed pipe can effectively block the splashing concrete caused by the pressure of the pump truck after being ejected. When the construction personnel move or support the feed pipe, the splashing concrete will not splash onto the skin, thus avoiding skin burns caused by concrete due to long-term work.
[0004] However, during use of the above device, the position of the protective cover is fixed and cannot be adjusted. When the protective cover is at a high height from the casting surface, concrete will still splash onto the skin of the construction workers due to falling and causing harm. Utility Model Content
[0005] The main technical problem solved by the utility model is to provide a concrete pouring device for construction, which can solve the problem that when the protective cover is at a high height from the pouring surface, concrete will still splash onto the skin and cause harm to the construction workers due to falling.
[0006] To solve the above technical problems, according to one aspect of the utility model, more specifically, a concrete pouring device for construction, comprising a feed pipe, a guide pipe is fixed to the lower part of the outer wall of the feed pipe, an adjusting pipe is plugged into the outer lower part of the guide pipe, adjusting devices are symmetrically fixed to the upper parts of the left and right outer walls of the adjusting pipe, a protective cover is provided below the adjusting pipe, a connecting pipe is fixed to the upper part of the inner wall of the protective cover, the upper part of the connecting pipe is plugged into the lower part of the inner wall of the adjusting pipe, and connecting devices are symmetrically provided above the front and rear outer walls of the protective cover.
[0007] Furthermore, the adjusting device includes a handle, which is symmetrically fixed on the upper part of the left and right outer walls of the adjusting tube, and a mounting groove is provided in the middle part of the side of the handle close to the adjusting tube, a limiting spring is fixed at the bottom of the mounting groove, and a limiting rod is fixed at one end of the limiting spring away from the bottom of the mounting groove, and a plurality of groups of limiting holes are evenly provided on the left and right outer walls of the guide tube, and through holes are symmetrically provided on the upper part of the left and right outer walls of the adjusting tube, and the limiting rod is inserted into the interior of the limiting hole and the interior of the through hole on the side close to the adjusting tube, and an adjusting groove is provided on the rear outer wall of the mounting groove close to the side of the adjusting tube, and an adjusting rod is inserted into the interior of the adjusting groove.
[0008] Furthermore, the connecting device includes a mounting seat, which is symmetrically fixed to the upper parts of the front and rear outer walls of the protective cover, a connecting seat is fixed in the middle of the top of the mounting seat, a connecting frame is symmetrically fixed to the lower parts of the front and rear outer walls of the adjusting tube, the connecting seat is inserted into the interior of the connecting frame, connecting grooves are symmetrically opened in the middle of the left and right sides of the connecting seat, a connecting spring is fixed to the bottom of the connecting groove, a connecting block is fixed to one end of the connecting spring away from the bottom of the connecting groove, a connecting hole is opened in the middle of the left and right inner walls of the connecting frame, and the side of the connecting block away from the connecting spring is inserted into the interior of the connecting hole.
[0009] Furthermore, the outer diameter of the guide tube is equal to the inner diameter of the adjusting tube.
[0010] Furthermore, the outer wall of the limiting rod is in contact with the inner wall of the limiting hole.
[0011] Furthermore, the distance between the left and right sides of the connecting seat is equal to the distance between the left and right inner walls of the connecting frame, and the distance between the front and back sides of the connecting seat is equal to the distance between the front and back sides of the connecting frame.
[0012] The utility model provides a beneficial effect of a concrete pouring device for building construction: concrete is discharged from a material delivery pipe for pouring, and under the action of the regulating pipe and the protective cover, concrete splashing can be avoided to cause harm to the operator; the position of the regulating pipe can be adjusted by the regulating device, and then the height of the protective cover can be adjusted, so that the operator can adjust the height of the protective cover according to actual conditions when pouring concrete, further avoiding concrete splashing and improving the protective effect of the protective cover on the operator; at the same time, the regulating device and the connecting device can realize the separate replacement of the regulating pipe and the protective cover, thereby reducing the use cost and improving the economic benefit; the operator moves the material delivery pipe by the handle to facilitate the operator to perform the pouring operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The utility model is further described in detail below with reference to the accompanying drawings and specific implementation methods.
[0014] Figure 1 This is a schematic diagram of the overall structure of the device;
[0015] Figure 2 for Figure 1 Schematic diagram of the enlarged structure at A;
[0016] Figure 3 It is a schematic diagram of the structure of the regulating tube and the through hole;
[0017] Figure 4 This is a schematic diagram of the cross-sectional structure of the handle;
[0018] Figure 5 It is a schematic diagram of the protective cover and the connecting pipe structure;
[0019] Figure 6 It is a schematic diagram of the cross-sectional structure of the connecting seat;
[0020] Figure 7 Schematic diagram of the connection frame and connection hole structure.
[0021] In the figure: 1. feed pipe; 2. guide pipe; 3. adjustment pipe; 4. adjustment device; 5. protective cover; 6. limit hole; 7. connecting device; 8. mounting seat; 9. connecting seat; 10. connecting frame; 11. through hole; 12. handle; 13. mounting slot; 14. limit spring; 15. limit rod; 16. adjustment slot; 17. adjustment rod; 18. connecting pipe; 19. connecting slot; 20. connecting spring; 21. connecting block; 22. connecting hole. DETAILED DESCRIPTION
[0022] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present application can be combined with each other without conflict.
[0023] According to one aspect of the present invention, Figure 1-7 As shown, a concrete pouring device for construction is provided, including a conveying pipe 1, a guide pipe 2 is fixed to the lower part of the outer wall of the conveying pipe 1, an adjusting pipe 3 is inserted into the outer lower part of the guide pipe 2, an adjusting device 4 is symmetrically fixed to the upper parts of the left and right outer walls of the adjusting pipe 3, a protective cover 5 is provided below the adjusting pipe 3, a connecting pipe 18 is fixed to the upper part of the inner wall of the protective cover 5, the upper part of the connecting pipe 18 is inserted into the lower part of the inner wall of the adjusting pipe 3, and connecting devices 7 are symmetrically provided above the front and rear outer walls of the protective cover 5. Concrete is discharged from the conveying pipe 1 for pouring. Under the action of the adjusting pipe 3 and the protective cover 5, concrete splashing and pushing the operator to cause injury can be avoided. The position of the adjusting pipe 3 can be adjusted by the adjusting device 4, and then the height of the protective cover 5 can be adjusted, so that the operator can adjust the height of the protective cover 5 according to the actual situation when pouring concrete, further avoiding concrete splashing and improving the protective effect of the protective cover 5 on the operator. At the same time, the adjusting device 4 and the connecting device 7 can realize the separate replacement of the adjusting pipe 3 and the protective cover 5, thereby reducing the use cost and improving the economic benefit.
[0024] The adjusting device 4 includes a handle 12, which is symmetrically fixed to the upper part of the left and right outer walls of the adjusting tube 3. A mounting groove 13 is provided in the middle of the side of the handle 12 near the adjusting tube 3. A limiting spring 14 is fixed to the bottom of the mounting groove 13. A limiting rod 15 is fixed to one end of the limiting spring 14 away from the bottom of the mounting groove 13. A plurality of groups of limiting holes 6 are evenly provided on the left and right outer walls of the guide tube 2. Through holes 11 are symmetrically provided on the upper part of the left and right outer walls of the adjusting tube 3. The side of the limiting rod 15 near the adjusting tube 3 is plugged into the inside of the limiting hole 6 and the inside of the through hole 11. An adjusting groove 16 is provided on the rear outer wall of the mounting groove 13 near the adjusting tube 3. An adjusting rod 17 is plugged into the inside of the adjusting groove 16. The front end of the adjusting rod 17 is fixed The middle part of the limit rod 15 is fixed, and the handle 12 is held to push the adjusting rod 17 in the direction away from the adjusting tube 3, so as to drive the limit rod 15 to separate from the limit hole 6 and move the adjusting tube 3 up and down, so as to adjust the height of the protective cover 5 according to the actual situation. After adjusting to the appropriate position, the hand moves in the direction of the adjusting tube. Under the action of the limit spring 14, the limit rod 15 is inserted into the corresponding limit hole 6, and the positions of the adjusting tube 3 and the protective cover 5 are fixed. The operator can move the discharge pipe through the handle 12 to facilitate pouring. When the adjusting tube 3 needs to be disassembled, the adjusting rod 17 is pushed in the direction away from the adjusting tube 3 to separate the limit rod 15 from the limit hole 6, and the adjusting tube 3 is moved downward until the adjusting tube 3 is separated from the guide tube 2 to complete the disassembly.
[0025] The connecting device 7 includes a mounting seat 8, which is symmetrically fixed to the upper part of the front and rear outer walls of the protective cover 5. A connecting seat 9 is fixed in the middle of the top of the mounting seat 8. A connecting frame 10 is symmetrically fixed to the lower part of the front and rear outer walls of the adjusting tube 3. The connecting seat 9 is inserted into the interior of the connecting frame 10. Connecting grooves 19 are symmetrically provided in the middle of the left and right sides of the connecting seat 9. A connecting spring 20 is fixed to the bottom of the connecting groove 19. A connecting block 21 is fixed to one end of the connecting spring 20 away from the bottom of the connecting groove 19. Connecting holes 22 are provided in the middle of the left and right inner walls of the connecting frame 10. The side of the connecting block 21 away from the connecting spring 20 is inserted into the interior of the connecting hole 22. The protective cover 5 can be disassembled by pressing the connecting block 21 to move the protective cover 5 downward. When installing the protective cover 5, press the connecting block 21 to insert the connecting seat 9 into the interior of the connecting frame 10. When the connecting block 21 and the connecting hole 22 are relative to each other, the connecting block 21 is inserted into the interior of the connecting hole 22 under the action of the connecting spring 20 to complete the installation of the protective cover 5.
[0026] The outer diameter of the guide tube 2 is equal to the inner diameter of the adjusting tube 3, so as to ensure that the adjusting tube 3 does not shake when moving.
[0027] The outer wall of the limiting rod 15 fits with the inner wall of the limiting hole 6 to ensure that the position of the adjusting pipe 3 is fixed and will not shake to affect the concrete pouring.
[0028] The distance between the left and right sides of the connecting seat 9 is equal to the distance between the left and right inner walls of the connecting frame 10, and the distance between the front and back sides of the connecting seat 9 is equal to the distance between the front and back sides of the connecting frame 10, thereby ensuring the stability of the protective cover 5 when in use.
[0029] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present invention also fall within the protection scope of the present invention.
Claims
1. A concrete pouring device for building construction, comprising a conveying pipe (1), characterized in that: A guide tube (2) is fixed to the lower part of the outer wall of the feed conveying tube (1), an adjusting tube (3) is plugged into the outer lower part of the guide tube (2), adjusting devices (4) are symmetrically fixed to the upper parts of the left and right outer walls of the adjusting tube (3), a protective cover (5) is provided below the adjusting tube (3), a connecting tube (18) is fixed to the upper part of the inner wall of the protective cover (5), the upper part of the connecting tube (18) is plugged into the lower part of the inner wall of the adjusting tube (3), and connecting devices (7) are symmetrically provided above the front and rear outer walls of the protective cover (5).
2. A concrete pouring device for construction according to claim 1, characterized in that: The adjusting device (4) comprises a handle (12), the handle (12) being symmetrically fixed to the upper parts of the left and right outer walls of the adjusting tube (3), a mounting groove (13) being provided in the middle of the side of the handle (12) close to the adjusting tube (3), a limiting spring (14) being fixed at the bottom of the mounting groove (13), a limiting rod (15) being fixed at one end of the limiting spring (14) away from the bottom of the mounting groove (13), and a plurality of groups of limiting holes being evenly provided on the left and right outer walls of the guide tube (2) (6), through holes (11) are symmetrically provided on the upper parts of the left and right outer walls of the adjusting tube (3), the limiting rod (15) is inserted into the inside of the limiting hole (6) and the inside of the through hole (11) on the side close to the adjusting tube (3), an adjusting groove (16) is provided on the rear outer wall of the mounting groove (13) on the side close to the adjusting tube (3), an adjusting rod (17) is inserted into the inside of the adjusting groove (16), and the front end of the adjusting rod (17) is fixed to the middle part of the limiting rod (15).
3. A concrete pouring device for construction according to claim 1, characterized in that: The connecting device (7) comprises a mounting seat (8), the mounting seat (8) being symmetrically fixed to the upper parts of the front and rear outer walls of the protective cover (5), a connecting seat (9) being fixed in the middle of the top of the mounting seat (8), a connecting frame (10) being symmetrically fixed to the lower parts of the front and rear outer walls of the adjusting tube (3), the connecting seat (9) being plugged into the interior of the connecting frame (10), connecting grooves (19) being symmetrically provided in the middle parts of the left and right side surfaces of the connecting seat (9), a connecting spring (20) being fixed at the bottom of the connecting groove (19), a connecting block (21) being fixed at one end of the connecting spring (20) away from the bottom of the connecting groove (19), a connecting hole (22) being provided in the middle parts of the left and right inner walls of the connecting frame (10), and the side of the connecting block (21) away from the connecting spring (20) being plugged into the interior of the connecting hole (22).
4. A concrete pouring device for construction according to claim 1, characterized in that: The outer diameter of the guide tube (2) is equal to the inner diameter of the adjustment tube (3).
5. A concrete pouring device for construction according to claim 2, characterized in that: The outer wall of the limiting rod (15) and the inner wall of the limiting hole (6) are in contact with each other.
6. A concrete pouring device for construction according to claim 3, characterized in that: The distance between the left and right sides of the connecting seat (9) is equal to the distance between the left and right inner walls of the connecting frame (10), and the distance between the front and back sides of the connecting seat (9) is equal to the distance between the front and back sides of the connecting frame (10).